Professional Documents
Culture Documents
Method Statment of Installation and Testing of STP
Method Statment of Installation and Testing of STP
2. PURPOSE ............................................................................................................................................... 3
3. DEFINITIONS ..................................................................................................................................... 3
4. REFERENCES ....................................................................................................................................... 3
5. RESPONSIBILITIES ......................................................................................................................... 4
7. HSE .......................................................................................................................................................... 7
9.2 INSTALLATION PROCEDURE PIEPS FITTING AND VALVES OF STP SYSTEM: ... 10
• Resources to be used.
• Work procedure for installation of Sewage Treatment Plant.
• Handling and storage of materials.
• Responsibility.
• Risk Assessment.
• Inspection and test plan.
• Inspection checklist.
2. PURPOSE
Sewage treatment plant is one of the most distinctive projects, as it is unique in design and concept,
the purpose of this Method Statement is to describe the details of activities involved for installation
and Testing of the STP at STC SQUARE Project.
3. DEFINITIONS
4. REFERENCES
• Will ensure that the installation of activities is carried out according to the final approved
shop drawings, specifications, manufacturer recommendation, MS and MIR.
• Promote a culture in which HSE are the prime concern that shall never be compromised.
• Provide resources to eliminate hazards and improve safety.
• Shall monitor and review the overall project HSE performance and implement timely
mitigation and corrective action(s).
• Promote the involvement of all employees in improving HSE performance
• Ensure that safe systems of work are defined and documented, and that hazard analysis and
risk control methods have been incorporated during the preparation.
• Will go through the project scope of work such as final approved shop drawings,
specification, Quality Plans.
• Will supervise site mobilization and demobilization for each and every activity under his /
her control
• Will formulate work breakdown structure and document sub-contractor package including
estimates of man hours.
• Will oversee and administer Forman’s daily report to ensure direct labour efficiency.
• Will ensure periodic reports are transmitted to Project Leader.
• Will track and report material delivery.
• Will ensure SAFETY requirements are maintained?
• Will co-ordinate with sub-contractor to ensure interface problem are avoided and maximum
Quality work achieved.
• Will prepare and control inspection requests, ITPs, method statements, risk assessment,
check sheets and any other quality requirements in conjunction with the project quality
representative (QA/QC Engineers & Managers).
• Will ensure that the requirements of the Quality Procedures and followed and adhered to it.
• Will assist supervisors and managers to allocate correct resource to activities and to review
and report on the same.
• Ensure that site personnel are aware of requirements and that works are carried out as per
project’s requirements. They are responsible for the implementation of related QA/QC
activities as detailed in relevant QCP’s and ITP’s. They will also coordinate with site team
and store if the materials are delivered to site as per approved material and manufacturer
recommendation.
• Promote a culture in which health, safety and the environment are the prime concern and
shall never be compromised.
• Review the ITPs for each activity along with method statement, to verify the compliance to
Project requirements. Ensure the subcontractors are adhering to their ITP and inspections
are raised accordingly.
• Conduct day to day site surveillance, identify, record and communicate the deficiencies to
team to avoid reoccurrence.
• Conduct work inspections in co-ordination with subcontractor, site engineers and
consultant to verify the compliance to drawings and specifications, ensure the records are
maintained.
• Coordinate and Conduct Material inspections with subcontractors and Consultant to verify
the compliance to the specifications. Ensure all rejected materials from internal and
consultant inspections are tagged and removed from the site.
• Conduct subcontractor/supplier factory/fabrication yard inspections as per QA QC Manager
Instruction to verify the compliance with project requirements and communicate the
observations to project team.
• Coordinate with subcontractor, site engineers and Consultant and ensure all the inspections
are conducted as per approved ITP and ensure the records are maintained.
• Conduct internal verification/inspections for the implementation of corrective and
preventive actions for the site NCRs and deficiencies identified by the QA QC Team. Verify
the effectiveness of corrective and preventive actions.
• Analyse the status of QA QC activities, prepare the trends including submittals, inspections,
tests, deficiencies identified & NCRs and communicate to QA QC Manager/Project team.
6. EQUIPMENT & MATERIALS
The following tools and equipment should be used during handling, shifting, installation and
workmanship of the Installation activities.
Note: The type and quantities of equipment are subject to change to suit the site
requirements.
6.2. Materials
• CS Tanks
• Air blowers
• Bar screen
• Dewatering system
• Filtration and circulation pumps.
