Professional Documents
Culture Documents
Optimal Allocation of DSTATCOM in Distribution System
Optimal Allocation of DSTATCOM in Distribution System
DOI 10.1007/s13369-017-2518-y
Received: 24 August 2016 / Accepted: 5 April 2017 / Published online: 26 May 2017
© King Fahd University of Petroleum & Minerals 2017
123
2852 Arab J Sci Eng (2017) 42:2851–2865
deployed to distributed transformers to reduce the power loss taken into account to evaluate the benefit and cost of the
and decrease the cost of capacitor installation scheme, and entire scheme, but these are considered for PV alone with a
this approach adopted the NPV principle for the evaluation proper selection of PV and DSTATCOM capacities [28]. In
of cost–benefit of the capacitor installation scheme [16–19]. most of these approaches in using DSTATCOM, the objec-
A capacitor is allocated on DN to minimize the investment tive function is formulated for the minimization of power
cost and energy loss at different load levels. Authors of [5] loss and improvement of voltage profile; a very few works
proposed the minimization of power loss and cost of energy are appraised minimization of total ELC of the DN to maxi-
loss with the optimal allocation of the capacitor in DN by mizing the TNP/savings of the entire scheme.
using TLBO technique. The optimal placement and sizing of Out of these reviews of studies, this paper proposes an
fixed capacitor banks in DN is done to minimize the kW loss interest of using DSTATCOM in DN appropriately. DEA
and maximize net savings [4]. But capacitors are not capa- [29,30] is used as a solution strategy for optimal sizing and
ble of providing smooth reactive power compensation and placement of DSTATCOM. The appropriate modeling on the
suffering from inevitable oscillations [20], and the proposed size of DSTATCOM is used so as to incorporate it into the
approach obtained higher total net savings compared to the FBS load flow algorithm [31] for the reactive power com-
approach of [21] in which capacitor is located in of 33 and pensation. To realistically appraise the TNP/savings of the
69 bus DN. DSTATCOM installation project, PWF criterion is applied.
The DSTATCOM can alleviate the difficulties that are dis- The main objectives of proposed work are improving the volt-
cussed to minimize the energy loss and to maximize the age profile, minimizing the power loss so that minimizing
TNP/savings of DN. Some of the power quality issues of the energy loss, and total ELC of the DN, thereby maximiz-
electrical DN influenced by the allocation of DSTATCOM ing the TNP/savings over PH of DSTATCOM installation
with distribution generator are given in [22]. These same scheme. IEEE 30, 33 and 69-bus DN are used for the case
type devices are optimally sized and allocated in DN by study. Simulation results have demonstrated the effectiveness
using the particle swarm optimization algorithm to compen- of proposed work. The reduction in power loss and ELC and
sate the reactive power for the reduction of power loss [23]. maximization of TNP/savings are found to be better in the
Reconfiguration and optimal size and allocation of PV arrays proposed approach as compared to IA approach used in [27]
and DSTATCOM are simultaneously done on DN by using and GSA used for optimal capacitor placement [21]. The
the combination of fuzzy multi-objective approach and ACO abbreviations used in the proposed approach are given in
metaheuristic algorithm to reduce the power loss and improve Table 1.
voltage profile [24]. The optimal allocation of DSTATCOM The paper is organized as follows: The modeling of
along with network reconfiguration by using DEA is pro- DSTATCOM and the incorporation of DSTATCOM model
vided to minimize the power loss in DN [25]. However, the in FBS load flow are shown in Sects. 2 and 3, respectively.
approaches with the combination of DSTATCOM and recon- Objective function formulation is provided in Sect. 4. Imple-
figuration are an expensive issue because the reconfiguration mentation of proposed approach using DEA is provided in
problem is defined as the process of changing the topology Sect. 5. Simulation results are provided in Sect. 6, and the
of the network using some sectionalizing switches (closed paper concluded in Sect. 7.
switches), and tie switches (open switches), so as the num-
ber of lateral branches increases the circuit length increases 2 Modeling of DSTATCOM
which results in increase in the cost of scheme [7].
