Doc No: 01A SUBJECT: MC-9 KILN#1, 2, 3&4 CABIN PAC AC DUCT 09/09/2023
REPAIR & MODIFICATION
Rev 00
PROJECT : MC-9 KILN#1, 2, 3&4
Task (Steps) Potential Hazard Who might be Existing Control Responsible Current Risk Additional Control Responsible Final Risk
affected person Con Prob Risk person Cons Prob `
Demonstrate
competency in
performing the task
safely.
Scaffolding inspection to
beconducted. Monthly inspection of
Scaffolding tag system ladders to be conducted.
to be followed.
Scaffolding should be
inspected by certified person.
Tool box talk Training to
workers prior to start work
about ladder use.
Ladder must be
installed on firm & level footing.
Leveling device to be used
if required.
Straight ladder to be tied
on top,
Do not use the top two steps.
During working on
ladder one person should
hold the ladder
Always face the ladder and
hold on with both hands
When climbing up or down.
Monthly inspection of ladders to
be conducted,