KABUYANDA BIDDING Section-VII

PART 2 - WORKS REQUIREMENTS


DOCUMENTS Vol 3 - Specifications

Table of contents

PART 1 – Bidding Procedures

Section I – Instructions to Bidders (ITB)


Section II – Bid Data Sheet (BDS)
Section III – Evaluation and Qualification Criteria
Section IV – Bidding Forms
Section IV – Vol. 2 - Bill of Quantities
Section V – Eligible Countries
Section VI – Fraud and Corruption

PART 2 – Works’ Requirements

Section VII – Vol. 3 - Specifications


Section VII – Vol. 4 – Drawings
Section VII – Vol. 5 - Environmental and Social (ES) requirements

PART 3 – Conditions of Contract and Contract Forms

Section VIII – General Conditions (GC)


Section IX – Particular Conditions (PC)
Section X – Contract Forms

_______________________________________________________________________________
1
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

PART 2
WORKS REQUIREMENTS

_______________________________________________________________________________
2
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

Section VII
Volume -3: Specifications

_______________________________________________________________________________
3
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

Section VII – Volume-3: Specifications


Contents

1 PREAMBLE TO THE TECHNICAL SPECIFICATIONS....................................................................................14


1.1 GENERAL .......................................................................................................................................... 14

1.2 SUBMITTAL ...................................................................................................................................... 14


1.3 STANDARDS AND CODES ................................................................................................................. 14
1.3.1 GENERAL ...................................................................................................................................14
1.3.2 NATIONAL STANDARDS, CODES, LAWS AND REGULATIONS .....................................................15
1.3.3 INTERNATIONAL STANDARDS AND CODES ...............................................................................15
1.3.4 SYSTEM OF UNITS .....................................................................................................................15
1.4 DEFINITION OF TIME AND KEY DATES ..............................................................................................16

2 SAFETY PRECAUTIONS ............................................................................................................................17


2.1 SAFETY PROGRAM AND ITS IMPLEMENTATION................................................................................17
2.2 SAFETY STANDARDS ..........................................................................................................................17

2.3 PERSONAL SAFETY EQUIPMENT .......................................................................................................17


2.4 RESCUE TEAM ...................................................................................................................................18

2.5 ILLUMINATION AND EARTHING ........................................................................................................18


2.5.1 ILLUMINATION ..........................................................................................................................18
2.5.2 EARTHING, WET WORK AREAS, CONTROL OF ELECTRIC DISCHARGES .....................................18
2.5.3 MAINTENANCE OF TRAFFIC AND SAFETY ON PUBLIC ROADS ..................................................18
2.6 STORAGE AND TRANSPORT OF EXPLOSIVES .................................................................................... 19
2.7 BLASTING ......................................................................................................................................... 19
2.8 FIRE PRECAUTIONS .......................................................................................................................... 20
2.9 DUST ABATEMENT ........................................................................................................................... 20
2.10 POLLUTION OF STREAMS AND RIVERS ........................................................................................ 20

2.11 NOISE DUE TO CONSTRUCTION ACTIVITIES................................................................................. 20


2.12 LOCAL COMMUNITIES AND RELIGIOUS CUSTOMS ...................................................................... 21
2.13 VEGETATION AND WILDLIFE ........................................................................................................ 21

2.14 FINDINGS OF ARCHEOLOGICAL, HISTORICAL OR CULTURAL INTEREST ....................................... 21


2.15 ESHS RISKS AND IMPLEMENTATION PLANS ................................................................................. 21
2.16 MEASUREMENT AND PAYMENT .................................................................................................. 22
3 SURVEYING, SETTING-OUT WORK AND CONSTRUCTION DRAWINGS ...................................................23

3.1 SCOPE OF WORKS ............................................................................................................................ 23


_______________________________________________________________________________
4
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

3.2 SUBMITTALS..................................................................................................................................... 23
3.3 GROUND CONTROL POINTS............................................................................................................. 23
3.3.1 GENERAL ...................................................................................................................................23
3.3.2 BENCH MARKS AND TRIANGULATION STATIONS ......................................................................24
3.3.3 ACCURACY OF SURVEYING .......................................................................................................24
3.3.4 AUXILIARY WORKS ....................................................................................................................24
3.3.5 DAMAGE TO CROPS AND VEGETATION.....................................................................................25
3.3.6 CHECKING OF CONTRACTOR'S WORK BY THE ENGINEER .........................................................25
3.4 CONSTRUCTION DRAWINGS .............................................................................................................25

3.5 MEASUREMENT AND PAYMENT .......................................................................................................26


3.5.1 SURVEY AND GROUND CONTROL POINTS ................................................................................26
3.5.2 CONSTRUCTION DRAWINGS .....................................................................................................26
4 SITE INSTALLATIONS AND SERVICES .......................................................................................................27

4.1 SCOPE OF WORK ...............................................................................................................................27


4.1.1 TEMPORARY SITE INSTALLATION ..............................................................................................27
4.1.2 PERMANENT SITE INSTALLATIONS ............................................................................................27
4.1.3 SERVICES ...................................................................................................................................27
4.2 SUBMITTALS......................................................................................................................................27

4.3 SITE INSTALLATIONS ..........................................................................................................................28


4.3.1 CAMPS ......................................................................................................................................28
4.3.2 AUXILIARY BUILDINGS AND STORAGE AREAS ...........................................................................28
4.3.3 MEDICAL CARE FACILITIES ........................................................................................................29
4.3.4 COMMERCIAL CONCESSIONS ...................................................................................................30
4.3.5 STATIONARY PLANTS .................................................................................................................30
4.3.6 MATERIALS TESTING LABORATORY ...........................................................................................30
4.3.7 COMMUNICATION SYSTEMS.....................................................................................................30
4.3.8 POWER SUPPLY AND ILLUMINATION ........................................................................................31
4.3.9 WATER SUPPLY ..........................................................................................................................31
4.3.10 SANITATION AND SEWERAGE ...............................................................................................32
4.3.11 WASTE AND GARBAGE DISPOSAL .........................................................................................32
4.3.12 FENCING AND SITE SECURITY ...............................................................................................32
4.3.13 INSPECTION BY THE EMPLOYER OR ENGINEER ....................................................................32
4.3.14 FINAL CLEAN-UP ...................................................................................................................32
4.4 SERVICES FOR EMPLOYER AND ENGINEER .......................................................................................33
4.4.1 COMMUNICATION SYSTEMS.....................................................................................................33
4.4.2 SURVEY EQUIPMENT ................................................................................................................33
4.4.3 VEHICLES ...................................................................................................................................33
4.4.4 OFFICE CLEANING AND GARBAGE DISPOSAL ...........................................................................34
4.4.5 MEDICAL CARE FACILITIES ........................................................................................................34
4.4.6 CATERING, RECREATION FACILITIES, AND COMMERCIAL CONCESSIONS .................................34
4.5 MEASUREMENT AND PAYMENT .......................................................................................................34
4.5.1 SITE INSTALLATIONS ..................................................................................................................34
4.5.2 SERVICES FOR EMPLOYER AND ENGINEER ...............................................................................35
5 CARE OF WATER DURING CONSTRUCTION ............................................................................................37
_______________________________________________________________________________
5
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

5.1 SCOPE OF WORK ...............................................................................................................................37


5.2 SUBMITTAL .......................................................................................................................................37
5.3 RIVER DIVERSION ..............................................................................................................................37
5.3.1 GENERAL ...................................................................................................................................37
5.3.2 REQUIREMENTS ........................................................................................................................38
5.4 OTHER FLOOD PROTECTION WORKS ................................................................................................38
5.4.1 REQUIREMENTS ........................................................................................................................38
5.4.2 MATERIALS AND EXECUTION ....................................................................................................38
5.4.3 DIVERSION OF CREEKS ..............................................................................................................38
5.5 CARE OF WATER AT CONSTRUCTION SITES.......................................................................................39
5.5.1 GENERAL ...................................................................................................................................39
5.5.2 REQUIREMENTS AND DESIGN...................................................................................................39
5.5.3 SURFACE EXCAVATION DEWATERING .......................................................................................39
5.6 MEASUREMENT AND PAYMENT .......................................................................................................40
5.6.1 RIVER DIVERSION AND CARE WATER DURING CONSTRUCTION...............................................40
5.6.2 OTHER FLOOD PROTECTION WORKS ........................................................................................40
5.6.3 CARE OF WATER AT CONSTRUCTION SITES...............................................................................40
6 EXCAVATION AND FILLING ......................................................................................................................41

6.1 SCOPE OF WORK ...............................................................................................................................41


6.2 SUBMITTAL .......................................................................................................................................41
6.3 LINES AND GRADES ...........................................................................................................................42
6.4 SLOPES, SLIDES, GEOLOGICAL OVERBREAK AND UNSUITABLE FOUNDATIONS ................................42
6.5 EXCAVATION......................................................................................................................................42
6.5.1 GENERAL ...................................................................................................................................42
6.5.2 CLASSIFICATION OF EXCAVATION .............................................................................................43
6.5.3 CLEARING AND GRUBBING .......................................................................................................43
6.5.4 STRIPPING AND COMMON EXCAVATION ..................................................................................44
6.5.5 EXCAVATION BY RIPPING ..........................................................................................................44
6.5.6 ROCK EXCAVATION BY BLASTING ..............................................................................................44
6.5.7 MINOR EXCAVATION WORKS ....................................................................................................46
6.5.8 BORROW AND QUARRY EXCAVATION .......................................................................................46
6.5.9 ADDITIONAL EXCAVATION ........................................................................................................47
6.6 LINE-DRILLING...................................................................................................................................47
6.7 PROTECTION AND SUPPORTS ...........................................................................................................47
6.7.1 GENERAL ...................................................................................................................................47
6.7.2 TEMPORARY PROTECTION AND SUPPORTS..............................................................................47
6.8 EXCAVATED MATERIALS ....................................................................................................................48
6.9 DISPOSAL OF EXCAVATED MATERIALS ..............................................................................................48

6.10 CLEANING, PREPARATION AND PROTECTION OF EXCAVATION SURFACES ...................................48

_______________________________________________________________________________
6
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

6.11 PROTECTION OF EXISTING STRUCTURES DURING BLASTING .......................................................49


6.12 FILL ................................................................................................................................................49
6.12.1 GENERAL ...............................................................................................................................49
6.12.2 RANDOM FILL AND BACKFILL................................................................................................50
6.12.3 FREE-DRAINING BACKFILL .....................................................................................................50
6.12.4 SAND-GRAVEL SELCTED BACKFILL AND BEDDING ................................................................51
6.12.5 SAND BEDDING .....................................................................................................................51
6.13 MEASUREMENT AND PAYMENT ...................................................................................................51
6.13.1 EXCAVATION..........................................................................................................................51
6.13.2 DISPOSAL OF THE EXCAVATED MATERIAL .............................................................................54
6.13.3 STOCKPILING .........................................................................................................................54
6.13.4 FILLS AND BACKFILL ..............................................................................................................54
6.13.5 EXCLUSIONS ..........................................................................................................................54
7 SLOPE PROTECTION ................................................................................................................................56
7.1 SCOPE OF WORK ...............................................................................................................................56
7.2 SUBMITTALS......................................................................................................................................56
7.3 RIPRAP ..............................................................................................................................................56
7.3.1 MATERIAL..................................................................................................................................56
7.3.2 EXECUTION ...............................................................................................................................56
7.4 STONE PAVING ..................................................................................................................................57
7.4.1 MATERIALS ................................................................................................................................57
7.4.2 7.4.2 EXECUTION ..................................................................................................................57
7.5 FIELD SOD .........................................................................................................................................57
7.5.1 GENERAL ...................................................................................................................................57
7.5.2 MATERIALS AND EXECUTION ....................................................................................................57
7.6 TOPSOIL AND SEEDING .....................................................................................................................58
7.6.1 GENERAL ...................................................................................................................................58
7.6.2 MATERIALS ................................................................................................................................58
7.6.3 EXECUTION ...............................................................................................................................58
7.7 PLANTING .........................................................................................................................................59
7.8 MEASUREMENT AND PAYMENT .......................................................................................................60

8 CONCRETE ..............................................................................................................................................61
8.1 GENERAL ...........................................................................................................................................61
8.2 STANDARDS.......................................................................................................................................61
8.3 COMPOSITION AND CLASSES OF CONCRETE ....................................................................................61
8.4 SUBMITTAL .......................................................................................................................................62

8.5 TESTING ............................................................................................................................................63


8.5.1 TESTS PRIOR TO THE START OF CONCRETE WORK (TRIAL MIX STAGE).....................................63
8.5.2 TESTS DURING EXECUTION OF THE WORK ...............................................................................65
_______________________________________________________________________________
7
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

8.6 PRESCRIPTIONS TO BE FOLLOWED IN CASE THE STRENGTH IS NOT ATTAINED ................................67


8.7 CONCRETE MATERIALS .....................................................................................................................68
8.7.1 CEMENT ....................................................................................................................................68
8.7.2 AGGREGATES ............................................................................................................................69
8.7.3 WATER.......................................................................................................................................72
8.7.4 ADMIXTURES ............................................................................................................................72
8.8 STEEL REINFORCEMENT....................................................................................................................73
8.8.1 GENERAL ...................................................................................................................................73
8.8.2 QUALITY REQUIREMENTS .........................................................................................................73
8.8.3 STORAGE ...................................................................................................................................73
8.8.4 CUTTING AND BENDING ...........................................................................................................73
8.8.5 SPLICING ...................................................................................................................................73
8.8.6 PLACING ....................................................................................................................................74
8.8.7 CONCRETE COVER OF THE REINFORCEMENT ...........................................................................74
8.9 SURFACE FINISHES ............................................................................................................................74
8.9.1 GENERAL ...................................................................................................................................74
8.9.2 FORMED SURFACES ..................................................................................................................74
8.9.3 UNFORMED SURFACES .............................................................................................................75
8.10 TOLERANCES .................................................................................................................................76
8.10.1 CONCRETE.............................................................................................................................76
8.10.2 REINFORCEMENT ..................................................................................................................77
8.11 FORMWORK..................................................................................................................................77
8.11.1 DESIGN ..................................................................................................................................77
8.11.2 WORKMANSHIP ....................................................................................................................77
8.11.3 MATERIALS ............................................................................................................................77
8.11.4 FORM TIES ............................................................................................................................78
8.11.5 MAINTENANCE OF FORMWORK ...........................................................................................78
8.11.6 REMOVAL OF FORMWORK ...................................................................................................78
8.12 JOINTS IN CONCRETE STRUCTURES ..............................................................................................79
8.12.1 CONSTRUCTION JOINTS ........................................................................................................79
8.12.2 MOVEMENT JOINTS ..............................................................................................................80
8.13 PREPARATION FOR CONCRETE PLACING.......................................................................................82
8.13.1 GENERAL ...............................................................................................................................82
8.13.2 CONCRETE ON EARTH FOUNDATION ....................................................................................83
8.13.3 CONCRETE CAST AGAINST ROCK ..........................................................................................83
8.13.4 CONCRETE CAST AGAINST OR UPON PREVIOUSLY PLACED CONCRETE ...............................83
8.14 PRODUCTION OF CONCRETE ........................................................................................................83
8.14.1 CONCRETE MIXES..................................................................................................................83
8.14.2 BATCHING .............................................................................................................................84
8.14.3 MIXING .................................................................................................................................85
8.14.4 TRANSPORTING ....................................................................................................................86
8.14.5 COMMUNICATIONS ..............................................................................................................87
8.15 TEMPERATURE OF CONCRETE ......................................................................................................87
8.16 CONCRETE PLACING......................................................................................................................87
_______________________________________________________________________________
8
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

8.16.1 GENERAL ...............................................................................................................................87


8.16.2 CASTING SEQUENCES............................................................................................................88
8.16.3 PLACING AND COMPACTION ................................................................................................88
8.16.4 PUMPING CONCRETE............................................................................................................89
8.17 PROTECTION AND CURING ...........................................................................................................90
8.17.1 PROTECTION .........................................................................................................................90
8.17.2 CURING .................................................................................................................................90
8.18 REPAIR OF DEFECTIVE CONCRETE .................................................................................................91
8.18.1 GENERAL ...............................................................................................................................91
8.18.2 DRY-PACK MORTAR ...............................................................................................................92
8.18.3 MORTAR FILLING...................................................................................................................93
8.18.4 CONCRETE FILLING ...............................................................................................................93
8.18.5 EPOXY-RESIN BONDING ........................................................................................................93
8.18.6 STAINS AND DISCOLOURATION .............................................................................................93
8.19 PARTICULAR REQUIREMENTS FOR INDIVIDUAL CONCRETE STRUCTURES ...................................93
8.19.1 SPILLWAY CHUTE ...................................................................................................................93
8.19.2 CONCRETE GRAVITY STRUCTURES ........................................................................................94
8.19.3 CONTROL BUILDING..............................................................................................................94
8.19.4 BLOCKOUTS FOR EQUIPMENT EMBEDDING .........................................................................95
8.19.5 GROUTING OF THE EQUIPMENT BEARING PLATES AND ANCHORS......................................95
8.19.6 POROUS CONCRETE ..............................................................................................................95
8.19.7 PRE-CAST CONCRETE ............................................................................................................95
8.20 MEASUREMENT AND PAYMENT ...................................................................................................96
8.20.1 CONCRETE.............................................................................................................................96
8.21 CEMENT ........................................................................................................................................97
8.21.1 ADMIXTURES ........................................................................................................................98
8.21.2 STEEL REINFORCEMENT........................................................................................................98
8.21.3 FORMWORK..........................................................................................................................98
8.21.4 MOVEMENT JOINTS ..............................................................................................................98
8.21.5 TESTS.....................................................................................................................................98
9 DRILLING AND WATER PRESSURE TESTING ..........................................................................................100

9.1 SCOPE OF WORK .............................................................................................................................100


9.2 SUBMITTAL .....................................................................................................................................100

9.3 EQUIPMENT ....................................................................................................................................101


9.3.1 GENERAL .................................................................................................................................101
9.3.2 DRILLING WITH CORE RECOVERY ...........................................................................................101
9.3.3 WATER PRESSURE TESTING .....................................................................................................102
9.4 EXECUTION .....................................................................................................................................102
9.4.1 GENERAL .................................................................................................................................102
9.4.2 DRILLING FOR CURTAIN GROUTING........................................................................................103
9.4.3 EXPLORATORY HOLES, DRILLING .............................................................................................103
9.4.4 EXPLONATERY HOLE, SAMPLING AND TESTING......................................................................104
9.5 MEASUREMENT AND PAYMENT .....................................................................................................106

_______________________________________________________________________________
9
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

9.5.1 GENERAL .................................................................................................................................106


9.5.2 SETTING UP OF DRILL RIGS .....................................................................................................107
9.5.3 DRILLING .................................................................................................................................107
9.5.4 SAMPLING AND TESTING ........................................................................................................108
9.5.5 INSTALLATION IN DRAIN HOLES ..............................................................................................109
9.5.6 EXCLUSIONS ............................................................................................................................109
10 GROUTING ............................................................................................................................................110

10.1 SCOPE OF WORK .........................................................................................................................110


10.2 DEFINITIONS ...............................................................................................................................110
10.2.1 CEMENT GROUT .................................................................................................................110
10.2.2 SINGLE-STAGE GROUTING ..................................................................................................110
10.2.3 MULTIPLE-STAGE GROUTING ..............................................................................................110
10.2.4 WATER-CEMENT RATIO .......................................................................................................111
10.3 SUBMITTAL .................................................................................................................................111

10.4 SAMPLING AND TESTING ............................................................................................................111

10.5 GROUTING MATERIALS ...............................................................................................................112


10.5.1 GENERAL .............................................................................................................................112
10.5.2 CEMENT ..............................................................................................................................112
10.5.3 SAND ...................................................................................................................................112
10.5.4 WATER.................................................................................................................................113
10.5.5 ADMIXTURES ......................................................................................................................113
10.5.6 BENTONITE .........................................................................................................................113
10.5.7 FLY ASH OR POZZOLANA .....................................................................................................113
10.5.8 CHEMICALS .........................................................................................................................113
10.6 GROUT MIXTURES.......................................................................................................................114
10.6.1 GENERAL .............................................................................................................................114
10.6.2 UNSTABLE CEMENT MIXTURES ...........................................................................................114
10.6.3 STABLE CEMENT MIXTURES ................................................................................................114
10.6.4 GROUT MIXES FOR DAM/SPILLWAY GROUT CURTAIN ........................................................114
10.7 EQUIPMENT ................................................................................................................................115
10.7.1 GENERAL .............................................................................................................................115
10.7.2 GROUT MIXERS AND AGITATOR SUMPS .............................................................................115
10.7.3 GROUT PUMPS ...................................................................................................................115
10.7.4 PRESSURE GAUGES .............................................................................................................116
10.7.5 CONNECTIONS TO GROUT HOLES AND PACKERS ...............................................................116
10.7.6 EMBEDDED PIPES AND FITTINGS FOR GROUTING .............................................................116
10.8 GROUTING OPERATIONS.............................................................................................................117
10.8.1 GENERAL .............................................................................................................................117
10.8.2 CURTAIN GROUTING ...........................................................................................................117
10.8.3 CLOSURE OF HOLES AND CLEAN-UP ...................................................................................118
10.8.4 CONTACT GROUTING BETWEEN CONCRETE AND EMBEDDED COMPONENTS ..................118
10.8.5 GROUTING OF CONTRACTION AND CONSTRUCTION JOINTS.............................................118
10.9 MEASUREMENT AND PAYMENT .................................................................................................118
10.9.1 GENERAL .............................................................................................................................118
_______________________________________________________________________________
10
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

10.9.2 CONTACT GROUTING BETWEEN CONCRETE AND EMBEDDED COMPONENTS ..................119


10.9.3 GROUTING OF CONTRACTION AND CONSTRUCTION JOINTS IN CONCRETE STRUCTURES 119
10.9.4 EMBEDDED STEEL PIPES AND FITTINGS .............................................................................119
10.9.5 EXCLUSIONS ........................................................................................................................119
11 DAM EMBANKMENT CONSTRUCTION .................................................................................................120
11.1 SCOPE OF WORK .........................................................................................................................120
11.2 SUBMITTAL .................................................................................................................................120
11.2.1 SUBMITTALS BEFORE CONSTRUCTION ...............................................................................120
11.2.2 SUBMITTALS DURING CONSTRUCTION...............................................................................120
11.3 MATERIALS ..................................................................................................................................120
11.3.1 GENERAL .............................................................................................................................120
11.3.2 DAM BODY (CL/SC) .............................................................................................................121
11.3.3 UPSTREAM DAM SURFACE (LARGE_STONE) .......................................................................121
11.3.4 COARSE FILTER (GW/GP).....................................................................................................121
11.3.5 FINE FILTER (SM/SC) ...........................................................................................................122
11.3.6 BORROW / QUARRY OPERATIONS ......................................................................................123
11.3.7 ORGANIC MATTER ..............................................................................................................123
11.3.8 STOCKPILING OF EMBANKMENT MATERIALS .....................................................................123
11.4 FOUNDATION PREPARATION ......................................................................................................123
11.4.1 GENERAL .............................................................................................................................123
11.4.2 FOUNDATION FOR OTHER STRUCTURES.............................................................................124
11.5 PLACING ......................................................................................................................................124
11.5.1 GENERAL .............................................................................................................................124
11.5.2 WATER CONTENT ................................................................................................................125
11.5.3 INSTRUMENTATION ............................................................................................................125
11.6 TESTS AND QUALITY CONTROL ...................................................................................................125

11.7 TOLERANCE .................................................................................................................................125


11.8 MEASUREMENT AND PAYMENT .................................................................................................126
11.8.1 TRIAL EMBANKMENT AND TESTS .......................................................................................126
11.8.2 FOUNDATIONS ....................................................................................................................126
11.8.3 EXCAVATED MATERIALS ......................................................................................................126
11.8.4 EMBANKMENTS ..................................................................................................................126
11.8.5 EXCLUSIONS ........................................................................................................................126
12 DAM INSTRUMENTATION .....................................................................................................................128
12.1 SCOPE OF WORK .........................................................................................................................128
12.2 SUPPLY ........................................................................................................................................128

12.3 INSTALLATION .............................................................................................................................128

12.4 TYPE OF INSTRUMENTS ..............................................................................................................129


12.5 USE OF INSTRUMENTS ................................................................................................................136

12.6 MEASUREMENT AND PAYMENT .................................................................................................136

_______________________________________________________________________________
11
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

13 ROAD WORKS .......................................................................................................................................137


13.1 GENERAL .....................................................................................................................................137
13.2 PERMANENT ROADS ...................................................................................................................137
13.2.1 GENERAL .............................................................................................................................137
13.2.2 SCOPE OF WORK .................................................................................................................137
13.2.3 CONSTRUCTION MATERIAL SOURCES .................................................................................137
13.2.4 SUB-BASE MATERIAL ...........................................................................................................137
13.2.5 BASE COURSE MATERIAL ....................................................................................................138
13.2.6 SUB-GRADE PREPARATION AND COMPACTION ..................................................................138
13.2.7 PLACING ..............................................................................................................................138
13.3 MAINTENANCE ...........................................................................................................................139
13.4 TEMPORARY ROADS ...................................................................................................................139
13.5 MEASUREMENT AND PAYMENT .................................................................................................139
13.5.1 PERMANENT ROADS CONSTRUCTION ................................................................................139
13.5.2 PERMANENT ROADS MAINTENANCE .................................................................................140
13.5.3 TEMPORARY ROADS CONSTRUCTION ................................................................................140
13.5.4 TEMPORARY ROADS MAINTENANCE ..................................................................................140
14 MISCELLANEOUS and ANCILLARY WORKS............................................................................................141

14.1 SCOPE OF WORK .........................................................................................................................141


14.2 ROOFING .....................................................................................................................................141
14.3 PLASTERING ................................................................................................................................141
14.4 PAINTING ....................................................................................................................................142
14.4.1 GENERAL .............................................................................................................................142
14.4.2 MATERIALS ..........................................................................................................................142
14.4.3 PREPARATION OF SURFACES ...............................................................................................142
14.4.4 WORKMANSHIP ..................................................................................................................143
14.4.5 PAINTING SCHEDULE ..........................................................................................................143
14.5 FLOORING AND TILING ...............................................................................................................144

14.6 WINDOWS AND DOORS ..............................................................................................................145


14.7 CEILINGS .....................................................................................................................................146
14.8 PLUMBING ..................................................................................................................................146
14.9 ELECTRICAL SYSTEMS..................................................................................................................147
14.10 WATER SUPPLY PLANT ................................................................................................................147
14.11 REQUIRED DEMOLITIONS ...........................................................................................................147
14.11.1 GENERAL .............................................................................................................................147
14.11.2 EXECUTION METHOD..........................................................................................................147
14.12 NON-SHRINK GROUT ..................................................................................................................147
14.12.1 GENERAL .............................................................................................................................147

_______________________________________________________________________________
12
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

14.12.2 MATERIAL AND PLACING ....................................................................................................148


14.13 MEASUREMENT AND PAYMENT .................................................................................................148
14.13.1 ROOFING .............................................................................................................................148
14.13.2 PLASTERING ........................................................................................................................148
14.13.3 PAINTING ............................................................................................................................148
14.13.4 FLOORING AND TILING .......................................................................................................148
14.13.5 WINDOWS AND DOORS ......................................................................................................149
14.13.6 CEILINGS .............................................................................................................................149
14.13.7 PLUMBING ..........................................................................................................................149
14.13.8 ELECTRICAL SYSTEM ...........................................................................................................149
14.13.9 WATER SUPPLY PLANT ........................................................................................................149
14.13.10 REQUIRED DEMOLITIONS ...............................................................................................149
14.13.11 NON-SHRINK GROUT ......................................................................................................149

_______________________________________________________________________________
13
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

1 PREAMBLE TO THE TECHNICAL SPECIFICATIONS

1.1 GENERAL
1) The following Specifications are part of the requirements related to the Works which are to be
provided according to the stipulations of the Contract. Hence, the instructions given herein form
an integral part of, and are applicable to, all technical and Contract Documents issued for the
Works.
2) These Specifications shall be read in conjunction with the Conditions of Contract, the Drawings
and the Bill of Quantities, and the Contractor shall comply with all provisions contained within
the Contract Documents and Engineer's instructions.
3) It is the intent of these Specifications, together with other relevant documents issued as part
of the Bid (or Contract Documents to follow later on), to provide the Contractor with complete
and detailed information and subsequent instructions necessary to enable him to submit a
well-planned Bid, to carry out the design, where and when required, and to execute properly
the work prescribed.
4) It is the intent of these Specifications to establish acceptable standards of quality. Minor
deviations in details due to manufacturer's standard shop process will be considered for
acceptance provided that, in the opinion of the Engineer, the proposed substitutions are equal
in quality to those specified. All deviations shall be called out in writing in the Bid and shall be
specifically indicated on the shop drawings.
5) All work shall be executed according to the Detailed Design and/or Construction Drawings as
approved by the Engineer and requirements released for construction, in a professional and
diligent manner, and all supplies and work shall comply with the quality requirements defined
in the relevant sections of these Specifications and other Contract Documents. The Contractor
shall make all necessary efforts to comply with the intent of these Specifications to the
satisfaction of the Engineer.
6) Any approval given by the Engineer of the Contractor's methods and equipment shall not
relieve the Contractor of his full responsibility for the proper and safe execution of any work
covered by these Specifications, or his liability for injuries to or death of persons, or any other
obligation under this contract.
1.2 SUBMITTAL
1) The Contractor shall provide the Engineer with all submittals required by these Specifications
and other Contract Documents. Although their extent shall be at the Contractor’s discretion,
such submittals shall adequately illustrate all the main aspects of the matter under
consideration for an easy understanding by the Engineer.
2) At any time, the Engineer may call either for additional information, completion of the
submittal or request the Contractor not to submit some of them.
3) The Contractor shall submit these documents to the Engineer so that, even if not specifically
expressed, reasonable time will be given to the Engineer to comment on or approve the
submittal.
1.3 STANDARDS AND CODES
1.3.1 GENERAL
1) Standards referred to in these Specifications are considered to form part of these
Specifications.
2) All standards and codes employed or referred to shall be the latest current issue in effect at
the date 28 days prior to the Bid submission date.
3) One complete set of standards and codes adopted for the Works shall be submitted free of
_______________________________________________________________________________
14
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

charge by the Contractor to the Engineer immediately after the Contract has come into force
or upon the Engineer's request. Such copies shall also be available at the Contractor's
business domicile(s) and at Site, for the use also of the Employer and of the Engineer.
4) In case of discrepancies between these Specifications and national or international standards
and codes, these Specifications being part of Contract Documents shall govern, unless
otherwise established by the Engineer in each particular case.
1.3.2 NATIONAL STANDARDS, CODES, LAWS AND REGULATIONS
1) Throughout the duration of the Contract, the materials, equipment, services, design and
workmanship shall conform to applicable national codes, standards, laws and regulations in
force in Republic of Uganda if not otherwise specified.
2) It is the Contractor's duty to acquaint himself with all available national codes, standards,
laws and regulations related to the Works in any way and he shall procure and keep at the
Site a copy of each of such applicable documents.
1.3.3 INTERNATIONAL STANDARDS AND CODES
1) International standards/codes series may be adopted provided:
• The standards/codes proposed are at least as stringent as the equivalent national
ones relevant to the Works, or if there is no applicable national standard/code for
the specific item concerned.
• The Contractor states, prior to starting the work, the international standard/code he
proposes to apply, giving full identification of each of them. The Contractor's
proposals are subject to the approval by the Engineer.
2) Where reference is made in the technical documents to standards/codes of the country of
origin for a supply item, it shall be a recognized national standard/code of the country where
the specific supply item is manufactured. To be acceptable under these Specifications, such
standards/codes must comply in all respects with the quality requirements of above
mentioned international standards/codes and must be approved by the Engineer.
1.3.4 SYSTEM OF UNITS
1) The SI system of units has been used throughout these Specifications and this system of
units shall be used consequently throughout the duration of Contract for all technical or
contractual purposes.
2) The following abbreviations are used in these Specifications and related other Contract
Documents:
Unit Abbreviation

millimeter centimeter mm
Length meter cm
kilometer km

square millimeter mm2


square centimeter cm2
Area 2
square meter m

3
Volume cubic meter m
kilogram kg
Mass
ton t
Density kilogram per cubic meter kg/m3

_______________________________________________________________________________
15
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

Newton N
kilo Newton kN
Force
mega Newton MN
Moment kilo Newton-meter kN m
Newton per square millimeter N/mm2
kilo Newton per square millimeter kilo kN/mm2
Stress or Strength
Newton per square meter kN/m2

bar Pascal bar Pa


Pressure mega Pascal MPa

millisecond ms
Time second hour sh

liters per second or minute cubic l/s, l/min


meters per second m/s
Rate of Flow
cubic meters per minute m3/min
Velocity meter per second m/s
Velocity of
revolutions per minute rpm
Rotation
Temperature degree Celsius °
C
Concentration parts per million ppm
Illumination
lux lx
Intensity
Energy kilowatt-hour kWh
Watt W
kilowatt kW
Power
Megawatt MW
Slope and
percent %
Percentage

3) The term "day" as used in these Specifications means the calendar day according to the
Gregorian Calendar.
4) Any other system of units utilized shall have only a descriptive value and shall in no case
replace the above-mentioned SI system.
1.4 DEFINITION OF TIME AND KEY DATES
The periods of time and key dates used throughout these Specifications have the meanings as
assigned to them in the “CONDITIONS OF CONTRACT FOR CONSTRUCTION” by FIDIC, 2017, with
amendments.