The modeling and the optimal allocation of single and DSTATCOM is a shunt connected VSC device that absorbs or
multiple DSTATCOM in DN to reduce the power loss has injects both active and reactive current, respectively, through
been investigated in [26]. The Authors of [27] proposed opti- PCC. In this work, the modeling of DSTATCOM is referred
mal sizing and allocation of DSTATCOM in DN by using the from our previous work [20,31]. DSTATCOM is used only
immune algorithm for the compensation of reactive power for reactive power compensation in DN. Figure 1. is the single
to optimize the power loss and total cost savings. How- line diagram of two successive buses n and n + 1 of DN,
ever, in this approach maintenance cost, the operational cost there are real and reactive power demands connected to these
of DSTATCOM, PWF, and PH of DSTATCOM installation buses, and it is used to place the DSTATCOM in DN. The
scheme for the evaluation of total ELC after DSTATCOM is Kirchhoff’s voltage law equation of Fig. 1. is given by Eq. (1)
installed is not considered except for the initial capital invest-
ment cost of the DSTATCOM. NPV or PWF is taken into V n+1 βn+1 = V n αn − (Rb + j X b ) I b θ. (1)
account to evaluate an economic assessment of the hybrid
voltage control scheme with PV penetration and DSTAT- The phasor diagram corresponding to Eq. (1) is shown in
COM in Taipower DN. However, in this work, the initial Fig. 2. The Kirchhoff’s voltage law equation of Fig. 3. is as
capital investment cost, O&M cost of DSTATCOM are not expressed in Eq. (2)
123
Arab J Sci Eng (2017) 42:2851–2865 2853
Vn Vn +1 V'
n
R jX
b b
jX I
I b b
b
I DSTAT R I
V b b
P + jQ P + jQ
n +1
n n n +1 n +1 jX b I DSTAT
Rb I DSTAT V'
α' n +1
Fig. 1 Two successive buses of DN drawn as a single line diagram n β
n +1
I β'
V θ b n +1
n
jX I Reference axis
b b
Fig. 4 Phasor diagram for the network shown in Fig. 3
R I
V b b
α n +1 Real part:
n
β I
θ n + 1b IDSTAT cos βn+1 + 90◦
Reference axis
V n Rb cos αn V n X b sin αn V n+1 Rb cos βn+1
= + −
Fig. 2 Phasor diagram for the network shown in Fig. 1 Rb2 + X b2 Rb2 + X b2 Rb2 + X b2
V n+1 X b sin βn+1
Vn' Vn' +1 − − Ib cos θ (4)
Rb2 + X b2
R jX
b b
PCC Imaginary part:
I I
b DSTAT
j IDSTAT sin βn+1 + 90◦
P + jQ
V n Rb sin αn V n X b cos αn V n+1 Rb sin βn+1
n n P + jQ = + −
n +1 n +1 Rb2 + X b2 Rb2 + X b2 Rb2 + X b2
V n+1 X b cos βn+1
DSTATCOM
(VSC )
− − I b sin θ (5)
Rb2 + X b2
V R V n+1 X b V n Rb
Energy Storage Let, a = − Rn+1
2 +X 2 , b =
b
Rb2 +X b2
,c = Rb2 +X b2
,d =
b b
Fig. 3 Single line diagram with a DSTATCOM placed at bus i + 1 V n Xb
, e = I DS , ψ = βn+1 + 90◦ , and φ = I b
Rb2 +X b2
By replacing these parameters in Eqs. (4) and (5), the mag-
V n+1 βn+1 = V n αn − (Rb + j X b ) nitude of the injected current of DSTATCOM has obtained
π as:
× I b θ + I DSTAT + βn+1 . (2)
2
K 1 + K 2 sin αn − θ − ϕ
I DS = (6)
The phasor diagram corresponding to Eq. (2) is shown in sin (ψ + θ )
Fig. 4. Due to the injection of IDSTAT at PCC, the voltage
. The angle of the I
at bus n + 1 is changed to Vn+1 DSTAT is where K 1 = a sin βn+1 + θ + b cos βn+1 − θ , K2 =
expressed as follows √ V
c2 + d 2 = 2 n 2 , “ϕ” is a unique angle satisfying the
Rb +X b
π
I DSTAT = + βn+1 (3) following conditions:
2
The real and imaginary parts of Eq. (2) are separated and (i) −π < ϕ < π,
are computed as Eqs. (4) and (5). (ii) tan ϕ = dc = XRbb , Since d = 0, c = 0
123
2854 Arab J Sci Eng (2017) 42:2851–2865
123
Arab J Sci Eng (2017) 42:2851–2865 2855
Fig. 5 Time duration curve where f 21 and f 22 and f 23 are the total initial capital
investment cost and the total operational cost and the total
