Alappuzha Panchakarma Estimate
Alappuzha Panchakarma Estimate
Paravur Municipality
DR
PANCHAKARMA AYURVEDA HODPITAL
Detailed Estimate
AF
Sl No Description No L B D CF Quantity Remark
1 300mm dia
1 26.28.1
Chipping of unsound/weak concrete material from slabs, beams, columns etc.with manual Chisel and/ or
T
by standard power driven percussion type or ofapproved make including tapering of all edges, making
square shoulders ofcavities including cleaning the exposed concrete surface and reinforcementwith wire
brushes etc. and disposal of debris for all lead and lifts all completeas per direction of Engineer-In-
Charge75mm average thickness
2 26.29.1
Cleaning of reinforcement from rust from the reinforcing bars to give it a totalrust free steel surface by
using alkaline chemical rust remover of approvedmake with paint brush and removing loose particles
after 24 hours of itsapplication with wire brush and thoroughly washing with water and allowingit to dry, all
complete as per direction of Engineer-In-Charge.Bars upto 12 mm diameter
8# 39 0.780 30.420
3 od1148208/2021_2022
Applying a coat of passivating / bond coat Zink ZR or like over the old new reinforcement
1 70.000 70.000
4 26.31.2
Providing, mixing and applying bonding coat of approved adhesive on chippedportion of RCC as per
DR
specifications and direction of Engineer-In-chargecomplete in all respect.Epoxy bonding adhesive having
coverage 2.20 sqm/kg of approved make
1 4.800 0.590
Total Quantity
2.832
2.832 sqm
2.832 sqm
Rs 1230.25
T
5 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and
binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
1 60.000 60.000
6 od1148103/2021_2022
Providing and laying Reinforced cement concrete for construction of column, at all locations with
specified grade using Ordinary
Portland Cement (conforming to strength requirement of IS:8112) including the
cost of steel centering and shuttering etc. complete including testing of materials
etc. for casting pier & pier cap in one/two stage, necessary tools, plants, machinery
and all related operations as required to complete the work as per drawings and
Specifications with all leads, lifts and depths true to level and position but excluding
the cost of providing reinforcement. Reinforcement shall be measured and paid
separately. Cement content considered in this item is 480 kg/cum. Excess/less
cement used as per design mix is payable/recoverable separately.
Reinforced Cement Concrete M60.
15 15.000
2 300*600mm column
1 26.28.1
DR
Chipping of unsound/weak concrete material from slabs, beams, columns etc.with manual Chisel and/ or
by standard power driven percussion type or ofapproved make including tapering of all edges, making
square shoulders ofcavities including cleaning the exposed concrete surface and reinforcementwith wire
brushes etc. and disposal of debris for all lead and lifts all completeas per direction of Engineer-In-
Charge75mm average thickness
AF
4.800 1.800
Total Quantity
8.640 sqm
0.000 sqm
T
Net Total Quantity 8.640 sqm
2 26.29.1
Cleaning of reinforcement from rust from the reinforcing bars to give it a totalrust free steel surface by
using alkaline chemical rust remover of approvedmake with paint brush and removing loose particles
after 24 hours of itsapplication with wire brush and thoroughly washing with water and allowingit to dry, all
complete as per direction of Engineer-In-Charge.Bars upto 12 mm diameter
8# 39 1.500 58.500
3 26.31.2
Providing, mixing and applying bonding coat of approved adhesive on chippedportion of RCC as per
specifications and direction of Engineer-In-chargecomplete in all respect.Epoxy bonding adhesive having
coverage 2.20 sqm/kg of approved make
4 od1148208/2021_2022
Applying a coat of passivating / bond coat Zink ZR or like over the old new reinforcement
1 115.000 115.000
5 5.22.6
DR
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and
binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
1 80.000 80.000
AF Total Quantity
0.000 kilogram
80.000 kilogram
T
Say80.000 kilogram @ Rs 78.07 / kilogram Rs 6245.60
6 od1148103/2021_2022
Providing and laying Reinforced cement concrete for construction of column, at all locations with
specified grade using Ordinary
Portland Cement (conforming to strength requirement of IS:8112) including the
cost of steel centering and shuttering etc. complete including testing of materials
etc. for casting pier & pier cap in one/two stage, necessary tools, plants, machinery
and all related operations as required to complete the work as per drawings and
Specifications with all leads, lifts and depths true to level and position but excluding
the cost of providing reinforcement. Reinforcement shall be measured and paid
separately. Cement content considered in this item is 480 kg/cum. Excess/less
cement used as per design mix is payable/recoverable separately.