_______________________________________________________________________________
16
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

2 SAFETY PRECAUTIONS
2.1 SAFETY PROGRAM AND ITS IMPLEMENTATION
1) Within 14 days from the date of issue of the Notice to Commence, the Contractor shall submit, in
writing, his proposal for a comprehensive safety program covering all aspects of the Works.
2) This safety program shall detail policies, procedures, and plans which the Contractor intends to
implement to ensure the safety and health of his employees. It shall comply with the standards
and regulations in force in the country of the Works applicable to construction safety.
3) The Contractor shall designate a competent employee specially trained and experienced to act
as Safety Officer, who will administer and be responsible for the implementation of the safety
program. He shall carry out frequent and regular safety inspections of the working areas,
materials, and equipment. The name and qualifications of the Safety Officer shall be submitted
for approval to the Engineer prior to his appointment.
4) The Contractor shall be responsible for the enforcement of the health and safety provisions that
he himself and his subcontractors shall adopt on Site.
5) Prior to the start of any major construction activity or hazardous operation, the Contractor shall
submit to the Engineer for approval, a specific plan for safety precautions covering such
operation.
6) All accidental occurrences with serious accident potential such as major equipment failures,
contact with high-voltage lines, exposure to hazardous materials, slides, cave-ins, etc., shall be
reported to the Engineer as soon as practicable.
7) All serious and fatal injuries and diseases caused by the progress of work shall be immediately
investigated by the Contractor and a comprehensive report shall be submitted to the Engineer.
8) In case of a fatal accident, only rescue and emergency teams and operations shall be permitted
at the place of the occurrence until the Engineer gives permission to resume normal
operations.
2.2 SAFETY STANDARDS
In addition to the requirements specified herein, the Contractor shall comply with applicable
safety requirements of the following documents and/or organizations:
a) Safety regulations in force in the country of the Works
b) US Bureau of Mines or equivalent
c) USBR-Construction Safety Standards or equivalent
In addition to the requirements specified herein, the Contractor shall comply with applicable
safety requirements in force in the United Republic of Uganda.
2.3 PERSONAL SAFETY EQUIPMENT
1) The Contractor shall provide his and his subcontractor's personnel as well as the Employer's and
Engineer's representatives and visitors with appropriate personal safety equipment. The use of
such equipment shall be compulsory.
2) All persons entering the working areas wear a protective helmet.
3) Safety footwear with steel toe caps shall be worn by all personnel engaged in work having an
inherent danger to the feet.
4) During drilling works and in areas where workers are exposed to harmful noise and dust levels,
ear protectors and dust masks shall be worn.
5) Workers engaged in work having an inherent danger of eye or face injury shall be furnished and
required to wear protection glasses, goggles or face masks. Where irritants or toxic substances
may come in contact with the skin or clothing, employees shall wear protective clothing or
apply a protective ointment prescribed by a competent physician.
6) Employees working on steep slopes or otherwise subject to possible falls from levels not
protected by fixed guardrail or safety nets, shall be secured by safety belts and lifelines.
_______________________________________________________________________________
17
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

7) A suitable protection shall be installed on the upstream face of the dam during construction of
the asphaltic concrete facing to limit fall hazard associated with this type of work.
2.4 RESCUE TEAM
1) Prior to the commencement of construction, the Contractor shall organize and train a Rescue
Team composed of his employees. This Rescue Team shall be capable to render help after
accidents caused by fire, gas, explosion, rockslides, etc.
2) The Rescue Team shall be organized in such a way that a sufficient number of its members will
be ready for action at any time until the Completion of Works.
3) The Rescue Team members shall be instructed and trained for their task by a qualified and
experienced person. If necessary, the Contractor shall hire an outside specialist to perform such
training. A refresher training for all members of the Rescue Team shall be conducted at least
every six months
4) Each Rescue Team member shall be skilled in giving the first aid, dealing with the appliances for
artificial respiration, and firefighting equipment and shall possess a good local knowledge.
Adequate equipment for reaching even the remotest working area shall be at their disposal.
5) The Contractor shall submit the details of the proposed Rescue Team organization to the
Engineer for approval.
2.5 ILLUMINATION AND EARTHING
2.5.1 ILLUMINATION
All outdoor working sites, roads, storage and borrow areas, stationary plants, and all other
site facilities, shall be adequately illuminated during night work by electrical lights.
2.5.2 EARTHING, WET WORK AREAS, CONTROL OF ELECTRIC DISCHARGES
1) Equipment and appliances which are exposed to lightning shall be electrically earthed and the
effectiveness of such earthing shall be periodically checked by the Contractor's specialized
personnel.
2) Where electrical blasting will be used, equipment shall be installed to control possible electric
discharges in the ground due to storms, electrical motors, etc. As soon as such discharges are
noted, electrical blasting operations shall be suspended, or the detonator type changed.
3) No equipment electrically powered by more than 24 Volts shall be operated by personnel
standing in water.
4) Only suitable insulated equipment shall be allowed in the very wet areas.
2.5.3 MAINTENANCE OF TRAFFIC AND SAFETY ON PUBLIC ROADS
1) The Contractor shall be responsible for the safety along the roads related to the Site, and he
shall take all necessary precautions for the protection of the work and the safety of the public
on the roads affected by his activities. Where the work will be carried out at the site of, or
close to an existing road, the Contractor shall maintain the vehicular and pedestrian traffic
safe at all times. If his operations can cause traffic hazards, he shall repair or fence or take
such other measures for ensuring safety which are satisfactory to the Engineer.
2) Public roads subject to interference by the works shall be kept open or suitable detours shall
be provided and maintained by the Contractor, who shall provide, erect and maintain all
necessary barricades, suitable and sufficient flagmen, danger signals, signs etc.
3) Roads which will be closed to traffic shall be protected by effective barricades on which
acceptable warning and detour signs shall be placed. All barricades and all lights shall be kept
burning from sunset to sunrise.
4) The Contractor shall submit his weekly activities schedule and the locations of his work along
the existing public roads to the authorities concerned and obtain all necessary approvals prior
to commencement of the respective work.
5) At the road crossings or in heavy traffic locations, the Contractor shall carry out the work
within the working hours as directed by the Engineer, and after the completion of the work
_______________________________________________________________________________
18
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

he shall immediately make the necessary backfill and pavement at the crossings.
6) The Contractor shall provide temporary passes and bridges to give an access to the existing
villages, houses, etc., to the satisfaction of the Engineer and the authorities concerned
whenever he disturbs such existing way during the execution of the Works.
2.6 STORAGE AND TRANSPORT OF EXPLOSIVES
1) The Contractor shall in due time apply for a permit which allows him to buy, store and use the
explosives required for the Works. The local security forces or other competent authorities will
issue the permit.
2) The Contractor shall strictly comply with the rules and regulations in force in the country of
the Works regarding purchase, transport, storage, handling and use of explosives.
3) Explosive magazines shall be reinforced concrete buildings with walls and slabs of a minimum
25 cm thickness. Doors shall be made of double sheets having a minimum thickness of 5 mm
each and shall be fitted with safety type locks.
4) Explosives magazines shall be kept at a safe distance from working areas and living quarters.
They shall be surrounded with barbed wire, protected by safety locks, ventilated, and fitted
with lightning arresters. An air space shall be provided between the ceiling and the roof to
prevent temperatures from reaching dangerous levels.
5) Blasting caps and detonators shall not be stored in the same magazines as explosives but shall
be located in separate magazines at least 15 m away if barricaded and 30 m if un- barricaded.
6) Explosives shall be stored only in their original containers and with the top side up as
designated on the container.
7) Access to the magazines and permission to handle explosives shall be granted exclusively to
trustworthy personnel, adequately instructed and experienced in the use and handling of
explosives.
8) The Contractor shall provide all reasonable and adequate security measures necessary to
prevent loss or theft of explosives. Storage of explosives and detonators outside of the
magazines shall not be permitted.
9) The Contractor shall maintain a record of storage and withdrawal of all explosives. This record
shall be made available to the Engineer on request. The Engineer shall be promptly notified of
any loss or theft of explosives.
10) Between the magazines and the place of use, the explosives and detonators shall be
transported separately in lockable metallic containers loaded on a special wagon destined for
the purpose of explosives transport only. These wagons shall be painted with striking colours
for easy recognition. The inside of the containers shall be lined with wood in order to prevent
a direct contact of the explosive or detonators with the metal.
2.7 BLASTING
1) All blasting shall be carried out in a proper and safe manner by a competent and experienced
blast-man and no blast shall be fired without his approval.
2) Blasting will be permitted only after adequate provisions have been made for the protection
of persons, the Works, and public or private property. The Engineer's approval of any of the
Contractor's blasting operations shall not relieve the Contractor of his sole responsibility for
the safety of persons and property. Any damage done to the Works or property by blasting
shall be repaired by the Contractor.
3) Blasting in the open air shall be carried out only at certain hours of the day agreed upon by
the Contractor and the Engineer. Barriers shall be erected, and warning shall be given to the
workers at the Site and to the public immediately before blasting, so that no person will
enter the danger zone until blasting is finished.
4) Upon completion of blasting, an "all clear" signal shall be given by the responsible blasting
engineer after he has satisfied himself that all charges loaded have detonated and that no
_______________________________________________________________________________
19
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

delay-explosions or misfiring are to be expected.


5) Such methods of blasting shall be employed that shock and vibration are minimized.
6) No blasts involving charges larger than 200 kg shall be carried without the written approval
by the Engineer, who shall be notified at least one hour prior to the blast.
7) No blasting shall be permitted within 30 m of any concrete placed within the previous 7
days. After 7 days, blasting may be performed only with the approval of the Engineer.
Blasting will not be permitted within 10 m of structures or installations vulnerable to
damage by blasting.
8) No charging and firing will be executed during thunderstorm (except in underground works)
and other electrical disturbances which can cause uncontrolled blasting.
9) Mats or rubber tires tied together with rope shall be used as protection from flying debris to
cover the charges where blasting may expose persons or property to injury or damage.
2.8 FIRE PRECAUTIONS
1) The Contractor shall organize a fire brigade equipped for the fighting of any fires which could
break out on the construction sites, in temporary structures, stores, residential quarters, etc.
2) An adequate number of fire extinguisher shall always be available at each construction site
and in each building in camps and in offices and they shall be kept in satisfactory working
order.
3) Firefighting equipment shall be of the gas, dry powder or other suitable chemical or pumped
water type. Their number, type and location will be subject to the approval of the Engineer.
2.9 DUST ABATEMENT
During the performance of the work and any operations appurtenant there to, the Contractor
shall carry out proper and efficient measures, such as sprinkling with water or other means,
whenever necessary to reduce the dust nuisance, and to prevent dust which has originated
from his operations from damaging crops, cultivated fields, and dwellings, or causing a nuisance
to persons. The Contractor will be held liable for any damage resulting from dust originating
from his operations.
2.10 POLLUTION OF STREAMS AND RIVERS
1) The Contractor shall take all possible steps to prevent pollution of streams, rivers, and other
water supplies, at or in the vicinity of the Site and shall comply with applicable laws, orders
and regulations in force in the country of the Works concerning the control and abatement of
water pollution.
2) Under no circumstances shall the sewage from the camps, or other contaminated water, be
released directly into river or other natural streams or any open areas without prior
treatment.
2.11 NOISE DUE TO CONSTRUCTION ACTIVITIES
1) The Contractor shall take adequate measures to keep as low as possible noise caused by
construction activities and specially that due to construction equipment and stationary
plant. In particular, the following shall be observed.
a) All engine operated equipment shall be as a minimum provided with standard
silencer; however, equipment operating near the Contractor’s camps or existing
villages and houses shall be provided with high performance silencers, keeping the
noise level below 70 dB measured at a distance of 3 m from the equipment.
b) Motor compressors, motor generators, ventilation fans and other similar equipment
if located near camps or existing villages and houses shall also, if necessary, be housed
in a building;
c) Equipment and stationary plant shall be generally located at adequate distance from

_______________________________________________________________________________
20
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

camps or existing villages and houses, in such a way to avoid disturbance to


personnel working on the project and local inhabitants.
2) The Engineer shall have the right to require additional measures such as sound-dampening
screens or more efficient silencers in case the noise level results higher than 70 dB measured
at camp or village or house close- to the source of noise.
2.12 LOCAL COMMUNITIES AND RELIGIOUS CUSTOMS
1) The Contractor shall pay care to avoid damage to properties, buildings, artifacts and objects
of local communities or individuals during the execution of the Works; similarly, he shall
avoid to make use or occupy areas without the prior consent of the owners.
2) The Contractor shall also have due regard to religious and other, customs of local
communities, and shall never interfere in any religious or civil ceremony.
2.13 VEGETATION AND WILDLIFE
The Contractor shall care, in planning, constructing, maintaining and operating temporary
works, such as camps, roads, spoil, stockpile and construction facilities areas, to avoid
unnecessary damage to areas of particular environmental interest, such as patches of
remaining forest, valuable trees and erosion sensitive areas.
2.14 FINDINGS OF ARCHEOLOGICAL, HISTORICAL OR CULTURAL INTEREST
1) In case fossils, articles of value or antiquity and/or structures and other remains of things of
archaeological, historical or cultural interest are discovered during the activities related to the
construction of permanents or temporary works, the Contractor shall notify the Engineer
without removing any part of the article or thing found.
2) The Contractor shall take the necessary measures for preventing that any person or
equipment may damage the article or thing, and shall provide barricades, fences, signals and,
if necessary, protection against atmospheric agents.
3) The Engineer shall agree with the Contractor about the possible required modification of
permanent and/or temporary works in connection with archeological or historical findings
and deal with the additional costs to the Works, if any, as a Variation.
2.15 ESHS RISKS AND IMPLEMENTATION PLANS
The Contractor shall submit the Implementation Plans to manage the following key
Environmental, Social, Health and Safety (ESHS) risks.
• Construction Environmental and Social management Plan, to ensure the compliance with
the ESMP findings
• Labour Influx Plan, to avoid negative impacts on the host community,
• Traffic Management Plan, to ensure safety of local communities from construction traffic
• Water Resource Protection Plan, to prevent contamination of drinking water
• Boundary Marking and Protection Strategy, for mobilization and construction to prevent
offsite adverse impacts
• Consents/Permits Strategy, to obtain Consents/Permits prior to the start of relevant earth
works,
• Occupational Health and Safety Plan, to entails the inclusion of EHS considerations in the
implementation processes
• Access Road Plan, to cover the road risks and to avoid erosion effects,
• Material Use, Handling and Storage Plan, for the management for use and disposal of
hazardous substances
• Waste management Plan, for the management of waste and dump sites
• Wastewater Plan, to adhere to the national rules and regulations,
• Dust, Air Emission and Noise Pollution Plan, to avoid risks of related accidents and risks,
_______________________________________________________________________________
21
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

• Emergency Preparedness Plan, to ensure the efficiency of the safety procedures. The plan
should include emergency preparedness during construction and actions to be taken
upon emergent situations such as collapse of coffer dam.

The Contractor shall be required to submit for approval, and subsequently implement, the
Contractor’s Environment and Social Management Plan (C-ESMP), in accordance with the
Particular Conditions of Contract Sub-Clause 4.1, that includes the agreed Management
Strategies and Implementation Plans described here.

The CESMP will cover the remedial and/or mitigation measures identified and reported in the
Environmental and Social Impact Assessment (ESIA), Environmental and Social Management
Plan (ESMP), Resettlement Action Plan and the Consent Conditions issued by the regulatory
authority and to be attached to any permits or approvals for the project.

Furthermore, it will indicate the strategies to be adopted during the construction and operation
phases to be submitted in appropriate Method Statements namely: Work site boundaries and
safety area, Access Roads, Site clearing, Materials Use, Handling and Storage, Quarries,
Refueling and Workshop management, Waste Management, Wastewater, Fire Control, Dust
control and Air Pollution Management, Water Pollution Management, Noise control, Cement
and concrete batching, Emergency Procedures, Safety Plan, Traffic Management Plan,
Biodiversity protection.
2.16 MEASUREMENT AND PAYMENT
1) Except for items provided for in the Bill of Quantities, no extra measurement for payment or
payment will be made for the other items listed in chapter 2 and the entire cost thereof shall
be included in the Unit Prices for other items of the Works.
2) Any repair work or any indemnities required due to Contractor's non-compliance with the
safety requirements shall be to the Contractor's expense.

_______________________________________________________________________________
22
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

3 SURVEYING, SETTING-OUT WORK AND CONSTRUCTION DRAWINGS

3.1 SCOPE OF WORKS


The Contractor shall:
1) verify the accuracy of the existing topographic surveys, provided by the Employer;
2) set-up a network of permanent benchmarks to be used for laying out the project works;
3) perform some additional geological and geotechnical investigations (Drillings, Situ and
Laboratory Tests);
4) Prepare Construction Drawings (and relative support calculations); These drawings must
take into consideration:
a. detailed geological conditions that could emerge during excavations;
b. details (such as weights and dimensions, etc.) provided by the electromechanical and
hydromechanical equipment contractors;
These drawings shall be sufficiently detailed to allow construction of each project component.
3.2 SUBMITTALS
The Contractor shall submit to the Employer within one month from the completion of specific
survey for establishing the new main benchmarks the following:
1) the survey methods and the instrumentation used for establishing the benchmarks
and base lines necessary for the construction of the permanent works;
2) the calculations performed for establishing such benchmarks and base lines.
The Contractor shall submit to the Engineer at least forty-five (45) days before the start of each
activity the relative Construction Drawings. The Engineer shall issue his observations within
twenty-one (21) days from receipt of such drawings after which time the Drawings will
automatically be deemed to be approved.
3.3 GROUND CONTROL POINTS
1) Prior to commencing the work, the Contractor shall undertake the check survey of the
reference data provided by the Employer and satisfy himself as to their accuracy. Should he
have any objections to this data and the relevant drawings, he shall inform the Engineer in
writing within 2 weeks of the hand-over.
2) The Contractor shall realize, in order to locate accurately the setting out points, a net of
permanent benchmarks, according to the detailed instructions given by the Engineer.
The following requirements shall apply:
3.3.1 GENERAL
1) The Contractor shall perform surveys and setting-out necessary to establish the accurate
location of the structures as shown on the Tender Design or Construction Drawings and
shall carry out all necessary surveys to verify the topographical data used by the Engineer
for the tender design and measuring purposes.
2) Within 15 days after the day of receipt of the Notice to Commence, the Contractor shall
submit his proposed survey plan to the Engineer. The proposed plan shall indicate the
accuracy for all surveys.
3) In advance of any setting-out work associated with all principal project features, the
Contractor shall submit to the Engineer for approval a description of the method and
procedures he intends to use in establishing Bench Marks and base lines.
4) If the Contractor chooses to use triangulation points or Bench Marks other than those
furnished by the Employer, he shall do so at his own expense and risk.
5) The Contractor shall carry out topographical surveys of the original ground surface in each
sector of the Works where surface excavation will be necessary, and produce sufficient and

_______________________________________________________________________________
23
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

adequate cross-sections which will permit later to evaluate the volume of excavation for
the measurement purposes and payment of excavation.
6) The Contractor shall entrust the surveying works only to persons who, by their training and
experience, have sufficient qualifications and knowledge to ensure proper fulfillment of the
survey tasks assigned to them. For the performance of survey work, the Contractor shall
provide a sufficient number of reliable and accurate survey instruments.
3.3.2 BENCH MARKS AND TRIANGULATION STATIONS
1) Permanent survey control points shall be established prior to starting the work and such
permanent points shall be preserved and protected during construction operations.
2) A minimum of 2 permanent bench marks shall be established for each major structure, and
referenced to data established by survey control points. The location of such points with
horizontal and vertical data shall be recorded on the construction record drawings by the
Contractor.
3) From the primary survey control points the construction surveys shall be performed as
required to locate, set-out and construct each portion of the Works.
4) Complete and adequate logs of all control and survey work shall be maintained as it
progresses. Such logs shall be available for the Engineer's inspection at all times.
5) The Contractor shall protect, preserve and keep accessible the bench marks and
triangulation stations of the basic survey and those provided by himself. Any damage or
removal of bench marks and stations, including such of other parties shall be prevented.
Any accidental damage shall immediately be brought to the attention of the Engineer. It is
expressly stated that the Contractor will be made responsible for the damage and its
consequences.
6) Bench marks shall be of stainless steel or cast iron. In softer soil, the steel bolt shall be
embedded in a block of concrete of suitable size, and absolutely stable. Inscriptions shall be
durable and clearly legible.
7) Subordinate points may be marked by steel pipes or pegs, subject to the approval of the
Engineer. Every newly fixed point shall be checked, as far as possible, through elements
other than those used to establish the point.
3.3.3 ACCURACY OF SURVEYING
1) Horizontal distances shall normally be measured with optical or electronic distance
measuring instruments. Chaining shall be restricted to measuring of short distances and will
not be used in survey of traverse nets.
2) Elevations and angles shall be measured by using an appropriate electronic or optical
instrument.
3) Traverse nets shall be executed with the precision as indicated in Table 3-1 at the end of this
Section.
4) Levelling shall be checked by closing the loop to the initial bench mark. The elevation
difference of the two legs of the loop shall not exceed 12mm √K
5) where K is the total levelling distance in kilometres.
6) The Contractor may adopt GPS differential methods for the measurement of coordinates
and levels after prior approval by the Engineer of the proposed procedure and the relative
accuracy of the measurements.
3.3.4 AUXILIARY WORKS
The Contractor shall perform auxiliary works with regard to surveying which shall include,
but not be limited to, the following:
a) Perform all necessary calculations with clear presentation of calculations and results
in order to facilitate verification
b) Expose covered bench marks
c) Provide bench marks in lieu of and/or in addition to the existing ones
_______________________________________________________________________________
24
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

d) Remove machinery and obstructions from the required sight-lines


e) If it is hindering the survey work, stop all machinery, drilling, blasting, driving and
other work causing ground vibration and stop all smoke, dust, gas, etc., obscuring
clear view or causing refraction
f) Restrict or stop traffic of persons and vehicles near instruments or in sight-lines during
instrument observations as required
g) Provide adequate lighting or shut off sources of interfering light to ensure the
necessary clear view
h) Provide adequate labour, and materials as deemed necessary and suitable by the
Engineer for the control and auxiliary surveys
i) Remove all obstructive accumulation of water
j) Carry out additional topographical surveys in cases where the existing topographical
data is, in the opinion of the Engineer, insufficient for accurate measurement of the
Works
k) Carry out all necessary topographical surveys for the incorporation of measuring
equipment and instrumentation located in the Permanent Works
l) Carry out all necessary topographical surveys for the observation of the behavior of
structures during construction
3.3.5 DAMAGE TO CROPS AND VEGETATION
1) No trees or crops of economic value existing at the Site shall be damaged or removed by the
Contractor during survey and cross-sectioning works prior to their enumeration and
evaluation.
2) Throughout the surveying and setting-out the Contractor shall work closely with the
authorized local appraisers of crops and vegetation in question and shall provide them with
facilities necessary for the expeditious performance of their duties.
3) As soon as a section of work has been defined and valued, the Contractor shall delineate
the boundaries of the areas to be cleared by approved markings.
3.3.6 CHECKING OF CONTRACTOR'S WORK BY THE ENGINEER
1) All elements of the Contractor's survey work associated with the setting-out of principal
project features will be regularly checked by the Engineer during the course of the work,
and the Contractor shall provide assistance at any time as required in the performance of
such control work.
2) The Contractor may be required to provide the Engineer with any information, readings or
computations for checking.
3) The regular checks will usually be made during work breaks, but in case of urgency, the
Contractor shall restrict or stop the affected work.
4) Any checks by the Engineer shall not relieve the Contractor of his full responsibility for the
accuracy of structures and parts of them with regard to their position and dimensions.
3.4 CONSTRUCTION DRAWINGS
The Construction Drawings shall completely define each architectural, structural and plant
detail of the works to be realised.
The Construction Drawings shall be prepared in full respect of the Tender Design and technical
specifications annexed to the contract, or based on the additional Detailed Drawings provided
by the Engineer.
The Construction Drawings shall include:
1. structures in reinforced concrete or precompressed reinforced concrete, including the
shop drawings;
2. Hydro-Mechanical structures. These drawings shall contain the details regarding joints,
connections, number and position of nuts and bolts, weldings, etc.;

_______________________________________________________________________________
25
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

The Drawings shall be accompanied by accurate technical reports.

3.5 MEASUREMENT AND PAYMENT


3.5.1 SURVEY AND GROUND CONTROL POINTS
No extra measurement for payment or payment will be made for Contractor's survey and
setting-out work and the entire cost thereof shall be included in the Unit Prices for other items
of the Works.
Table 3.1-Accuracy of Transverse Nets

Traverse net for Traverse net for


additional fixpoint setting out
Number of azimuth courses azimuth n = 25 n = 50
checks not to exceed
Max. difference in cm between two d d
measurements of the distance of two d = 0.003 d + d = 0.004 d +
points (d = distance in m) 5000 5000

Azimuth closure at azimuth: check c3 c3


points not to exceed (centesimal 2 n 3 n
degrees)
Closing error in position, after azimuth f = 0.001 d + 10cm f = 0.002 d + 10cm
adjustment s s
(d = distance in m)
f = f 2 + f 2 ( cm)
s y x

3.5.2 CONSTRUCTION DRAWINGS


No extra measurement for payment or payment will be made for the above-mentioned
drawings. The related cost is included in the Unit Prices for other items of the Works.

_______________________________________________________________________________
26
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

4 SITE INSTALLATIONS AND SERVICES


4.1 SCOPE OF WORK
4.1.1 TEMPORARY SITE INSTALLATION
1) The Contractor shall be responsible for providing construction equipment, materials and
labour for the provision of all necessary Temporary Site Installations and facilities adequate
for carrying out the Works under this Contract.
2) The Contractor shall design, furnish, install, operate and maintain the Site installation,
workshops, warehouses, storage areas etc. including the related facilities.
3) Site installation carried out by the Contractor shall conform to the applicable standards,
codes and sanitary requirements in force in Republic of Uganda for such purpose.
4) The design, construction, operation and maintenance of the Contractor's temporary
installations shall be subject to inspection and approval by the Engineer.
5) All site installations and facilities provided by Contractor, shall at all times remain
Contractor's property unless otherwise specified in the Contract or agreed by the Parties.
6) Unless otherwise agreed with the Employer, upon the Completion of Works, the Contractor
shall dismantle and remove from the Site the site installations and facilities.
4.1.2 PERMANENT SITE INSTALLATIONS
1) The Contractor shall provide the following:
a. the Workers’ Camp;
b. the Management’s Camp;
c. Offices.
2) The Contractor shall provide Construction Drawings.
3) The structures shall be used by the Contractor, the Engineer and the Employer during the
construction phase.
4) The Contractor shall be responsible for the cleaning, security and maintenance of the camps
during the construction period.
5) The Contractor shall be liable for any damage to or deterioration of the structures until the
end of the works.
6) At the end of the works, the above structures shall be handed over to the Employer in perfect
condition.
4.1.3 SERVICES
1) The Contractor shall be responsible for providing services to the Employer, the Engineer
and Employer’s other contractors working for the Kabuyanda Project.
2) The services will include the rent of vehicles, the use of the medical care facilities, the use
of the communication systems, the use of survey equipment, the cleaning of offices, the
disposal of garbage, the availability of site facilities (catering, recreation and commercial
concessions), the use of the water supply, ventilation and illumination systems.
4.2 SUBMITTALS
1) Within 21 days from the date of issue of the Notice to Commence, the Contractor shall
submit to the Engineer updated layout plans showing at adequate scale the locations and
arrangement of all site installations along with the related facilities. These plans shall be
consistent with the plan submitted by the Contractor with his Bid as well as with any
amendments and additions subsequently agreed to by the Engineer and the Contractor,
and shall include:
a) camps and offices
b) Parking areas, warehouses, storage areas, and medical care facilities
c) Temporary roads
d) Water supply, sewerage, sewage treatment and disposal
e) Power supply and illumination, telephone and internet services

_______________________________________________________________________________
27
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

f) Equipment pools and mechanical workshops


g) Spoil areas, quarry and stockpile areas
h) Concrete aggregates processing plant
i) Concrete batching and mixing plant including cement storage
j) Explosives magazines
k) Security and safety arrangements
2) Within 28 days from the date of issue of the Notice to Commence, the Contractor shall
submit to the Engineer the following:
a) Detailed drawings at scale 1:500 showing the camps layout, buildings, roads,
recreation areas, utilities, etc., and drawings at scale 1:50 showing typical
construction details of all buildings;
b) Detailed design of clinic\infirmary;
c) Detailed design for industrial and potable water supply to the camps and working
areas as well as sewerage systems, sewage treatment and disposal;
d) Detailed layout drawings for electrical installations and distribution systems, at
the Site, showing voltages, outlets, and routing of power lines;
e) Detailed design and drawings including manufacturer's drawings and flow charts
for the concrete and aggregate processing plant, in accordance with the
requirements of the pertinent Sections of these Specifications.
4.3 SITE INSTALLATIONS
4.3.1 CAMPS
1) The Contractor shall construct, provide furnishings, maintain, and operate the camps
necessary for his staff and labour as well as for the staff and labour of his subcontractors.
2) The camps shall include offices, kitchens, dining rooms, recreation facilities, family
dwellings, dormitories, sanitary facilities, medical service, shops, chapel and/or mosque,
roadways, drainage, fire control, commercial facilities, and all utility services (potable water,
power, lighting, ventilating, sewage treatment and disposal, cleaning and sanitation,
garbage collection and disposal, etc.). The camps shall be large enough to accommodate
the expected peak work force.
3) The areas approved by the Engineer will be put at the Contractor's disposal free of charge
and in their natural conditions. The Contractor shall be responsible for the necessary
topographical surveys, clearing, and earthwork required for the landscaping and to provide
satisfactory foundations for buildings, streets and auxiliary facilities.
4) No camp construction shall commence until the Contractor's drawings and specifications
have been approved by the Engineer.
5) All camp buildings shall be of sound construction and neat appearance, and connected to
all utility services.
6) Food handling, preparation and serving shall be arranged by the Contractor in properly
equipped canteen buildings for all his, his subcontractors' employees, Engineer’s staff and
the Employer.
7) The prices charged by the Contractor for food, beverages, etc., available in the camp shall
be calculated on a non-profit basis.
8) The Contractor shall be responsible for keeping the camp, and the buildings within it, in
good hygienic conditions. The standards and regulations presently in force in Republic of
Uganda with regard to personnel treatment, sanitary conditions, and fire and accident
prevention shall be duly taken into account.
4.3.2 AUXILIARY BUILDINGS AND STORAGE AREAS
1) The Contractor shall provide, equip and maintain, for his own and his subcontractors' use,
main and secondary offices, warehouses, materials storage areas, fuel storage areas,

_______________________________________________________________________________
28
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

explosives magazines and other necessary auxiliary buildings.


2) Listed hereunder are the shops, warehouses, stores and stations expected to be required
for the performance of the Works under this Contract, in addition to facilities explicitly
specified elsewhere in these Specifications:
a) Mechanical repair shop
b) Electrical repair shop
c) Metalwork and wood fabrication shop
d) Main warehouse
e) Bagged cement store
f) Spare parts store
g) Gasoline and oil stations
3) The Contractor is required at all times to have at the Site at least one month's minimum
reserve of the following materials:
a) Gasoline
b) Diesel and lubricants
c) Cementitious materials (unless any other reserve requirements are given
elsewhere in these Specifications)
d) Explosives
e) Steel reinforcement
f) Medical supplies
g) Main foodstuff and beverages
4.3.3 MEDICAL CARE FACILITIES
1) The Contractor shall comply with laws and health standards presently in force in Uganda. In
the event of illness of an epidemic nature breaking out, the Contractor shall carry out and
comply with all orders, arrangements or regulations which may be issued by the
Government or local authorities.
2) The Contractor shall construct, equip, and maintain at the Site, at least the following
medical care facilities:
a) One clinic/infirmary, with two ambulances and drivers:
b) One first aid station, near the quarry
3) The clinic/infirmary shall be available and fully operational beginning of the Works. The
construction of this facility shall be such as to provide reasonable quiet, privacy,
communications, adequate ventilation, air conditioning system, light, hot and cold water,
toilet facilities and electrical outlets.
4) The first aid station shall consist of cabinets equipped with apparatus and materials
necessary for the treatment of minor injuries and the assistance for transferring the
personnel that incurs in major accidents to the site clinic/infirmary.
5) The clinic/infirmary shall have separate rooms for normal and epidemic illnesses and shall
be fully equipped and staffed to meet the requirements of the peak anticipated work load
and labour force, taking into account the nature of the Works and its occupational hazards.
6) Medical services in the clinic/infirmary shall be under the direction of a licensed
physician/surgeon on a 24-hour basis throughout the duration of the construction and shall
be available, including drugs, free of charge to all persons and participants engaged in the
Works and their families or dependents living at the Site.
7) Treatment facilities and care of seriously ill or injured patients shall be on an emergency
basis until their transfer to an established hospital is made. Standing arrangements to this
effect shall be made by the Contractor with the nearest general hospital, and the Engineer
shall be notified accordingly.
8) Upon the Completion of Works, the Contractor shall hand over the medical care facilities to
the Employer.
_______________________________________________________________________________
29
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

4.3.4 COMMERCIAL CONCESSIONS


1) Possible commercial concessions such as for laundry, catering, shops, etc., granted to a
third party by the Contractor for the use of his personnel resident at the Site, shall be
subject to approval by the Engineer. Any concession shall be revoked if the concessionaire
violates the law or the provisions governing the granting of the concession. Concessions
shall automatically terminate upon completion of the Works or in the event of the
termination of the Contract.
2) No concession shall be granted for activities that are contrary to statutory regulations or are
declared by the Engineer to be offensive to the community.
3) Concessionaires will be regarded as subcontractors of the Contractor.
4.3.5 STATIONARY PLANTS
1) The Contractor shall install and erect all plants necessary for production of filter material
and for aggregate processing and concrete batching-mixing, of sufficient capacity to meet
the planned peak requirements during construction. The plants shall be subject to approval
by the Engineer and shall be designed and fabricated according to the modern technical
criteria.
2) All plants shall be kept in good running order to ensure compliance with the materials
quality specifications. All control and measuring equipment shall be regularly serviced and
calibrated.
3) Basic characteristics of the required plants are given in the pertinent sections of these
Specifications.
4.3.6 MATERIALS TESTING LABORATORY
1) The Contractor will be responsible of all tests for the Quality Control to be performed in
connection with the concrete and other materials used for the construction of the Works.
2) The Contractor shall supply, install, operate, maintain and remove at the end of the Works a
site laboratory that will have to function as Quality Control of the Works.
3) The laboratory shall be run by Contractor's personnel experienced in sampling and testing
of materials, and quality control.
4) The Contractor’s laboratory shall be designed for performing all sampling and tests required
in the Technical Specifications.
5) All sampling and testing to be undertaken shall be under the direct supervision of the
Engineer.
6) Specialized testing may be required and which cannot be performed in the site laboratory
due to unavailability of proper equipment shall be assigned to independent organizations at
Contract’s cost.
7) The Contractor shall be responsible for the handling and transport of all materials that will
be required specialized testing.
4.3.7 COMMUNICATION SYSTEMS
4.3.7.1 Communications
1) The Contractor shall supply, install, operate and maintain a telephone switchboard,
complete with standby power supply, to connect his offices with those of the Employer and
Engineer, as well as campsite, laboratory, workshops, stores, aggregate plants, batching
plants, medical care facilities and other work areas within the Site.
2) The Contractor shall furnish a directory of the telephones installed at the Site and make it
available to the Engineer.
3) In addition to the local telephone system, the Contractor shall supply, install and maintain
mobile two-way radio transceiver sets for the Engineer's and for his service vehicles for on-
site communications.
4) Upon the Completion of Works, the Contractor shall dismantle and remove from the site
the installed site communication. However, the Employer reserves the right to purchase

_______________________________________________________________________________
30
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

some or all of the equipment.


