VD-LINE-WP57-SUB-ATM-0001-017 - ERECTION AND INSTALLATION PROCEDURE ATM TANK - Rev.1

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 18

PAGES 1 OF 18

DOC NO. VD-LINE-WP57-SUB-ATM-0001-017

JOB NO. 15005

Document Title :

ERECTION & INSTALLATION PROCEDURE


(ATM TANK)

PROJECT NAME : LINE PROJECT

CLIENT : PT LOTTE CHEMICAL INDONESIA

LOCATION : CILEGON, INDONESIA

P.O NO. : LINE-WP5&7-SUB-ATM-001-01

VENDOR DATA STATUS


1 : APPROVED
2 : APPROVED AS NOTED
3 : WITH COMMENTS
4 : REJECTED

NOTE: Permission to proceed does not constitute


acceptance of approval of design details,
calculations, analysis, test methods or materials
developed/selected by the Contractor and does not
relieve the Contractor from full compliance with
contractual obligations.

Review Date: . . .
Engineer Lead Engineer
S.H. OH C.S. BANG

1 8-Mar-23 ISSUED FOR CONSTRUCTION M.M. SON H.G. LEE I.R. JUNG

0 26-Dec-22 ISSUED FOR CONSTRUCTION M.M. SON H.G. LEE I.R. JUNG

A 20-Dec-22 ISSUED FOR APPROVAL M.M. SON H.G. LEE I.R. JUNG

REV. DATE DESCRIPTION PREPARED CHECKED APPROVED


Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 2 of 18

REVISION HISTORY
Rev. Date Description Page

A 15 Dec 2022 Issued for Approval -

0 26 Dec 2022 Revised as per Client Comment 1,2,4,6,7,11,15,17,18

1 08 Mar 2023 Revised as per Client Comment 7,8,9,10


Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 3 of 18

CONTENTS

1. GENERAL .................................................................................. 4

2. RELATED DOCUMENTS ............................................................ 4

3. SEQUENCE OF TANK ERECTION ............................................... 5

4. FOUNDATION WORK ............................................................... 5

5. BOTTOM .................................................................................. 6

6. SHELL ....................................................................................... 11

7. TOP ANGLE, WIND STIFFENER ................................................. 14

8. ROOF........................................................................................ 14

9. TEMPORARY ATTACHMENTS................................................... 16

10. INSPECTION ............................................................................. 17

11. PWHT ....................................................................................... 17

12. HYDROSTATIC TEST ................................................................. 17

13. PAINTING WORKS .................................................................... 17

14. SAFETY ..................................................................................... 17


Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 4 of 18

1. GENERAL
1.1. This procedure is applied to the field erection requirements for the Cone Roof Tank (CRT) and
Internal Floating Cone Roof Tank (IFRT) for the following articles.
1.2. Project: LINE (Lotte Chemical Indonesia New Ethylene Complex) Project.

2. RELATED DOCUMENTS
2.1 Standard and Codes
1) API Standard 650 12th Ed., 2021 Welded Tanks for Oil Storage
2) ASME Section V, 2021 Ed. Nondestructive Examination
3) ASME Section IX, 2021 Ed. Welding and Brazing Qualifications
4) ASME Section II, 2021 Ed. Material

2.2 Procedure
1) WPS/PQR (ATM TANK) (VD-LINE-WP57-SUB-ATM-0001-008)
2) SURFACE PREPARATION & PAINTING PROCEDURE (VD-LINE-WP57-SUB-ATM-0001-011)
3) INSPECTION AND TEST PLAN FOR ATM TANK (LINE-000-QB-4-0017)
4) ATM TANK INSPECTION AND TEST PROCEDURE (LINE-000-QA-4-0018)
5) HYDROSTATIC TEST PROCEDURE (VD-LINE-WP57-SUB-ATM-0001-007)
6) PWHT (KINE SCOPE)
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 5 of 18

3. SEQUENCE OF TANK ERECTION

4. FOUNDATION WORK
Prior to erection of bottom plates, the following items shall be confirmed by civil contractor.
4.1 Check the center of the foundation.
Stretched out piano chords on the axis (0°-180°) and (90°-270°) and the tank foundation shall
be obtained at the crossing points of the chords.
Marking of the final tank foundation center shall be done after lay down of the bottom center
plate.
4.2 Check the (0°- 180°) axis and the (90°-270°) axis.
Verify (0°-180°) axis and (90°-270°) axis, using transit or measuring chord between axis with
same radius from foundation center.
4.3 Check horizontality and the slope of the foundation surface.
Using automatic level, verify that the foundation has the slope as per construction drawing.
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 6 of 18