count
count count−1 maintenance costs [34] of the DSTATCOM, respectively, in
V n+1 = abs V n+1 − abs V n+1 (13)
the whole PH of DSTATCOM installation scheme, Ce is the
count energy cost per kWh; Tk is the duration of time in kth load
If V n+1 < accuracy. (14)
level; Cin is the initial capital investment cost (purchase cost)
Count = the iteration number, Accuracy = 0.0001 of DSTATCOM per kVAr; Cop is the operational cost of the
DSTATCOM per kWh; Cma is the DSTATCOM maintenance
cost which in terms of the % of initial cost of DSTATCOM
4 Mathematical Problem Formulation per a year; Q DSTAT
k is the size of the DSTATCOM placed
at optimal location during kth load level; kck is the propor-
4.1 Objective Function (F) tionality constant of kth load level time duration to the total
duration of the time formulated as following Eq. (22)
In the proposed method, the optimal location and the size
Tk
(kVAr rating) of DSTATCOM in DN in a steady-state condi- kck = (22)
nl
tion are used to optimize the objectives such as ELC of DN Tk
to achieve the maximization of TNP. Hence, minimizing the k=1
ELC ( f 1 ) and total installation cost of DSTATCOM ( f 2 ) in
DN is considered in the objective function (F). The total ELC 4.1.1 Real Power Loss
and TNP of the DN are evaluated per for a given period ‘T’,
i.e., per annum and PH of DSTATCOM installation scheme The real power loss encountered in Eq. (17) is expressed by
by taking the three load levels (light, medium and peak lev- Eq. (23) [31]
els) into account in the network as shown in Tables 4 and 5. ⎡ ⎤
Here the load duration curve is divided into discrete intervals nl n−1
DSTAT
PLoss = ⎣ Ib2 ( j) × Rb ( j)⎦ (23)
as shown in Fig. 5 [27,30]. k
by Eq. (15)
DSTAT is the active power loss during kth load level
where Ploss k
F = min (( f 1 ) + ( f 2 )) (15) after DSTATCOM is installed, nl is the number of load levels
mentioned in Table 5, k is the load level, n is the total number
The first part of ‘F’ is the total ELC ( f 1 ). The second part is of buses in the DN, Ib ( j) and Rb ( j) are the line current and
the total installation cost of DSTATCOM ( f 2 ) that includes the resistance of jth branch, respectively.
initial capital investment cost, the O&M cost (running costs)
of the DSTATCOM placed in DN. Therefore, the objective of 4.1.2 Present Worth Factor (PWF) Analysis
optimal DSTATCOM placement problem is defined by Eq.
(16) [32,33] To evaluate the economic value of the DSTATCOM installa-
tion scheme, it is required to compare the expected revenue
Objective function = F = f 1 + f 2 (16) and investment costs over the whole PH of DSTATCOM
ph nl installation scheme. In the proposed objective function as
f 1 = E Losscost
DSTAT
= Ce DSTAT
PLoss × Tk ×PWF (17) given in Eq. (17), the PWF principle is adopted for cost–
k
y=1 k=1 benefit analysis of the scheme. The PWF offers a net worth of
123
2856 Arab J Sci Eng (2017) 42:2851–2865
the scheme in today’s dollars by discounting each year’s cash (1). Initialization, (2). Mutation, (3). Crossover and (4).
flow back to the present and then, deducing the initial invest- Selection
ment. The mathematical expression of PWF is expressed by
Step 1. Initialization this operation is based on following Eq.
Eq. (24): [3,35,36]
(26); in this operation, the target vector (TV) is generated
(1 + γ ) y × γ randomly
PWF = . (24)
(1 + γ ) y − 1
j j j
TVi,gen = round TVmin + TVmax
j
− TVmin .rannd()
4.1.3 TNP/Savings
(26)
The TNP which is to be maximized is the difference between
where j = 1, 2, . . . , D; i = 1, 2, . . . , N p and gen =
the expenditure of the energy loss cost of a DN without
the generation number.