4.3.7.2 Long-Distance Communications
1) The Contractor shall supply, install, operate and maintain the access to the national and
international telephone grid (Voice and Data).
2) The Employer will endorse the necessary license applications of the Contractor.
3) Upon the Completion of Works, the Contractor shall dismantle and remove from the Site
the installed outside communications. However, the Employer reserves the right to
purchase some or all of the equipment.
4.3.8 POWER SUPPLY AND ILLUMINATION
1) The Contractor shall provide, install and keep operational throughout the execution of the
Works his own electric power generation equipment, with a capacity sufficient to satisfy
the requirements of the Works, including electric powered construction equipment, camps,
buildings, water supply, de-watering, safety and security systems etc.
2) The power generating station shall be fitted with devices that can automatically govern the
operation of the sets according to the actual network load.
3) The Contractor shall install, operate and maintain the electrical distribution systems which
he deems necessary, including all necessary transformers, circuit breakers, disconnect and
safety switches, voltage regulators, transmission lines, poles, pole hardware, conductors
and other equipment necessary for power distribution throughout the work areas and
temporary facilities.
4) The Contractor shall ensure adequate illumination for all his working activities and at the
camp, including illumination of the streets.
5) Upon the Completion of Works, the Contractor shall:
• dismantle and remove all power generation and distribution facilities installed by
him for the temporary camps;
• overhaul and handover to the Employer all power generation and distribution
facilities installed by him for the permanent camp.
4.3.9 WATER SUPPLY
1) The Contractor shall design, install, operate and maintain water supply facilities for the needs
of the works and the camps.
2) Two separate water supply systems for raw water and potable water are foreseen.
3) The raw water will be used for construction activities and therefore it shall be treated to the
extent necessary to meet specified requirements for concrete, mortars, aggregates, curing,
etc.
4) The potable water will be used for the buildings. The potable water shall be of high quality
meeting official requirements for drinking water supply.
5) The water supply systems shall allow for the provision of water to the hydrants of the whole
site for fire fighting.
6) The Contractor shall obtain the water from suitable natural local sources, free of
contamination and unaffected by the Site construction work approved by the Engineer. For
working areas with no natural sources, the Contractor shall provide sufficient number of
water-tank trucks to cover the requirements on both the industrial as well as potable water.
7) The Contractor shall furnish, install, operate and maintain all pumps, piping, fittings, valves,
storage tanks, purification plant and chlorination for the water supply and distribution
systems, adequate in quantity and pressure. There shall be no cross connections of any kind
between the industrial and potable water supply systems.
8) Throughout the duration of the construction, the Contractor shall take regular samples
from all water supplies to examine it for suitability and treatment required, and make
weekly the bacteriological tests from potable water systems.
9) Drinking points of potable water shall be provided by the Contractor for the use of

_______________________________________________________________________________
31
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

personnel in all working areas.


10) Upon the Completion of Works, the Contractor shall:
• dismantle and remove all water supply systems installed by him for the temporary
camps,
• overhaul and handover to the Employer all water supply systems installed by him
for the permanent camp.
4.3.10 SANITATION AND SEWERAGE
1) All offices, workshops, laboratory and other occupied work buildings shall be provided with
toilets connected to properly constructed and regularly maintained septic tanks approved
by the Engineer.
2) The camp sites shall be provided with a complete, properly maintained and operated
sewerage system, including septic tanks, sewage treatment and disposal facilities. Facilities
for washing clothes shall also be provided and linked to the sewerage system.
3) Portable chemical toilets shall be provided and maintained by the Contractor for the use of
all personnel at all work locations which are remote from fixed sanitary facilities. The
Contractor shall arrange for all chemical toilets to be attended to for proper sanitary
disposal on a daily basis.
4) Upon the Completion of Works, the Contractor shall:
• dismantle and remove all sanitation and sewerage systems installed by him for the
temporary camps,
• overhaul and handover to the Employer all sanitation and sewerage systems
installed by him for the permanent camp.
4.3.11 WASTE AND GARBAGE DISPOSAL
1) The Contractor shall collect waste material and garbage from camp, offices and workshops
on a daily basis and transport them to an area approved by the Engineer where it shall be
incinerated and/or buried.
2) The Site shall be kept clean and free of refuse at all times. No waste shall be dumped in areas
other than those approved by the Engineer for waste disposal. No waste of any kind shall be
deposited in any watercourses.
4.3.12 FENCING AND SITE SECURITY
1) The Contractor's offices, workshops and storage compounds, campsites and all construction
areas where exclusion of unauthorized personnel is necessary for safety and security, shall
be adequately fenced, gated and guarded.
2) The Contractor shall employ an adequate force of properly trained security guards at the
work site and at the construction camp on 24-hour duty including Sundays and holidays.
Storage areas shall be fenced, lighted and regularly patrolled by security guards. Warehouse
buildings and explosive magazines shall be kept locked and keys accounted for at all times.
3) All employees engaged in the execution and maintenance of the Works shall wear
identification badges when at the work site.
4) The Contractor shall be responsible for the losses occurring in his installations.
4.3.13 INSPECTION BY THE EMPLOYER OR ENGINEER
The Employer and the Engineer have the right at any time to inspect any part of the
Contractor's temporary facilities, without advance notification, and to require immediate
rectification of any contravention of the specified requirements.
4.3.14 FINAL CLEAN-UP
1) Upon the Completion of Works, or when any plant has completed its functions, the
Contractor shall dismantle and demobilize all temporary facilities erected by himself or his
subcontractors, and remove all debris, objectionable material, and all other refuse which
may have been deposited on Site during the construction period. Such materials may be
deposited only in areas approved by the Engineer. The Contractor shall also remove from
_______________________________________________________________________________
32
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

the Site any plant and equipment which he finds at the commencement of the Works in
accordance with the instructions of the Engineer.
2) All excavated areas shall be filled, graded and dressed in a clean and orderly condition
acceptable to the Engineer. As far as possible, such areas should conform to the natural
appearance of the landscape.
3) No demobilization or removal of temporary facilities and equipment shall be made without
prior approval of the Engineer.
4.4 SERVICES FOR EMPLOYER AND ENGINEER
4.4.1 COMMUNICATION SYSTEMS
The Contractor shall make both the site and long-distance communications systems available
to the Employer and the Engineer.
4.4.2 SURVEY EQUIPMENT
1) Surveying instruments shall be provided by the Contractor for exclusive use of the Employer's
and Engineer's site staff. These instruments shall be brand new, of the latest design and manufactured by
reputable manufacturer acceptable to the Engineer. The instruments shall include all items
necessary for the Engineer to be able to establish horizontal and vertical control and to check
the Contractor's surveying work.
2) The Contractor shall submit to the Engineer for approval the proposed make, type, and
models with catalogues, prior to place the purchase order. The following minimum equipment
shall be provided:
• 1 No total station Make TRIMBLE, Model S9 0.5" Robotic, DR HP, Long Range
FineLock (with an accuracy of 0.8 mm) or similar complete with all accessory
items such as 2 No batteries, battery charger, memory card, power cable, carrying
case and other standard accessories supplied with the instrument;
• 3 No 360 degree TRIMBLE prism complete with telescopic range poles, circular
bubbles, extension rods and carry bags;
• 1 No TRIMBLE hardwood tripod to suit the total station;
• 1 No TRIMBLE automatic level;
• 1 No aluminium tripod to suit the automatic level ;
• 1 No, 4 metre long aluminium staff graduated at 0.005m intervals;
• 2 No, 50 metre fibron tapes;
• 3 No, 5 metre steel tapes.
3) The Contractor shall provide the Engineer with any additional surveying equipment and
materials such as pegs, mallets, stakes, nails, paint, etc., as required for checking the Works.
Any instrument which has been damaged or is non-operational shall be immediately replaced
or repaired by the Contractor.
4) Upon the Completion of Works, all surveying equipment will be returned to the Contractor.
However, the Employer reserves the right to purchase some or all of the equipment.
5) The Contractor shall make available to the Engineer any surveying instrument owned by his
surveying department, but not included in the above list of equipment, which may be
necessary for checking the Works.
4.4.3 VEHICLES
1) The Contractor shall provide, repair and maintain the following vehicles for the exclusive use
of the Engineer within 56 days after the day of receipt of the Notice to Commence:
a) 3 Nos Land Cruiser type, 4-wheel drive, minimum 5 passengers capacity
b) 3 Nos Pickup truck of 1.5 t capacity
The vehicles shall be of the latest design of Rover, Toyota or other reputable
manufacturer acceptable to the Engineer.
These cars shall be supplied brand new, fully licensed and insured, and shall be replaced

_______________________________________________________________________________
33
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

by new ones in case of repeated breakdowns. The estimated number of vehicles and the
number of months they will be required are given in the Bill of Quantities.
2) The above vehicles shall be assigned full time to the Engineer, for official and private use. In
case of breakdown or if a vehicle is undergoing repair and maintenance at the workshop, the
Contractor shall provide a replacement immediately.
3) All service vehicles shall be returned to the Contractor upon the Completion of Works.
However, the Employer reserves the right to purchase some or all of the vehicles.
4.4.4 OFFICE CLEANING AND GARBAGE DISPOSAL
1) The Contractor shall provide personnel and perform daily cleaning of the Engineer's site
offices.
2) The Contractor shall collect daily and dispose of, in a location and manner approved by the
Engineer, all domestic waste and garbage from the Engineer's site offices and housing
compound. Collection times shall be arranged for the convenience of the Engineer.
4.4.5 MEDICAL CARE FACILITIES
The Contractor's medical care facilities shall be made available for use by the Employer's and
Engineer's site staff and their families or dependents living at the Site.
4.4.6 CATERING, RECREATION FACILITIES, AND COMMERCIAL CONCESSIONS
1) The Contractor's catering and recreation facilities including canteen, and commercial
concessions shall be made available for use by the Employer's and Engineer's site staff and
their families living at the Site on the same terms and conditions as the Contractor's personnel
of equivalent rank.
2) The Contractor shall take care that these facilities and supplies available are suitable for
expatriate personnel.
3) The Contractor’s canteen facilities shall be designed and operated in such a way that the
Employer’s personnel may have meals which are prepared in accordance with Ugandan
customs.
4.5 MEASUREMENT AND PAYMENT
4.5.1 SITE INSTALLATIONS
4.5.1.1 Camp, Auxiliary Buildings, Materials Testing Laboratory and Storage Areas
1) Payment for the camp, auxiliary buildings, materials testing laboratory, storage areas and
appurtenant facilities will be made as Lump Sum entered in the Bill of Quantities.
2) Payment shall cover the entire cost of design, delivery, land preparation, earthmoving,
fencing, tests, dismantling, removal from Site and reinstatement of the Site.
3) Payment will be made in two instalments. The first, of 85% will be made when the said
facilities are, in the opinion of the Engineer, fully installed, commissioned and ready for use.
The second, of 15% will be made:
• for the temporary site installation: upon removal and Site reinstatement to the
satisfaction of the Engineer;
• for the permanent installation: after verification of the efficient working
conditions of the installations by the Engineer.
4) Should the Contractor fail to execute the final clean-up to the full satisfaction of the Engineer,
the second instalment of 15% will be retained. In the event that this amount proves to be
insufficient for financing of the Site reinstatement, all extra costs shall be deducted from the
money due to the Contractor.
4.5.1.2 Stationary Plants
1) Payment for the stationary plants (aggregate processing plant and concrete batching and
mixing plants), including the related facilities, will be made at the Lump Sum price entered in
the Bill of Quantities.
2) Payment shall cover the entire cost of design, delivery, earthmoving, installation and tests,
dismantling, removal from Site and reinstatement of the Site.
_______________________________________________________________________________
34
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

3) Payment will be made in two instalments. The first, of 85% will be made when the said
facilities are, in the opinion of the Engineer, fully installed, commissioned and ready for use.
The second, of 15% will be made upon removal and Site reinstatement to the satisfaction of
the Engineer.
4) Should the Contractor fail to execute the final clean-up to the full satisfaction of the Engineer,
the second instalment of 15% will be retained. In the event that this amount proves to be
insufficient for financing of the Site reinstatement, all extra costs shall be deducted from the
money due to the Contractor.
4.5.1.3 Exclusions
No separate payment will be made for, but not be limited to, the following Contractor's
temporary installations and facilities and the entire cost thereof shall be included in the Unit
Prices and Lump Sum of the Bill of Quantities:
a) Medical care facilities;
b) Commercial concessions;
c) Communication systems;
d) Power Supply and Illumination;
e) Water supply;
f) Sanitation and sewerage;
g) Waste and garbage disposal;
h) Fencing and site security.
4.5.2 SERVICES FOR EMPLOYER AND ENGINEER
4.5.2.1 Communication Systems
No separate payment will be made for the use of the Contractor’s communication systems,
except for the long-distance telephone communications bills, which will be issued by the
public service utility.
4.5.2.2 Survey Equipment
1) Payment for the rental and maintenance of survey equipment will be made as Lump Sum
entered in the Bill of Quantities, which shall cover the entire cost of furnishing and maintaining
of the equipment and accessories.
2) Payment for survey equipment will be made in two instalments. The first, equal to 90% of the
Lump Sum, will be made when the complete equipment is handed over to the Engineer. The
second, equal to 10%, will be made at the completion of the works.
4.5.2.3 Service Vehicles
1) Payment for the service vehicles will be made under two headings:
a) Supply of each Vehicle
b) Operation Cost of each Vehicle
2) Payment for supply of the vehicles will be made at the Lump Sum entered in the Bill of
Quantities, at the time of delivery of the requested vehicle, fully licensed, insured and road
worthy. The Lump Sum shall include the entire cost for supply, transport to site, taxes, duties
and the driver’s salary. The driver’s salary shall include all compensation for night work, work
on weekends or holiday, vacations, social and security contributions, and taxes as prescribed by
the rules and laws of Uganda.
3) Payment for operation will be made at the unit price per kilometer entered in the Bill of
Quantities, which shall cover the entire cost of servicing and maintaining of the vehicles. In
particular the unit price shall include the supply of fuel, lubricants, spare parts and tires.
4.5.2.4 Medical Care Facilities
No separate payment will be made for the use of the Contractor’s medical care facilities, and
the entire cost thereof shall be included in the Unit and Lump Sum Prices of the Bill of
Quantities.
4.5.2.5 Catering, Recreation Facilities and Commercial Concessions
1) The Employer's and Engineer's employees will directly reimburse the Contractor for the use of
_______________________________________________________________________________
35
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

Contractor's catering facilities.


2) Payment will be made at the unit price entered in the Bill of Quantities for every meal
(breakfast, lunch and dinner) served in the canteen to Engineer's site staff or dependents living
at the Site.
3) No separate payment will be made for the use of Contractor’s recreation facilities and
commercial concessions, and the entire cost thereof shall be included in the Unit and Lump
Sum Prices of the Bill of Quantities.
4.5.2.6 Waste and Garbage Disposal
No separate payment will be made for the waste and garbage disposal service performed by
the Contractor, and the entire cost thereof shall be included in the Unit and Lump Sum Prices
of the Bill of Quantities.

_______________________________________________________________________________
36
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

5 CARE OF WATER DURING CONSTRUCTION

5.1 SCOPE OF WORK


1) The Contractor shall provide all labour, material, and equipment necessary to build and
maintain the Temporary Works for protecting the Works under construction against flood flows
in the rivers and creeks, and to design, build, install, operate, maintain and dismantle the
temporary de-watering facilities required to remove service water and natural surface flow or
groundwater seepage from the working areas.
2) The temporary works and facilities for the care of water during construction shall be designed by
the Contractor, subject to the approval of the Engineer.
3) All such Temporary Works and dewatering facilities shall be removed at the end of the works, so
as to give a slightly appearance and not to interfere in any way with the operation or usefulness
of the permanent works, except different authorization of the Engineer.
4) The Contractor shall not interrupt or interfere with the flow of the Mishumba River or other
streams for any purpose without the approval of the Engineer.
5) The areas of the temporary protection works shall be readily accessible at all times and the
Contractor shall make continuous survey of floods to the satisfaction of the Engineer.
6) The hydrology of the Mishumba River and the discharge capacity of the main river diversion
facilities shown in the drawings or in the Information for Bidders are to be regarded as merely
indicative to aid the Contractor in his planning of the construction works.
7) The Employer and the Engineer do not guarantee the reliability or accuracy of this information
and assume no responsibility for any interpretation or conclusion which may be made or drawn
by the Contractor.
8) The Contractor shall be fully responsible for any damage or delay to the Works caused by failure
of his protective works.
9) The Contractor shall also be responsible for and shall repair or reinstate at his expense any
damage to foundations, excavation slopes or any other part of the Works caused by the failure
of the protective works and/or pumping installation.
5.2 SUBMITTAL
1) The Contractor shall submit to the Engineer the design, including full details of equipment to be
installed and all necessary construction details required for the de-watering purposes, at least
30 days prior to scheduled construction of the particular work.
2) This design shall be consistent with the outline description submitted by the Contractor with his
Bid, and shall include the following:
a) Design assumptions and calculations
b) Layouts of diversion and drainage facilities
c) Layout and capacity of pumps and pipes, sumps, drains, etc.
d) Any other arrangements or installations the Contractor may propose for
temporary protection of the Works and de-watering of the surface working areas
5.3 RIVER DIVERSION
5.3.1 GENERAL
A possible solution for river diversion is proposed in the tender documents and drawings. This
solution comprises of:
1. Phase 1: EXCAVATION OF INLET AND BARREL WORKS;
2. Phase 2: CONSTRUCTION OF
• INLET AND BARREL
• RE-FILLING WITH EXCAVATED MATERIAL:
3. Phase 3: CONSTRUCTION OF APPROACH & TAIL CHANNELs;
4. Phase 4: CONSTRUCTION of the U/S and D/S COFFERDAMS;
_______________________________________________________________________________
37
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

5. Phase 5: PLUGGING of the DIVERSION BARREL.


The most suitable choice for the diversion works strongly depends on the means and needs
of the Contractor.
The Contractor shall propose his own alternatives and submit them to the Engineer for his
approval. Should the Contractor elect to adopt the proposed tender solution, he shall execute
it under his own responsibility.
5.3.2 REQUIREMENTS
1) The Contractor shall construct the upstream cofferdam, the downstream cofferdam and the
other auxiliary works.
2) The Contractor shall maintain throughout the entire construction period the diversion
structures as necessary to keep unchanged the discharge capacity of the diversion canal and
the safety conditions of the upstream and downstream cofferdams. In particular, the
Contractor shall keep the entrance of the barrel free from all floating debris that may get
stuck against the entrance structure.
3) The Contractor shall perform all works necessary to drain the dam, spillway, control building,
and intake foundation area of rain, groundwater, seepage water through the bodies of the
cofferdams, and service water.
5.4 OTHER FLOOD PROTECTION WORKS
5.4.1 REQUIREMENTS
1) The work shall be executed in accordance with the Contractor's drawings, specifications and
sequences as approved by the Engineer.
2) The flood protection works shall be designed in such a way that they will not interfere with
any work to be performed or with any permanent structure.
3) The approval given by the Engineer shall not relieve the Contractor from being fully
responsible for the design, construction, maintenance, safety and removal of the works as
specified herein, and he shall be fully liable for any damages or delays caused by its failure.
The Contractor shall indemnify the Employer against claims arising out of any such failure,
made by other contractors, landholders or any other persons.
5.4.2 MATERIALS AND EXECUTION
1) The Contractor shall select material and construction methods he considers appropriate for
the flood protection works, subject to approval by the Engineer.
2) Seepage through dikes, cofferdams and surface runoff from adjacent areas shall be properly
collected and disposed of.
3) Should the Contractor notice that any part of the flood protection works is in such condition
that it poses a serious risk, he shall notify the Engineer immediately of the situation, no
matter what the causes. Remedial measures approved by the Engineer shall be undertaken
without delay.
4) After they have served their purpose, the dikes, cofferdams or other protective works shall be
removed as needed to such level as not to interfere in any way with the operation of
Permanent Works and with the flow of water.
5) The removal of the flood protection works shall cause no undue interference with other
works and the Contractor shall be responsible for any damage to Temporary or Permanent
Works caused by the removal of flood protection works.
5.4.3 DIVERSION OF CREEKS
1) Creeks in the stockpile, spoil, and quarry areas or where required by the construction of any
permanent structure shall be diverted into culverts or ditches lined as required to prevent
ditch erosion. Waters that have become sediment laden due to construction activities shall be
handled according to the requirements for soil erosion and pollution control as stipulated, and
as follows:

_______________________________________________________________________________
38
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

a) Sediment laden water caused by road transport activities shall be diverted


through settling ponds
b) Check dams shall be constructed as required downstream from spoil areas to
detain sediments laden waters long enough for sediments to settle down
2) The peak capacities of the systems shall be selected taking into account the extent of the sites
to be de-watered and the diversion arrangements proposed.
5.5 CARE OF WATER AT CONSTRUCTION SITES
5.5.1 GENERAL
The Contractor shall perform all works necessary to drain and dewater the construction sites of
rain, groundwater and service water. The work shall include, but not be limited to the following:
a) Design and construction of drainage, ditches, pits, pump sumps and settlement
ponds with oil separators
b) Design, furnishing, operation and maintenance of de-watering equipment
c) Relocation of de-watering facilities required for the performance of other works
d) All auxiliary works required for safe and continuous de-watering of the
construction sites
5.5.2 REQUIREMENTS AND DESIGN
1) The Contractor shall design and install complete facilities for all construction sites.
2) The de-watering systems shall be designed to accommodate, without undue disruption to the
work, any rainfall event. The peak capacities of the systems shall be selected to satisfy the maximum
intensity, taking account of the extent of the sites to be de-watered and the de- watering
arrangements proposed.
3) Claims for extension of time due to delays caused by unfavourable weather conditions will
not be considered.
4) The Contractor shall provide, install, maintain, and operate adequate pumping and other
equipment, including standby units, to handle all water entering into any of surface
construction sites. In addition, he shall provide sumps and pumps in the immediate vicinity of
the structure foundations using such water conductors as are necessary to conduct the water
away from the excavation and concrete placement operations in an approved manner, so that
such operation shall be kept free from standing or running water.
5) The Contractor shall ensure that all drainage water will be disposed of without causing
interference to his own or other contractors operations elsewhere at the Site and that no
drainage water runs into adjacent Works. Water discharged from work areas shall meet the
requirements for pollution control referenced above.
6) The de-watering systems shall be designed and installed in such a way that modifications and
extensions to the systems are possible while they are in full operation.
7) All the components of the de-watering systems shall be installed and operated in accordance
with the agreed method and the construction time schedule, or approved modification
thereof.
8) The approval by the Engineer of the de-watering system shall not relieve the Contractor from
being fully responsible for the design and operation of the de-watering systems and he shall
be liable for any damage or delays caused by its failure. The Contractor shall indemnify the
Employer against claims arising out of any such failure, land holders or other persons.
5.5.3 SURFACE EXCAVATION DEWATERING
1) Drainage ditches shall be excavated along the top of excavated slopes and on the berms. Such
ditches shall be kept well back from the excavation edges in order to prevent saturating the
upper part of the slopes. The ditches shall be regularly cleaned out of all accumulated silt and
other matter so that water may flow freely at all times.
2) The Contractor shall take measures to ensure that the foundation surfaces remain free of

_______________________________________________________________________________
39
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

standing water and undamaged by the passage of construction traffic. All ditches shall be
outside the foundation areas. The water shall be collected and removed by pumping if no
outflow by gravity is possible.
3) Where excavation is to be made below the groundwater table in loose material, the Contractor
shall lower the water table sufficiently below any working surface in advance of the excavation
by proper means.
4) Where concrete is to be placed, the water table shall be maintained below the lowest part of
the finished excavation for minimum one day following the raising of structure above the
natural groundwater table, and for such additional time as may be necessary to preclude
damages to structure foundation.
5) Upon completion of de-watering, temporary pipes and pump sumps beneath permanent
structures shall be closed off and completely filled with grout, mortar or concrete as required
by the Engineer.
5.6 MEASUREMENT AND PAYMENT
5.6.1 RIVER DIVERSION AND CARE WATER DURING CONSTRUCTION
1) Payment for the diversion works will be made at the appropriate lump sum price entered in
the Bill of Quantities. Any alternative proposed by the Contractor for river diversion shall not
result in a variation to the lump sum price entered in the Bill of Quantities.
2) Payment for the maintenance throughout he construction period of the diversion structures,
for the provision and operation of the facilities required to de-water the culvert, will be made
at the single lump sum provided in the Bill of Quantities, which shall include, but not limited
to, the provision of all labour, material, plant, equipment and auxiliary works required.
Payment of the lump sum will be made as follows:
a) four (4) equal instalments of 20% each at five months intervals, starting five
months after the signature of the Contract.
b) The balance corresponding to 20% of the lump sum, at the end of the works.
3) Payment for removal of the downstream cofferdams will be made at the appropriate lump
sum price entered in the Bill of Quantities.
5.6.2 OTHER FLOOD PROTECTION WORKS
No separate payment whatsoever will be made for other flood protection works and relocation
of creeks during construction, and all related costs for the provision of labour, material, plant,
equipment and auxiliary works etc. required for design, construction, installation and removal of
dikes and other protective works shall be deemed to be included in other items of the works.
5.6.3 CARE OF WATER AT CONSTRUCTION SITES
No separate payment whatsoever will be made for the care of water at construction sites and
all related costs for the following shall be deemed to be included in other items of the works.
a) Design of all de-watering systems
b) All labour for excavation, construction and protection of drainage ditches, wells,
pits, pump sumps and settlement ponds
c) Capturing and conveying the water into the drainage system
d) Supply, installation, operation, maintenance and removal of all pumps, pipes and
equipment for pumping water, regardless of the amount of water
e) Grouting of pipes and pump sumps where required
f) All auxiliary works required

_______________________________________________________________________________
40
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

6 EXCAVATION AND FILLING


6.1 SCOPE OF WORK
1) This Section covers the surface excavation and fill works to be performed under this Contract. The
excavation shall consist of removing all existing material of whatever nature to the lines and
grades shown on the Detailed Design and/or Construction Drawings as otherwise directed by the
Engineer and shall include drilling and blasting, loading, hauling and disposal of materials in
designated spoil or stockpile or fill areas.
2) Rock support, slope protection, stabilization measures, sprayed concrete, de-watering, and
exploratory drilling, which may be needed in conjunction with excavation work, are covered in
other Sections of these Specifications.
3) The Contractor shall comply with all safety procedures and requirements as stipulated in the
"Safety Precautions".
4) The approval given by the Engineer to the Contractor's methods and equipment shall not
relieve the Contractor of his full responsibility for the proper and safe execution of surface
excavations, or of liability for injuries to, or death of persons, or any obligations under this
Contract.
6.2 SUBMITTAL
1) At least 28 days prior to the commencement of any excavation, the Contractor shall submit to
the Engineer details of the proposed excavation methods and sequences, necessary site
drainage and safety precautions, including (if necessary) equipment and rock supports.
2) Where the excavation for the main permanent structures involves blasting, the data shall
include the following:
a) Location and area of blast
b) Diameter, spacing, depth, pattern and orientation of blast holes
c) Type, strength, amount, column load and distribution of explosives to be used
per hole, per delay and per blast
d) The type of detonators, powder factor, and sequence and pattern of delays to be
used per blast
e) Description and purpose of any special method to be adopted by the Contractor
3) The plans shall be in conformity with detailed requirements for excavation sequencing, for
blasting and for precautions in proximity to concrete and grouting operations.
4) At least 14 days prior to dumping or stockpiling any material, the Contractor shall submit the
layout of spoil or stockpile areas, which will be within areas approved by the Engineer. All
pertinent data of working methods and provisions for the security, stability and temporary and
permanent drainage of the areas shall be included. Details of volumes, material types, heights
and grades shall be provided.
5) Prior to starting any excavation in any particular area, the Contractor shall confirm in writing his
agreement with the existing surveys and topographical data showing the original ground
surface for the area in question which will be used for measurement purposes. Should the
Contractor have any doubts as to the correctness, or sufficiency, of such data, he shall carry out
an independent survey on his own and submit his survey to the Engineer for approval. In case
of disagreement, the Engineer and Contractor shall mutually review the existing data. The
agreement concerning the location of the original ground surface must be reached before
commencing excavation work. Contractor's failure to follow the procedure outlined above will
forfeit his right to claim any other locations of the original ground surface than that established
by the Engineer.
6) To enable the Engineer to verify all necessary elevations and cross-sections of the original
ground surface, prepared by the Contractor, the latter shall notify the Engineer in writing, giving

_______________________________________________________________________________
41
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

at least 7 days notice before the commencement of any excavation. The Contractor shall clear,
in advance, all vegetation that may interfere with this survey work.
6.3 LINES AND GRADES
1) The Contractor shall be responsible for setting-out all the structures and slopes as shown on the
Detailed Design and/or Construction Drawings in accordance with the Section 3, "Surveying and
Setting-out Work". All extra work and over excavation caused by improper setting-out by the
Contractor shall be corrected by himself immediately upon the request of the Engineer.
2) The final excavation grades are defined by line and grade, the Contractor shall take every
precaution, and use the most appropriate method of excavation, to avoid the loosening of
material or the breaking of rock beyond the lines and grades shown on the Detailed Design
and/or Construction Drawings.
3) All excavated surfaces shall be trimmed to line and grade. Upon request of the Engineer, the
final 20 cm of any loose geological formation in excavations where concrete is to be placed,
shall be excavated by hand methods to avoid disturbance of rock, at no extra cost.
4) Excavation beyond the lines and grades shown in the Detailed Design and/or Construction
Drawings, or as modified by the Engineer, is defined as overbreak.
5) If, for any reason, excavation is carried out beyond the lines and grades shown on the Detailed
Design and/or Construction Drawings shall remove the material resulting from the overbreak
and backfill with concrete or shotcrete, as directed by the Engineer, the same overbreak.
6) Should the Contractor wish to excavate beyond the limits given on the Drawings for his own
convenience, he may do so only with the prior consent of the Engineer.
6.4 SLOPES, SLIDES, GEOLOGICAL OVERBREAK AND UNSUITABLE FOUNDATIONS
1) If geological conditions during the performance of the surface work do not permit excavation of
slopes as shown on Detailed Design, or where the material is unsuited to a firm foundation for
the structures, the Engineer may modify the drawings accordingly or issue direct order to
change the slopes and grades.
2) If, in the Contractor's opinion, the surface slopes as shown on Detailed Design are unsafe or
otherwise objectionable, and in his opinion should be changed, he shall ask in writing for
technically justifiable modification prior to starting the work, or in the course of the work, but in
any case before commencing such modified excavation. Only if consent has been given by the
Engineer may he change the slopes.
3) Geological accepted overbreak in surface excavation is defined as overbreak which occurs while
both of the following conditions are simultaneously fulfilled:
a) The Engineer is informed and given an opportunity for inspection while both the
cause and the extent of the overbreak are clearly visible;
b) The overbreak did not occur while, in the opinion of the Engineer, the Contractor
was using improper working methods or was otherwise negligent, and it could
not have been prevented by prompt and appropriate installation of supports.
6.5 EXCAVATION
6.5.1 GENERAL
1) The Contractor shall conduct his operations so as to produce the required lines and grades.
2) The surface excavation shall be performed by any approved method using any excavating and
hauling equipment suitable for the work in accordance with the submitted detailed plans and
time schedule, or approved modifications thereof.
a) The work areas shall be properly drained in accordance with the provisions of the
Section 5, "Care of Water During Construction".
b) The Contractor shall carry out periodic cleaning to ensure that no hazardous
accumulation of loose material occurs on the slopes or on any berm or ledges

_______________________________________________________________________________
42
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

forming part of the excavation profile.