Figure 4.1 Level Check Point of Foundation

4.4 Visual inspection of the unevenness of the foundation top surface.


Stretched out piano chords on the axis (0°-180°) and (90°-270°) and visually inspection
uneven top surface.
4.5 Tolerances:
1) Where a concrete ring wall is provided, ±3 mm in any 9m of the circumference and ±6 mm
in the total circumference.
2) Where a concrete ring wall is not provided, ±3 mm in any 3 m of the circumference and
±13 mm in the total circumference.

5. BOTTOM
After foundation has been found to be acceptable as per applicable standards (API 650 para 7.5.5),
annular plate and bottom plate laydown shall be started.
5.1 Shop Cutting
1) Mark dimensional of plate for bottom and annular as per approved drawing and cutting
using cutting machine.
2) After cutting bevel the edge of plate as per approved drawing.
3) Do dimensional inspection of finish cutting bottom and annular plates as per approved
drawing and mark bottom tagging for installation.
4) For annular plates dimension tolerance + 3 mm or follow approved ATM TANK
INSPECTION AND TEST PROCEDURE (LINE-000-QA-4-0018).
5.2 Annular Plates Arrangement
1) From the established marks on the foundation, stretch piano wire along 0°-180°and 90°-
270°axes.
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 7 of 18

2) Mark off the position of annular plates on the foundation, e.g. annular joints and outside
radius of annular.
The last joint of annular plate may be cut in field depend on another joints condition.
Note that the laydown radius of annular plate is larger than the theoretical radius
required due to anticipating for the shrinkage.
The designed diameter plus shrinkage all allowance shall be considered in the laydown.

*N: Total Annular Plate quantity

Figure 5.1 Annular Plate Laydown Radius

3) Lay down the annular plates.


4) Tack welding to keep the correct positions.
5) Arrange the annular plates in accordance with orientation of tank construction drawing.
6) Weld back-up strips to the annular plates before the arrangement of annular plates in
accordance with construction drawing.
7) Weld the outer 250mm of all annular plate joints for backing strip, grind the top and test
according to the Project Inspection & Testing Sequence.
8) Annular plate shall be prevented from distortion when welding work is performed as
shown below;

Figure 5.2 Back-up Strip on Annular Plate

9) Performed NDE shall be conducted on annular plates welds such as:


a. Radiography test as per API 650 para. 8.1.2.9 (Project requirement)
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 8 of 18

5.3 Bottom Plates Arrangement


1) Arrange the bottom plate in accordance with the bottom plate arrangement drawing.
2) Plate lay down shall start from the center of the tank towards the circumference.
3) Set the center plate at the position, straddling the four (4) centerlines. Tack a welding rod
to the center of the plate.
4) Lay the center course plates using another piano chord to keep one edge straight. Tack
lightly to keep in proper position.
5) Lay and tack the remaining rectangular plates lightly.
6) Occasionally check with the centerline to ensure that the plates are running square. A
simple check is to measure from the outside edge to the center pin (welding rod).
7) After all the rectangular bottom plates have been arranged and laid down, these shall be
left free to prevent any distortion. They shall be temporarily fitted with dog plates.

Figure 5.3 Fit up Bottom Plate

8) In dealing with three (3) lap joints of bottom plates and cut off top plate in accordance
with bottom plate drawing. Cutting pattern and fit up of three plates lap joint are shown
below;

Figure 5.4 Cutting Pattern and Fit up of Three Plate Lap Joints

9) When plate corners are cut using flame, pay attention not to damage the plate
underneath.
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 9 of 18

5.4 Bottom Welding


1) Welding sequence is as follows:

7 1 5

6
2

Note; The annular butt joint shall be welded in two (2) stages to minimized distortion of
annular plate itself.

Figure 5.5 Welding Sequence of Bottom Plate and Annular Plate


Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 10 of 18

2) The welding must principally start from the center of the tank toward the circumference.
Refer to the figure below for the welding sequence.