• Chemical system.
• Valves.
• Pipes
• Control Panel and SCADA system
• Electrical Cables and Conduits.
• Supports.
• Supervisor / Foreman.
• Plumbers.
• Operators.
• Drivers.
• Skilled and unskilled labour.
7. HSE
• STP shall comply with all the necessary mitigation measures against potential hazards in
order to reduce or eliminate the risks that are stated in Risk Assessment Analysis.
• Daily site inspections before work commences should be carried out to look for
indications of any situation that could result in indications of failure of protective
systems.
• Will ensure implementation of all safety procedures and precautions, safety measures
related to the nature of works being carried out and in accordance to the HSE Plan.
9. INSTALLATION PROCEDURE:
• Ensure that all the materials are received & inspected at store and are available to carry
out the work.
• All Equipment and material related to STP system components will be visually inspected
to ensure that no damage has occurred during storage and handling.
• Prior to Commencement of work, areas and access will be inspected to confirm that Site
is safe and ready to commence the work.
• All relevant documentation (shop drawings, material submittal & method statement)
and materials applicable to particular area of works will be checked by site supervisor
prior to commencement of work.
• The subcontractor Site Supervisor will give necessary instructions to tradesmen and
provide necessary approved shop drawings of latest revision.
• The Site Supervisor/Foremen will also check that proper tools and equipment are
available to carry out the work and are in compliance with contract specification. List of
tools is included as part of this method statement.
• The Site Supervisor and safety officer will explain to the tradesmen regarding safety
precautions to be observed.
9.2 INSTALLATION PROCEDURE PIEPS FITTING AND
VALVES OF STP system:
Trench Preparation:
1. Mark the route of pipe for the water supply pipe as per approved shop drawing.
2. Excavation for the trench to be done to the depth indicated or required as per approved shop drawing.
3. Carry the depth of trenches for pipes to below the invert elevations as required for pipe bedding or other
supports.
4. Safe Removal of the excavated materials.
5. Preparation of required formation level as per the pipe requirement.
6. provide adequate working space on its sides and is approved by the Engineer as the maximum
permissible width for this part of the trench.
1. As per approved civil drawings, all routes shall be marked carefully from the reference point benchmark
on permanent structure provided by surveyor and routes shall be reconfirmed with other MEP services.
2. Co-ordination with other discipline will be carried out while marking the route of piping, any interference
may appear due to changed locations and elevations of piping shall be discussed to obtain approval.
3. Joint pipes and fittings to the required length and joining procedure shall be as per manufacturer’s
recommendations and Specification.
4. It has to be made sure that pipes are straight prior to installation.
5. Pipe Fittings for Solvent Weld Jointing (Bend, Elbow, Tee, Union, Flanges, Socket, Reducing Bush).
6. Bends can be supplied with a choice of end configuration to match the pipe joining range chosen for the
installation. Where the direction of flow is changed, bends and elbows are used.
7. Couplings are intended for use with plain ended pipe lengths. Couplings of approved materials shall be
provided for connecting the pipes.
8. Ensure and confirm the Cut pipe ends shall be clean, and free from distortion of the pipes to be
connected with fittings.
Where the size of the pipeline is reduced, the reducing bushes are used.
• It shall be ensured that concrete bases have been prepared by Civil Team as per specification and approved
shop drawing.
• It shall be ensured that concrete bases are flat, free from visible damages.
• It shall be ensured that concrete bases have been prepared by civil team as per specification and approved
shop drawing.
• Tanks shall be placed in correct location on concrete base and all connection shall be completed as per
approved shop drawing.
• As per approved drawings each equipment will be transferred safely to its position.
• Control panel to be inspected and tested in prior of any terminations.
• All wires will be routed as per the approved drawings.
• All pipes shall be tested hydrostatically in sections by plugging the ends with end plug.
• No vertical loop shall be provided.
• Site Engineer shall ensure that all valves and equipment are isolated during the testing.
• Test Pressure shall be applied gradually to reach pressure as per project specifications.
• The inspection shall be raised for Client’s witness and approval.
• Upon completion of installation works, identification stickers shall be provided in all the
system.
• Raise WIR for inspection of Identification to Consultant Engineers. (by contractor).
• Ensure that all the pre-commissioning checks are carried out successfully.
• The STP system shall be completed & tested for proper sequence of operation.
• Commissioning checklists to be filled and approved.
15. APPENDICES
HSE Risk Assessment.
Checklists