c) Excavation for dam and structure foundations shall be performed in the dry. Final
surfaces shall be protected against damage by erosion and travel of the construction
equipment. Any damage caused shall be repaired by the Contractor.
d) Rock surfaces at sensitive locations shall be carefully excavated and preserved during
construction. Pre-splitting or smooth blasting techniques shall be used as
appropriate. Rock supports shall be installed where indicated on the Detail Design
and/or Construction Drawings, or directed by the Engineer, to suit the actual geologic
conditions encountered.
e) The Contractor shall exercise particular care when excavating in the vicinity of existing
structures or those under construction. He shall be liable for any damage to
structures or equipment caused by his operations. Acceleration due to the blasting
shall be monitored as specified hereinafter.
f) The Contractor shall protect the subsoil and particularly the ground water from
contamination by fuel or oil from his equipment.
g) When existing obstructions such as buried pipelines and cable ducts are not indicated
on the Detail Design and/or Construction Drawings, but are encountered and
interfere with required work, relocation or protection will be requested by the
Engineer. The Contractor shall not proceed until he receives the written approval and
instructions from the Engineer.
h) The Contractor must avoid any alteration to the foundation material. Should this
occur, the Contractor shall, at his own expense, deepen the excavation front until a
suitable foundation is reached.
6.5.2 CLASSIFICATION OF EXCAVATION
1) Surface excavation is classified according to the method used to carry out the work, as
follows:
a) Clearing and Grubbing
b) Stripping and Common Excavation
c) Excavation by Ripping
d) Rock Excavation by Blasting
e) Minor Excavation Works
f) Borrow and Quarry Excavation
2) Miscellaneous excavation includes:
a) Additional Excavation
6.5.3 CLEARING AND GRUBBING
1) Clearing means the removal, transport and disposal of all trees, brush, stumps, fences,
existing structures, debris and other obstructions in the areas to be occupied by Permanent
Works, surfaces of borrow and quarry areas, spoil and stockpile areas, and where interfering
with the prosecution or functioning of the work.
2) The Contractor shall clear the areas indicated by the Engineer of all trees, stumps and brush
which are 1 m or more in height, regardless of diameter, and thicker than 5 cm or more,
regardless of height. Trees and stumps shall be cut off not higher than 20 cm above ground.
Brush shall be cut off, as far as possible, flush with the ground level. All down timber, branches or
other floatable material longer than 1.5 m or thicker than 5 cm shall be removed.
3) The clearing limits shall extend 5 m beyond the limits of excavation, toes of embankments
and spoil tips except where otherwise indicated on Detail Design and/or Construction
Drawings or directed by the Engineer.
4) No trees shall be cut outside of the clearing limits without prior approval by the Engineer. All
trees designated by the Engineer to be left intact shall be protected from damage by the
Contractor's operations.
_______________________________________________________________________________
43
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

5) Grubbing means the removal, transport and disposal of all roots, buried logs, foundations of
structures (except concrete or masonry in mortar) and other materials foreign to the natural
topsoil in the areas to be occupied by Permanent Works and surfaces of borrow and quarry
areas.
6) No grubbing will be required in the areas not excavated, and in spoil and stockpile areas.
7) Clearing and grubbing work shall be performed either manually or with mechanical
equipment. The Contractor shall make every reasonable effort to salvage such material which
may be put to beneficial use.
8) All materials from clearing and grubbing work remain at all times the property of the Employer
and they shall be prepared for sale, burnt, buried or otherwise disposed of by the Contractor
in areas as directed by the Engineer.
9) All wood and vegetation shall be disposed of in such a way that it cannot become floating
debris in the future reservoir.
10) Materials to be burnt shall be piled neatly in such a manner and in such locations as to not
cause any fire risk and shall be burnt completely so that all material is reduced to ashes.
11) The Contractor shall have suitable equipment and supplies for fighting fire during the burning
of material and shall take all necessary precautions to prevent fire from spreading.
6.5.4 STRIPPING AND COMMON EXCAVATION
1) Stripping consists of removing all rubbish, humus, vegetable material and all or part of the
organic topsoil in the areas and to the depth as indicated on Detail Design and/or Construction
Drawings or as directed by the Engineer.
2) Common Excavation means excavation of material such as organic topsoil, clay, silt, sand,
gravel, and boulders of up to 0.75 m3 in volume and soft or disintegrated weathered rock,
which can be removed by bulldozer with ripper as specified in subsection 6.5.5.
3) Stripping and common excavation shall be accomplished by proper excavation and hauling
equipment suitable for the work which allows for an efficient work progress adapted to the
soil conditions encountered.
4) When the bottom of excavation as indicated on the Detailed Design and/or Construction
Drawings is not rock and the natural foundation material is disturbed or loosened for any
reason, the Contractor shall improve it by compaction or replace it with approved fill and
compact as directed by the Engineer.
6.5.5 EXCAVATION BY RIPPING
1) Rippable material is defined as rock which can be loosened or broken down by a bulldozer
capable of developing 220 kW (300 PS) of continuous power equipped with a single shank
rock ripper, operating in low gear.
2) Material which in the opinion of the Contractor should be removed by ripping shall be
exposed, and the Engineer notified before proceeding further. The top of the rock surface
shall be surveyed by the Contractor. The survey and classification is subject to approval of the
Engineer.
3) Contractor’s failure to follow the procedure outlined above will forfeit his right to claim any
classification other than that allowed by the Engineer, who, in such case, will classify the
excavated quantities.
4) Ripping shall be performed in such manner that the ripper tooth does not damage the
material laying beyond the final excavation lines. Any material remaining to the final
excavation lines shall be removed by wedging, barring, broaching, or other suitable methods
approved by the Engineer.
6.5.6 ROCK EXCAVATION BY BLASTING
1) Rock excavation by blasting includes all solid rock in place which cannot be removed until
loosened by blasting or mechanical breakers, and boulders or detached pieces of solid rock
larger than 0.75 m3 in volume, which cannot be removed by ripping.
_______________________________________________________________________________
44
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

2) Material which in the opinion of the Contractor can be removed only by blasting, shall be
exposed, and the Engineer notified before commencing with blasting. The top of the rock
surface shall be surveyed by the Contractor. The survey and classification is subject to
approval of the Engineer.
3) Contractor's failure to follow the procedure outlined above will forfeit his right to claim any
classification other than that allowed by the Engineer, who, in such case, will classify the
excavated quantities.
4) Lines shown on the Drawings such as "sound rock", "top of rock" etc., are approximate and
for information only. They will not be used for measurement purpose.
5) Drilling and blasting shall be done in such a manner as to ensure that the rock will break
along the desired lines and grades. Rock shattered by blasting operations outside the
established limits of excavation shall be removed and replaced by concrete if necessary. Rock
faces and slopes shall be scaled or cleaned of loose or overhanging rock immediately after
excavation. Rock surfaces, both temporary and permanent, shall be regularly inspected by the
Contractor and rectified whenever necessary.
6) The diameter and the spacing of the blast holes shall be constantly adapted to the actual
conditions at the Site. The Contractor shall develop the blasting techniques as the work
progresses to obtain the best possible excavation surface after blasting. The techniques used
shall be at all times subject to the Engineer's consent, who may order general blasting tests to
be undertaken by the Contractor to substantiate his proposed methods of blasting.
7) Rock excavation close to the final excavated surfaces shall be performed using controlled
blasting methods such as "presplitting", or "smooth-wall blasting". Presplitting involves a
single row of closely spaced holes along the neat excavation line which are fired before the
main charge, with a result of creating of a clean fracture running from hole to the next.
Smooth-wall blasting is similar to presplitting exempt that line of holes is fired after the main
blast.
8) The excavation shall be made to sufficient depths to secure foundations on rock of adequate
quality free from highly weathered materials or other objectionable defects, as determined
by the Engineer. The exploratory investigations of the foundations are not sufficiently
complete to disclose all seams, defects, and other irregularities that may exist in the
foundation rock. The lines of excavation shown on the Detailed Design shall therefore not be
interpreted as indicating the final or actual lines of excavation or that no defects exist. The
excavations at all elevations shall be so shaped as to produce as uniform and regular a profile
as is practicable to obtain using excavation methods described herein.
9) The final excavated surfaces of outdoor works shall have no abrupt changes in slope and
sharp projections greater than 50 cm. Projections in excess of 50 cm shall be treated where
necessary by supplementary excavation as determined by the Engineer, to produce the
desired surface of contact between concrete and rock.
10) Whenever, in the opinion of the Engineer, further blasting may injure the rock upon or against
which concrete is to be placed, or is otherwise undesirable, the use of explosives shall be
limited to light charges or discontinued, and the excavation shall be completed by wedging,
barring, line-drilling or other suitable methods approved by the Engineer.
11) Should the presence of rock make excavation for foundation of structures unnecessary to the
extent shown on the Detail Design and/or Construction Drawings, the Contractor shall consult
the Engineer before proceeding with such work. The Engineer will issue a direct order in
writing whether to proceed with the work as shown or to which extent the work shall be
modified.
12) When the excavation has been completed to the approximate grade, as shown on Detail
Design and/or Construction Drawings or established by the Engineer, the surface shall be
cleaned off by barring, wedging, picking or other approved methods, and with an air and/or
_______________________________________________________________________________
45
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

water jet under high pressure for purpose of inspection. If the foundation is found to be not
satisfactory, as determined by the Engineer, supplementary excavation shall be made as
directed, and the surface again cleaned for inspection. This procedure shall be repeated until
a satisfactory foundation is obtained. Just prior to placing the concrete, a final cleanup of the
rock surface shall be made. All loose, shattered, or disintegrated material shall be removed,
and the final surface cleaned with jets of air and/or water under high pressure.
6.5.7 MINOR EXCAVATION WORKS
1) Minor excavation work consists of excavation, in all materials, of trenches less than or equal
to 2 m of width, or excavation in small and restricted areas, which has to be carried out
manually or using small equipment.
2) The Contractor shall excavate to the limits, lines and grades shown on the Detail Design
and/or Construction Drawings.
3) Bracing, shoring or other methods of supporting the excavation shall be carried out as
necessary.
4) Mechanical excavation of trenches, except those in rock, shall be stopped not less than 10 cm
above final excavation level. The remainder of the excavated material shall be removed,
shaped and graded manually.
5) In rock, the trenches shall be excavated to such depth that space for placing of compacted
sand bedding at least 10 cm thick shall be provided between the rock and the underside of
any equipment or pipe.
6.5.8 BORROW AND QUARRY EXCAVATION
1) The borrows area and quarries will provide materials for the construction of the dam, as well
as the concrete works.
The dam body will be realized with the following materials:
• crushed rockfill for upstream facing, for the fine and coarse filters;
• CL / SC for the dam body.
2) The crushed rockfill for the dam as well as for the concrete aggregates will come from the
quarry identified and illustrated in the Geo-technical Baseline Report. At the moment the
quarry is already being exploited as a tin mine, but only as far as the tin is concerned and not
the rock material so the Contractor will have to make suitable arrangements with the mining
company to remove this material. Currently the rock material is crushed and stockpiled as
waste. It is estimated that the mine produces approximately 20,000 m3/month of rock.
The Contractor may however select a different quarry area that will be subject to approval by
the Engineer.
The CL/SC materials will be taken from the flat area of the dam axis (upstream and
downstream) if suitable.
The characteristics of the material are indicated in the Geotechnical Baseline Report.
3) Prior to commencing borrow and quarry excavation, the Contractor shall clear and strip the
area and remove all material which is unsuitable for use in the construction of the Works.
Topsoil shall be stripped from the excavated areas and stockpiled for future use apart from
other excavated material. The Contractor shall, at his own expense, carry out all necessary
tests to verify the amount of usable material.
4) The Contractor shall make such tests, use such equipment, and vary his excavating methods
and blasting patterns as necessary to produce the required grading, uniformity or mixture of
each material, and shall be fully responsible that those materials meet the specifications, and
for adequacy and safety of the quarrying and borrowing operations.
5) Borrow excavation will produce material for fills, backfills, road bases and subbases, etc. If
required to prevent excessive moisture, the Contractor shall lower the water table in the
borrow area by appropriate means, stockpile the excavated material to permit drying or
perform such work as necessary to reduce the moisture content.
_______________________________________________________________________________
46
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

6) Borrow areas (except those located within the future reservoir) shall be kept graded and
drained so that water will not collect or stand there. Upon completion of the work, excavated
surfaces shall be left with stable slopes not steeper than two horizontal to one vertical.
Unless specifically waived by the Engineer, the slopes and bottoms of the borrow pits shall be
evenly graded to present a neat and orderly appearance. Tracks or marks of heavy equipment
or other disturbed earth shall be smoothed or filled to the surrounding level. The stockpiled
topsoil shall be evenly spread over the subsoil exposed by the excavation.
7) Quarry excavation will produce material for concrete aggregates, road bases and sub-bases,
filters, fills, backfills etc. Unsuitable material or material not required for permanent
construction purposes found in the quarry shall be left in place, or, with the approval of the
Engineer, shall be excavated and disposed of in an approved spoil area. The Contractor shall
avoid contamination of construction material by such unsuitable material.
8) During excavation at the quarry, if necessary, berms approximately 3 m wide at 15 m vertical
intervals shall be provided.
9) During quarrying operations the Contractor shall take precautions in order not to interrupt
the traffic along nearby roads and provide personnel and devices to warn the road users of
blasting.
10) On completion of the exploitation the Contractor shall ensure that the quarry is left in a safe
and tidy condition to the satisfaction of the Engineer.
6.5.9 ADDITIONAL EXCAVATION
1) The Contractor may be directed by the Engineer to perform excavation beyond the lines and
grades of already completed work. Such excavation shall be defined as additional excavation.
2) Additional excavation may consist of any or all classes of excavation stipulated in this Section.
6.6 LINE-DRILLING
1) Line-drilling shall be used where pre-splitting may cause excessive damage to the
surrounding rock or where there are structures adjacent to the excavation.
2) Line-drilling is defined as a single row of unloaded holes drilled along the neat excavation
line, spaced no more than two times the hole diameter on centers. These will form asurface
of weakness to which the primary blast can break. Light blasting with well-distributed charges
fired after the main excavation is removed may be permitted in the holes. If, however, in the
opinion of the Engineer the blasting may injure the rock, the use of explosives shall be
discontinued and the excavation shall be completed by broaching, wedging, or barring.
6.7 PROTECTION AND SUPPORTS
6.7.1 GENERAL
1) The Contractor shall secure the stability of any excavation by using, where necessary, suitable
protection and supports in quantities sufficient to avoid loosening, slides, cave-in, and to
guarantee the safety of work.
2) The Engineer may order the use of additional protection and supports when he consider that
there may be some danger for the safety of workmen or for the good progress of the Works.
The responsibility of stability always remains at the Contractor's charge.
6.7.2 TEMPORARY PROTECTION AND SUPPORTS
1) According to the difficulties encountered during the excavation works, the Contractor may
select the temporary protection and supports he deems most convenient and suitable to bear
and stabilize the unstable material and to facilitate the installation of permanent protection
and supports.
2) Temporary protection and supports shall be removed by the Contractor shortly before placing
the concrete or when the work is completed and it shall be the Contractor's responsibility to conduct his
operations during excavation so that no temporary protection or supports are installed, which
cannot be removed when required by the Engineer.
_______________________________________________________________________________
47
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

6.8 EXCAVATED MATERIALS


1) All suitable materials from the excavations shall be utilized to the fullest extent practicable as
construction materials in Permanent Works.
2) The Contractor's blasting and excavating techniques shall be such that, as much as
practicable, construction materials will be yielded. Where possible, suitable materials shall be
excavated separately from materials to be wasted.
3) Whenever possible, the suitable materials shall be transported directly from the excavation to
the designated final locations.
4) If the immediate placement in the final location is not possible, the materials shall be
stockpiled at no additional cost. If the moisture content of excavated materials which would
be suitable for embankments or backfill is too high after excavation, such material shall be
drained and dried in the stockpile until the moisture content is sufficiently reduced
to allow for placement.
5) The Contractor shall remove any cobbles, boulders or rock fragments found in otherwise
approved materials which are greater than permitted for fills and backfills and dispose of them
appropriately.
6.9 DISPOSAL OF EXCAVATED MATERIALS
1) The Contractor shall create a disposal area to stock material suitable for construction of the
dam body. The disposal area will be proposed by the Contractor and submitted to the
Engineer for his approval.
2) Excavated materials which are not suitable for, or are in excess of the construction
requirements, shall be disposed of in spoil areas studied by the Contractor and submitted to
the Engineer for approval.
3) The spoil areas shall be located where they will not interfere with the natural flow of streams
or rivers.
4) No rock material may be dumped into rivers or creeks. The earth or soil material may be
dumped into natural flows only after written approval by the Engineer.
5) The material proceeding from excavation shall be disposed in the designated areas dividing
the rock material by the common and/or clayey material and the topsoil.
6) The Contractor shall shape and trim the spoil tips and stockpiles to the lines and grades as
directed or approved by the Engineer. Adequate diversion of water courses in such areas and
proper drainage shall be provided.
7) At the end of the works, the rock material not used for the production will be properly graded
so that no unstable slopes are left in the permanent deposits of excavated materials.
Drainage pipes or ditches shall be disposed so as to guarantee a proper de-watering of the
area, and the common material and the topsoil shall be used to cover the rock material.
8) Landscaping of the permanent deposit of the excavated material shall be executed as
directed by the Engineer.
9) The Contractor shall be liable for any damage to Temporary or Permanent Works or to the
property of third parties caused by poor drainage in the spoil or stockpile areas.
6.10 CLEANING, PREPARATION AND PROTECTION OF EXCAVATION SURFACES
1) Excavation surfaces against or upon which concrete, embankment fill, or backfill will be placed
shall be prepared and protected as specified herein and in combination with specifications
contained in the pertinent Sections of these Specifications or as shown on the Detailed Design
and/or Construction Drawings.
2) If, during excavation work, material beyond the limits of excavation shown on the Detailed
Design and/or Construction Drawings is loosened or disturbed, the Contractor shall re-
compact the loosened material or remove it altogether and replace it with other compacted

_______________________________________________________________________________
48
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

fill as directed.
3) If, during excavation in rock for concrete structures or linings, the rock beyond the limits of
excavation shown on the Detailed Design and/or Construction Drawings becomes broken or
shattered, the Contractor shall remove all loose material and replace it with concrete or
shotcrete as directed.
4) Foundation excavation shall be kept well drained and free of standing water. The Contractor
shall provide all necessary drains, ditches and sumps, and use pumps when necessary, in
order to ensure that foundation surfaces are not harmed by water. When foundations are
thus affected, the affected material shall be removed and replaced with approved backfill.
5) Cleaning of sound rock shall be done by directing a jet of water or air at the surface. Compact,
washable rock shall be cleaned with compressed air-water jets. Rock which tends to a quick
disintegration, or is interspersed with clay fissures, shall be cleaned with compressed air only.
The cleaning shall be carried out to the satisfaction of the Engineer.
6) Sprayed concrete (Shotcrete) shall be applied to finished excavation surfaces where, in the
opinion of the Engineer, it is deemed necessary to prevent air slaking, erosion or other
deterioration of the surface. The protective coating shall be applied to excavated surfaces
either with or without steel wire mesh reinforcement in accordance with the provision of the
Section "Sprayed Concrete".
6.11 PROTECTION OF EXISTING STRUCTURES DURING BLASTING
1) The Contractor shall adequately protect existing structures from the effects of blasting, both
from impact with rock or debris and from excessive shock. Structures at risk shall be inspected
both before and after blasting, and shall be monitored during the blasting operations by
appropriate means, if so directed by the Engineer.
2) In any case, the particle velocities shall be limited to 15 cm per second at new concrete
structures which have attained design concrete strength; 10-15 cm per second at structures 7
to 28 days old; and 0-4 cm per second for structures 0 to 7 days old, proportionally.
3) The above limits shall be approached gradually with caution using a commercially available
velocity seismograph and with immediate inspection of structure for evidence of stress after
each blast operation.
4) In the event of stress evidence, the limiting particle velocity shall be reduced to that of the
blast prior to the one causing stress evidence and maintained at that level with continued
velocity and stress monitoring as described above. If the structure cannot be inspected,
particle velocity shall be limited to 5 cm per second.
6.12 FILL
6.12.1 GENERAL
1) The Contractor shall place and compact fill and backfill of the specified type to the lines,
grades and dimensions shown on Detailed Design and/or Construction Drawings, or where
directed by the Engineer.
2) Material to be used as fill and backfill shall be subject to the Approval of the Engineer, and
shall be, as far as possible, obtained from excavations required for temporary or permanent
works.
3) The distribution and gradation of fill material shall be such that the finished backfill is free
from lenses, pockets, streaks or layers of material differing substantially in texture or
gradation from the surrounding material. Backfill material shall include no organic matters,
and the Engineer reserves the right to reject entire loads of material which contain a high
percentage of organic matter which cannot be satisfactorily removed.
4) Traffic over the fill shall be adequately controlled to avoid rutting or disturbing the placed
backfill. Each load of material shall be placed in such a way as to achieve the best practicable
distribution of material. The operation of trucks and heavy equipment shall be restricted near
_______________________________________________________________________________
49
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

buildings, walls, piers and other facilities to avoid damage to any permanent structure.
5) Any material which in the opinion of the Engineer is objectionable or inadequate shall be
removed at the Contractor's cost. If the compacted surface of any layer of material is
determined to be too smooth and impermeable to bond properly with the succeeding layer, it
shall be loosened by harrowing or by other approved method before the succeeding layer is
placed thereon.
6) No filling shall commence until the foundation and permanent works have been inspected
and approved by the Engineer.
7) Backfilling adjacent to concrete structures one meter or more in height shall not commence
until 7 days after concrete placement. Prior to backfilling, forms shall be removed, and the
area cleaned of all waste and debris. Backfill shall be placed in proper sequences so that no
differential earth pressure occurs on footings, pipes and other structures.
8) The Contractor shall maintain and protect the finished fill in satisfactory conditions at all
times until completion and acceptance of the works. After filling operations have been
finished and before final grading, the Contractor shall slope the surfaces to prevent pounding
of water.
6.12.2 RANDOM FILL AND BACKFILL
1) The random fills and backfills may consist of any and all types of materials, except clayey
mud, loam and high plasticity clay, but including low plasticity clay, sand, gravel and rock
fragments.
2) The materials shall in general be placed mixed in them to obtain a well-graded soil having a
coefficient of uniformity larger than five (5) suitable to obtain the best compacted stability for
the specific fill.
3) The liquid limit and plasticity index of fraction passing No. 40 sieve shall be 40 and 10
maximum respectively.
4) The maximum size of rock fragments, which may be incorporated in the mass of fills and
backfills shall not be more than 2/3 of the specified compacted layer.
5) For confined backfills, the quantity of stones over 20 cm in size shall not exceed 30 % by
volume.
6) Random fills and backfill mainly composed of materials with a size up to 10 cm shall be placed
and compacted in horizontal layers of 30 cm while the random fills and backfill mainly
composed of coarse rock fragments shall be compacted in horizontal layers of 50 cm.
7) The moisture content prior to and during compaction of the fills shall be near the optimum
moisture content distributed evenly throughout each layer of material as established with
laboratory tests.
8) Random fill and backfill mainly composed of fine materials shall be compacted to at least 95
% standard Proctor density in accordance with ASTM Test Method D-698. The in-situ density
tests shall be determined in accordance with ASTM D-1556-00 (Sand Cone Method) or by BS
1377-9.2.4 (Core Cutter Density Method).
9) Random fill and backfill mainly composed of coarse materials shall be compacted with not
less than six full (6) passes of vibrating rollers having a min. weight of 25 kg per centimeter of
drum axis. If a heavier vibrating roller is used the number of passes may be reduced upon the
results of compaction site tests.
10) Random backfill to be placed adjacent to structures shall be carefully placed to prevent its
displacement or damage
6.12.3 FREE-DRAINING BACKFILL
1) Free-draining backfill material shall consist of a well graded gravel or cobbles with particle
size ranging from 100 to 300 mm (except as stated below) with a maximum of 3% by weight
passing US Standard Sieve No. 200 (0.075 mm).
2) Material to be placed within one meter of any structure shall contain no material greater than
_______________________________________________________________________________
50
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

100 mm.
3) Free-draining backfill shall be placed moist in layers not exceeding 50 cm, after compaction. It
shall be compacted to 70% relative density as defined in ASTM Test Method D 4254.
4) Gravel free-draining backfill shall be compacted by vibratory rollers. Where backfill has to be
placed adjacent to structures or in other restricted areas, it shall be compacted by mechanical
tampers or other approved methods.
6.12.4 SAND-GRAVEL SELCTED BACKFILL AND BEDDING
Reasonably well graded sand and gravel shall be used for backfilling of trenches for pipes, cables,
ducts, bedding for ditches etc. The maximum particle size shall not exceed 75 mm and a
maximum of 5% by weight shall pass US Standard Sieve No. 200 (0.075 mm). The material shall
be spread in layers of 30 cm and compacted by approved vibratory equipment.
Maximum particle size shall not exceed 4.75 mm and a maximum of 5% by weight passing US
Standard Sieve No. 200 (0.075 mm).
6.12.5 SAND BEDDING
Reasonably well graded sand shall be used for backfilling of trenches for pipeline. The maximum
particle size shall not exceed 20 mm and a maximum of 5% by weight shall pass US Standard
Sieve No. 200 (0.075 mm). The material shall be spread in layers of 30 cm and compacted by
approved vibratory equipment.
6.13 MEASUREMENT AND PAYMENT
6.13.1 EXCAVATION
6.13.1.1 General
1) Measurement for payment for any class of excavation specified herein, except for clearing
and grubbing, will be of the in-situ volume as measured from a survey performed by the
Contractor prior to any excavation work and the lines and grades shown on the Detailed
Design and Construction Drawings or established at the Site by the Engineer.
2) Payment will be made at the appropriate Unit Price per cubic meter or per linear meter
entered in the Bill of Quantities, which shall include the entire cost of, but not be limited to,
the following:
a) Provision of all labour, equipment and materials required for excavation,
including any hand work necessary for trimming excavated surfaces; preparation,
protection and maintaining excavated surfaces in satisfactory conditions until
concrete or fill is placed; all additional excavation for Contractor's convenience;
any temporary supports necessary to support the sides of the excavations
b) Loading, hauling and dumping the excavated material on stockpiles, spoil areas or
points of incorporation in Permanent Works; clearing of the spoil areas and
formation of spoil tips as specified for use in embankment construction or as
backfill
c) All delays during excavation work resulting from installation of rock supports
required by the geotechnical conditions of the material encountered
d) Complying with all requirements of statutory laws and regulations relating to
blasting work and any restrictions resulting therefrom; obtaining all necessary
permits and licenses for the purchase, use, storage and transport of explosives or
any other material and equipment
e) Surveying, setting-out, checking of excavated profile and alignment, and any
subsequent rectification works resulting from undue or incorrect surveys;
provision of suitable equipment for, and delays due to carrying out this work
3) Measurement for payment of possible additional volumes of excavation resulting from
modification of lines, slopes and grades shown on the Detailed Design and Construction
Drawings, which may be necessary in the course of the work, will be of the in-situ volume as
measured between the original and the modified lines and grades. No increase in Unit Prices
_______________________________________________________________________________
51
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

will be allowed for such additional excavation.


6.13.1.2 Clearing and Grubbing
Payment for clearing and grubbing in the areas to be occupied by Permanent Works as shown
on the Detailed Design and Construction Drawings or as directed by the Engineer will be
made at the unit price per hectare entered in the Bill of Quantities. This sum will include all
costs of disposing of cleared materials.
6.13.1.3 Stripping and Common Excavation
1) Measurement for payment for common excavation will be of the in-situ volume of the
material removed between the original ground surface and the lines and grades shown on
the Detailed Design and Construction Drawings or the surveyed lines of material classified as
"Rock Excavation".
2) Payment will be made at the Unit Price per cubic meter entered in the Bill of Quantities.
6.13.1.4 Excavation by Ripping
1) Measurement for payment for excavation by ripping will be of the in-situ solid volume of the
material removed between the surveyed rock surface and the lines and grades shown on the
Detailed Design and Construction Drawings or the surveyed surface for the classification
“Excavation by Ripping”.
2) Payment will be made at the Unit Price per cubic meter entered in Bill of Quantities.
6.13.1.5 Rock Excavation by Blasting
1) Measurement for payment for rock excavation by blasting will be of the in-situ solid volume
of the rock between the surveyed rock surface and the lines and grades shown on Detailed
Design and Construction Drawings or as directed by the Engineer.
2) Payment will be made at the Unit Price per cubic meter, entered in the Bill of Quantities,
which shall, in addition to work included under “General”, include the entire cost of removal
of any material which cannot be removed by ripping; protection of structures, properties,
installations, trees, etc.; drilling holes for blasting and blasting, development and using
controlled blasting methods, blasting tests, works underwater and any cost associated with
establishing satisfactory blasting techniques.
3) In addition to material actually removed under this title the following shall also be classified
as "Rock Excavation by Blasting", and shall be measured and paid for under this item:
a) Large boulders and rock fragments over one (1) cubic meter that cannot be
removed by ripping or by excavation machinery used for loose excavation
b) Rock removed by mechanical breakers, swelling agents or other approved
methods in areas where blasting would be required but not possible or permitted
for whatever reason
4) Separate measurement for payment will be made for excavation performed at the final
surfaces of excavation by controlled blasting methods. Measurements for payment will be of
excavation area for which controlled blasting is required, calculated from the required lines
and grades shown on Detailed Design and Construction Drawings or as directed by the
Engineer. Payment will be made at the Unit Price per square meter entered in the Bill of
Quantities.
6.13.1.6 Minor Excavation Work
1) For payment purposes, minor excavation is divided into two categories:
a) Excavation in loose materials which can be removed without recourse to blasting.
b) Excavation in rock.
2) Measurement for payment for either category of minor excavation will be of the in-situ volume
removed between the original surface and the lines and grades shown on Detailed Design and Construction
Drawings or as directed by the Engineer.
3) Payment will be made at the Unit Price per cubic meter entered in the Bill of Quantities for
loose material or rock respectively.

_______________________________________________________________________________
52
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

6.13.1.7 Borrow and Quarry Excavation


No extra measurement for payment or payment will be made for borrow and quarry
excavation, and clearing, grubbing and stripping in, and trimming, levelling and draining of
the borrow and quarry areas. The entire cost thereof shall be included in the Unit Prices for
furnishing, placing, mixing, compaction, etc., of such materials as specified in the pertinent
Sections of these Specifications.
6.13.1.8 Test Pits and Trench Excavation
1) Measurement for payment for test pits and trench excavation will be of the in-situ volume of
material removed.
2) Payment will be mate at the Unit Price per cubic meter entered in the Bill of Quantities, which
shall include the use of any special equipment, hand works, supports of the excavation,
placing of excavated material, sampling, transport to laboratory and fencing.
3) Separate measurement for payment and payment will be made to the Contractor for
underwater excavation, as indicated in the corresponding paragraph.
6.13.1.9 Underwater Excavation
1) Underwater excavation is defined as excavation performed in the water deeper than 50 m.
2) Measurement for payment will be of the volume of material effectively removed.
3) Payment will be made at the Unit Price for the respective excavation as stipulated above, plus
additional Unit Price per cubic meter entered in the Bill of Quantities, which shall cover all
additional difficulties and equipment necessary for excavating underwater.
4) For payment purposes, the underwater excavation is divided into three categories:
a) Removal of loose material under water
b) Removal of material under water by ripping
c) Underwater blasting and removal of material
6.13.1.10 Geological Overbreak and Unsuitable Foundations
1) Measurement for payment for the removal of material arising from overbreak accepted by
the Engineer as occurring entirely for geological reasons, will only be made if the Contractor
request measurement directly after excavation, or as long as the overbreak can clearly be
determined as being due to adverse geological conditions.
2) Excavation and refill ordered in writing by the Engineer due to cave-ins or overbreak for
geological reasons or unsuitable foundations will be measured for payment and paid for as
follows:
a) Removal of material resulting from overbreak accepted by the Engineer will be
paid per cubic meter in-situ, at 50% of the Unit Price related to the excavated
material
b) The concrete placed for refilling additional excavation in rock foundation will be
measured in cubic meter of the in-situ volume and payment will be made
o at the Unit Price per cubic meter for the required classes of concrete for
the related surface works
o at 70% of the Unit Price per cubic meter for the required classes of
concrete for the related underground work
c) Payment for excavation, transportation and placing of selected earth fill materials
for use in refilling additional excavation in loose material will be made at the Unit
Price per cubic meter for random fills and backfills.
6.13.1.11 Line Drilling
1) Measurement for payment for line drilling will be of the length of the holes actually drilled
into the rock along the side of the excavation as directed by the Engineer.
2) Payment will be made at the Unit Price per meter of drilled hole entered in the Bill of
Quantities, which shall include the entire cost of drilling the holes, light blasting, broaching,
wedging, barring, or other methods used in conjunction with line drilling.

_______________________________________________________________________________
53
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

6.13.2 DISPOSAL OF THE EXCAVATED MATERIAL


No separate measurement for payment and payment will be made to the Contractor for the
disposal in the spoil areas of materials proceeding from required excavations.
Landscaping of the permanent deposits of materials proceeding from required excavations,
where required by the Engineer, will be paid according to the items of the Bill of Quantities
as indicated in Section 8 of these Technical Specifications.
6.13.3 STOCKPILING
No separate measurement for payment and payment will be made to the Contractor for
stockpiling of materials proceeding from required excavations.
6.13.4 FILLS AND BACKFILL
1) Measurement for payment of fills and backfills will be of the in-situ compacted volume in cubic
meters of backfill placed.
2) Payment shall be made according to the unit prices entered in the Bill of Quantities for the
following categories of backfill:
a) Random fill and backfill
b) Free-draining backfill (gravel or boulders)
c) Sand-gravel selected backfill and bedding
d) Sand bedding
3) The unit prices shall include the supply of fill material and all costs for placing and compacting
as specified.
4) Backfilling with concrete and shotcrete are covered in the pertinent sections of these
Specifications.
6.13.5 EXCLUSIONS
1) No extra measurement for payment or payment will be made for the following:
a) All costs of de-watering and keeping the surface excavation sites dry
b) Extra work caused by the Contractor's negligence in setting-out the structures
and slopes
c) Surveys to verify the original ground surface, or for recording the top of the rock
surface
d) Removal of the materials resulting from the slides or overbreak caused by
Contractor's inappropriate working methods and for the additional materials
required to fill the voids so created
e) Additional work of removing material and backfilling voids with approved
material where overbreak due to adverse geological conditions coincides with
that due to Contractor's poor working methods or negligence
f) Excess excavation required for Contractor's convenience and the resulting
additional backfilling with approved materials
g) Additional work resulting from the Contractor changing slopes without prior
approval by the Engineer. In such event, payment will be made only to the lines and grades
shown on Detailed Design and Construction Drawings
h) Excavation which is incidental to the installation of Temporary Works
i) Shoring, bracing, and supporting of excavation surfaces except as specified in the
Sections "Rock Stabilization and Supports" and "Slope Protection"
j) Clearing and grubbing in the borrow and quarry areas, and spoil and stockpile
areas
k) Draining, shaping, and trimming the dumped material in the spoil tips to the lines
and grades as directed or approved by the Engineer
l) Preparation and protection of foundation and slopes with the exception of
concrete protective coating, which will be measured and paid for in accordance
with the provisions of the Section "Sprayed Concrete"
_______________________________________________________________________________
54
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

m) Work or materials required when foundation surfaces have been allowed to


become unsuitable due to the action of ground or surface water
n) Extra work or material required to repair damages to the final excavation surfaces
caused by the erosion or travel of the construction equipment
o) Monitoring of existing structures during blasting operations
p) Stockpiling of excavated material for later utilization by the Contractor in the
Permanent Works, when decided by the Contractor for his own convenience.
2) Any additional excavation in areas where surface excavation has already been completed,
which the Contractor may be directed by the Engineer to carry out, will be measured and paid
for at the same Unit Prices entered in the Bill of Quantities as for the original excavation. No
increase in Unit Prices will be allowed for such additional excavation.