Figure 5.6 Bottom Plate Welding Sequence

① Weld rectangular adjacent bottom plates together. (lengthwise) Before welding the
joint, plates shall be free from tacks.
② Weld the rectangular adjacent bottom plates together. (widthwise)
③ Weld the sketch plates together. (i.e. the adjacent plate side of one sketch plate to
another sketch plate.)
④ Weld sketch plates to bottom plates. This is the final seam.
3) After completing the welding of all outer 250 mm of annular plate joints, erect the first
shell ring course and weld the vertical joints.
4) Fit-up the corner weld joint.
5) Weld the corner weld joint of the shell plate to annual plate.
Use channels as knee braces between shell and annular plates to control the rise of
inside annular plate due to shrinkage. Leave a few places without welding to provide
drainage for rainwater temporarily.

Figure 5.7 Corner Weld Joint of The Shell Plate to Annular Plate
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 11 of 18

6) Finish welding the annular plates together. Examine the first pass as per Project
Inspection & Testing.
7) Fit-up & weld the bottom sketch plates to the annular plates.
8) Prior to start of all welding, the welding joint shall be cleaned using grinding and wire
brush to remove moisture, oil dust, waste and other foreign materials.
9) The bottom plate welding can be performed by either manual welding or machine
welding (FCAW) in accordance with WPS.
10) In case of the tanks for which coating have applied to the inside, weld bead and plate
edges shall be smoothed.
11) After completing all the welding of the bottom plates, inspection shall be carried out as
per approved ITP (LINE-000-QB-4-0017) and procedures (VD-LINE-WP57-SUB-ATM-
0001-017).

6. SHELL
6.1 General Shell Erection Sequence
1) Erect the Shell Course No. 1.
2) Fit-up & Weld the Course No.1 vertical joints.
3) Fit-up & Weld the Corner (Shell to annular) welds joint.
(Can be done after erecting of shell course from No.1 up to top at any time, according
to the site conditions)
4) Erect at least (3) three plates at the same time (Fit-up only) in Course No.2.
5) Fit-up and weld these three plates together (Vertical).
6) Continue erecting, fitting and welding of Course No. 2
7) Fit-up & Weld the horizontal seam.
8) Erect the remaining Courses and weld the same sequence as explained above.

6.2 Shell Plate Erection


1) Make sure that the tank center & four centerlines have been accurately transferred from
the foundation to the bottom plates. Mark these lines by series of center punch marks
about 150mm from edge of bottom.
2) Hook one end of a tape over a weld rod stub welded at the center of the tank. Mark a
circle on the bottom at the radius of the inside of the Course No. 1.
Banding strap with mark same as the bottom radius can be used in marking the tank
inside radius.
3) From the Course No.1 start point shown on the drawing, start to chord off the shell
location. This location will be the centerline of vertical seam. After marking the shell
inside radius, auxiliary reference line shall be drawn 100mm inside the shell circle line
for later shell plate roundness checking.
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 12 of 18

Figure 6.1 Marking of Auxiliary References

4) Tack pair of nuts to the bottom at the minimum spacing of 2500mm on a radius of 20mm
inside and outside shell.

Figure 6.2 Nuts Position

5) Weld all the nuts and temporarily attach the key plate on the shell before erection.
6) Hang the Course using proper lifting equipment with clamp.
7) Set the end of the plate on the previously made punch marks.
8) Plumb plate using long level (at least 2 meters long) and tack channels between the plate
and the bottom to hold it in place.
9) Hang and hook the next plate to the first plate erected. Move the plate in or out as
required to put the other end on the punch mark.
10) Plumb the plate and tack a channel on the leading end and one at the middle sheet to
hold it plumb.
11) As the plates are hung, drive wedge to the nuts at the bottom to round the plate to
proper position.
12) Continue hanging the remaining plates using the same procedure. Hang the plates so
that both ends are on the third points of the next lower plate.
13) Do not fit the horizontal seam past any vertical seam that has not been completely
welded.
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 13 of 18

14) Tolerance
After erection but before welding, first course shell plates roundness, level and
plumbness shall be checked and adjusted to within tolerance shown below;
· Plumbness
- 1/200 of the total tank height, Max. 6mm in any shell
· Levelness
- ±3 mm in any 9 m
- Max. ±6 mm in total circumference
· Shell inside Radius (Difference from the reference marking in radius.)
- Diameter < 12 m : ±13 mm
- 12 m ≤ Diameter < 45 m : ±19 mm
- 45 m ≤ Diameter < 75 m : ±25 mm
- Diameter ≥ 75 m : ±32 mm