Reinforced Cement Concrete M60.
23 23.000
1 26.28.1
Chipping of unsound/weak concrete material from slabs, beams, columns etc.with manual Chisel and/ or
by standard power driven percussion type or ofapproved make including tapering of all edges, making
square shoulders ofcavities including cleaning the exposed concrete surface and reinforcementwith wire
brushes etc. and disposal of debris for all lead and lifts all completeas per direction of Engineer-In-
Charge75mm average thickness
2 26.29.1
DR
Cleaning of reinforcement from rust from the reinforcing bars to give it a totalrust free steel surface by
using alkaline chemical rust remover of approvedmake with paint brush and removing loose particles
after 24 hours of itsapplication with wire brush and thoroughly washing with water and allowingit to dry, all
AF
complete as per direction of Engineer-In-Charge.Bars upto 12 mm diameter
8# 39 1.578 61.542
3 26.31.1
T
Total Deducted Quantity
138.342 metre
Rs 791.32
Providing, mixing and applying bonding coat of approved adhesive on chippedportion of RCC as per
specifications and direction of Engineer-In-chargecomplete in all respect.SBR Polymer (@10% of cement
weight) modified cementitious bond coat @2.2kg cement per sqm of surface area mixed with specified
proportion of approvedpolymer
4 od1148208/2021_2022
Applying a coat of passivating / bond coat Zink ZR or like over the old new reinforcement
1 140.000 140.000
5 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and
binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
1 80.000 80.000
DR
od1148103/2021_2022
Providing and laying Reinforced cement concrete for construction of column, at all locations with
specified grade using Ordinary
Portland Cement (conforming to strength requirement of IS:8112) including the
AF
cost of steel centering and shuttering etc. complete including testing of materials
etc. for casting pier & pier cap in one/two stage, necessary tools, plants, machinery
and all related operations as required to complete the work as per drawings and
Specifications with all leads, lifts and depths true to level and position but excluding
the cost of providing reinforcement. Reinforcement shall be measured and paid
T
separately. Cement content considered in this item is 480 kg/cum. Excess/less
cement used as per design mix is payable/recoverable separately.
Reinforced Cement Concrete M60.
9 9.000
1 26.28.1
Chipping of unsound/weak concrete material from slabs, beams, columns etc.with manual Chisel and/ or
by standard power driven percussion type or ofapproved make including tapering of all edges, making
square shoulders ofcavities including cleaning the exposed concrete surface and reinforcementwith wire
brushes etc. and disposal of debris for all lead and lifts all completeas per direction of Engineer-In-
Charge75mm average thickness
2 26.29.1
Cleaning of reinforcement from rust from the reinforcing bars to give it a totalrust free steel surface by
using alkaline chemical rust remover of approvedmake with paint brush and removing loose particles
after 24 hours of itsapplication with wire brush and thoroughly washing with water and allowingit to dry, all
complete as per direction of Engineer-In-Charge.Bars upto 12 mm diameter
8# 39 3.438 134.082
3 26.31.1
DR Net Total Quantity
Rs 1206.25
AF
Providing, mixing and applying bonding coat of approved adhesive on chippedportion of RCC as per
specifications and direction of Engineer-In-chargecomplete in all respect.SBR Polymer (@10% of cement
weight) modified cementitious bond coat @2.2kg cement per sqm of surface area mixed with specified
proportion of approvedpolymer
2*(0.188+
T
1 4.800 10.330
0.888)
4 od1148208/2021_2022
Applying a coat of passivating / bond coat Zink ZR or like over the old new reinforcement
1 212.000 212.000
5 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and
binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
1 94.000 94.000
6 od1148103/2021_2022
Providing and laying Reinforced cement concrete for construction of column, at all locations with
specified grade using Ordinary
Portland Cement (conforming to strength requirement of IS:8112) including the
cost of steel centering and shuttering etc. complete including testing of materials
etc. for casting pier & pier cap in one/two stage, necessary tools, plants, machinery
and all related operations as required to complete the work as per drawings and
Specifications with all leads, lifts and depths true to level and position but excluding
the cost of providing reinforcement. Reinforcement shall be measured and paid
DR
cement used as per design mix is payable/recoverable separately.
Reinforced Cement Concrete M60.