_______________________________________________________________________________
55
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

7 SLOPE PROTECTION

7.1 SCOPE OF WORK


1) Work under this Section include all labour, materials, equipment and services required to
protect the slopes either excavated or those of fills and backfills.
2) This Section covers the following items:
a) Riprap
b) Stone paving
c) Field sod
d) Topsoil and seeding
e) Planting
3) The Contractor shall place the various items specified herein as protection to slopes to the lines
and thicknesses and in the locations shown on the Detailed Design and Construction Drawings,
or as directed by the Engineer.
4) Shotcrete, rock bolts, wire mesh, and drainage work, which may also be required for the slope
protection, are specified in other Sections of these Specifications.
7.2 SUBMITTALS
Thirty days before starting the construction of any slope protection listed hereinabove, the
Contractor shall submit to the Employer a statement inclusive of description, drawings and
construction method.
7.3 RIPRAP
7.3.1 MATERIAL
Material required for riprap shall be obtained and selected from the quarry shown on the
Drawings or other sources as approved by the Engineer.
Rock for riprap shall be sound, dense, resistant to abrasion and weathering and free from
cracks, seams and holes. Angular rock fragments shall preferably be used. Well-rounded
cobbles and boulders will not be accepted excepted on very flat slopes. The minimum
dimension of any single rock shall not be less than one-third to one-fourth of its maximum
dimension.
Riprap shall be reasonably well graded within the following limits:

Nominal Thickness of Maximum Weight (kg/block) Size Range as % by Weight


Riprap (cm) 30-40% 60-70% 0-10%
(kg) (kg) (kg)
40 250 110 - 250 10 - 110 0 - 10
60 550 275 - 550 20 - 275 0 - 20
80 1,000 500 - 30 - 500 0 - 30
1,000

Sand and rock dust may not exceed 5% of the total weight of the riprap material. Maximum size
of boulder shall be limited to the nominal thickness of riprap.
7.3.2 EXECUTION
Riprap shall be dumped in place or placed by backhoe or dragline. It need not to be compacted,
but shall be roughly graded to the specified thickness in such a way as to ensure that larger rock
fragments are uniformly distributed, with the smaller rocks filling the remaining spaces. Pockets
of small stones shall be removed and replaced with larger material such that the required
grading is achieved. Placing operations shall be such that the riprap layer is well-keyed, uniform
and dense.
_______________________________________________________________________________
56
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

7.4 STONE PAVING


7.4.1 MATERIALS
1) Fragments of rock for “Dry Stone Paving” and “Stone Paving in Mortar” specified in this Section
shall be selected from required excavation or quarries and shall have the same properties and
qualities as material for riprap. They shall be chosen such that they have a reasonably flat upper
surface when laid. Stones for dry rock paving shall not have a round or spherical form and shall
be of regular shape. Stones for rock paving in mortar shall be not less than 20 cm thick and not
less than 50 cm2 in area.
2) Bedding material for dry rock paving shall consist of a mixture of sand and gravel reasonably well
graded between 0.5 and 25 mm.
3) Mortar for rock paving in mortar shall comprise 3 parts of clean fine aggregate to one part of
cement by volume. Fine aggregate and cement shall comply with the requirements specified in
the Section “Concrete”.
7.4.2 EXECUTION
7.4.2.1 Dry Stone Paving
1) The Contractor shall place dry stone paving on a bedding of sand and gravel of minimum
thickness of 15 cm.
2) Rocks fragments shall be hand placed in a regular pattern such that no continuous vertical or
horizontal joints occur, and the spaces between the stones shall be filled with smaller rocks or
gravel.
3) The surface of complete paving shall be even with surface projections not exceeding 20% of the
specified layer thickness.
4) The nominal thickness of this paving shall be 40 cm, of which 15 cm for bedding and 25 cm for
stones.
7.4.2.2 Stone Paving in Mortar
1) The Contractor shall place selected pieces of rock on a mortar bed and fill the joints with
mortar. The work shall be performed by experienced masons, duly qualified in their trade.
2) Prior to placing, the rock shall be cleaned of all adherent soil, dust and earthy or organic
impurities, and wetted sufficiently to saturate it, but leaving the surface in a damp condition.
3) Rocks shall be placed on a mortar bed of minimum thickness of 5 cm and carefully arranged in
such a way that the minimum of voids remain between rocks, no continuous horizontal or
vertical joints exist, and the largest rocks are evenly distributed.
4) After rock placing, the joints shall be completely filled with mortar. Splashing of exposed rock
surfaces with mortar shall be avoided, and where splashing does occur, the surface of the rock
shall immediately be cleaned down with a sponge and clean water.
5) Finished surfaces shall be adequately protected against rainfall until the mortar has set. After
setting, mortar shall be raked out to a depth of approximately 15 mm from the face of the rock,
and the rocks sponged off along their edges.
6) Joints and weepholes shall be provided in the locations and in accordance with the details
shown on Detailed Design and Construction Drawings, or as directed by the Engineer.
7) The nominal thickness of this paving shall be 30 cm, of which 5 cm for mortar bedding and 25
cm for stones.
7.5 FIELD SOD
7.5.1 GENERAL
The Contractor shall furnish and place the field sod as protection of excavated surfaces and
slopes of fills where shown on Detailed Design and/or Construction Drawings or directed by the
Engineer.
7.5.2 MATERIALS AND EXECUTION
1) Field sod shall consist of a dense and well rooted growth of permanent and desirable grass.

_______________________________________________________________________________
57
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

When sod is lifted, it shall be covered with grass recently cut to a length of not more than 7 cm.
2) Areas to be sodded shall be fine graded to an uniform surface and loosened to a depth of 3 cm.
Where directed, the topsoil shall be placed on the prepared surfaces. Field sod shall be placed
over a whole area (not in strips) of the designated slope. Field sod, excluding grass depth, shall
be at least 5 cm thick. When laid on the slopes steeper than three horizontal to one vertical, it
shall be pegged with wooden stakes.
3) The Contractor shall be responsible for all completed sodding for a period of 30 days and shall
water the sodding whenever necessary to ensure rooting. During this period any break which
may occur through slippage of sod shall be repaired and any sod which is dead shall be
removed and replaced by the Contractor.
7.6 TOPSOIL AND SEEDING
7.6.1 GENERAL
1) The Contractor shall prepare the ground for, and load, transport, place, spread and roll the
selected topsoil material, water the areas, furnish and plant approved seed, furnish and spread
mulch, and furnish and spread approved fertilizer. Application techniques such as hydroseeding
and hydromulching will be acceptable.
2) The topsoil shall be placed and seeding performed as protection of excavated surfaces and
embankment slopes where shown on Detailed Design and Construction Drawings or directed by
the Engineer.
3) Topsoil shall not be placed on excavation surfaces with slopes of 1:1 or steeper.
7.6.2 MATERIALS
1) Topsoil shall be obtained from stockpiles of material stripped from excavated or borrow areas.
The material shall contain the fertile loam suitable for plant growth containing at least 6%
organic matter with pH range 6.5 to 7.0. It shall be free from excessive quantities of grass, roots,
weeds, sticks, stones, or other objectionable objects.
2) Seeds and seeding mixture shall be free of all harmful or prohibited weed seeds. The kind of
seeds and its distribution in kg per hectare shall be carefully established by an expert,
depending on the geographic, climatic and ecological conditions.
3) All different kinds of seeds shall be separately packaged, sealed, and labeled when received on
the Site.
4) Chemical fertilizer shall be a mixed, general purpose commercial product and shall be approved
by the Engineer prior to applying. Percentages of nitrogen, phosphoric acid and potash to be
10/10/10 of total weight. Fertilizer shall be packaged, scaled, and labeled when received on the
Site.
5) Animal fertilizer shall be well composed cattle and/or horse manure free from sawdust or
refuse of any kind.
7.6.3 EXECUTION
1) The areas over which topsoil is to be placed shall be clean of debris. Surfaces shall be leveled to
within 20 cm of the final lines or grades before topsoil is applied. Topsoil shall be evenly placed
and spread over the area with the required thickness. Topsoil shall not be placed when
subsurface is detrimental to proper seeding.
2) The seeding mixture shall be sown by drilling with either an approved disc or grass drill,
hydroseeders, or by mechanical or hand broadcasting. The method of seeding shall be
proposed by the Contractor and subject to Engineer's approval. Suggested methods are as
follows:
• Hydroseeding: Seeding with an approved hydroseeder will be acceptable providing the
wind velocities permit uniform distribution of the seed and fertilizer slurry on the areas
to be seeded. The mixture of seed and fertilizer shall be properly mixed with water to
form a slurry. The slurry mixture shall be prepared immediately prior to application, and

_______________________________________________________________________________
58
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

shall be promptly applied on the designated areas. Slurry mixtures prepared more than
1 hour prior to application will not be acceptable. The hydroseeder shall be designed in
such a way as to insure that seed and fertilizer are distributed uniformly. The
hydroseeder shall be equipped with a paddle-type agitator and recirculation pump that
will continuously stir and mix the slurry to prevent settling of solids in corners and at the
bottom of the tank, and maintain a uniform mixture of seed, fertilizer, and water at all
times during the entire seeding operation.
Broadcast Seeding: In areas inaccessible by methods described above, the seed and
fertilizer may be applied by either mechanical or hand broadcasting. When either of
these methods are used, the seed and fertilizer shall be applied separately.
• Hydromulching: Wood-cellulose fiber mulch or other approved material to be used in
hydromulching shall contain no germination or growth-inhibiting factors. It shall be
dyed an appropriate colour to allow visual metering of its application. The mulching
shall have the property of becoming evenly dispersed and suspended when agitated in
water. When sprayed uniformly on the surface of the soil, the fibers shall form a
blotterlike ground cover which readily absorbs water, and allows infiltration to the
underlying soil. Weight specifications from the suppliers, and for all application, shall
refer only to air-dry weight of the fiber, a standard equivalent to 10% moisture. The
mulch material shall be supplied in packages marked by the manufacturer to show the
air-dry content. Suppliers shall be prepared to certify that laboratory and field testing of
their product has been accomplished and that it meets all the forgoing requirements.
For the application, the mulching material shall be added to the water slurry in the
hydraulic seeder after the proportionate quantities of grass seed and fertilizer materials. All
slurry ingredients shall be mixed to form a homogeneous slurry. Slurry mixtures
prepared more than 1 hour prior to application will not be acceptable. Using the colour
of the mulch as a metering agent, the operator of the hydraulic seeder shall spray the
slurry mixture uniformly to the prepared seedbed to correspond with the hectare
requirements of all materials.
3) Fertilizer may be applied prior to seeding by mechanical spreaders, blowers, or hydraulic
equipment or may by applied during seeding if seeding equipment is provided with fertilizer
attachment.
4) After seeding the Contractor shall provide and cover the seeded area with hay or straw mulch
of minimum 5 tons per hectare. Mulch shall be free of mold and weed seeds and a major
proportion shall exceed 25 cm in length.
5) Seeded areas shall be watered. The frequency and quantities of water shall be approved by the
Engineer.
7.7 PLANTING
1) The Contractor shall furnish all plants, labour, materials, tools and equipment necessary for the
performance of planting as directed by the Engineer.
2) Where required, landscaped areas shall be planted with trees to provide protection against
erosion.
3) Trees shall have a well-developed root system, straight trunks, well-branched with dense
foliage, free from plant disease. The height of the trees shall be not less than 2 m.
4) Trees shall be planted on the day of delivery. Plant pits shall be excavated circular with vertical
sides and flat bottom. Tree pits shall be at least 60 cm greater in diameter than spread of roots
and 15 cm below depth of roots. Bedding soil shall consist of 3 parts topsoil to 1 part animal
fertilizer. Backfilling soil of pits shall consist of 3 parts topsoil and 1 part peat by volume with
uppermost layer treated with 0.15 kg/m2 chemical fertilizer. Plants shall be watered
immediately after planting operations have been completed.

_______________________________________________________________________________
59
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

7.8 MEASUREMENT AND PAYMENT


1) RIPRAP
a) Measurement for payment will be of the volume of material placed to the lines and thicknesses
shown on Detailed Design and Construction Drawings or those determined by the Engineer.
The actual volume will be determined by survey.
b) Payment will be made at the appropriate Unit Price per cubic meter for bedding or riprap
entered in the Bill of Quantities, which shall include the entire cost of all operations required
to furnish, select, blend, transport and place the required materials, irrespective of source.
2) STONE PAVING
a) Measurement for payment and payment will be made separately for dry stone paving and for
stone paving in mortar.
b) Measurement for payment will be of the area of stone paving, placed to the lines and
thicknesses shown on Detailed Design and Construction Drawings or those determined by the
Engineer. The actual surface area will be determined by survey.
c) Payment will be made at the appropriate Unit Price per square meter entered in the Bill of
Quantities, which shall include for the cost of furnishing, handling, transportation, and
placing of paving materials including sand and gravel or mortar bedding.
3) FIELD SOD
a) Measurement for payment of the field sod will be of the area actually sodded.
b) Payment for the field sod will be made at the Unit Price per square meter entered in the Bill
of Quantities, which shall include furnishing, transportation, preparation of surfaces, placing
and watering of field sod.
4) TOP SOIL AND SEEDING
a) Measurement for payment for topsoil will be of the volume placed within the lines shown on
Detailed Design and/or Construction Drawings or as established by the Engineer. Payment will
be made at the Unit Price per cubic meter entered in the Bill of Quantities, which shall
include all cost of labour, loading, transportation, placing, compacting, and excavating of
additional material if necessary.
b) Measurement for payment for seeding will be of the surface area actually seeded. Payment
will be made at the Unit Price per hectare entered in the Bill of Quantities, which shall include
the cost of furnishing, sowing, and covering of the seed, furnishing and spreading of fertilizer,
furnishing and placing of mulch, and watering.
5) PLANTING
Measurement for payment for planting will be of the number of trees planted, as shown on
Detailed Design and/or Construction Drawings or directed by the Engineer. Payment will be at
the Unit Price per plant entered in the Bill of Quantities.

_______________________________________________________________________________
60
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

8 CONCRETE
8.1 GENERAL
1) The work under this Section includes all labour, materials, equipment and services related to the
concrete work to be carried out by the Contractor under this Contract.
2) The concrete work shall be performed to the dimensions as shown on Detailed Design and/or
Construction Drawings or as otherwise directed by the Engineer. Lift drawings shall be prepared
by the Contractor.
3) The approval given by the Engineer to the Contractor's Equipment or their operation, or of any
construction methods shall not relieve the Contractor of his full responsibility for the proper
and safe execution of concrete work or any obligations under this Contract.
8.2 STANDARDS
1) Concrete materials, methods and procedures shall conform to the applicable standards of the
American Society for Testing and Materials (ASTM) or, where not covered by ASTM Standards,
shall conform to the applicable standards or recommended practices of the American Concrete
Institute (ACI) and those contained in the US Bureau of Reclamation "Concrete Manual".
2) In cases of conflict between these Specifications and the above, these Specifications shall take
precedence.
8.3 COMPOSITION AND CLASSES OF CONCRETE
1) Concrete shall be composed of cement, water, fine and coarse aggregate and possible
admixtures.
2) The design of concrete mixtures will be aimed to securing a plastic, workable mixture suitable
for the specific conditions at placement and, when properly cured, a product having durability
and strength in accordance with all the requirements of the structures covered by the Contract
Documents. The water content of all concrete mixtures shall be the minimum necessary to
produce a workable mixture. Admixtures shall only be used with the approval of the Engineer.
3) According to the use of the different structures of the Works and the stresses expected to be
acting upon them, various concrete classes have been designated. Denomination of concrete
classes is based on the nominal cylinder compressive strength (in Newton per square mm) and
maximum aggregate size.
4) The cylinder compressive strength is defined as the strength as measured on the test cylinders
150 mm diameter and 300 mm high tested at 28 days. The nominal strength is defined from a
sequence of samples produced and used in standard conditions so that 85% of all samples
exceed the nominal strength, assuming a normal statistical distribution for the majority of test
values. No test value, however, may lie below a minimum, which is at 70% for concrete of less
than 20 N/mm2, and at 85% for concrete of more than 20 N/mm2 of the corresponding
nominal strength. With very large numbers of test values a 1-2% below the minimum will be
acceptable, providing they do not compromise the safety of structure.
5) Concrete mixes with the indicated nominal compressive strengths and maximum aggregates
sizes which will be required for the construction of the Permanent Works are indicated in the
following Table. The class of concrete required to be used in any specific location shall be as
shown on the Detailed Design and/or Construction Drawings, or as directed by the Engineer.

Class of Concrete Characteristic Strength Max. Size of


Aggregates (mm)
MP 2
kg/cm
C15D32 15 150 32
C20D32 20 200 32
_______________________________________________________________________________
61
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

C20D76 20 200 76
C25D20 25 250 20
C25D32 25 250 32
C25D32 W(1) 25 250 32
C30D20 30 300 20
C30D32 30 300 32
C35D20 30 300 20
C35D32 30 300 32

Differs from previous by impermeability (letter W added)


6) The final design of concrete mixes will be established by the Engineer, at the Site laboratory. The
execution of all testing on concrete and its constituent materials, both before and during
placing, will be the responsibility of the Contractor.
8.4 SUBMITTAL
1) Submittal listed herein are related to items which require the consent of the Engineer and are to
be made by the Contractor before the appropriate work may proceed.
2) Within 28 days from the date of issue of Notice to Commence, but before procuring or
mobilizing to the Site the equipment, the Contractor shall submit to the Engineer updated and
detailed plans and descriptions, consistent with those submitted with his Bid and any
subsequent amendments and additions agreed to by the Engineer and the
Contractor, of the following:
a) Aggregates Processing Plant: description, flow diagrams and drawings in
sufficient details to indicate layout, type and capacity of crushing, screening,
washing, conveying and other aggregate processing and handling equipment
b) Batching and Mixing Plants: description, flow diagrams, and drawings of the
plants, and details of the equipment the Contractor intends to use to determine
and control the amount of each separate concrete ingredient and mixing thereof
into uniform mixture
c) Transport and Placing of Concrete: full details of the equipment and methods for
transporting the concrete from the concrete plant to the final point of placing,
including numbers, type and capacity of transport vehicles a concrete pumps, and
details of standby plants to be installed
d) Sampling and Testing of Materials: list and details of equipment for sampling and
testing, detailed program for quality control of concrete work, and qualification
and experience of the proposed personnel.
3) At least 28 days in advance of any concrete work being carried out at the Site, the Contractor
shall submit to the Engineer following notifications based on the results of the preliminary
material testing:
a) Notification of the mill or mills from which cement will be obtained and whether
cement will be ordered in bulk or bags. If cement is to be obtained from several
factories, the estimated amount of cement from each factory and the proposed
schedule of shipment shall be stated
b) Notification of the source, analysis, method of delivery, and storage of water for
concrete manufacture
c) Notification of the admixtures which the Contractor will supply along with the
catalogs and laboratory analyses. Should the Contractor intend to use admixtures
in any concrete work for his own convenience, he shall give full details of the type,
dosage, and influence on durability
d) Details of the materials for formwork and surface finishes, treatment of
_______________________________________________________________________________
62
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

construction joints, and construction techniques which the Contractor proposes


to use in order to achieve the required concrete surfaces and allowable tolerances
e) Notification of the factory or factories from which steel reinforcement will be
obtained. If reinforcement is to be obtained from several factories, the estimated
weight from each factory and the proposed schedule of shipment shall be stated.
4) At least 28 days prior to procuring or dispatch to the Site of the particular item of work to which
the submittal relates, the Contractor shall submit to the Engineer the following:
a) Details covering the properties and performance, including the certified copies of
reports of all tests made by the manufacturers of waterstops, expansions joint
fillers, and joint sealing compounds along with material samples of the products
b) Details of curing compounds
c) Details of epoxy mortar for concrete repair
5) Drawings showing the location of construction joints proposed by the Contractor which differ
from those shown on the Detailed Design and/or Construction Drawings, including formwork
and reinforcement details, shall be submitted to the Engineer at least 15 days prior to
commencement of work on that particular structure.
6) During the performance of the concrete work, the Contractor shall keep a diary where he shall
record the construction procedures related to concreting. This diary shall be made available to
the Engineer upon request. The records shall contain at least the following:
a) Commencement and termination of concreting of various parts of the structures
b) Quantities and quality of aggregates and cement provided, and the storage from
which they were drawn
c) Temperature of air, water, cement, aggregates, and concrete
d) Meteorological conditions and humidity of air
e) Sampling and testing performed and summary of results
f) Personnel employed during various stages of the concreting operation and name
of the responsible inspector or foreman
g) Equipment used
h) Directives received from the Engineer
i) Any special material or procedures employed
7) The Engineer reserves the right to require any additional information deemed necessary to be
included in the submitted documents.
8.5 TESTING
8.5.1 TESTS PRIOR TO THE START OF CONCRETE WORK (TRIAL MIX STAGE)
8.5.1.1 General
1) At least 2 months prior to commencement of any concreting of Permanent Works, the
Contractor shall start the testing of materials, propose the composition of concrete mixes and
prepare trial mix of each of the proposed concrete class. The Contractor shall prepare the trial
mixes using the cement, water, aggregates and admixtures intended for the work and which
conform to the requirements specified in this Section.
2) This preliminary test program shall include the determination of following parameters:
a) Cement properties
b) Characteristics of aggregates
c) Mix water properties
d) Admixture properties
e) Proportion of aggregate ranges in the mix
f) Proportion of un-crushed to crushed aggregates
g) Cement dosage
h) Water-cement ratio (W/C)
i) Workability of concrete mixes
_______________________________________________________________________________
63
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

j) Compressive and tensile strength


k) Entrained air
l) Density
m) Water tightness
3) These test shall be carried out until the concrete mixes show appropriate strength, workability,
density, and water tightness without the use of excessive cement.
8.5.1.2 Cement
1) Cement shall be sampled and tested for strength and physical properties, and chemical analysis
under method EN 196.
2) The Contractor shall obtain the cement samples for testing at the cement mill as the bins are
being filled. Tests for false set shall be made on samples taken at the latest time prior to
shipment.
8.5.1.3 Aggregates
1) Aggregates shall be sampled and tested as set out in ASTM Specification C33.
2) Tests shall be made on samples that are representative of the grading that will be used in the
concrete.
8.5.1.4 Water
1) The suitability of the water for concrete shall be evaluated and the permissible amount of silt or
suspended solids established in accordance with ASTM Test MethodC-1602/C-1602M-06.
2) Water which quality is questionable or suspected of having detrimental amounts of sulfates
shall be chemically analyzed in a specialized laboratory designated by the Engineer.
3) For the examination of mixing water, the Contractor shall deliver to the laboratory at least one
liter in a thoroughly cleaned and tightly sealed bottle.
8.5.1.5 Admixtures
1) Admixtures proposed by the Contractor shall be tested for their suitability with the cement and
materials to be used in the Works and under proposed construction conditions.
2) Admixtures shall be sampled and tested as set out in ASTM Specification C494.
3) Air-Entraining admixtures shall be tested in accordance with ASTM Test Method C233.
8.5.1.6 Concrete
1) Concrete test cylinders shall be made and cured in accordance with ASTM Standard Method
C31. Sixteen test cylinders 150 mm diameter, 300 mm high shall be made from each mix
proposed for the different classes of concrete. Compressive strength of concrete shall be tested
on four test cylinders at 3, 7, 14 and 28 and 90 days in accordance with ASTM Test Method C39.
2) Splitting tensile strength of concrete shall be tested in accordance with ASTM Test Method
C496. Cylindrical beams of concrete for testing shall be made and cured in accordance with
ASTM Standard Method C31.
3) The consistency of the proposed mixes shall be tested by means of slump test in accordance
with ASTM Test Method C143. Specimen for slump tests shall be taken from each batch of
concrete used to make the test cylinders and beams.
4) Time of setting of concrete mixes shall be determined in accordance with ASTM Test Method C-
403.
5) Static modulus of elasticity and Poisson's ratio of concrete in compression shall be determined in
accordance with ASTM Test Method C-469.
6) Prior to execution of large scale concreting work at the Site, test shall be performed to
determine the temperature development due to hydration within the concrete with various
types of cement. The temperature rise shall be recorded and corresponding diagrams
established.
7) Air content shall be determined in accordance with ASTM test method C-231.
8.5.1.7 Aggregates Processing Plant and Concrete Plant
The performance of aggregates processing plant and concrete plant shall be tested by carrying
out a trial concrete production run prior to any concreting of Permanent Works.
_______________________________________________________________________________
64
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

8.5.1.8 Waterstops
1) All types of waterstops shall be tested in a recognized laboratory prior to shipment to the Site.
Test specimens shall be furnished by the manufacturer and the tests shall be carried out at the
place of waterstop manufacture.
2) Waterstop shall be tested as to their tensile strength, elongation, duration, water absorption,
specific gravity, effect of alkali and impact resistance.
8.5.2 TESTS DURING EXECUTION OF THE WORK
8.5.2.1 General
1) The Contractor shall carry out tests on materials and samples of concrete during the execution of
work in order to provide proper quality control of the concrete production. The test program shall
be as stipulated hereinafter and the Contractor shall comply with the requirements and give all
needed assistance in the performance of test program.
2) The Contractor shall keep records of test results which shall be presented to the Engineer upon
request.
3) Should the Contractor wish to reduce his approved testing program he shall notify the Engineer
of these changes 2 weeks in advance.
4) Aside from Contractor's testing program, the Engineer will make control test to the extent as he
deems necessary. The Contractor shall give all required assistance in sampling and provide for
the proper storage and transport of the specimens to be tested by the Engineer.
5) The Contractor shall make any arrangements needed or purchase new equipment, should the
test results prove that changes in the aggregates or concrete plant are necessary to obtain the
required concrete quality.
8.5.2.2 Cement
1) Cement shall be inspected for contamination and for lumps caused by moisture after arrival
on the Site.
2) When cement is delivered in bags, sufficient checks shall be made to assure that the bag
weights conform with the stated weight. Packages that vary more than 3% from the stated
weight or when the average weight of 50 packages taken at random from any shipment is
less than stated, the entire shipment may be rejected by the Engineer.
3) Cement shall be sampled and tested for strength and physical properties under method EN
196
8.5.2.3 Aggregates
Sampling and testing of aggregates in accordance with ASTM Specification C 33 shall be
carried out at the frequency shown in the table below.
a) Coarse Aggregate
Test Description ASTM Test No. Frequency
Gradation C 136 Not less than twice per week or per
500 Cum of concrete
Amount of material finer than C 117 Not less than twice per week or per 500
75 mm sieve Cum of concrete
Soundness C 88 per 1,0000 Cum of concrete
Clay lumps and friable C 142 per 1,0000 Cum of concrete
particles
Lightweight Pieces in C 123 per 1,0000 Cum of concrete
Aggregate
Abrasion Test C 131 per 5,000 m3 of concrete
Alkali Reactivity C 289 Once for each source of aggregates
Petrographic Analysis Designation 7 of Once for each source of aggregates
USBR Concrete

_______________________________________________________________________________
65
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

Manual

Specific Gravity of Coarse C 127 In early stages of work, and when


Aggregate changes in aggregates, but not less than
every 10,000 Cum of concrete

b) Fine Aggregate
Test Description ASTM Test No. Frequency
Moisture Contents C 70 Twice per shift or as necessary
Gradation C 136 Twice per shift or as necessary
Amount of material finer than C 117 Twice per shift or as necessary
75 mm sieve
Fineness Modulus Designation 4 of Twice per shift or as necessary
USBR
Concrete Manual
Organic Impurities C 40 per 5 000 Cum of concrete
Soundness C 88 Every 10,000 Cum of concrete
Clay lumps and friable C 142 Every 10,000 Cum of concrete
particles
Lightweight Pieces in C 123 Every 10,000 Cum of concrete
Aggregate
Alkali Reactivity C 289 Once for each source
Petrographic Analysis Designation 7 of Once for each source
USBR Concrete
Manual
Specific Gravity of Fine C 128 In early stages of work, and when
Aggregate changes in aggregates, but not less than
every 10,000 Cum of concrete
8.5.2.4 Water
Testing of water after the sources have been established shall be carried out at the frequency
shown in the table below.

Test Description Standard Frequency


Specifications
ASTM – C 602 M
Total Suspended Solids EN - 1008 Once per month or when
necessary
Chemical Test: ASTM -C-1602 M Once per month or when
PH-Chloride-Sulphate-Ammonium- necessary
Magnesium-Total Hardness-
Carbonate Hardness-Calcite
Dissolution Capacity

8.5.2.5 Admixtures
Each shipment of admixtures to the Site shall have a quality certificate. The quality certificate
inclusive of all the main tests performed shall be issued by the manufacturer.
8.5.2.6 Fresh Concrete
1) All concrete samples shall be obtained in accordance with ASTM Standard Method C172 for
_______________________________________________________________________________
66
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

sampling fresh concrete.


2) The Contractor shall make three sets of 3 cylinders from each 300 m3 of fresh concrete
placed in the Works during the day (or shift), but not less than 6 cylinders for each class
used for each day (or shift) of concreting. The test cylinders shall be 150 mm in diameter
and 300 mm high.
3) Each set of cylinders shall be composed of a single batch of concrete and then cured in
accordance with ASTM Standard Method C-31. The sets of cylinders shall be tested at 3, 7
and 28 days for concrete having the characteristic strength established at 28 days, and at 7,
28 and 90 days for concrete having the characteristic strength established at 90 days.
4) The Contractor shall take slump tests in accordance with ASTM Test Method C- 143 of each
concrete class throughout the duration of concreting work with a frequency of one slump
test each three mixer trucks at the batching plant and at the pouring location. Whenever a
concreting operation is started, a slump test of the first two mixes shall be made for each
class of concrete
5) Unit weight shall be determined for each concrete batch placed in the work or each day.
The air content shall be determined according ASTM C-231 in principle once per week or
when necessary the class of concrete to be tested shall be determined by the Engineer.
6) The Contractor shall furnish the batching plant laboratory with all facilities and apparatus to
carry out all the prescribed tests. The sampling of the fresh concrete will be at the batching
plant.
8.5.2.7 Placed and Hardened Concrete
1) Where considered necessary by the Engineer, in-situ characteristics of placed concrete shall
be tested in accordance with ASTM Standard Method C 42. The Contractor shall obtain
samples and perform such tests. Samples found to be defective shall not be deemed to be
included in this amount and shall be replaced by new ones by the Contractor.
2) Holes left after the cutting or core drilling shall be carefully filled with dry-pack mortar or
epoxy mortar as directed by the Engineer.
3) Specific gravity, absorption, and voids in hardened concrete shall be tested in accordance
with ASTM Test Method C 642, and compressive strength in accordance with ASTM Test
Method C 39.
4) When required by the Engineer, the Contractor shall test the placed and hardened concrete
by means of "Schmidt Concrete Test Hammer".
8.5.2.8 Reinforcing Steel
Reinforcing steel shall be accompanied by a factory certificate and, when directed by the
Engineer, tested in a recognized laboratory to demonstrate compliance with ASTM Specification
A 615 M or ASTM Specification A 185.
8.5.2.9 Curing Compounds
Curing compounds shall be tested in accordance with ASTM Test Method C 156 to demonstrate
compliance with ASTM Specification C 309 or EN 8656 when directed by the Engineer.
8.5.2.10 Concrete Plant
Monthly checks, or when requested by the Engineer, of the concrete plant's weight-batching
accuracy, including the accuracy of any admixture dispenser, shall be made by the Contractor in
the presence of the Engineer. When checked by standard weights and volumes its accuracy
shall be within 0.5% or as specified by the manufacturer.
8.6 PRESCRIPTIONS TO BE FOLLOWED IN CASE THE STRENGTH IS NOT ATTAINED
1) When the results of the tests carried out do not comply with the specifications, the Engineer
shall have the right to require that one or more of the following measures are
taken:
a) Extraction of a sufficient number of concrete samples (core taken with the rotary
drilling method) from the structure for which a compressive test, or group of
_______________________________________________________________________________
67
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

compressive tests, have given unsatisfactory results. These samples shall be taken
and tested according to ASTM C 42.
b) Performance of load tests, where possible, on the structure whose compression
tests were found unsatisfactory.
c) Other tests ordered case by case.
2) If, after carrying out such investigations, the Engineer finds out that the concrete in the
structure is not of the specified quality, he may order the strengthening or replacement of all or
part of the entire volume of hardened concrete represented by the test failure, or any other part
of the Work whose safety in the opinion of the Engineer is prejudiced or whose strength is
impaired, either by virtue of the faulty concrete or the remedial measures ordered.
3) The expenses borne for the above mentioned investigations and tests as well as for
strengthening, demolition and reconstruction of defective works shall be at Contractor's
expenses whenever it is proved that the concrete in place after 28 days has a strength less than
the specified one for its class.
8.7 CONCRETE MATERIALS
8.7.1 CEMENT
1) The Contractor shall supply ordinary Portland cement Type I conforming to ASTM Specification
C150. The use of other cements shall be subject to the approval of the Engineer and they shall
be stored separately.
2) The alkali content of the cement shall not exceed 1% by weight.
3) Each consignment of cement delivered to the Site shall be accompanied by a test certificate
issued by the manufacturer in quadruplicate. The Engineer will have the right to attend the
sampling and testing at the manufacturer's plant at any time. If delivery is not directly from the
manufacturer, the intermediate storage and delivery arrangements shall be subject to the
approval of the Engineer.
4) Cement which does not comply with ASTM Specification C150 or is damaged in consignment,
handling or storage shall be promptly removed from the Site.
5) All facilities for transport and storage of cement shall be subject to approval of the Engineer
and shall be such that easy access for inspection is assured.
6) Bulk cement shall be transported from the port or factory to the Site in adequately designed
weather-tight trucks, or other means where cement will be protected from exposure to
moisture. Immediately upon receipt at the Site, cement shall be stored in a dry, weather-tight
and properly ventilated structure with adequate provisions for the prevention of absorption of
moisture, and constructed in such a way that there will be no dead storage. The vents of the
bins and silos shall be equipped with dust collectors to reduce loss of cement during handling
and inconvenience to the personnel.
7) Cement bags shall be stored in weatherproof buildings with a raised, well ventilated wooden
floor, and placed so that each consignment can be segregated if required and used in order of
its age. Bags shall not be stacked more than 1.5 m high. Cement shall not be stored out of
doors, except for immediate use, and in such event shall be protected during storage and
handling by waterproof covers and a raised floor. Unused cement shall be placed back into the
storage buildings.
8) Cement shall be used in approximately chronological order in which it has been received at the
Site. Storage of cement shall be limited to 90 days in bags a 150 days in bulk. Cement that has
been in storage for longer than these periods or which may have absorbed moisture shall not
be used unless it has been retested by the Contractor and approved by the Engineer. Cement
that has become lumpy shall not be used. The cements coming from different mills or of
different makes shall be stored separately.
9) The temperature of cement upon arrival to the Site shall not exceed 70°C and when entering

_______________________________________________________________________________
68
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

the mixers shall not exceed 50°C unless otherwise approved.