Figure 6.3 Inspection Position

6.3 Shell Plate Welding


1) Vertical Joints
a) Before starting welding, it is important that the plate be straight and plumb after it is
fit, which means if the gap varies, the edge must be built up before welding.
b) Check the fit-up with a radius board.
c) Misalignment shall not exceed 10% of the plate thickness or 1.5 mm, whichever is
greater.
d) Weld the joint following the Project Welding Procedure. Complete the weld first on
the side that has no fit-up gadgets on it.
e) The upper courses of shell plate can be erected after completion of lower course
welding, or may be erected successively without completion of lower courses welding
(i.e. spiraling type of erection).
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 14 of 18

2) Horizontal Joints
a) Do not fit the horizontal seam until all the vertical joints of above and below the seams
have been welded completely.
b) Before starting welding, it is important that the plate be straight and plumb after it is
fit, which means if the gap varies, the edge must be built up before welding.
c) Misalignment shall not exceed 20% of the upper plate thickness or 3mm whichever is
the smaller.
d) Due to fabrication error, uneven gap may result. In this case, built up with weld metal
to produce even gap.
e) Fit and tack in the bevel on all beveled round seam.
f) Weld the joint following the Project Welding Procedure.

Figure 6.4 Shell Plate Welding Sequence

g) All before/after PWHT, NDE shall be conducted in accordance with approved ITP and
procedures only for nozzle part tank no. 80-TK-121.

7. TOP ANGLE, WIND STIFFENER


7.1 Before fitting or welding any top angle/wind stiffener, make sure that the shell ring which the
angle attaches is round in accordance with approved drawings.
7.2 Weld the top angle and the wind stiffener in accordance with the WPS.

8. ROOF
8.1 Roof Column Assembly, if any
1) The roof column shall be pre-assembled on the temporary stand, prior to erection in the
tank.
2) The top plate, base plate and required parts shall be installed, also. And the guy wires for
erection shall be provided at the top of columns.
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 15 of 18

Figure 8.1 Leveled Temporary Stand

8.2 Roof Framing Erection & Welding


1) After completion of bottom plate, pre-assembled column shall be erected in the tank
some guy wires, adjusting the position, direction and verticality.
2) Carefully lay out the column circles and mark the locations of the column on the tank
bottom as shown on the construction drawings.
3) Erect the first outer columns and first outer girder with some guy wires.
4) Completely fit and weld the outer span framing before starting intermediate span framing.
Erect, fit and weld the outer rafters.
5) Erect the fit intermediate column and first intermediate girder with some guy wires.
Completely erect and weld the remaining intermediate column and girders.
6) Erect fix and weld the intermediate rafters.
7) Attach the center ring to the center column and stand the center column up with some
guy wires. Erect fix and weld the inner rafters.
8) Install diagonal bracing and then install lateral bracings.
9) After all rafters, diagonal and lateral braces are erected, check the column and re-plumb
if necessary.
10) In order to eliminate any roof plate sag, which exceeds the project required allowable
values, the column length should be adjusted after hydrostatic test.
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 16 of 18

Figure 8.2 Roof Framing Layout

8.3 Roof Plates Erection & Welding


Do not begin roof plate erection until all rafters, gussets, diagonal and lateral braces have been
completely installed and welded in an entire span.
1) Erect sketch plates.
2) Rectangular plates erection can proceed at the same time with the sketch plate erection.
3) After all the roof plates have been erected fit the roof plates.
4) Weld the roof plates.
8.4 Lifting of the Roof Assembly
1) The roof frame assembly is erected by crane.
2) Roof plates are erected by crane when roof frame assembly is placed final position.