DSTATCOM and the total expenditure of the energy loss
cost of a DN with the scheme of DSTATCOM. It is given by Step 2. Mutation in this operation, the mutant vector MVi,Gen
Eq. (25) [27] j
is generated by Eq. (27) for each target vector TVi,Gen
ph nl
1 MVi,gen = TVbest,gen + F. TVr1 ,gen − TVr2 ,gen (27)
TNP = Ce w/o DSTAT
PLoss × Tk × − F.
k
(1 + γ ) y
y=1 k=1 r1 , r2 are the integers ranged between the ranges [1, Np]. ‘F’
(25) is the scaling factor ranged from 0 to 2.
TNP, in fact, yields an economic savings or benefit in the DN Step 3. Crossover the operation of crossover takes place after
with DSTATCOM for the total PH of DSTATCOM installa- operation of mutation; this operation is performed between
tion scheme, [1,30]. Therefore, the purchasing cost of power the target vector and its corresponding mutant vector and
from substation according to the customer’s demand can be produces the trial vector. This operation is performed based
reduced. on the following equation
MV ji,gen if rand () ≤ CR
4.2 Constraints CV ji,gen = (28)
TV ji,gen or else
Proposed Eq. (17) is bounded by various active constraints
where CR = C crossover rate ranged between [0, 1].
to meet the limitations on DSTATCOM operation and elec-
trical requirements for the DN. Penalty factor is considered Step 4. Selection in this operation, the fitness of trial vector
when the operating variables such as bus voltages, line cur- and corresponding target vector in the present population is
rents and the capacity of the DSTATCOM violate the desired compared. If trial vector is best compared to target vector
safe limits. The minimum and maximum voltages are con- fitness, then the target vector is replaced in trail vector and
sidered as 0.9 and 1.1 p.u., respectively, [27]. If the voltage is entered into the population of the future generation. If it is
at bus i crosses these limits, the penalty factor is considered not so, the target vector has remained in the population in the
in objective function Eq. (17). Maximum limit of the current coming generation. The operation of selection is as follows:
in the network is taken as 1.2 times the base current of the
branch j. The line will be melted if the maximum limit of CVi,gen if f (C V ) ≤ f (TVi,gen )
TV ji,gen = (29)
the current exceeds. The maximum capacity is considered as TVi,gen or else
10,000 kVAr beyond which the penalty factor is considered.
where f = the fitness (objective) function; the above steps
are repeated until the population is converged to the best
5 Implementation of Proposed Approach Using value.
DEA
5.2 Solution Strategy Using DEA
5.1 The Operation of DEA
The main purpose of the DEA in this approach is the min-
DEA is the population-based metaheuristic algorithm [29, imization of an objective function given in Eq. (16) by
30]. It has strings, and each string consists of population Np determining the capacity of the DSTATCOM at the candi-
and the dimension (D) of optimization variables. The overall date locations. A typical string structure is shown in Fig. 6.
algorithm has mainly four steps of operation; they are: The candidate locations for DSTATCOM are considered to
123
Arab J Sci Eng (2017) 42:2851–2865 2857
'
formance and run on the same parametrical basis. The DEA
n+1,N (which yields QDSTAT)
N parameters, initial population size (NP ), dimension of each
population (D), weighting factor (F), crossover rate (CR),
and maximum generations, are taken as mentioned in Table 3.
Initial strings that are produced randomly contain bus loca-
Location of Value of 'i+1 corresponding to
DSTATCOM
tion for compensation as well as optimal variable angle βn+1
the location of DSTATCOM
of DSTATCOM for the respective location at all(three) load
Fig. 6 A typical string for DEA levels. The objective function is calculated for each string by
running load flow algorithm at all load levels.
24 25 26 27
20 21 22 23 18 19 6 Simulation Results
28 29 30
6.1 Impact of DSTATCOM Allocation
123
2858 Arab J Sci Eng (2017) 42:2851–2865
36 37 38 39 40 41 42 43 44 45 46
47 48 49 50
51 52 68 69
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
66 67
53 54 55 56 57 58 59 60 61 62 63 64 65
28 29 30 31 32 33 34 35
Table 3 Parameters of DEA NP D F CR Generations currents connected to that bus according to Eq. (10). If the
demand of the load at the bus is high, then the current drawn
50 2 1 0.8 100 by the load is high. This results in an increase in ‘Ib ’, which
in turn causes the increase in Ploss . Also, the bus voltage
will fall due to the increase in voltage drop in the branch.