10) The maximum heat of hydration for Portland cement Type I shall not exceed 80 and 90 calories
per gram at ages 7 and 28 days respectively, and 70 and 80 calories per gram at same ages for
Portland cement Type II.
11) The Contractor shall keep and make available to the Engineer records of the date, amount, and
storage location of each delivery of cement and of the part of the Works in which it was used
and shall provide facilities for checking the stock of cement.
12) The Contractor is solely responsible for the timely supply of cement meeting the requirements
of these Specifications and the Works. The delay due to the lack of suitable cement will not give
the Contractor any right for the extension of time for the Completion of Works, or any claims
resulting here from.
8.7.2 AGGREGATES
8.7.2.1 General
1) Fine and coarse aggregates shall conform to the requirements of ASTM Specification C 33. They
shall consist of clean, hard, dense, durable and un-coated materials, and shall have a stable
moisture content and grading when delivered to the batching plant. Aggregates shall not
contain substances which may impair the quality of the concrete, attack reinforcing steel or
reduce bond. The following substances are regarded as being harmful: loam, clay, pieces with
large cavities, foam-like or vitreous pieces, and organic materials such as topsoil, roots, wood,
coal, lignite, etc. The deleterious substances are defined in ASTM Standards C117, C142, C123,
C40. In doubtful cases the effects of harmful substances shall be established by tests.
2) The shape of the particles shall be generally spherical or cubical. The amount of flat or
elongated particles shall not exceed 25% by weight. A flat or elongated particle is defined as
one in which the width to thickness, resp. length to width ratio is greater than 3.
3) The Contractor shall make provisions for crushing and processing of material in accordance with
recommendations contained in ACI 221 R-61 "Selection and Use of Aggregates for Concrete" to
meet the gradation and other requirements of these Specifications, in order to obtain the total
amount of aggregate required for concrete manufacture. Crushing, screening and washing
operations, bonification of aggregates, and blending of crushed and natural aggregates shall at
all time be subject to the approval of the Engineer. The secondary crushers shall be of the cone
type.
4) The optimum proportion of crushed to natural aggregate, and in particular the possibility to use
crushed sand, shall be determined at trial mix stage. During the construction of the Works, the
Contractor may use a greater proportion of crushed to natural aggregate than used in the
approved trial mixes only with the consent of the Engineer, providing that no claim for
reimbursement for additional cement used will be raised by the Contractor.
5) Natural and crushed aggregates shall be stockpiled and batched separately.
6) The handling, transporting, and stockpiling of aggregates shall be such that there will be a
minimum amount of fines resulting from breakage and abrasion of material resulting from free
fall and improper handling. Excess in any of fine or coarse aggregate sizes shall be disposed of in
approved manner.
8.7.2.2 Source
1) Coarse and fine aggregates shall be produced from suitable material obtained from required
excavation for Permanent and Temporary Works and from the approved quarry and borrow
areas shown on the Final Design and described in the Information to Tenderers or from other
sources as may be designed or approved in the course of the work.
2) The Contractor shall carefully clear and prepare the stockpile areas so that excavated materials
are free of unsuitable materials and other objectionable matter. All materials removed from the
area and not used in the work shall be disposed of as directed.
3) The disposal of excavated materials shall be selective. The suitable rock for aggregates shall be

_______________________________________________________________________________
69
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

unloaded in the approved stockpiles, while the rock not suitable for aggregates shall be
unloaded in the approved disposal areas.
4) The suitability of the rock for aggregates shall be established with laboratory tests carried out
by the Contractor.
5) Alternative sources developed by the Contractor shall be subjected to approval by the Engineer.
The Contractor shall carry out tests to furnish satisfactory evidence that aggregates from such
alternative sources comply with the requirements of this Section.
6) The approval of the sources shall not be construed as constituting the approval of all materials
taken from the deposits. The Engineer reserves the right to reject certain localized areas, strata,
or channels within the approved areas and zones, when the material is unsatisfactory for use.
7) The Contractor shall prepare and submit to the Engineer a detailed report concerning the
quarry exploitation within 60 days from the date of issue of Notice Commence.
8.7.2.3 Fine Aggregate (Sand)
1) The term "fine aggregate" is used to designate aggregate in which the maximum size of
particles is 4.75 mm.
2) The gradation of fine aggregate shall be as given below:

US Standard Square Mesh Square Mesh Sieve Opening


Sieve Sieve Opening
No. 4 4.750 mm 95 - 100
No. 8 2.360 mm 80 - 100
No. 16 1.180 mm 50 - 85
No. 30 0.600 mm 25 - 60
No. 50 0.300 mm 10 - 30
No. 100 0.150 mm 5 - 15
No. 200 0.075 mm 0-5

3) Fine aggregate shall have a fineness modulus in a range between 2.5 and 3.0. The fineness
modulus is calculated by adding the cumulative percentages retained on US Standard Sieves
Nos. 4, 8, 16, 30, 50 and 100 and dividing the sum by 100. The grading shall be controlled so
that at any time the fineness modulus of at least 9 out of 10 consecutive test samples of
finished sand will not vary more than 0.20 from the average fineness modules of the 10 test
samples.
4) The amount of deleterious substances in fine aggregate shall not exceed the limits given below:
• Organic matter Limits: as per Table 9.2 of ASTM C40-04
• Clay lumps and friable particles (as per Table 1 of ASTM C-33-03) 3 % by
weight
• Lightweight material 2 % by weight
• Total of other deleterious substances 2 % by weight
The sum of percentages of all deleterious substances shall not exceed 5 % by weight. The
percentage passing the75 μm shall be limited in accordance with BS 882:1992 Section
5.4.
5) Sand producing a colour darker than the standard set out in the test for organic impurities
(ASTM C 40) may be rejected.
6) Should the loss of weight of portion retained on No. 50 Sieve, when subjected to five cycles of
soundness test by use of sodium sulfate (ASTM C 88), exceed 10% by weight, the fine aggregate
may be rejected.
_______________________________________________________________________________
70
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

7) Fine aggregate, upon delivery to the batching plant, shall have a uniform and stable moisture
content. The amount of moisture shall be less then 6% by weight, and shall not vary by more
than 0.5% per hour.
8) Fine aggregate shall be stored in such a manner as to avoid the inclusion of any foreign
materials and segregation.
9) The Contractor shall provide suitable drainage facilities to secure that the sand delivered to the
batching plant shall have uniform and stable moisture content. If required, two or three
separate stockpiles shall be maintained, one for wet sand, eventually one in the process of
draining, and one where the drained sand shall remain for a minimum 48 hours prior to the
use.
10) No fine aggregate from the bottom 50 cm of the stockpile shall be used for mixing concrete.
11) The Contractor shall maintain at all times sufficient storage of fine aggregate to permit
continuous placement of concrete.
8.7.2.4 Coarse Aggregate
1) The term “coarse aggregate” is used to designate aggregate which is retained on sieve No. 4
(4.75 mm). The coarse aggregate shall conform to ASTM Specification C-33. The coarse
aggregate may be rejected if the specific gravity (bulk, saturated surface-dry basis) is not in
accordance with ACI 207.1R (par. 2.5.5) and tested in accordance with ASTM Standard Test C-
127.
2) The coarse aggregate shall be processed, stockpiled, and used in groups designated by the
maximum size aggregate. The gradation of aggregate in each group shall be as given below
unless site laboratory tests prove that a different gradation is more suitable for concrete mix:
US Standard Sieve Percent by Weight Passing Individual Sieve
(mm)
20 mm 32 mm 76 mm

76 - - 100
50 - 100 90-100
37.5 - 90-100 20-45
25 100 22-45 0-10
19 90-100 0-10 0-5
9.5 30-55 0-5 -
4.75 0-5 - -

3) The amount of deleterious substances in coarse aggregate shall not exceed the limits given
below:
• Organic matter Limits: as per Table 9.2 of ASTM C-40-04
• Clay lumps and friable particles
• (as per Table 1 of ASTM C-33-03) 1.0 % by weight
• Material passing No. 200 sieve 1.5 % by weight
• Lightweight material 2.0 % by weight
• Total of other deleterious substances 1.0 % by weight
The sum of the percentages of all deleterious substances in any category shall not exceed 3% by
weight.
4) Should the loss by weight, when the aggregate is subjected to abrasion test by use of the Los
Angeles machine (ASTM C131), exceed 10% at 100 revolutions or 40% at 500 revolutions, the
coarse aggregate may be rejected.
5) Should the weighted average loss by weight exceed 10%, when the aggregate is subjected to
_______________________________________________________________________________
71
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

five cycles of soundness test by use of sodium sulfate (ASTM C88), the coarse aggregate may be
rejected by the Engineer.
6) Coarse aggregates, upon delivery to the batching plant, shall have a uniform and stable
moisture content.
7) The nominal maximum aggregate size in relation to the structure dimension shall not be larger
than:
a) 1/5 of the narrowest dimension between the side of forms
b) 3/4 of the minimum clear spacing between the reinforcing bars
c) 1/3 of the slab depth
8) Stockpiles of coarse aggregate shall be formed in such manner as to avoid the ingress of any
foreign matter and to prevent segregation. Sufficient storage shall be maintained at all times to
permit continuous placement of concrete.
8.7.3 WATER
1) Water for mixing and curing of concrete, mortar, plaster, and grout shall be taken from an
approved source and shall be clean, colourless, free from deleterious substances including salt,
oil, alkaline or organic matters, sugar compounds, and shall not have brackish or saline taste.
When shaken no permanent foam may be formed.
2) The limits of the content of sulphates, chlorides, alkali and turbidity shall conform with ASTM C-
1602/C-1602M-06.
8.7.4 ADMIXTURES
8.7.4.1 General
1) Water-reducing, water-reducing-retarding, air-entraining and super plasticizer admixtures shall
be used for cast-in-situ and precast concretes. Only admixtures that have been commercially
used with satisfactory service in a similar type of concrete work shall be considered for
approval. All admixtures shall be manufactured by a reputable company(ies) such as Sika, Grace,
Master Builders supported by a fully staffed technical service organization and research group.
2) Admixtures shall be stored and handled so as to avoid contamination or damage to their
properties by temperature or moisture changes or other influences.
3) The quantity of admixture used, and the method of mixing shall be strictly in accordance with
the manufacturer's printed instructions, or as required to produce specified results and
approved by the Engineer.
4) The Contractor shall be held liable for any damages and difficulties resulting from the selection
and use of admixtures such as delay in concrete placing or damage to concrete during forms
removal and shall not be entitled to any time extension or claims resulting here from.
8.7.4.2 Accelerators
1) Only non-chloride accelerators meeting the requirements of ASTM Specification C 494, Type C
may be used if permitted by the Engineer. The use of calcium chloride or other admixture in
which chloride is added or serves as an active ingredient shall not be permitted.
2) Accelerators shall not be used in hot weather concreting.
8.7.4.3 Air-Entraining Admixtures
1) Air-entraining admixtures shall conform to the requirements of ASTM Specification C 260.
2) Air-entraining admixture shall be used to achieve the following air content in concrete:

Maximum size Total air Percentage by


aggregate in volume of concrete
concrete
20 mm 6.0 ± 1
32 mm 4.5 ± 1
76 mm 3.5 ± 1
_______________________________________________________________________________
72
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

8.7.4.4 Water-reducing, Set-controlling Admixtures


1) Water-reducing, set-controlling admixtures shall conform to the requirements of ASTM
Specification C 494, Type A, D, E, F or G.
2) The dosage to be used shall be within the range recommended by the manufacturer and as
determined by tests or as directed by the Engineer, but type and quantities will vary with
changing climatic conditions at the Site and/or other job conditions.
8.7.4.5 Combined Admixtures
Combined air-entraining, water-reducing admixtures shall be used where required to increase
the watertightness and strength of the concrete (e.g. Plastocrete-DM of SIKA).
8.8 STEEL REINFORCEMENT
8.8.1 GENERAL
1) The Contractor shall furnish, fabricate, and install all reinforcement steel as shown on the
Detailed Design and/or Construction Drawings and bar lists. The work shall further include the
furnishing and installation of all tie wires, clips, supports, chairs, spacers, and other
appurtenances necessary to produce finished concrete structures.
2) All reinforcing bars shown on the Detailed Design and/or Construction Drawings shall be
identified on the bar lists and all bars shall be defined and given dimensions in a clear and
unambiguous way. All bar lists shall be referenced to the relevant reinforcement drawings. The
Contractor shall be responsible for the correctness of the reinforcement drawings and bar lists.
3) The Contractor shall submit to the Engineer prints and electronic files of the reinforcement
drawings and bar lists.
8.8.2 QUALITY REQUIREMENTS
1) Reinforcing bars shall be Grade 60 (420 MPa) deformed billet-steel bars conforming to ASTM
Specification A-615-M. Plain bars may only be used where shown on the Drawings. Minimum
yield strength of the bars shall be 400 N/mm2 (4,077 kg/cm2).
2) Wire for tying reinforcement shall be smooth wire conforming to ASTM Specification A82.
3) Welded wire fabric for in-situ or sprayed concrete reinforcement shall be made from electrically
welded smooth wire and shall conform to the requirements of ASTM Specification A185.
8.8.3 STORAGE
1) Reinforcement shall be stored at the Site and separate into the various sizes in such a manner
that it is not contaminated with deleterious matter. Reinforcement coming from different
manufacturers shall be stored separately.
2) Reinforcement fabric supplied in rolls shall be straightened into flat sheets before being placed.
8.8.4 CUTTING AND BENDING
1) Steel bars shall be accurately cut and bent to the dimensions and shapes as shown on the
Detailed Design and/or Construction Drawings and Bar Lists.
2) The bars shall be bent cold at temperature greater than 5°C. Bending below that temperature
or warm bending will only be permitted when adequate precautions are taken to comply with
the corresponding direction issued by the steel manufacturer for such bending.
3) Temporary bending and subsequent straightening of bars partially embedded in concrete shall
not be permitted, except when shown on the Detailed Design and/or Construction Drawings or
with the written approval of the Engineer.
4) Should the necessity of welding of reinforcement arise, the provisions of the American Welding
Society "Reinforcing Steel Welding Code" (AWS D 12.1) shall be followed.
8.8.5 SPLICING
Reinforcement bars, other than tie bars, shall not be spliced at points other than those shown
on the Detailed Design and/or Construction Drawings without the consent of the Engineer. On
occasions when it becomes necessary to alter the position of such splices, the new position and
the type of splice shall be subject to the written approval of the Engineer.

_______________________________________________________________________________
73
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

8.8.6 PLACING
1) Reinforcing steel, before being positioned, shall be free from loose mill and rust scale, and from
any coating that may destroy or reduce the bond between the steel and concrete.
2) As a rule, the same type of reinforcement from the same source shall be used in any one part of
the structure.
3) Reinforcing steel shall be accurately positioned and secured against displacement by using ties
made of annealed iron wire of not less than No. 16 gauge, dobies, or suitable clips at
intersection.
4) The metal chairs, bar spacer and similar reinforcement support devices that touch the forms
shall be galvanized or shall have plastic tips at the point where the support device touches the
forms.
5) The bottom layer of reinforcing steel in slabs on the ground shall be supported by means of pre-
cast concrete blocks (dobies). The concrete blocks shall have a horizontal surface approximately
7x10 cm and be of concrete quality at least equivalent to that which is to be placed. The upper
layer of reinforcement in slabs on ground and all other slabs and in beams shall be supported
by means of metal chairs. In all cases, sufficient supports for horizontal reinforcement shall be
used so that there will be no sagging of the bars.
6) All reinforcement shall be inspected in place and approved by the Engineer before placing the
concrete. Concrete placed in violation of this provision may be rejected and removal required.
8.8.7 CONCRETE COVER OF THE REINFORCEMENT
The cover of the reinforcement shall be as indicated below or as shown on the Detailed Design
and/or Construction Drawings:

1) In-situ concrete:
o Concrete cast directly against soil or rock and being permanently
exposed to it
60mm
o Formed concrete permanently exposed to
backfill or water 50 mm
o Outside exposure 40 mm
o Inside exposure 30 mm
2) Pre-cast concrete:
o Outside exposure 40 mm
o Inside exposure 30 mm
8.9 SURFACE FINISHES
8.9.1 GENERAL
1) The quality of the surface finish shall be appropriate to the classification as described
hereunder. Generally it shall be free from areas of honeycombs, segregation, loss of cement or
fine material, from damage due to stripping of forms, from boltholes, abrupt irregularities
caused by movement of forms or components, loose knots and similar features and bulges or
depressions in the general plane of the surface.
2) Only one type of formwork shall be used for all parts of a concrete structure which is visible
from any direction.
3) The classes of finish shall be as shown on the Detailed Design and/or Construction Drawings or
as directed by the Engineer.
8.9.2 FORMED SURFACES
The classes of finish for formed surfaces are designated by the use of symbol F and the shape of
the formwork panels required for concrete work shall be either plane ( F1, F2, F3 and F4) or
curved (F1C, F2C, F3C and F4C).

_______________________________________________________________________________
74
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

a) Finish F1, F1C: this finish shall be for surface concealed from view, including surface upon
or against which backfill, or concrete is to be placed, formed surfaces of expansion and
contraction joints, and blockouts for equipment embedding or other parts which are to
be built in. It may be obtained by the use of properly designed formwork or molds of
closely- jointed rough sawn boards. The surfaces will be imprinted with the grain of the
sawn boards and their joints. Small blemishes caused by entrapped air or water may be
expected, but the surface shall be free from voids, honeycombs, or other large blemishes.
The surfaces require no treatment after formwork removal, with the exception of the
filling of form-tie holes, correction of surface depressions deeper than 3 cm, the repair of
defective concrete and curing as specified.
b) Finish F2, F2C: this finish shall be for all surfaces exposed to view not in contact with
flowing water. It is achieved by the use of properly designed forms of closely jointed
wrought boards. The surfaces will be imprinted with the slight grain of the wrought
boards and their joints. Alternatively, steel or other suitable material may be used for the
forms. Fascia boards consisting of 25x25 mm timber strips shall be fixed to the
tops of forms to ensure the formation of straight and even horizontal construction joints.
After removal of forms, the surface shall be improved by carefully removing all fins and
other projections, thoroughly washing down, and then filling the most noticeable surface
blemishes using methods described hereafter in "Repair of Defective Concrete". Form-tie
holes shall be filled, and all voids, honeycombs, and other defective concrete repaired
before curing as specified. When filling holes and repairing defective areas, every effort
shall be made to match the colour of the concrete. The use of release agents which may
permanently stain or discolour the finished surface will not be permitted.
c) Finish F3, F3C: this finish shall be for surfaces in contact with flowing water where
cavitation, head loss, freeze/thaw or erosion are of concern. The standard of finish
required is similar to an F2 finish, but with no surface bubbles or holes larger than 3 mm
diameter allowed, and with more stringent tolerance requirements measured along a line
parallel and transverse to the direction of flow. Variations in concrete colour as a result of
concrete repairs or staining due to release agents will be allowed. Fascia boards will not
be required.
d) Finish F4, F4C: this finish shall be for surfaces where plaster, stucco, or wainscoting is to
be applied. Formwork shall consist of rough-faced form boards. Steel lining or steel
sheathing shall not be permitted. No form oil may be used. Forms shall be removed as soon
after pouring as conditions will permit. Surfaces shall be roughened with a heavy wire
brush, cleaned of all materials that might prevent satisfactory bond and washed
thoroughly. Immediately prior to plastering, concrete surfaces shall be recleaned and damped
by means of a fog spray.
8.9.3 UNFORMED SURFACES
1) The classes of finish for unformed concrete surfaces are designated by the use of symbol U:
a) Finish U1 (screeded finish): this finish shall be applied to unformed surfaces that will
be covered by fill material or concrete. Finishing operations shall consists of sufficient
leveling and screeding to produce even, uniform surfaces. Surface irregularities shall
not exceed those specified for Finish F1. This finish is also the first stage of finishes
U2 and U3.
b) Finish U2 (floated finish): this finish applies to unformed surfaces not permanently
concealed by fill material or concrete. Finishing operations shall consist of sufficient
leveling and screeding to produce even surfaces in which the surface irregularities
shall not exceed those specified for Finish F2. Floating with hand or power-driven
equipment shall be started as soon as the screeded surface has stiffened sufficiently,
to produce a surface that is free from screed marks and is uniform in colour and
_______________________________________________________________________________
75
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

texture. This finish is also the second stage of finish U3. If finish U3 is to be applied,
floating shall be performed until a small amount of mortar without excess water is
brought to the surface, so as to permit effective trowelling.
c) Finish U3 (steel troweled finish): this finish shall be for surfaces in contact with
flowing water where cavitation, head loss, freeze/thaw or erosion are of concern,
as well as inside floors of buildings except where a bonded concrete finish or tile
floor is foreseen. The standard of this finish is similar to U2, but with more stringent
tolerance requirements parallel and transverse to the direction of flow. Steel
troweling shall start when the floated surface has hardened sufficiently to prevent an
excess of fine material from being drawn to the surface. It shall be performed with a
firm pressure that will produce a dense, uniform surface free of blemish, ripples, and
trowel marks.
d) Interior surfaces shall be sloped for drainage where shown on the Detailed Design
and/or Construction Drawings. Exterior surfaces, which will be exposed to the
weather, shall be sloped for drainage even if there is no such indication on the
Detailed Design and/or Construction Drawings. In such case the slope shall be at
least 1% but not exceed 3%.
8.10 TOLERANCES
8.10.1 CONCRETE
1) Concrete surface irregularities caused by the roughness of the formwork facing or by
inaccurately aligned joints between the formwork panels shall not exceed the following
tolerances:

Specified Finishes Permissible Irregularities


Abrupt Gradual
F1, F1C, U1 6 mm 12 mm
F2, F2C, F4, U2 3 mm 6 mm
F3, F3C, U3
a) Measured A line parallel to the flow
along direction 3 mm 6 mm

b) Measured A line perpendicular to 1 mm 3 mm


along flow the flow
direction
2) Abrupt irregularities are offsets caused by displaced or misplaced form sheathing or lining or
form sections, or by loose knots in forms or otherwise defective form lumber. They shall be
tested by direct measurements.
3) Gradual irregularities are all other irregularities and shall be tested by a 2 m long template. The
templates will be a straight edge for plane surfaces or a "shaped" template for curved or
warped surfaces.
4) Further limitation for allowable abrupt irregularities for surfaces of structures with high velocity
water flow shall be as follows, if not otherwise shown on the Detailed Design and/or
Construction Drawings or directed by the Engineer:
a) Abrupt irregularities parallel to the flow direction shall be eliminated completely
by grinding to bevel of 1 to 20 ratio of height to length.
b) Abrupt irregularities transverse to the flow direction shall be eliminated

_______________________________________________________________________________
76
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

completely by grinding to bevel of 1 to 50 ratio of height to length.


5) Deviations of concrete structure outlines from the lines and grades shown on the Detailed
Design and/or Construction Drawings shall not exceed 20 mm.
6) Variations in thickness of slab, columns and walls shall be within the limits 5 mm and +10 mm.
7) The Contractor shall repair hardened concrete which is not within specified tolerances as
stipulated in "Repair of Defective Concrete" later in this Section. Such repair shall, however, be
done only after consultation with the Engineer and after his consent.
8) Concrete surface which may be in contact with high velocity flow shall be, without exception,
brought within the specified tolerances. Grinding shall be limited in depth so that no aggregate
particles remain exposed more than 2 mm in cross section at the finished surface. Where
grinding would cause exposure of aggregate greater than the above limit, concrete shall be
removed from the area affected and replaced by new concrete.
8.10.2 REINFORCEMENT
1) The center-to-center distance between parallel bars shall be as shown on the Detailed Design
and/or Construction Drawings, with a tolerance of 20 mm, or as directed by the Engineer.
2) In placing reinforcement steel, the tolerance from indicated protective cover shall be:
• for 40 mm cover and less: ± 5 mm
• for 50 mm cover and more: ± 10 mm
8.11 FORMWORK
8.11.1 DESIGN
1) The Contractor shall assume full responsibility for the adequate design of all formwork,
falsework, and all accessories.
2) For the purpose of formwork and falsework design, the Contractor shall assume a value of 2.5
t/m3 for the density of concrete.
3) Formwork shall be designed to withstand the full hydrostatic head of concrete.
8.11.2 WORKMANSHIP
1) All forms shall be true to the required shape and size, shall conform to the established
alignment and grade, and shall be of sufficient strength and rigidity to maintain their position
and shape under the loads and operations incident to placing and vibrating the concrete.
2) Suitable and effective means shall be provided on all forms for holding adjacent edges and ends
of panels and sections tightly together and in accurate alignment so as to prevent the formation
of ridges, fins, offsets, or similar surface defects in the finished concrete. Forms shall be tight so
as to prevent the loss of water, cement and fines during placing and vibrating of the concrete.
3) Any forms which in the opinion of the Engineer are unsafe or inadequate in any respect may, at
any time, be rejected and the Contractor shall promptly remove the rejected forms from the
Works and replace them.
4) An adequate number of temporary clean-out holes or short pipes shall be provided in the forms
to secure the draining of rainwater.
5) All exposed finished edges of concrete shall be chamfered 20 mm (at 1:1) unless otherwise
shown on the Detailed Design and/or Construction Drawings.
6) When a second lift is placed on hardened concrete, the number, location and tightening of ties
at the top of the old lift and bottom of the new shall be such as to prevent any damage to
concrete. The form of a new lift shall overlap the hardened concrete by 10 cm, to prevent
abrupt irregularities.
7) Forms for sloping concrete surfaces shall permit their placing board-by-board or panel-by-
panel immediately ahead of concrete placement so as to enable access for placement,
vibration, and inspection of the concrete.
8.11.3 MATERIALS
1) Materials used for form sheathing and lining shall be of wood, steel, plywood, or fiberglass.

_______________________________________________________________________________
77
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

2) Forms for concrete surfaces exposed to flowing water shall be lined with sanded, un-coated,
plywood veneer. Steel or impermeable plastic liners will not be permitted.
3) Except as expressly approved by the Engineer, all timber brought to the Site for use as forms,
shoring or bracing shall be new material. Plywood for use as form shall be mill-oiled and edge-
sealed.
4) Rough sawn boards may be used only for the lowest grade of surface finish (F1).
5) Where required, expanded metal fixed to the formwork shall be used in vertical construction
joints.
8.11.4 FORM TIES
1) The type, number and positions of internal formwork supports, and ties shall be to the approval
of the Engineer.
2) The whole or part of such formwork supports, and ties shall be removed without damage to the
concrete so as to leave no part embedded nearer the surface of the concrete than the designed
cover of the reinforcement or 50 mm in the case of un-reinforced concrete. Only metal portions
of formwork support and ties shall be allowed to remain in place.
3) Through-bolts will not be permitted in water retaining walls.
4) Holes left after the removal of supports and ties shall be filled as described hereinafter in
"Repair of Defective Concrete” and shall be finished off neatly to the standard of the concrete
surface. Such filling shall be adequately cured.
8.11.5 MAINTENANCE OF FORMWORK
1) Forms shall be maintained at all times in good condition, particularly as to size, shape, strength,
rigidity, tightness and smoothness or surface.
2) All timber forms shall be given a preliminary oil treatment by the manufacturer or shall be oiled
by the Contractor at least 2 weeks in advance of their use.
3) The surface of the forms shall be free from encrustation of mortar, grout, or other foreign
matter at the time of concrete placement.
4) Before concrete is placed, the forms shall be thoroughly cleaned and treated with a nonstinging
mineral oil or other lubricant approved by the Engineer. Any excess lubricant shall be removed
before placing the concrete. Care shall be exercised in keeping oil off the surfaces of steel
reinforcement and other metal items to be embedded in concrete.
5) Forms may be reused provided that they are in good condition, and that the required concrete
form and finish may be achieved with their use. The Engineer will, at any time, have the right to
reject formwork which he considers to be no longer fit for such use.
8.11.6 REMOVAL OF FORMWORK
1) Removal of forms shall be performed with care so as to avoid injury to the concrete and as soon
as permissible in order to avoid delay in curing and repair of surface imperfections. Forms shall
not be removed without the consent of the Engineer.
2) Forms shall not be removed until the concrete has attained sufficient strength to prevent
damage to concrete. Damaged concrete shall be repaired or treated by the Contractor as soon
as possible, but not before the Engineer has inspected such damage and agreed to the remedial
works.
3) The minimum period before the removal of formwork shall be in accordance with the following
table:
Type of Formwork Days % of 28-day compressive
strength
Vertical formwork to columns, walls 2 40%
and
large beams

_______________________________________________________________________________
78
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

Ceiling formwork to slab 7 70%


Props to slabs 12 85%
Ceiling formwork to beams 10 80%
Props to beams 14 90%

4) The minimum periods in days are only indicative. The governing rule to be observed is the
percentage of the required 28-day compressive strength, which shall be determined by the
cylinder test in addition to those required by the provisions as described in aforesaid "Test
During Execution of the Work". When fixing the minimum period for formwork removal, the
shrinkage and creep of the concrete shall be taken into consideration.
8.12 JOINTS IN CONCRETE STRUCTURES
8.12.1 CONSTRUCTION JOINTS
8.12.1.1 General
1) Concreting shall be carried out continuously up to construction joints, the arrangement and
positions of which shall be as shown on the Detailed Design and/or Construction Drawings, or
as approved by the Engineer. Also, whenever concreting is forced to be interrupted and placed
concrete has become so hard that it does not permit the entry of a vibrator, a new construction
joint shall be formed conforming to these Specifications.
2) The position of certain construction joints shown on the Detailed Design and/or Construction
Drawings as mandatory may not be altered. The Contractor may propose for approval different
locations of other construction joints for reasons of concrete placement. Necessary
rearrangement of steel reinforcement arising from such modifications shall be to the
Contractor's debit.
3) Construction joints shall be approximately horizontal or vertical. The joints shall appear as
straight lines, produced by a board fixed to the formwork, at exposed faces.
4) The faces of vertical joints shall be shuttered with expanded metal or other approved rough
material. The expanded metal shall be removed as far as possible, before the adjacent lift is
poured. If required, the surface shall be cleaned by wet sandblasting and roughened by light
bush-hammering.
5) The surface of construction joints upon or against which new concrete is to be placed and to
which new concrete is to adhere shall be clean, rough, and free of water when covered with
fresh concrete. The laitance, loose or defective concrete and foreign material shall be removed
from the surface of existing concrete. The previous concrete lift shall be saturated by water but
surface dry when the successive lift is placed.
6) The surface of the hardened concrete shall be cleaned and roughened by wet-sandblasting and
washing thoroughly with air-water jet. Care shall be taken to prevent undercutting of aggregate
in the concrete during sandblasting.
7) Wet-sandblasting equipment shall be operated at an air pressure of approximately 7 bars. Sand
to be used for blasting shall be dense, hard, not easily broken and sufficiently dry.
8) In lieu of wet-sandblasting the Contractor may propose high-pressure water blasting utilizing
pressures not less than 400 bars, provided that such high-pressure water blasting produce
equivalent results to those obtainable by wet-sandblasting.
9) The horizontal surfaces of construction joints may be treated by cutting with an air-water jets
("green-cutting"). This shall be performed after the initial set has taken place but before the
concrete has become too hard for effective cutting. The fresh concrete surface shall be cut with
air-water jets to remove all laitance and to expose clean, sound aggregate. After cutting, the
surface shall be washed with clean water. Care shall be taken that the treated surface does not
become contaminated before new concrete is placed upon it. Should the surface become
_______________________________________________________________________________
79
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

contaminated that a satisfactory joint with new concrete is not ensured the Contractor shall
clean it by means of wet sandblasting.
10) Water used in cutting, washing and rinsing of concrete surfaces shall be disposed of in such a
way that it does not stain, discolour or affect exposed surfaces of the structures.
11) When necessary, as determined by the Engineer, structural concrete placement in forms shall
be started with an over-sanded mix with 19 mm maximum size aggregate, an extra 50 kg of
cement per cubic meter and a 10 cm slump. This mix will be referred to as a starter mix and
shall be placed approximately 5 cm deep.
12) In the heavy concrete structures and mass concrete, the construction joint surface shall receive
layer of mortar approximately 10 mm thick immediately prior to placing of the new lift. This
mortar shall be of the same proportions as those in the concrete with coarse aggregate omitted
and shall have the same air content, by volume.
13) The mix or mortar shall be spread over the whole surface except in case of permanently visible
construction joints where it shall be kept 5 cm back from the exposed surface. It shall be
worked thoroughly into all irregularities of the surface. In inaccessible locations it shall be
spread by means of air-suction gun.
14) Concrete shall not be placed upon mortar which has dried out or become contaminated by
water, debris or other deleterious material. Mortar which has been so contaminated or dried
out shall be removed from the surface of the construction joint, the surface shall be re-cleaned,
and a fresh layer of mortar spread on the surface prior to placing of a new concrete lift.
15) Where indicated on the Detailed Design and/or Construction Drawings, construction joints shall
be formed with shear keys. The Contractor's proposed method for forming such keys shall be
subject to the approval by the Engineer.
16) Where indicated on the Detailed Design and/or Construction Drawings or where directed by the
Engineer, flexible PVC water stop shall be placed in construction joints.
8.12.1.2 Cold Joint
1) Cold joint is an unplanned joint which is the result of hardening of the concrete surface before the
next batch is placed against it. Cold joints are undesirable and should be avoided. However, in
the event of equipment breakdown, prolonged heavy rainfall, or other unforeseen prolonged
interruption the continuous placing may not be reasonable.
2) When such event become apparent, and the unconsolidated concrete may harden to the extent
that later vibration would not fully consolidate it, the Contractor shall immediately consolidate
such concrete to a stable and uniform slope.
3) If delay in placement is short and it is still feasible to penetrate the underlying concrete,
placement shall resume with care to thoroughly penetrate and re-vibrate the concrete surface
placed before the delay.
4) If the concrete cannot be penetrated with the vibrator, the cold joint shall be treated as a
construction joint, if the design requirements tolerate such joint. If such joint would impair the
structural integrity of the structure, as determined by the Engineer, the concrete, or a part of it,
shall be repaired or removed as directed by the Engineer.
8.12.1.3 Construction Joints for Stage Concreting
1) Constructions joints for stage concreting are joints, or joint systems where in-fill concrete or
bays shall not be placed before one or two months after placing of the first stage concrete.
2) Where indicated in the Detailed Design and/or Construction Drawings or where directed by the
Engineer, waterstops shall be provided in construction joints for stage concreting. Waterstops
shall be joined and fixed in place strictly in accordance with manufacturer's recommendations.
8.12.2 MOVEMENT JOINTS
8.12.2.1 General
1) Movement joints in the concrete structures shall be constructed at such locations and to such
dimensions as shown on the Detailed Design and/or Construction Drawings or as directed by