9. TEMPORARY ATTACHMENTS
9.1 Holes in plate work, to assist in erection, are not permitted. Lugs, nuts, clamps and other
devices to assist in erection may be attached to the tank plants by welding, nut all such
attachments required only for the purpose of erection shall ultimately be removed and any
noticeable projections of welded metal remaining shall be carefully ground or chipped away.
9.2 Great care shall be exercised to avoid gouging or tearing of plates in the process of removing
attachments. However, when such instances occur, remedial welding shall be restricted to
areas where the depth exceeds 1.5 mm. Shallower area shall be carefully “blended” by grinding
only.
9.3 If, necessary, repair welds shall, on completion be ground smooth (but not necessarily flush
with the plate)
9.4. NDE (PT/MT) after removing temporary attachment.
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 17 of 18

10. INSPECTION
· All Inspections shall be followed in accordance with the approved ATM Tank Inspection
Procedure (LINE-000-QA-4-0018) and Inspection and Test Plan for ATM Tank (LINE-000-QB-4-
0017).
· The inspection records shall be reviewed and signed off by the KINE’s inspector. The records
shall be submitted to KINE as required in applicable project specification.

11. PWHT
· PWHT shall be conducted by CONTRACTOR (KINE) and followed in accordance with the related
code requirement (API 650 para 5.7.4).
· The relevant procedure will be prepared and submitted later by KINE

12. HYDROSTATIC TEST


· The tank shall be filled with tested water as a hydrostatic test medium to verify the load
supporting capability of the foundation, tank structural integrity, and leak tightness.
· Hydrotest procedure (VD-LINE-WP57-SUB-ATM-0001-007) will be prepared and submitted
later.

13. PAINTING WORKS


· Surface Preparation and Painting procedure (VD-LINE-WP57-SUB-ATM-0001-011) will be
prepared and submitted later.

14. SAFETY
· Tank to be internally coated and to be installed with IFR shall be grinded smoothly on welding
seam parts.
· Risk Assessment of all activities associated with this procedure shall be done before starting
any activity.
· Permit to Work shall be obtained prior to commence any activity at site.
· Frequent participation shall be done in the tool box talk by site management (CCM & CM).
· Tank shall be secured by Guy rope against wind, if required.
· Oxy-acetylene/propane gas cylinder shall be secured properly all times at site.
· Cylinder trolley shall be used for carrying of oxy-acetylene/propane gas cylinder and always
keep in vertical position.
· Gas cylinders shall be covered by wet fire blanket to avoid from any ignition source during site
activity.
· Confined space log sheet maintained by confined space hole watcher during working in
confined space.
Doc. No. VD-LINE-WP57-SUB-ATM-0001-017
ERECTION & INSTALLATION PROCEDURE
Rev. No. 1
(ATM TANK) Page 18 of 18

· Confined space hole watcher must be reported to emergency response team, in case any
emergency in confined space.
· Full face shield shall be used for while cutting & grinding.
· All welders shall be used welding mask & dark glass while performing the welding work.
· Fire extinguisher shall be checked periodically and certified.
· All personnel must be mustered under the tent during lightening.
· Radiography source shall be stored in the approved pit constructed at site (If use RT)
· Area shall be cordoned off and warning sign to be posted prior to commence the radiography
work at site.
· Permit to Work must be obtained prior to commence the radiography work at site.
· All construction waste shall be stored in appropriate waste bin and transferred to designated
waste disposal yard.
· All scrap materials shall be stored approximately 40 meters away from the workplace to avoid
from tripping hazard.
· All personnel must be followed local rules & regulations and laws.
· Barricade shall be provided underneath of working at height to avoid falling object from height.
· Area shall be cordoned off while working at height (under the roof) by using of Mobile Scaffold
Tower.
· Daily inspection of trolley wheel break shall be done.
· Unauthorized entry restricted.
· Necessary safety Sign board shall be displayed at work site.
· Chemical using for developing of films shall be reused.
· Equipment and Personnel shall be deployed as per requirement.
· All instruments/equipment shall be maintained in good working condition as per maintenance
schedule.
· Radiography shall be done at lean time. Nobody shall be allowed to work nearby during
radiography.
· All workmen, supervisors and engineers shall use proper personnel protection equipment.
· All employees should follow the HSSE Rules. Full body harness and lifeline will be used while
working at height. Sufficient numbers of Fire Extinguishers will be placed for any fire incident.
· All power tools will be inspected by competent person P&E in-charge approved by HSE
department before use.
· Lifting will be done as per the lifting plan. All necessary precautions shall be taken during lifting
operation.
· Lifting plan shall be prepared by Tank Supervisor consultation with lifting supervisor/foreman,
reviewed by Tank Erection Engineer and approved by Construction Manager and will be
attached with lifting certificate prior to commence the lifting activity at site

You might also like