To minimize the power loss, should either active power be
6.2 Analysis of Power Loss Reduction injected or reactive power be compensated, which in turn
causes the decrease in ‘Ib ’. When ‘Ib ’ is decreased, the volt-
Power loss depends on branch current (Ib ) and resistance age drop in the branch will be decreased, and thus there is
(Rb ) since Ploss = Ib2 Rb according to Eq. (23). If ‘Ib ’ an improvement in the bus voltage profile. The proposed
increases, Ploss will also increase. Basically, ‘Ib ’ depends approach aims mainly to compensate the reactive power in
on two currents. One is the load current at the sending end DN to minimize the power loss, ELC, and to improve the TNP
bus according to Eq. (9), and the other is the lateral branch and voltage profile using DSTATCOM. If DSTATCOM volt-
123
Arab J Sci Eng (2017) 42:2851–2865 2859
350
Table 5 Parameters of objective function Power loss at light load with DSTATCOM
Power loss at medium load with DSTATCOM
Power loss at peak load with DSTATCOM
Objective function parameter Value 300
1 0.9
0.89
0.88
0.5
0.87
Minimum voltage at light load with DSTATCOM
0.86 Minimum voltage at medium load with DSTATCOM
0 Minimum voltage at peak load with DSTATCOM
IEEE 30 Bus System IEEE 33 Bus System IEEE 69 Bus System 0.85
0 5 10 15 20 25 30
Bus System Bus Number
Fig. 10 Cost analysis per annum Fig. 13 Minimum bus voltage at different loads with DSTATCOM at
each bus of IEEE 30-bus distribution network
5
13 x 10 1 Light load base voltage
Total planning Cost
Ligh load voltage with DSTATCOM
12 Total Eloss Cost With DSTATCOM Medium load base voltage
Total Eloss Cost Without DSTATCOM
0.98 Medium load voltage with DSTATCOM
Bus Voltage (p.u.)
0.94
9
0.92
8
0.9
7
6 0.88
5 0.86
0 10 20 30 40 50 60 70 80 90 100 0 5 10 15 20 25 30
Generation Bus Number
Fig. 11 Total scheme mean cost of IEEE 30-bus distribution network Fig. 14 Voltage magnitude at various loads with DSTATCOM at bus
5 of IEEE 30-bus distribution network
4000
Size of DSTATCOM at light load
age is greater than the bus voltage while it is being located 3500 Size of DSTATCOM at medium load
Size of DSTATCOM at peak load
in the bus, then DSTATCOM injects current into the bus 3000
with a phase angle of 90◦ as shown in Eq. (3) and Fig. 4.
Size (kVAr)
2500
Thus, the reactive power demand shall be compensated which 2000
minimizes the power loss and improves the bus voltage even- 1500
tually. 1000
In the case of the 33-bus DN, the complex load power 500
demand (P + jQ) at “bus 30” is higher than the load demand 0
0 5 10 15 20 25 30 35
in remaining buses as shown in the network data given in
Bus Number
“Table 8” in “Appendix”. Mainly, the reactive power demand
in “bus 30” is higher than all loads connected in remain- Fig. 15 Size of DSTATCOM at each bus of IEEE 30-bus distribution
ing buses. Hence, it is quite natural that the compensation network at various loads
123
2860 Arab J Sci Eng (2017) 42:2851–2865
(p.u.)
0.8888
0.8832
0.8899
is found to be “bus 30” with the size of 1252.7 kVAr as
–
shown in “Table 6”. Similarly, there is certain impact on
network power loss when DSTATCOM is located at buses
261.2
370.4
407.7
410.5
472
3–18, 23 and 26–33 as mentioned in Sect. 6.1. In case of the
–
69-bus DN, the load power demand at “Bus 61” is higher
Optimal size
than those of the remaining buses as shown in the network
(kVAr)
data in “Table 9” in “Appendix”. Hence, the best location
1271.3
1314.0
1222.6
1404.0
2606.8
for DSTATCOM allocation is found to be at “bus 61” with
–
the size of 1312.1 kVAr as shown in “Table 6”. There is
location
COM is located at buses 6–27 and 51–69 as mentioned in
Optimal
Sect. 6.1.