_______________________________________________________________________________
80
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

the Engineer. The Contractor shall supply and install the various joint components as specified
herein, as shown on the Detailed Design and/or Construction Drawings and in accordance with
the manufacturer’s recommendations.
2) Expansion joints are joints provided in concrete structures to prevent transfer of forces from
structure to structure or to accommodate volumetric changes due to temperature rise.
Expansion joints may be comprised of the following elements:
a) Flexible neoprene or PVC waterstop
b) Concrete shear keys
c) Expanded polystyrene joint filler (alternative: preformed expansion joint filler)
d) Joint sealing compound
3) Contraction joints are joints placed in concrete to provide for volumetric shrinkage of a
monolithic unit, or to allow movement between the units. No bond between the concrete
surfaces is acceptable. Contraction joints may be comprised of the following elements:
e) Flexible PVC waterstop
f) Concrete shear keys
8.12.2.2 Materials
1) Waterstops shall be an Elastomer (an artifical rubber compound based on long chain polymers),
cross linked to control their shape and deformation / movement under stress possibilities, by
vulcanising them. The Elastomer waterstops shall have the following properties:

2) Expanded polystyrene joint filler shall consist of panels 10 and 20 mm thick of specific weight
approximately 20 kg/m3. They shall be waterproof and shall not absorb water.
3) Joint sealing compound shall be:
a) Plasto-elastic, one-component, hot-poured sealant on bitumen/rubber for
horizontal floor joints.
b) Elastic two-component, non-sagging sealant on polyurethane-tar.
8.12.2.3 Construction
1) Where grouting is not required, the movement joints shall be formed with F1 finish. If grouting is
required, joints shall be formed with F2 finish.
2) Waterstops shall be joined and fixed in place in accordance with manufacturer's
recommendations to form a continuous watertight barrier. All cross-pieces, T pieces and corner-
pieces shall be factory produced. All joints shall be welded with approved, thermostatically
controlled electric heat equipment. The temperature at which the splices are made shall be
sufficient to melt but not char the plastic material. All splices shall be neat with the ends of the
joined waterstops in true alignment. A miter-box guide and portable knife shall be provided for
cutting the ends to be joined to ensure good contact between joined surfaces. The Contractor
_______________________________________________________________________________
81
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

shall supply all necessary supports and ties required for placing the waterstop and shall position
it so that its central axis coincides with the joint center. Care shall be taken that waterstop does
not bend or deflect during concreting. Concrete adjacent to the waterstop shall be thoroughly
worked to ensure full contact with the waterstop but without damaging it. Prior to
commencement of concrete placing, the waterstops placed shall be inspected by the Engineer.
3) Before casting the second part of a movement joint, the whole surface will be covered with
expanded polystyrene panels, bituminous roofing felt, bituminous coating, or other approved
bond breaker as shown on the Detailed Design and/or Construction Drawings. The panels or felt
shall be cut to the size and shape of the joint and shall be glued onto the joint face and tightly
joined. Holes and joints in the filler shall be filled with mastic to prevent passage of mortar or
concrete from one side to the other. Particular care shall be taken to ensure that all surfaces of
the shear key are covered.
4) Before applying the joint sealant, the joint shall be raked out to a depth as specified. All
laitance, dirt, oil and foreign matter shall be removed from the joint by sandblasting,
compressed air, grinding discs, or other effective means, and the concrete surfaces coated with
an approved suitable primer. Joint sealant shall be placed after the concrete curing period in
accordance with manufacturer's instructions. The concrete surface temperature shall not be higher than 30°Cat the
time of placing, and the concrete shall be surface dry. After placing, the sealant shall be
protected from the effects of water for a period of 10 hours.
5) Plastic tape shall be used to ensure that no bond develops between the sealant and the plastic
foam joint filler.
6) Sealant that becomes un-bonded from the concrete, or cracks, or shows any other defects
before final acceptance of the work, shall be replaced by the Contractor.
8.13 PREPARATION FOR CONCRETE PLACING
8.13.1 GENERAL
1) Concrete shall not be placed until all formwork, installation of embedded parts, reinforcing
steel, and surfaces against which concrete is to be cast have been accepted by the Engineer.
2) All surfaces of forms and embedded items that have become encrusted with dried material
from concrete previously placed shall be cleaned of all such material before the surrounding or
adjacent concrete is placed.
3) Concrete shall not be placed in any structure until all water entering the space to be filled with
concrete has been properly cut off or diverted by pipes, or by other means, and carried out of
the forms clear of the work. Water shall not be allowed to stand on any concrete surface until it
has attained its initial set. Water flow over the concrete, which may injure the surface finish, will
not be allowed.
4) Pipes, conduits, dowels and other items to be embedded in concrete shall be so positioned and
supported prior to placement of concrete to be stable and provide sufficient clearance (min.
50 mm) between said items and steel reinforcement to allow proper concreting. Securing such
items in position by wiring or welding to reinforcement will not be permitted.
5) Where excavated surfaces which are to form the foundations for structural concrete, are
absorptive or likely to become otherwise unsuitable, or where shown on the Final Design and /or
Construction Drawings, the Contractor shall place a 'blinding course' consisting of a layer of
Class C15D32 concrete 5 to 10 cm thick, as directed by the Engineer, uniformly over the
foundation such that the upper surface is at grade elevation. Blinding concrete shall be placed
before installing reinforcement or formwork.
6) Immediately before concreting, the forms and all other surfaces which will be in contact with the
fresh concrete shall be cleaned of all loose material and debris including shavings, wood chips,
sawdust, pieces of wire, nails, fragments of hardened concrete and mortar. Clean-out holes
which may be needed for this purpose shall subsequently be securely closed in order to obtain

_______________________________________________________________________________
82
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

the required surface finish.


7) The use of compressed air for cleaning will be allowed only if adequate precautions are taken to
avoid the deposition of suspended oil on construction joint surfaces, reinforcement or other
items which are to be bonded to concrete. The Contractor shall provide such personnel and
equipment so that the performance of the concrete work is in a satisfactory manner. The
transporting and placing equipment shall be clean and in good condition, adequate, and
properly arranged to proceed with the placing without undue delays. The number and
condition of vibrators for use and standby shall be ample for the requirements during
placement. The lighting system shall be sufficient to illuminate the inside of the forms when
concrete is placed at night.
8) The Contractor shall have protective coverings available for fresh concrete surfaces if there is a
possibility of rain, hail or sleet.
8.13.2 CONCRETE ON EARTH FOUNDATION
All concrete placed on earth shall be placed upon clean, damp surface, free from standing or
running water.
8.13.3 CONCRETE CAST AGAINST ROCK
1) Rock surfaces against which concrete is to be placed shall be clean and free from oil, standing or
running water, mud, loose rock, objectionable coating, debris, and loose or unsound fragment.
Faults, fissures and seams shall be cleaned to sound rock, and if directed, backfilled with dental
concrete, shotcrete or dry pack as appropriate.
2) Immediately before concrete is placed, all surfaces shall be cleaned thoroughly by the use of
high velocity air-water jets, brooming, wet sandblasting, bush-hammering, or other satisfactory
means including combinations of the above.
3) Where gravel drains are used to control seepage water, the drains shall be covered with low
slump concrete which shall be allowed to reach its final set before placement may begin.
4) Rock surface against which concrete is to be placed shall be kept wet for at least 12 hours
during the 24-hour period prior to placing concrete and shall be in a damp condition at the time
of placing, with all pools of water removed.
8.13.4 CONCRETE CAST AGAINST OR UPON PREVIOUSLY PLACED CONCRETE
Before any concrete is cast against previously placed concrete, the surface of the old concrete
shall be prepared as described in aforesaid "Construction Joints".
8.14 PRODUCTION OF CONCRETE
8.14.1 CONCRETE MIXES
1) The mixes for different classes of concrete shall be selected jointly by the Engineer and the
Contractor during the initial tests period (Trial Mix Stage).
2) During the progress of the work, the mixes may be adjusted whenever, in the opinion of the
Engineer, such change is necessary or desirable to secure the required strength, workability,
watertightness, density, economy, or to limit shrinkage. Adjustments of the mixes proposed by
the Contractor will be subject to the Engineer's approval.
3) The consistency as measured by the slump test shall be determined according to its class, for
which the range will be defined by laboratory tests. The slumps for the various classes of
concrete, in principle, will be within the limits given in the following table:
Concrete Class Slump (cm)
C15 D32 10 ± 3
C20 D32 10 ± 3
C20 D76 10 ± 3
C25 D32 12 ± 3

_______________________________________________________________________________
83
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

C30 D32 12 ± 3
C35 D32 12 ± 3
C25 D20 13 ± 3
C30 D20 13 ± 3

4) The value of slump will be defined by the site laboratory on the basis of requirements and the
results obtained on strength. The above values may therefore be varied in accordance with
laboratory and the Engineer instructions.
5) To maintain the proper consistency, the amount of water and sand batched for concrete shall
be adjusted to compensate for variation in the moisture content or gradation of aggregates as
they enter the mixer.
8.14.2 BATCHING
1) The Contractor shall provide, operate, and maintain at the Site automatic batching equipment to
determine and control the amount of each individual material entering the concrete. Batching equipment
shall be designed for such capacities which will permit performance of the concrete work in
accordance with Contractual Construction Program and conforming to ASTM Specification C94.
2) Bulk Portland cement silos shall be plainly marked as to their contents. Delivery slips shall be
reviewed by the plant operator prior to unloading of each material, and extreme care shall be
exercised to see that these are unloaded into their respective silos.
3) The bulk cement, sand, and each size of coarse aggregate shall be weighted separately. Water
shall be measured volumetrically or by weight as proposed by the Contractor. When cement in
bags is used the weight will be measured by number of bags multiplied by stated bag weight.
Powdered admixtures shall be measured by weight, paste or liquid admixtures by weight or
volume.
4) Aggregate batch bins shall be self-cleaning during draw-down. Finish-screening of coarse
aggregate will not be required provided that the aggregate meets the grading requirements
stipulated in this Section. Coarse aggregate not meeting the grading requirements, shall be
finish-screened over vibration screen connected to the batching plant or on the ground
adjacent to the batching plant. The finish screens, if installed on the batching plant, shall be so
mounted that the vibrations of the screens will not affect the accuracy of the batching scales.
The finished products shall pass directly to the batching plant bins.
5) Each weighing unit shall be spring-less and will register the scale load at any stage of the
weighing operation from zero to full capacity. For water measuring, two water meters shall be
installed in parallel so that no delay due to faulty operation shall occur. No leakage may occur
when the valves are closed. Liquid admixtures dispenser shall be of the visual type and shall be
interlocked with the batching plant to prevent overdosing.
6) The Contractor shall provide standard test weights and any other equipment required for
checking the operating performance of each scale or other measuring device. Periodic tests
according to the manufacturer's instructions shall be made in the presence of the Engineer.
Facilities for obtaining representative samples of concrete materials, between batch bins and
the weighing hoppers or between the batch hopper and the mixer, shall be provided with the
batching equipment. The Contractor shall make such adjustments, repairs, or replacements as
may be necessary to meet the specified requirements for accuracy of measurement.
7) The scales shall be interlocked so that a new batch cannot be started until the weighing
hoppers have been completely emptied of the last batch and the scales are in balance.
Provisions for easy removal of excess materials, adjustment for compensating the weight
variations of aggregates due to moisture content and changing the mix proportions shall be
incorporated in the equipment. All weight indicators shall be in full view of the operator.

_______________________________________________________________________________
84
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

8) The batching equipment shall be computerized and shall include a printer listing weights of all
materials, or an accurate recorder for making a continuous visible combined record on a single
chart of the separate measurement of each concrete ingredient, including all mixing water.
Summary of material batched at the end of each shift or a day shall also be provided. The
quantities recorder shall be located in an enclosed room adjacent to the batching and mixing
plants where it can be viewed without interfering with batching operation and where it is
isolated from vibration and dust. The capacity of the computer shall be to store a minimum of
20 mixes.
9) The batching plant shall be equipped with an instrument to check the consistency of the batch
in the mixer, and the equipment shall be capable of adjustment to compensate for the varying
moisture content of the sand and coarse aggregates and to adjust the mix proportions as
needed.
10) Admissible errors in batching shall be as follows:
Material Cement Water and Ice Admixtures Aggregate
(if any)
Error in Percent 1.5% 1% 3% 2%
Measured by Weight or Weight or Weight Weight
volume volume

11) Conveying batched materials from weighing hoppers into the mixer shall be so constructed and
operated that spillage of the batched materials and overlap of batches is prevented.
12) Construction and operation of the cement and pozzolan handling equipment shall be such that
no noticeable dust will be raised during measuring and discharging of each batch of material.
8.14.3 MIXING
8.14.3.1 General
1) Concrete shall be mixed in a power-driven stationary batch mixer of approved type and size.
They shall be kept clean and in proper working order. The mixing blades in the drum shall be
replaced when worn by 10% of their design dimensions.
2) Movable truck mixers shall not be permitted for mixing concrete mixes.
3) Concrete mixing equipment shall be capable of combining the aggregate, cement, admixture
and water into a uniform mixture within the time limit specified hereafter and of discharging
this mixture without segregation. If more than one liquid admixture is used, these shall be
discharged separately into the batch. The plant assembly shall be such as to facilitate the
inspection of all operations at all times.
4) Batching and mixing of concrete shall not commence unless due notice, at least 24 hours in
advance, has been given to the Engineer and written approval has been obtained for the
placing arrangements, and for the preparation and accuracy of the part of the Works in which
concrete is to be placed.
5) The quantity of material in each batch shall not exceed the normal continuous rated capacity of
the mixer and the speed of rotation shall be within 1 rpm of the manufacturer's recommended
speed.
6) Components shall be fed into the mixing drum so as to ensure the most efficient use of the
mixing period and to avoid any loss of material. Into case shall the mixers be overloaded by
more than 10% of their rated capacity recommended by the manufacturer. Uniformity in
concrete consistency from batch to batch will be required.
7) Mixing is considered to have started when all solid materials are in the mixer drum, provided
that all the mixing water is introduced within one fourth of the mixing time. The further
addition of water shortly before completion of mixing and excessive over-mixing, requiring
addition of water to preserve the required concrete consistency, will not be permitted.
_______________________________________________________________________________
85
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

8) The first batch of concrete materials in the mixer shall contain sufficient excess of cement, sand
and water to coat the inside of the drum without reducing the required mortar content of the
mix. The entire content of the mixer shall be removed from the drum before materials for a
succeeding batch are placed therein.
9) Mixing of concrete shall not commence without ensuring that the stocks of materials are
adequate, with a reasonable safety margin, for the completion of the particular pour of
concrete.
10) The mixing time of each batch shall be determined by the batching and mixing tests based on
manufacturer's recommendations. Suggested mixing times for various mixer capacities are as
follows:
Capacity of mixer Mixing time
< 1.5 Cum 1½ minutes
2.0 Cum 2 minutes
3.0 Cum 2½ minutes
> 4.0 Cum 3 minutes

11) Each mixer shall be equipped with a mechanically operated timing and signaling device which
will indicate and ensure the completion of the required mixing period and will count the
batches.
12) The Engineer reserves the right to vary the mixing time or to limit the batch size when the
batching and mixing operations fail to produce a concrete conforming to the requirements set
out during the trial mix stage.
8.14.3.2 Trial Run and Performance Control
1) Prior to any Permanent Works concreting, the Contractor shall carry out a trial concrete
production run.
2) All plants and materials used shall be those to be used for the actual production of concrete in
the Permanent Works.
3) The Contractor shall make all adjustments necessary to produce concrete of the quality of the
agreed trial mixes of each class. Only when this has been achieved will the Engineer give
consent to proceed with Permanent Works concreting.
4) The performance of mixers shall be controlled in accordance with the provisions of ASTM
Specification C94 and Designation 26 of USBR "Concrete Manual".
8.14.4 TRANSPORTING
1) The method and facilities for concrete transport shall be selected by the Contractor within the
limitations of these Specifications, and he shall be responsible for adequacy and suitability of
the transporting system. The time elapse between mixing and the initial set of the concrete
shall be taken into consideration.
2) The concrete transporting methods and facilities shall be such that will prevent segregation of
coarse aggregate, excessive loss of slump, and loss of ingredients. All equipment shall be kept
clean and in good working condition.
3) Concrete mixed in central stationary mixers and transported by equipment others than truck
mounted agitators, shall be placed within 30 minutes (of loading into the transport equipment)
in its final position.
4) The capacity of bucket haulers shall be of the concrete batch size or a multiple thereof in order
to prevent the splitting of batches. The dumping mechanism shall permit discharge of small
portion of concrete in one place. Buckets shall be capable of prompt discharge of low- slump,
lean-mix concrete with maximum aggregate size to be used.
5) Transportation of concrete by non-agitating cars or trucks shall be limited to a distance of 3 km

_______________________________________________________________________________
86
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

unless remixing facilities are provided at the place of final placement. Free water shall not stand
on the surface of concrete when delivered in cars or trucks.
6) If concrete is to be poured by tipping, chutes shall be used to keep it coherent, their ends being
placed just above the placing point. The slopes of chutes for conveying fresh concrete shall be
chosen so that the concrete with minimum water content flows in a steady stream without
segregating. Effective end control that will produce a vertical drop and prevent segregation of
ingredients shall be provided. The chutes and belt conveyors shall be protected from wind and
sun.
8.14.5 COMMUNICATIONS
1) The Contractor shall furnish, install, maintain and operate a telephone system or radio, linking the
points of placing concrete with the concrete batching and mixing plant. These facilities shall also be available to
the Engineer at all times.
2) When placing the concrete by pumping, direct communication shall be maintained between the
concrete placing crew and the pump operators.
8.15 TEMPERATURE OF CONCRETE
1) The Contractor shall make the necessary provisions in the concrete materials storage, handling
and batching facilities, as required to comply with the hot weather concreting requirements.
The proposed methods of temperature control shall be approved by the Engineer.
2) Hot weather conditions shall be considered to be in effect whenever the temperature is above
30°C and is expected to exceed this value over a prolonged period.
3) The temperature of concrete when being placed in hot weather shall be as follows, unless
otherwise permitted by the Engineer:
a) Mass concrete, thickness ≥ 3.00 m, not more than 28°C
b) Structural concrete, not more than 30°C
4) To meet these requirements, the Contractor shall be prepared to undertake any, or all of the
following measures:
a) Carry out batching and placing operations at night,
b) Supply cooler mixing water, or add ice to the concrete during mixing,
c) Cool the fine and coarse aggregates before mixing operations,
d) Spray the coarse aggregate stockpile with cool water,
e) Prevent exposure of batching, mixing and conveying equipment to direct sunlight,
f) Spray the forms and reinforcing steel with cool water.
5) Use of ice for mixing water shall be carefully controlled to ensure complete melting before
mixing is terminated.
8.16 CONCRETE PLACING
8.16.1 GENERAL
1) No concrete shall be placed until the construction site, forms, reinforcement, and embedded
parts have been inspected and a written approval given by the Engineer. This approval shall be
obtained before each and every concrete pour.
2) Written approval shall consist of a triplicate "Concrete Pour Advice Form" prepared by the
Contractor and approved by the Engineer, listing at least the following:
a) Date and times of commencing and finish of placing
b) Location
c) Composition of concrete mix
d) Volume placed
e) Foreman in charge
f) Equipment used
g) Cleaning and preparation of foundation performed
h) Reinforcement placed
_______________________________________________________________________________
87
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

i) Formwork used
j) Reference drawings
3) Concrete shall be placed before initial set as per ASTM Test Method C 403 has occurred, i.e. 60
to 90 minutes after adding water to the mix.
4) No concrete shall be placed when the atmospheric conditions are, in the opinion of the
Engineer, such that proper placing and hardening of the concrete are not guarantied.
Specifically, the Contractor shall have the responsibility for meeting the hot weather concreting
requirements and for postponing concreting whenever such requirements cannot be met or,
based on weather forecast, probably cannot be met. Even if the above requirements are
fulfilled, the Contractor has the responsibility of delivering concrete product that meets
specified requirements.
5) Concrete, which is found not to be in conformity with the requirements specified herein or has
been placed without the knowledge and authorization of the Engineer, shall be rejected and
removed from the Works and replaced by the Contractor.
8.16.2 CASTING SEQUENCES
1) The time between successive lifts and maximum permissible depth of concrete placed in one
lift, unless otherwise directed or shown on the Detailed Design and/or Construction Drawings,
shall be as follows:
Location Maximum permissible Minimum time
depth of one lift between successive
lifts
Mass concrete in massive 250 cm 72 hours
structures
Walls and piers less than 5 m 400 cm 48 hours
thick
Other structures As approved by the 48 hours
Engineer
2) The Engineer may change the minimum time elapsing between the pouring of successive lifts
and/or the maximum permissible depth of one lift for temperature control purposes or similar
reasons.
3) Concrete for beams, slabs and similar members shall be poured to the full depth in a single
operation.
4) Outdoor concreting shall not be started during rain. If concreting is already in progress during
the rain, it shall be suspended if the rain adversely affects the quality of the placed concrete.
5) Concrete that has been allowed to harden to the extent that additional concrete placed on it
will not satisfactorily bond shall be treated as a construction joint. When stoppage of concreting
operations occurs for any reason, construction joints shall be placed either horizontally or
vertically as needed.
8.16.3 PLACING AND COMPACTION
1) Concrete shall be carefully placed in position. Where dense reinforcement or deep forms may
cause segregation of concrete while placing, chutes shall be used to prevent segregation. The free
fall of concrete shall not exceed 1.5 m for structural concrete and 3.0 m concrete walls and
piles.
2) Concrete shall be placed directly in its permanent position and shall not be worked along the
forms to that position. Vibrators shall not be used to move concrete laterally.
3) The addition of water into concrete after batching to compensate for stiffening of the concrete
before placing shall not be permitted. Concrete corrections to the batching plant are permitted
keeping unmodified the design parameters (i.e. W/C ratio).
4) All concrete shall be placed in continuous approximately horizontal layers. The thickness of the

_______________________________________________________________________________
88
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

layers shall not exceed 40 cm for mass concrete, and 50 cm for structural and all other concrete.
Each layer shall be soft when a new layer is placed upon it so that no seams or planes of
weakness within the section can form, and the two layers shall be made monolithic by
penetration of vibrators.
5) The Engineer reserves the right to order a reduced thickness of layers where the layers as
stated above cannot be placed in accordance with the requirements of these Specifications.
6) Each layer of concrete while being placed shall be compacted by mechanical vibration to form a
dense, homogeneous material free from voids. The concrete shall be worked up hard against
adjoining surfaces. Each concrete layer shall be vibrated completely before another layer of
concrete is placed upon it.
7) Vibration of concrete shall be carried out by means of immersion-type vibrators, supplemented
if necessary by external vibrators of suitable design and capacity. Immersion vibrators, having
head diameters equal to or less than 100 mm, shall have a minimum speed of 7,000 vibrations
per minute when immersed in concrete. Those with head diameters more than 75 mm shall
have a minimum speed of 6,000 vibrations per minute when immersed in concrete. Formwork
vibrators shall operate at not less than 8,000 vibrations per minute when vibrating concrete.
8) Immersion vibrators shall penetrate the full depth of the layer and shall enter the underlying
layer so as to ensure proper integration of successive layers. They shall be inserted in a near-
vertical position at sufficiently close intervals for long enough time to ensure proper
compaction and shall be withdrawn slowly to prevent the formation of voids. The concrete shall
be vibrated until it presents a compact reflecting surface and the bubbles of entrapped air
cease to escape. Over-vibration causing segregation, surface laitance, or leakage through
formwork shall be avoided. Vibrators shall not be allowed to come into contact with formwork
and contact between vibrators and the reinforcement is to be avoided.
9) Vibrators shall be operated by experienced workers only. A spare vibrator of the appropriate
type and capacity shall be available and shall be tested to ensure that it is working before
concreting commences. At least one spare vibrator shall be available at each concrete pour, and
a minimum of one spare for each 5 vibrators in service at each construction site.
10) The Contractor shall modify his vibrating equipment if it does not perform satisfactorily under
operating conditions.
11) Internal struts, stays and braces, serving temporarily to hold the forms in correct shape and
alignment impeding the placing of concrete, shall be removed when the concrete placing has
reached an elevation rendering their service unnecessary.
12) The Contractor shall take care to prevent formation of cold joints during placing concrete in any
part of the Works. His concrete-placing rate shall be such that the concrete is placed while the
previously placed adjacent concrete is still plastic and the concrete can be made monolithic by
normal use of vibrators.
8.16.4 PUMPING CONCRETE
1) Positive displacement pumping or other approved methods may be used to place concrete in
locations approved by the Engineer. The type and arrangement of equipment shall be subject to
approval by the Engineer, and the equipment shall be operated only by experienced persons.
Pneumatic placing will not be allowed.
2) The equipment and its method of operation shall allow the concrete to enter the forms at a low
velocity.
3) Concrete pumps and auxiliary equipment shall be in good condition and shall be maintained as
such throughout the duration of the work. Thorough washing down of all parts that come in
contact with concrete shall be performed after each concreting operation.
4) Pump lines shall consist of rigid steel pipe or flexible pipe made of rubber, spiral-wound flexible
metal or plastic, or combination of both. Use of aluminium pipe for pump lines shall not be
permitted. Couplings shall be leak-proof and strong enough to withstand handling during
_______________________________________________________________________________
89
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

erection and poor support along the lines. They shall provide a full internal cross section with
no constrictions of the smooth flow of concrete.
5) Immediately prior to the start of all concrete pumping, the pump and pump lines shall be
primed by pumping an approved grout mixture through the equipment.
6) Concrete pumping operations shall be planned in such a way that concrete does not set before the
succeeding layer is place thereon. An adequate supply of fresh concrete shall be provided at all
times.

8.17 PROTECTION AND CURING


8.17.1 PROTECTION
1) The Contractor shall protect all concrete against injury or damage from excessive heat, lack of
moisture, over-stress, or any other cause until final acceptance by the Engineer.
2) Fresh concrete shall be protected from damage such as due to drying, sunshine, rain, hail, sleet,
and traffic. The Contractor shall provide such protection while the concrete is still plastic and
whenever such precipitation, either periodic or sustaining, is imminent or occurring.
3) Care shall be taken not to disturb the concrete by direct or indirectly loading, striking of forms
or otherwise, until it has hardened sufficiently.
4) Construction loads shall not be allowed on beams, decks or slabs until the concrete has
attained its design strength, nor shall the Contractor impose loads exceeding the design
loading.
5) All fresh concrete surfaces shall be protected from contamination and from foot traffic until the
concrete has hardened. Surfaces which have received the U2 or U3 finishes shall be protected
by covering with protective mats, plywood, or other effective means approved by the Engineer.
8.17.2 CURING
8.17.2.1 General
All concrete shall be moist cured for a period of not less than 14 consecutive days by an
approved method or combination of methods applicable to local conditions. The Contractor
shall have on hand, and ready to install, all equipment needed for adequate curing of concrete
before actual concrete placement of each pour begins. The curing medium and method, or the
combination of mediums and methods, will be subject to approval of the Engineer.
8.17.2.2 Water Curing
1) Water used for curing shall meet the requirements of mixing water, free of deleterious
materials and substances that will stain or discolour the concrete.
2) Water curing shall start as soon as the concrete has hardened sufficiently to prevent damage by
erosion and shall continue for the duration of the entire curing period or until covered with
fresh concrete. All surfaces shall be kept continuously wet during curing. Wetting the surfaces
only periodically will not be permitted.
3) Water curing shall be carried out by following methods:
a) Spraying or sprinkling by a system of perforated pipes, lawn sprinklers, soaking
hoses or by other approved methods. Intermittent sprinkling will not be
acceptable
b) Covering the concrete surfaces with burlap, cotton mats, or rugs which will hold
water on the surface either horizontal or vertical. The covering materials shall be
kept continuously water-saturated during the curing period
c) Covering the horizontal construction joints and finished surfaces with a minimum
thickness of 50 mm of sand which shall be kept uniformly distributed and
continuously saturated during the curing period.
8.17.2.3 Membrane Curing by Sealing Compound
1) Sealing compounds shall be used for concrete curing only if approved in writing by the
Engineer. Sealing compounds will generally be accepted on manufacturer's certification of
_______________________________________________________________________________
90
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

compliance with specifications, but such acceptance shall in no way relieve the Contractor of
the responsibility for furnishing a compound which meets the requirements of these
Specification. Sealing compounds will be subject to sampling and testing.
2) The liquid membrane-forming compounds for curing concrete shall conform to the
requirements of ASTM Specification C309. The compounds shall be of uniform consistency and
quality within each container and from shipment to shipment. When approved, the membrane
curing shall be performed by application of the sealing compound which forms a water-
retaining membrane on the surfaces of the concrete. The sealing compound shall be white-
pigmented except that compound used on surfaces that will be exposed permanently to view
shall be a gray-pigmented sealing compound.
3) Sealing compound shall not be used on concrete surfaces to which additional concrete, paint or
tile is to be bonded, unless the Contractor has demonstrated that the membrane can be
satisfactorily removed before subsequent application or can serve satisfactorily as a base for
the application.
4) When sealing compounds are used on unformed concrete surfaces, application of the
compounds shall commence immediately after finishing operations are completed. When
sealing compounds are to be used on formed concrete surfaces, the surfaces shall be
moistened with a light spray of water immediately after the forms are removed and shall be
kept wet until the surfaces will not absorb more moisture. As soon as the surface film of
moisture disappears but while the surface still has a damp appearance, the sealing compound
shall be applied.
5) Special care shall be taken to ensure ample coverage with the compound at edges, corners, and
rough spots of formed surfaces. After application of the sealing compound has been completed
and the coating is dry to touch, any required repair of concrete surfaces shall be performed.
Each repair, after being finished, shall be moistened and coated with sealing compound in
accordance with the foregoing requirements.
6) Equipment for applying sealing compounds and the method of application shall meet with the
approval of the Engineer. Traffic and other operations by the Contractor shall be such as to
avoid damage to coatings of sealing compounds for a period of not less than 14 days. Any
sealing membrane that is damaged or that peels from concrete surfaces, within 28 days after
application, shall be repaired without delay.
7) Sealing compounds used for surfaces exposed to view shall degrade completely when exposed
to air for more than 3 months. They are to remain at least 80% impermeable for 1 month after
application.
8.18 REPAIR OF DEFECTIVE CONCRETE
8.18.1 GENERAL
1) Concrete which is damaged, or which may have been originally defective, or which becomes
defective at any time prior to the final acceptance of the completed work, or which departs
from the established position, line or grade, or which, for any other reason, does not conform
to these Specifications, shall be satisfactorily repaired, or removed and replaced with
acceptable concrete by the Contractor.
2) The Contractor shall correct all imperfections on the concrete surface as necessary to produce
the specified finish within the time as specified below:
a) Minor formed surface repairs, such as surface grinding, shall be completed within 2
hours after form removal
b) Concrete replacement less than 25 cm thick, mortar and dry-pack repairs shall be
completed within 7 days after the original concrete placement
c) Concrete replacement more than 25 cm thick, epoxy-resin bonding repairs, and all
other repairs shall be completed after 7 days, but before 56 days after the original