Total Quantity
3.000
3.000 each
3.000 each
Rs 45054.60
T
Sl No Description No L B D CF Quantity Remark
1 26.28.2
Chipping of unsound/weak concrete material from slabs, beams, columns etc.with manual Chisel and/ or
by standard power driven percussion type or ofapproved make including tapering of all edges, making
square shoulders ofcavities including cleaning the exposed concrete surface and reinforcementwith wire
brushes etc. and disposal of debris for all lead and lifts all completeas per direction of Engineer-In-
Charge50mm average thickness
(.609+.159
1 6.170 7.756
+.489)
2 26.29.1
Cleaning of reinforcement from rust from the reinforcing bars to give it a totalrust free steel surface by
using alkaline chemical rust remover of approvedmake with paint brush and removing loose particles
after 24 hours of itsapplication with wire brush and thoroughly washing with water and allowingit to dry, all
complete as per direction of Engineer-In-Charge.Bars upto 12 mm diameter
16 # 3 6.170 18.510
(.158+.629
8# 50 64.800
+.509)
3 26.31.1
Providing, mixing and applying bonding coat of approved adhesive on chippedportion of RCC as per
specifications and direction of Engineer-In-chargecomplete in all respect.SBR Polymer (@10% of cement
weight) modified cementitious bond coat @2.2kg cement per sqm of surface area mixed with specified
proportion of approvedpolymer
DR 1 6.170
(.118+.568
+.448)
Total Quantity
6.997
6.997 sqm
AF
Total Deducted Quantity 0.000 sqm
4 od1148208/2021_2022
T
Applying a coat of passivating / bond coat Zink ZR or like over the old new reinforcement
1 85.000 85.000
5 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and
binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
1 50.000 50.000
6 od1148313/2021_2022
Drilling suitable hole in reinforced or plain cement concrete with power driven drill machine to a minimum
depth of 100 mm up to 200mm in RCC beams, lintles, columns and slab to introduce steel bars for
sunshade / balconies including fixing the steel bar in position using expoxy resin anchor grout of
approved make but excluding the cost of reinforcement, all complete as per direction of Engineering - in-
charge
56 56.000
7 5.9.5
Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams,
girders bressumers and cantilevers
DR Total Quantity
0.000 sqm
8.984 sqm
AF
Say8.984 sqm @ Rs 472.96 / sqm Rs 4249.07
8 od1148314/2021_2022
OD Micro concreting using high strength non-shrink, pourable / pumpable grout with 10mm down size
T
aggregate with water binder ratio 0.135
5 5.000
1 26.28.2
Chipping of unsound/weak concrete material from slabs, beams, columns etc.with manual Chisel and/ or
by standard power driven percussion type or ofapproved make including tapering of all edges, making
square shoulders ofcavities including cleaning the exposed concrete surface and reinforcementwith wire
brushes etc. and disposal of debris for all lead and lifts all completeas per direction of Engineer-In-
Charge50mm average thickness
(.11+.635
1 7.206 9.945
+.635)
2 26.29.1
Cleaning of reinforcement from rust from the reinforcing bars to give it a totalrust free steel surface by
using alkaline chemical rust remover of approvedmake with paint brush and removing loose particles
after 24 hours of itsapplication with wire brush and thoroughly washing with water and allowingit to dry, all
complete as per direction of Engineer-In-Charge.Bars upto 12 mm diameter
(.158+(2*.
8# 58 82.128
629))
3 26.31.1
DR Net Total Quantity
Rs 593.43
AF
Providing, mixing and applying bonding coat of approved adhesive on chippedportion of RCC as per
specifications and direction of Engineer-In-chargecomplete in all respect.SBR Polymer (@10% of cement
weight) modified cementitious bond coat @2.2kg cement per sqm of surface area mixed with specified
proportion of approvedpolymer
(.118+(2*.
T
1 7.206 11.444
735))
4 od1148208/2021_2022
Applying a coat of passivating / bond coat Zink ZR or like over the old new reinforcement
1 108.000 108.000
5 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and
binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
1 83.000 83.000
6 od1148313/2021_2022
Drilling suitable hole in reinforced or plain cement concrete with power driven drill machine to a minimum
depth of 100 mm up to 200mm in RCC beams, lintles, columns and slab to introduce steel bars for
sunshade / balconies including fixing the steel bar in position using expoxy resin anchor grout of
approved make but excluding the cost of reinforcement, all complete as per direction of Engineering - in-
charge
64.000 each
Rs 24336.00
AF
7 5.9.5
Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams,
girders bressumers and cantilevers
7.206*(.23
1 11.674
T
+(2*.695))
8 od1148314/2021_2022
OD Micro concreting using high strength non-shrink, pourable / pumpable grout with 10mm down size
aggregate with water binder ratio 0.135
Total Rs 1547326.03
TOTAL Rs 1547326.03
Rupees Fifteen Lakh Forty Seven Thousand Three Hundred and Twenty Six Only