30
12
61
61
5
–
F (kW) Min voltage
(p.u.)
0.9189
0.9058
0.9124
6.3 Analysis of ELC
–
The total ELC of the all three DN is described in this sec-
166.7
241.2
261.9
272.0
274.4
tion. Parameters of Table 5 are used to evaluate the objective
–
function F. Table 7 shows the comparative results of the
total annual ELC of the DN with DSTATCOM installation
Optimal size
scheme. In the approach of [27], to evaluate TNP the whole
(kVAr)
1204.9
1278.4
1360.8
1008.1
1911.2
PH, as shown in Table 5, is considered only for the evalua-
tion of the DSTATCOM initial capital investment cost ( f 21 )
–
Table 6 Comparative results of reactive power compensation with DSTATCOM for three load levels
Medium load level
but not for remaining costs such as energy (power) loss cost
( f 1 ), operational and maintenance cost ( f 22 and f 23 ) of the
location
Optimal
61
12
61
5
–
0.9358
0.9256
0.9338
143.5
152.0
171.8
157.5
1252.7
1312.1
1704.4
962.4
panies).
location
61
IA based [27] 12
IA based [27] 61
5
IA based [27] –
Proposed
Proposed
Proposed
33-bus
69-bus
123
Arab J Sci Eng (2017) 42:2851–2865 2861
123
2862 Arab J Sci Eng (2017) 42:2851–2865
Table 8 continued
Bus Line data Bus data
Send Receive Line resistance Line reactance Active load Reactive load
(Ω) (Ω) power (kW) power (kVAr)
2 19 0.1640 0.1565 90 40
19 20 1.5042 1.3554 90 40
20 21 0.4095 0.4784 90 40
21 22 0.7089 0.9373 90 40
3 23 0.4512 0.3083 90 50
23 24 0.8980 0.7091 420 200
24 25 0.8960 0.7011 420 200
6 26 0.2030 0.1034 60 25
26 27 0.2842 0.1447 60 25
27 28 1.0590 0.9337 60 20
28 29 0.8042 0.7006 120 70
29 30 0.5075 0.2585 200 600
30 31 0.9744 0.9630 150 70
31 32 0.3105 0.3619 210 100
32 33 0.3410 0.5302 60 40
1 2 0.0005 0.0012 0 0
2 3 0.0005 0.0012 0 0
3 4 0.0015 0.0036 0 0
4 5 0.0251 0.0294 0 0
5 6 0.366 0.1864 2.6 2.2
6 7 0.3811 0.1941 40.4 30
7 8 0.0922 0.047 75 54
8 9 0.0493 0.0251 30 22
9 10 0.819 0.2707 28 19
10 11 0.1872 0.0691 145 104
11 12 0.7114 0.2351 145 104
12 13 1.03 0.34 8 5.5
13 14 1.044 0.345 8 5.5
14 15 1.058 0.3496 0 0
15 16 0.1966 0.065 45.5 30
16 17 0.3744 0.1238 60 35
17 18 0.0047 0.0016 60 35
18 19 0.3276 0.1083 0 0
19 20 0.2106 0.0696 1 0.6
20 21 0.3416 0.1129 114 81
21 22 0.014 0.0046 5.3 3.5
22 23 0.1591 0.0526 0 0
23 24 0.3463 0.1145 28 20
24 25 0.7488 0.2745 0 0
25 26 0.3089 0.1021 14 10
26 27 0.1732 0.0572 14 10
123
Arab J Sci Eng (2017) 42:2851–2865 2863
Table 9 continued
Bus Line data Bus data
Send Receive Line resistance Line reactance Active load Reactive load
(Ω) (Ω) power (kW) power (kVAr)
123
2864 Arab J Sci Eng (2017) 42:2851–2865
References tems with uncertainty and time varying loads. IET Gen. Trans. Dist.
1, 244–252 (2007)
1. Moradi, M.H.; Zeinalzadeh, A.; Mohammadi, Y.; Abedini, M.: An 19. Huang, S.J.: An immune-based optimization method to capacitor
efficient hybrid method for solving the optimal sitting and sizing placement in a radial distribution system. IEEE Trans. Power Deliv.
problem of DG and shunt capacitor banks simultaneously based 15(2), 744–749 (2000)
on imperialist competitive algorithm and genetic algorithm. Int. J. 20. Sanam, J.; Ganguly, S.: Impact of distribution STATCOM allo-
Electr. Power Energy Syst. 54, 101–111 (2014) cation on radial distribution networks. In: IEEE International
2. Moradi, M.H.; Abedini, M.: A combination of genetic algorithm Conference on Energy, Power and Environment: Towards Sustain-
and particle swarm optimization for optimal DG location and sizing able Growth (ICEPE), pp. 1–6 (June 2015)
in distribution systems. Int. J. Electr. Power Energy Syst. 34(1), 66– 21. Shuaib, Y.M.; Kalavathi, M.S.; Rajan, C.C.A.: Optimal capacitor
74 (2012) placement in radial distribution system using gravitational search
3. Naderi, E.; Seifi, H.; Sepasian, S.M.: A dynamic approach for dis- algorithm. Int. J. Electr. Power Energy Syst. 64, 384–397 (2015)
tribution system planning considering distributed generation. IEEE 22. Eldery, M.A.; El-Saadany, E.F.; Salama, M.M.A.: Effect of dis-
Trans. Power Deliv. 27(3), 1313–1322 (2012) tributed generator on the allocation D-STATCOM in distribution
4. Shuaib, Y.N.; Kalavathi, M.S.; Rajan, C.C.A.: Optimal capacitor network. In: Power Engineering Society IEEE General Meeting,
placement in radial distribution system using gravitational search pp. 2360–2364 (2005)
algorithm. Int. J. Electr. Power Energy Syst. 64, 384–397 (2015) 23. Devi, S.; Geethanjali, M.: Optimal location and sizing determi-
5. Sultana, S.; Roy, P.K.: Optimal capacitor placement in radial dis- nation of distributed generation and DSTATCOM using particle
tribution systems using teaching learning based optimization. Int. swarm optimization algorithm. Int. J. Electr. Power Energy Syst.
J. Electr. Power Energy Syst. 54, 387–398 (2014) 62, 562–570 (2014)
6. Georgilakis, P.S.; Hatziargyriou, N.D.: A review of power distribu- 24. Tolabi, H.B.; Ali, M.H.; Rizwan, M.: Simultaneous reconfigura-
tion planning in the modern power systems era: models, methods tion optimal placement of DSTATCOM and photovoltaic array in
and future research. Electr. Power Syst. Res. 121, 89–100 (2015) a distribution system based on fuzzy-ACO approach. IEEE Trans.
7. Ganguly, S.; Sahoo, N.C.; Das, D.: Multi-objective planning of Sustain. Energy 6(1), 210–218 (2015)
electrical distribution systems using dynamic programming. Int. J. 25. Jazebi, S.; Hosseinian, S.H.; Vahidi, B.: DSTATCOM alloca-
Electr. Power Energy Syst. 46, 65–78 (2013) tion in distribution networks considering reconfiguration using
8. Hung, D.Q.; Mithulananthan, N.; Bansal, R.C.: An optimal invest- differential evolution algorithm. Energy Convers. Manag. 52(7),
ment planning framework for multiple distributed generation units 2777–2783 (2011)
in industrial distribution systems. Appl. Energy 124, 62–72 (2014) 26. Sanam, J.; Panda, A.K.; Ganguly, S.: Optimal phase angle injection
9. Niknam, T.; Taheri, S.I.; Aghaei, J.; Tabatabaei, S.; Nayeripour, for reactive power compensation of distribution systems with the
M.: A modified honey bee mating optimization algorithm for mul- allocation of multiple distribution STATCOM. Arab. J. Sci. Eng.
tiobjective placement of renewable energy resources. Appl. Energy 1–9 (2016)
88(12), 4817–4830 (2011) 27. Taher, S.A.; Afsari, S.A.: Optimal location and sizing of DSTAT-
10. Soroudi, A.; Ehsan, M.; Zareipour, H.: A practical eco- COM in distribution systems by immune algorithm. Int. J. Electr.
environmental distribution network planning model including fuel Power Energy Syst. 60, 34–44 (2014)
cells and non-renewable distributed energy resources. Renew. 28. Hsieh, S.C.: Economic evaluation of the hybrid enhancing scheme
Energy 36(1), 179–188 (2011) with DSTATCOM and active power curtailment for PV penetration
11. Kucuksari, S.; Khaleghi, A.M.; Hamidi, M.; Zhang, Y.; Szi- in taipower distribution systems. IEEE Trans. Ind. Appl. 51(3),
darovszky, F.; Bayraksan, G.; Son, Y.J.: An integrated GIS, 1953–1961 (2015)
optimization and simulation framework for optimal PV size and 29. Das, S.; Suganthan, P.N.: Differential evolution: a survey of the
location in campus area environments. Appl. Energy 113, 1601– state-of-the-art. IEEE Trans. Evolut. Comput. 15(1), 4–31 (2011)
1613 (2014) 30. Varadarajan, M.; Swarup, K.S.: Differential evolutionary algorithm
12. Hung, D.Q.; Mithulananthan, N.: Multiple distributed generator for optimal reactive power dispatch. Int. J. Electr. Power Energy
placement in primary distribution networks for loss reduction. Syst. 30(8), 435–441 (2008)
IEEE Trans. Ind. Electron. 60(4), 1700–1708 (2013) 31. Sanam, J.; Ganguly, S.; Panda, A.K.: Placement of DSTATCOM in
13. Georgilakis, P.S.; Hatziargyriou, N.D.: Optimal distributed gener- radial distribution systems for the compensation of reactive power.
ation placement in power distribution networks: models, methods, In: IEEE PES Intl. Conf on Innovative Smart Grid Technologies-
and future research. IEEE Trans. Power Syst. 28(3), 3420–3428 Asia (ISGT ASIA), pp. 1–6 (2015)
(2013) 32. Sajjadi, S.M.; Haghifam, M.R.; Salehi, J.: Simultaneous placement
14. Li, W.; Joos, G.; Belanger, J.: Real-time simulation of a wind tur- of distributed generation and capacitors in distribution networks
bine generator coupled with a battery supercapacitor energy storage considering voltage stability index. Int. J. Electr. Power Energy
system. IEEE Trans. Ind. Electron. 57(4), 1137–1145 (2010) Syst. 46, 366–375 (2013)
15. Pigazo, A.; Liserre, M.; Mastromauro, R.A.; Moreno, V.M.; 33. Ganguly, S.: Multi-objective planning for reactive power compen-
Dell’Aquila, A.: Wavelet-based islanding detection in grid- sation of radial distribution networks with unified power quality
connected PV systems. IEEE Trans. Ind. Electron. 56(11), 4445– conditioner allocation using particle swarm optimization. IEEE
4455 (2009) Trans. Power Syst. 29(4), 1801–1810 (2014)
16. Xu, Y.; Dong, Z.Y.; Wong, K.P.; Liu, E.; Yue, B.: Optimal capacitor 34. Gitizadeh, M.; Vahed, A.A.; Aghaei, J.: Multistage distribution-
placement to distribution transformers for power loss reduction in system expansion planning considering distributed generation
radial distribution systems. IEEE Trans. Power Syst. 28(4), 4072– usinghybrid evolutionary algorithms. Appl. Energy 101, 655–666
4079 (2013) (2013)
17. Chiou, J.P.; Chang, C.F.; Su, C.T.: Ant direction hybrid differential 35. Raju, M.R.; Murthy, K.V.S.R.; Ravindra, K.: Direct search algo-
evolution for solving large capacitor placement problems. IEEE rithm for capacitive compensation in radial distribution systems.
Trans. Power Syst. 19(4), 1794–1800 (2004) Int. J. Electr. Power Energy Syst. 42(1), 24–30 (2012)
18. Haghifam, M.R.; Malik, O.P.: Genetic algorithm-based approach 36. Sundhararajan, S.; Pahwa, A.: Optimal selection of capacitors for
for fixed and switchable capacitors placement in distribution sys- radial distribution systems using a genetic algorithm. IEEE Trans.
Power Syst. 9(3), 1499–1507 (1994)
123
Arab J Sci Eng (2017) 42:2851–2865 2865
37. Savier, J.S.; Das, D.: Energy loss allocation in radial distribution 38. Jeynes, P.H.: Present worth, or the time cost of money, as a factor in
systems: a comparison of practical algorithms. IEEE Trans. Power the economic comparison of alternative facilities. Trans. Am. Inst.
Deliv. 24(1), 260–267 (2009) Electr. Eng. 70(2), 1956–1962 (1951)
123