_______________________________________________________________________________
91
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

placement.
3) All repair work shall be finished to the same standard as the surrounding concrete and shall be
adequately cured. Plastering or rendering of surfaces to produce a smooth surface finish shall
not be permitted.
4) No repair work shall be carried out before the Engineer has inspected the defective area and
given consent in writing for remedial work to begin.
5) Concrete requiring F1, F1C, U1, F2, F2C or U2 finish that is honeycombed, fractured, that
contains surface depressions which exceed the allowable tolerance specified in this Section or
that is otherwise defective shall be cut back to a minimum depth of 25 mm into sound
concrete in all directions, and the edges undercut. The area to be removed shall
be outlined to a depth of 15 mm with a diamond or Carborundrum saw prior to removing the
defective concrete. The fresh concrete surface shall then be cleaned, washed down and
thoroughly soaked with water until the concrete becomes saturated. The concrete surface
should be damp. Repairs to the surface shall then be carried out using the materials and
methods described hereafter.
6) For bonding new concrete to older one, a bonding medium of epoxy, formulated for this
purpose, shall be used in accordance with manufacturer's instructions. Alternatively, a neat
cement paste may be used. A paste of Portland cement and water mixed to a thick cream
consistency shall be applied to damp, clean concrete. The concrete shall have no free water on
the surface.
7) Concrete requiring F3, U3 or U3C finish that is honeycombed, fractured, that contains surface
depressions which exceed the allowable tolerances specified in this Section or that is otherwise
defective shall be repaired as follows:
a) Minor areas of defective concrete: The Contractor shall drill a hole of such diameter
in the defective area into sound concrete, that the defective concrete is completely
removed. The minimum diameter of such hole shall be 50 mm, the minimum depth
shall be equal to the diameter of the hole drilled and the maximum depth shall be 70
mm. The hole shall then be reamed out such that the diameter at the bottom of the
hole is at least 20 mm larger than the hole at the surface. Finally, the hole shall be
cleaned and washed out, the surplus water removed, and then filled with concrete
incorporating a non-shrink agent approved by the Engineer.
b) Large areas of defective concrete: concrete which contains defective areas too large
to be repaired as described above shall be cut to the far face of surface reinforcement
or further if necessary, to remove all the defective material, and the edges undercut.
The fresh concrete surface shall then be cleaned, washed down and thoroughly
soaked with water until the concrete becomes saturated. The concrete surface should
be damp. Finally, the hole shall be filled with concrete which may incorporate a non-
shrink agent approved by the Engineer.
8) Concrete which will be exposed to public view shall be repaired in a manner which will result in
a concrete surface with a uniform appearance.
8.18.2 DRY-PACK MORTAR
1. The dry-pack mortar shall consist of 1-part cement to 2½ parts of sand, by volume, that will
pass a US Standard Sieve No. 16 (1.18 mm). Only enough water shall be used to produce a
mortar which will stick together when molded into a ball by a slight pressure of the hands and
will not exude water but will leave the dry pack in thin layers.
2. Dry-pack mortar shall be placed and packed in layers. Each layer shall be solidly compacted over
its surface by use of a hardwood stock and hammer.
3. Dry-pack mortar shall be used for filling holes having at least one surface dimension less than the
hole depth, for narrow slots cut for repair of cracks, for redrilled grout holes and grout pipe
recesses, and for tie-rod fastener recesses.
_______________________________________________________________________________
92
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

4. Dry-pack mortar shall not be used for filling behind reinforcement or for filling holes that
extend completely through the concrete section.
8.18.3 MORTAR FILLING
1. Mortar to be used for repair work shall have the same sand, cement and air proportions as the
mortar in the mix of the concrete to be repaired. The Contractor shall place mortar filling with a
mortar gun or by hand.
2. Mortar filling shall be used to repair defects which are too wide for dry pack filling and too
shallow for concrete filling and no deeper than the far side of the reinforcement that is nearest the
surface.
3. Mortar filling in concrete surfaces destined to be in contact with flowing water shall be used
only together with the application of epoxy coatings using a procedure approved by the
Engineer.
8.18.4 CONCRETE FILLING
1. Concrete filling shall be used for holes extending entirely through concrete sections, for holes in
which no reinforcement is encountered and which are greater in area than 0.1 m2 and deeper
than 100 mm and for holes in reinforced concrete which are greater in area than 0.05 m2. Holes
in reinforced concrete which extend beyond the reinforcement shall be enlarged as necessary
to permit satisfactory filling of the hole with concrete.
2. Concrete filling shall be tightly packed and completely bonded to the surfaces of the holes. The
mix proportions of the filling materials shall be such as to provide a strong, dense repair which
will avoid colour variations in surfaces exposed to view.
3. On surfaces permanently exposed to view, and where required by the Engineer, the Contractor
shall supply white cement in sufficient amount, as determined by trial, which when blended
with normal cement, will produce a finish of similar appearance to the adjacent concrete. Non-
shrink agent shall be used where a watertight joint is required. The surface of patches shall be
smooth and flush with the surrounding concrete.
8.18.5 EPOXY-RESIN BONDING
1. Any repairs made more than 7 days after the original concrete placement for thicknesses less
than 25 cm thick shall utilize epoxy-resin bonding system. The locations where epoxy-resin will
be used will be determined by the Engineer, who will approve the type and brand to be used.
2. The method of repair shall be as recommended by the manufacturer. The product used may
contain no toxic elements.
3. In areas exposed to public view, the concrete surfaces repaired with epoxy-resin bonded system
shall be lightly ground to eliminate gloss of the finished epoxy mortar surface and to produce a
surface colour and texture that closely matches the surrounding concrete surface.
8.18.6 STAINS AND DISCOLOURATION
Stains or discolouration of exposed (Class F2, F2C and U2) concrete surfaces shall be removed.
The procedure or method or removing the stains and/or discolouration will be subject to
approval. The removal of stains or discolouration shall not be started until the work that
originally caused the stains or discolouration is completed.
8.19 PARTICULAR REQUIREMENTS FOR INDIVIDUAL CONCRETE STRUCTURES
8.19.1 SPILLWAY CHUTE
1) Concrete used for construction of the spillway chute shall be class C35D32 containing Ordinary
Portland cement Type 1.
2) Drainage system shall be installed under the chute slab and behind the side walls prior to
casting any concrete, as shown on the Detailed Design and/or Construction Drawings and/or
specified by the Engineer.
3) Where the overbreak in excavation below the theoretical lines and grades exceeds acceptable
limits, as determined by the Engineer, the Contractor shall place blinding unreinforced concrete

_______________________________________________________________________________
93
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

class C15D32 over the rock foundation in such thickness that the upper surface is at the
theoretical grade elevation. Surface shall be roughened before placing the structural spillway
concrete.
4) The lower layer shall be formed as shown on the Drawings with Porous Concrete Class C15 D32.
5) If slipforms are used, they shall be of rigid construction capable of resisting the working loads
imposed upon them and of a configuration approved by the Engineer. The length of the
slipform along the slope shall be such that with the proposed concrete mix and slipform speed,
concrete emerging from the slipform will not slump.
6) No construction joints shall be allowed in the chute slab, unless otherwise approved or directed
by the Engineer. In case such joint is permitted, additional steel reinforcement shall be placed
across the joint and the joint surface shall be shuttered with expanded metal.
7) Contraction joints shall be executed in the chute walls at the distances as shown in the
drawings. Steel dowels shall be placed through these joints and the surface shall be painted
with bituminous coat or other approved bond breaker.
8) All movement joints exposed to flowing water shall be chamfered 1:1 on upstream side and
1:10 on downstream side.
9) Tolerances of the concrete surface in the chute and overflow weir shall conform to surface
finishes F3, F3C, U3 and U3C.
8.19.2 CONCRETE GRAVITY STRUCTURES
1) Concrete used for the construction of mass concrete gravity structures shall be class C20D76
unless otherwise approved or directed by the Engineer. However, concrete surface exposed to
weathering, freezing/thawing, and standing or flowing water shall be constructed of higher
strength concrete as indicated on the Final Design and /or Construction Drawings. Where such
higher strength concrete is used, part of each lift will normally be composed of two classes of
concrete. Water-cement ratio shall not exceed 0.52.
2) Reinforcement shall be provided at the surfaces in contact with standing or flowing water and at
all openings in mass concrete.
3) Mass concrete of gravity structures shall be water cured for at least 7 days unless otherwise
directed by the Engineer. When curing compound is used as a bond breaking membrane at
contraction joints, it shall be also be considered acceptable in meeting the curing requirements.
8.19.3 CONTROL BUILDING
General
1) Blockouts, holes, pipes, pits, pedestals and embedded metalwork for equipment, cables, anchor
bolts and other accessories shall be detailed by the Contractor on the basis of the indications
given by the supplier. The Contractor shall then prepare the Construction Drawings as
previously described.
Embedment of Equipment
1) Parts of the equipment to be installed in the buildings shall be encased in concrete and the first
stage concrete shall be formed to the openings required for the installation of the equipment.
As the installation of the equipment proceeds, and the second stage concrete is required to be
placed around the equipment or any part thereof, the Contractor shall place the reinforcement
and concrete.
2) The units to be embedded shall be checked for alignment immediately before, during and after
concrete placing operations.
3) At point where an inspection (e.g. by sounding) indicates that a cavity exists between steel
liners and the surrounding concrete, the Contractor shall drill and tap the liners to provide
grouting points. Backfill grouting shall be performed after the concrete has cooled and achieved
sufficient strength to resist the grouting pressures. After grouting, all grout holes shall be sealed
by welding.

_______________________________________________________________________________
94
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

8.19.4 BLOCKOUTS FOR EQUIPMENT EMBEDDING


1) The Contractor shall form blockouts, place reinforcement and concrete as shown on the Final
Design and /or Construction Drawings or as directed by the Engineer, and in such manner as to
ensure good bond with the existing concrete, to secure complete contact with the metalwork to
be embedded in the blockout concrete and to avoid displacement of the metalwork.
2) Before placing concrete, all parts to be embedded shall be checked to ensure that they are
firmly fixed in their required position. The surfaces of blockouts or holes shall be thoroughly
cleaned and wetted. Oil or grease shall be removed by brushing and chipping of affected
surfaces to a sufficient depth, or by application of approved chemicals and flushed with clear
water.
8.19.5 GROUTING OF THE EQUIPMENT BEARING PLATES AND ANCHORS
1) Limited spaces and small blockouts where equipment bearing plates, anchors, rails, etc. are
placed shall be grouted under pressure.
2) The mixture shall consist of non-shrink grout as specified in Section "Miscellaneous and
Ancillary Works".
3) Before placing grout, the surfaces of the base concrete to which the grout will be bonded shall
be roughened and cleaned of all laitance, loose or defective concrete, any coatings or other
foreign material, followed by thorough washing with water. Forms for grouting shall be installed
where necessary and care shall be taken that the grout fill all spaces under the plates leaving no
voids. The exposed surfaces of the grout shall be cured as recommended by the manufacturer
and no loads shall be applied until the grout has reached the design strength.
8.19.6 POROUS CONCRETE
1) Porous Concrete shall be placed where free drainage is required and shall be produced by gap
grading or single size aggregate grading.
2) The strength requirements for porous concrete shall be as for class C15D32 concrete. The
porosity shall be such that water will pass through a slab 30 mm thick at a minimum rate of 500
l/min/m2 with a constant depth of water on the slab of 10 cm.
3) Porous concrete shall not be vibrated but only placed and lightly rammed. Formed surfaces
shall be Class F1 finish. Exposed surfaces of the porous concrete shall be sealed in an approved
manner, such as the use of polyethylene or rendering with sand and cement, before structural
concrete is placed against it.
8.19.7 PRE-CAST CONCRETE
8.19.7.1 General
1) The Contractor shall investigate the possibility of obtaining and utilizing standard pre-cast
concrete products available in the local market, before commencing any such production on his
own.
2) When producing on his own, the pre-cast concrete units shall be manufactured and cured in a
properly equipped casting yard or shop. The facilities shall be subject to the Engineer's
inspection and approval.
3) The quality of the materials used in the manufacture of precast concrete units shall conform to
the applicable requirements of these Specifications.
4) Details of the design, concrete components and mixes, and test results shall be made available
to the Engineer.
5) Precast units which will be used in composite construction shall contain interlocking devices
welded or formed into the steel member for connection with the subsequently cast-in-situ
concrete to prevent a slip between the two materials and normal steel reinforcement. Such
connections shall be designed so that they can resist 1.8 times the working load to which they
will be subjected and that the ensuing movements cause no distress to the joint. The
Contractor shall submit design details and calculations for approval before commencing any
production.

_______________________________________________________________________________
95
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

6) Each unit is to be cast in one continuous operation and no construction joints will be permitted
unless expressly approved by the Engineer.
7) Care shall be taken during storage, hoisting and handling of precast units to prevent cracking or
damage. Units damaged by improper storing or handling shall be replaced by the Contractor.
8) Pre-cast units shall remain undisturbed until the concrete has developed at least 70% of the
required compressive strength at 28 days and shall not be installed until the unit has developed
the full required strength at 28 days, unless explicitly approved by the Engineer.
8.20 MEASUREMENT AND PAYMENT
8.20.1 CONCRETE
8.20.1.1 General
1) Measurement for payment of concrete, unless specified otherwise hereafter, will be of the
volume placed within the lines, grades, and pay-limits shown on the Final Design and /or
Construction Drawings or as established at the Site by the Engineer.
2) Unless otherwise stated, no payment will be made for concrete placed outside these limits,
other than in additional excavation directed by the Engineer, and the measurement shall not
include any filling of overbreak unless recognized as due to geological conditions conforming to
the limits defined in other Sections of these Specifications.
3) Payment will be made at the Unit Prices for different structures of concrete entered in the Bill of
Quantities, which shall include, but not be limited to, the following:
a) Drilling, blasting, loading, transportation, stockpiling, crushing, screening,
washing, blending, and storage of aggregates
b) Batching, supply of mixing water, mixing, transportation, placing, and compacting
the concrete
c) Labour, tools and equipment for cleaning, and preparing surfaces prior to
concreting
d) Forming and treatment of construction joints including furnishing and spreading
of mortar layers, or starter mixes before concrete placing
e) Surface finishing
f) Attaining the concrete temperature as specified, and hot weather precautions
g) Protection and curing of concrete
h) Repair of defective concrete
i) Communication system connecting the points of placing concrete with the
relevant mixing plant or delivery equipment
j) Provision of material samples and all activities required in connection with
the performance of the tests including their transportation to the testing
laboratory
k) Removal and disposal of waste concrete and test samples.
l) Preparation of contact surfaces for second stage concrete and blockouts for
equipment embedding.
4) No separate payment is provided in the Bill of Quantities for second stage concrete and
concrete in blockouts for equipment embedding as the unit prices of each structure include first
stage, second stage and blockouts.
8.20.1.2 Backfill Concrete Directed by the Engineer
1) Where backfilling with concrete is directed by the Engineer, payment will be made for concrete
placed as backfill in geologically accepted overbreak, dental excavation and in additional excavation directed by the
Engineer.
2) Payment will be made at the Unit Price entered in the Bill of Quantities for the specific backfill
concrete or for the structure with which it is associated.
8.20.1.3 Slush Grout
1) Measurement for payment of slush grout will be of the area of the foundation surface treated
_______________________________________________________________________________
96
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

accordingly.
2) Payment will be made at the unit price per square meter entered in the Bill of Quantities.
8.20.1.4 Placing Concrete in Water
Payment for concrete placed in water will be made at the Unit Price for the specified concrete
class plus additional Unit Price per cubic meter entered in the Bill of Quantities, which shall cover
the entire cost of labour equipment and additional cement required for placement of concrete
underwater.
8.20.1.5 Non-shrink Grout
Measurement for payment for the non-shrink grout will be as specified in Section
"Miscellaneous and Ancillary Works".
8.20.1.6 Pre-cast Concrete
1) Measurement for payment for pre-cast concrete units will be by the volume in cubic meters of
the units installed, as determined from the Final Design and /or Construction Drawings.
2) Payment will be made at the Unit Price per cubic meter entered in the Bill of Quantities, which
shall include, in addition to works included under "General", the entire cost of curing, storage,
transportation and erection. Cement, admixtures and reinforcing steel will be paid for
separately as specified here below.
8.20.1.7 Exclusions
No extra measurement for payment or payment will be made for the following:
1) Any rounded or beveled edges, fillets, scoring, chamfers, or any deduction made for voids or
embedded items which are either less than 0.10 m3 in volume or 0.05 m2 in cross section. No
allowance will be made for approved temporary openings, drains, embedded pipes, or recesses
created by the Contractor for his own convenience during construction provided they are filled
as directed
2) Any collecting of seepage water or water inflow from rock surfaces and diverting it into the
drainage systems as specified in the Section "Care of Water During Construction"
3) Any defective and wasted concrete. Concrete which has to be removed and replaced due to
Contractor's noncompliance with the Specifications or Engineer's directions, and all related cost
shall be at the Contractor's expense.
4) Any pre-cast concrete unit produced by the Contractor in excess of the number required,
damaged before the installation or otherwise rejected by the Engineer.
5) Any concrete which the Contractor places or uses for his own installations or for his own
convenience
6) Developing alternative sources of aggregates by the Contractor and the resulting additional
material testing
8.21 CEMENT
1) Measurement for payment for Portland cement used for concrete will be of the quantities, by
weight, of cement approved for the different classes of concrete specified and computed on the
basis of the number of cubic meters of concrete measured and approved for payment. The
amount of cement required per cubic meter of concrete of each class will be as established at
trial mix stage or the approved modifications thereof as established by the Engineer in the
course of concrete work.
2) Payment will be made at the Unit Price per metric ton entered in the Bill of Quantities, which
shall include the entire cost of supply, delivery, transportation, storage and mixing, and test for
complying with all requirements specified.
3) No measurement for payment or payment will be made for cement used for:
a) Contractor's own convenience
b) Used for defective and wasted concrete
c) Concrete placed outside of the concrete pay-lines (e.g. for filling the overbreak other
than approved overbreak due to geological conditions) or required as a result of
_______________________________________________________________________________
97
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

careless excavation
d) Any additional cement required due to usage of greater proportion of crushed
aggregate than established at trial mix stage for a specified concrete class
8.21.1 ADMIXTURES
1) Measurement for payment for air-entraining, water-reducing, water-reducing-retarding and
super plasticizer admixtures will be of the weight or volume of the agreed dosages established
at trial mix stages or the approved modifications thereof, for different classes of concrete, and
computed on the basis of the number of cubic meters of concrete measured and approved for
payment.
2) Payment will be made at the applicable Unit Price per kilogram entered in the Bill of Quantities,
which shall include the entire cost of supply, handling, storage, dispersing and tests for
complying with all requirements specified.
3) No extra measurement for payment or payment will be made for concrete admixtures used for
Contractor's convenience such as accelerators and non-shrink agents.
4) No payment will be made for admixtures used for Contractor's convenience only.
8.21.2 STEEL REINFORCEMENT
1. Measurement for payment for reinforcing bars will be of the weight of reinforcing steel,
including splices, as stated in the bar lists approved by the Engineer in the course of the work.
The weight entered in the bar lists will be computed using the nominal weight per lineal meter
of different bar diameters based on the specific weight of 7,850 kg/m3.
2. Payment will be made at the Unit Price per metric ton entered in the Bill of Quantities, which
shall include the entire cost of supply, storage, cutting, bending, placing, wire clips, ties,
separators, and any other fastening devices.
3. No extra measurement for payment or payment will be made for the following:
a. Wire for tying reinforcement
b. Any additional reinforcement or splices required when Contractor's casting sequences
differ from construction joints shown on the Final Design and /or Construction Drawings
c. Any reinforcing steel placed by the Contractor for his own convenience in addition to
those shown on the Final Design and /or Construction Drawings and entered in the
bar lists
d. Any reinforcing steel delivered for testing
8.21.3 FORMWORK
No Payment will be made towards form work. The cost thereof shall be included in the
applicable Unit Price for concrete in the structure with which it is associated.
8.21.4 MOVEMENT JOINTS
1) Measurement for payment will be made for the following items in the units stated:
e) Waterstops: per linear meter placed
f) Joint Sealing Compound (including primer and plastic tape): per dm3 placed
g) Joint Filler Panels: per square meter
2) Payment will be made at the appropriate Unit Price entered in the Bill of Quantities, which shall
include the entire cost of all materials, plant and labour for furnishing and constructing movement
joints as specified, and all temporary protection of the joints from damage.
3) Payment will only be made for the movement joints shown on the Final Design and /or
Construction Drawings or directed by the Engineer. Additional joints for Contractor's
convenience may be approved by the Engineer, but no payment will be made for materials used
in such joints.
8.21.5 TESTS
1) All cost associated with testing as described in this Section shall be borne by the Contractor,
who shall make allowance for such expense in the Unit Prices for the concrete work. These shall
include, but not be limited to, the following:
_______________________________________________________________________________
98
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

a) The costs for all tests to be carried out prior to the start of concrete work,
whether carried out at Site or elsewhere
b) Routine tests for quality control during the execution of the concrete work
carried out by the Contractor as specified herein and as directed
c) Other tests required during execution of the work to be carried out by an
approved test laboratory(ies)
d) Preparation, storage, handling, curing and delivery of additional samples to the
site laboratory, if so required for additional testing.
2) Should the Contractor fail to adhere to his testing program, all test deemed necessary by the
Engineer to check concrete work will be performed by the Engineer at the site laboratory or at
an independent laboratory assigned by him, at Contractor's expense.

_______________________________________________________________________________
99
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

9 DRILLING AND WATER PRESSURE TESTING

9.1 SCOPE OF WORK


1) The work under this Section includes all labour, materials, equipment and services required
for the execution of drillholes and water-pressure tests from surface construction sites, at
locations shown on the Construction Drawings or where the Engineer may direct. This
Section shall be read in conjunction with the Section "Grouting".
2) Drilling shall include the following:
a) Drilling of exploratory holes;
b) Drilling of boreholes;
c) Drilling for grout curtain below the cut of trench
d) Drilling of control holes to determine the effectiveness of grouting
e) Drilling of drainage holes
f) Drilling for installation of instrumentation, with or without core recovery
3) The general extent and the approximate location of the drill holes are tentatively indicated
on the Drawings for the purpose of Bid preparation. The final number, length and location
of the drill holes shall be determined by the Engineer, based upon the actual conditions
encountered at the site.
4) The direction of the drill holes may be vertical or inclined.
5) Selected holes shall be water tested in stages as the drilling progresses or after completion
of the drill hole, as directed by the Engineer.
9.2 SUBMITTAL
1) Within 24 hours of completion of any drilling with core recovery, the Contractor shall
submit, in duplicate, a technical log of the drillhole in a form approved by the Engineer. The
log shall include the following data:
a) Date of beginning and end of drilling
b) Drillhole number
c) Location, ground surface elevation, coordinates, inclination, direction, and length
of drillhole
d) Type and diameter of drilling bit and core barrel used, make of drilling rig and
length and diameter of casing, if used
e) Elevation of ground water levels encountered, including dates and times of
measurement
f) Results of leakage tests and other drillhole tests, if any
g) A record of the drillers observations on progress of drilling, rate of penetration,
speed and uniformity of rotation of bit, action of the drill rig such as jerky,
smooth, rough, steady, etc.
h) Length of each core run and the length, or percentage, or both of the core
recovered and location and cause of core losses
i) Any changes in the character of the drilling water or mud, and in case the drilling
water was lost (partly or totally), the elevation or depth when this happened
j) A simple drillers interpretation and description of the nature of the formation
encountered as the drilling progress
k) Location and nature of cavities, seams, cracks, soft or broken rock, whether filled
or open, and any other observation which could give information in connection
with the purpose of exploratory drilling
l) Names of drillers and inspectors
2) Geological logging shall be performed by the Contractor and submitted to the Engineer.
3) Colour photographs of the core boxes from each drillhole shall be taken by the Contractor

_______________________________________________________________________________
100
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

and submitted to the Engineer in a digital copy within 10 days from the completion of the
drillhole.
4) The Contractor shall submit reports in duplicate giving the results of each water-pressure
test performed, within 24 hours of the end of the shift in which the tests were carried out.
The reports shall contain the following:
a) Location and number of drillhole
b) Date and time of test performance
c) Type of test
d) Pressure readings and water levels before and after testing
e) Packer rod characteristics and depth of packer(s)
f) Total injected water volume and rate per minute and per linear meter of hole for
various pressures
g) Description of all surface water leaks indicating the distance and approximate
quantity.
5) Should the Contractor intend to use a water-soluble additive to drilling water, he shall
submit a notification and a sample of the additive to the Engineer for approval at least 15
days prior to being used.
9.3 EQUIPMENT
9.3.1 GENERAL
1) The Contractor shall have sufficient drilling rigs at the Site for the timely completion of the
Works. The drilling rigs shall be in good operating condition and adequate for the
satisfactory progress of the work.
2) Drilling equipment and methods shall be such as to minimize oversizing or caving of the
holes. Drill casing, where required, shall be of high-quality steel, plain or perforated as
directed or approved by the Engineer. The casing necessary for driving through soils shall be
of a diameter to take the largest size core barrel or bit to be employed. Auxiliary casing shall
be provided where it is necessary to case through formations already penetrated and
where no casing has been installed. This shall have a diameter to fit inside the hole and
permit the use of the next smaller core bit and barrel. When casing is installed to keep the
grout hole open for grouting, equipment and casing shall facilitate the casing removal
immediately prior to, or simultaneously with, the grouting process.
3) The Contractor shall have available at the Site drilling equipment for both rotary and
percussion type drills. The minimum diameter of drilling hole shall be 38 mm. Other
required diameters shall be 48 mm, 63 mm, 76 mm, 98 mm, and 101 mm according to the
purpose of the drilling as determined by the Engineer.
4) Drilling equipment shall be capable of drilling at any angle and shall have the following
capacity:
a) Exploratory holes up to 100 m
b) Boreholes up to 100 m
c) Dam grouting curtain up to 30 m
5) The Contractor shall keep at the Site an ample supply of different types and sizes of drilling
bits to allow optimal drilling in the different materials to be encountered in the course of
work, and sufficient rods and casings of various diameters to allow proper telescoping and
to ensure the stability of drillholes.
9.3.2 DRILLING WITH CORE RECOVERY
1) Drills for exploratory drilling shall have the following features:
a) Automatic adjustment for drill pressure and rate of advance
b) Proper working indicator of drilling pressure
c) Transmission gear to adjust spindle speed (e.g. 60 to 300 rpm for rock)

_______________________________________________________________________________
101
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

2) The Contractor shall use swivel-type double, or triple tube core barrels.
3) Drill rods shall be of sufficient diameter to permit adequate flow of the drilling fluid and to
provide sufficient upward velocity of the fluid to remove effectively the sediments.
9.3.3 WATER PRESSURE TESTING
1) The Contractor shall provide a sufficient number of complete sets of pressure testing equipment
(with spares) to allow simultaneous testing at the various drilling and/or grouting locations.
2) Unless otherwise directed by the Engineer, the pumps shall have a capacity of 200-250 liters per
minute at a pressure of 10 bar and shall be capable of exerting a pressure of at least 25 bar. The
pumping system shall be capable of maintaining any desired pressure without fluctuation and the
pressure and discharge must be continuously adjustable.
3) Water pressure shall be measured by means of a pressure gauge with an accuracy of 0.5 bar and
a range of 50 bar. Discharge shall be measured with an accuracy of 2%. The water meter shall
measure the discharge from 0.5 l/min. Water meters as well as all pipes, hoses and couplings shall
be designed to resist a pressure of 60 bar.
4) Water-meters and pressure gauges shall be calibrated and certified by an independent laboratory
prior to installation at the Site and shall be subject to weekly verification. One pressure gauge and
one water-meter shall, after independent checking, remain at the disposal of the Engineer for
further checking purposes. The Contractor may be requested to establish, by way of tests,
correction graphs for pressure losses occurring in the pipes. Pressure gauges shall either be
installed directly at the collar of the drillhole or preferably at the depth of the stage.
5) Packers shall consist of mechanically expanded rings or pneumatically expanded sleeves of rubber
or other suitable material, which can be set tightly in a drillhole at any depth required. Packers
shall be capable of withstanding pressures of up to 50 bar without leakage. The Contractor shall
keep at the Site an adequate supply of single packers, as well as double packers spaced 3 and 6 m
apart to allow to isolate a section of a hole, and of diameters to suit the various hole diameters.
Each packer shall have a minimum length of 50 cm.
6) For water level measurements, electrical probes with an accuracy of 10 mm shall be used. They
shall be provided with measuring tapes marked with centimeter gradations.
9.4 EXECUTION
9.4.1 GENERAL
1) Holes shall be drilled to an accuracy of within 3 degrees of the angle of inclination specified.
Holes shall be drilled within 25 cm of the positions shown on the Construction Drawings or
directed by the Engineer.
2) The diameter specified for any drillhole shall be the minimum diameter. The diameter of the hole
as drilled shall equal or exceed the specified diameter over the entire length of the hole.
3) Sufficient circulation water shall be used to flush out all sediments. The use of lubricants such as
metallic salts or mineral soaps in the circulating water to help the drilling process or to reduce the
wear on the drill bits shall require the consent of the Engineer. These products shall not impair
the quality of the grouting or the setting of the grout. The use of grease, oil, or other lubricants
shall not be permitted for grout holes. The injection of cement grout to stabilize the drillholes is
subject to approval by the Engineer.
4) Unless otherwise directed by the Engineer, all holes shall be thoroughly washed out from the
bottom with water under pressure immediately after drilling. Water flushing shall continue until
the waste water runs clear.
5) All surface holes (with drilling completed to any stage) shall be temporarily capped or otherwise
protected.
6) If the drilling plan is altered to require additional drillholes in any section of the works, the
Contractor shall reinstall the equipment and carry out new drilling in the pattern and lengths as
ordered by the Engineer. All such additional drilling shall conform to these Specifications.

_______________________________________________________________________________
102
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

9.4.2 DRILLING FOR CURTAIN GROUTING


1) The Contractor shall drill from the surface at locations, lengths, and directions indicated on the
Construction Drawings or as directed by the Engineer. Tentative systems of drillholes are indicated
on the Tender Drawings.
2) Holes for curtain grouting shall have the following minimum diameters, measured at the deepest
point of the hole:
a) AX (48 mm) for rotary drilling with length up to 75 m
b) 38 mm (1 ½”) for percussion drilling with length up to 10 m
c) 63 mm (2 ½”) for percussion drilling with length up to 25 m
d) 89 mm (3 ½”) for percussion drilling with length up to 75 m
3) The length of holes is tentatively indicated in the Drawings. The drill holes shall be vertical or
inclined as indicated on the Construction Drawings or instructed by the Engineer.
4) The holes in moderately permeable to tight foundations shall be drilled with rotary equipment,
while percussion or rotary-percussion drills may be used in very permeable and open
foundations. The choice between rotary and percussion and rotary percussion shall depend more
upon the mechanical characteristics and/or the weathering of the rock than its permeability.
5) For curtain grouting, primary holes with core recovery will be drilled with 6m spacing. They will
be used to determine the depth of the grout curtain. The remaining holes will be drilled without
core recovery and grouted with the split-spacing method. The efficiency of the grouting will be
then verified by the drilling of control holes with core recovery. Depending on the results, the
Engineer may require additional grout holes.
6) When the grouting is to be done in a descending arrangement, the drilling shall be interrupted to
grout the previous section. After the time specified by the Engineer the hole shall be washed
and/or re-drilled and the drilling resumed.
7) Holes drilled in soft rock or fractured formations shall, with the approval of the Engineer, be cased
with a perforated steel pipe. Where practicable, such casing shall be later removed. Casings shall
only be allowed to remain permanently in place with the approval of the Engineer.
9.4.3 EXPLORATORY HOLES, DRILLING
9.4.3.1 Drilling and Core Recovery
1) The Contractor shall carry out exploratory drilling work as directed by the Engineer at any time
throughout the duration of the Contract. The exploratory drilling shall comprise:
a) Drilling from the surface for geological exploration, testing and sampling
b) Exploratory and control holes for the grout curtains
c) Drilling for installation of instrumentation
2) Exploratory drillholes shall be of minimum diameter 76 mm (NX). However, the Engineer may
order exploratory drilling of 98 mm diameter. Drilling shall be performed with rotary drilling
equipment using coring type bits. Unless otherwise directed or approved by the Engineer, the
Contractor shall use a standard ball bearing, swivel-type, double tube core barrel equipped with
core bits set with diamonds, tungsten carbide, or similar hard materials and standard core lifters.
Core diameter shall be 54 mm minimum for 76 mm diameter drillhole and 68 mm for 98 mm
diameter drillhole.
3) Coring runs shall be limited to a maximum length of 3 m. The cores shall be removed from the
holes immediately if blocking of the bit or grinding of the core is indicated by the drill behavior
regardless of the length of the run which has been made. When less than 80% percent of core is
recovered from a 3 m run, the length of the following run shall be shortened by 50%, unless
otherwise approved by the Engineer.
4) Only samples not altered or damaged by the drilling process will be considered as "core". Core
must correspond to the depth of origin with an accuracy of 50 mm. The Engineer may at any time
check the accuracy of the core runs during drilling operations. Core recovery not representative of
the drillhole depth will lead to partial or total redrilling of the hole by the Contractor.

_______________________________________________________________________________
103
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

5) A core recovery of at least 95% is required in sound rock and 80% in weathered and fractured
rock and in soils of any nature. Drilling shall be stopped and the cores removed from the barrel as
often as is necessary to secure the required core recovery. Where a higher core recovery is
required, the Engineer may order the use of triple tube core barrels such as Mazier samplers or
similar approved.
6) Each hole drilled shall be protected from becoming blocked by means of a cap or other suitable
device on the collar. Any hole that becomes blocked before completion of operations shall be
cleaned out in a manner satisfactory to the Engineer or replaced by another hole drilled by the
Contractor.
7) Where indicated on the Construction Drawings or directed by the Engineer, the cored holes shall
be fill-grouted in accordance with the provisions of the Section "Grouting".
9.4.3.2 Handling and Storage of Cores
1) The Contractor shall provide strong core boxes, 1 m inside length, of wood, metal or other
durable material subject to approval by the Engineer. The boxes shall be provided with hinged
covers and with longitudinal spacers that will form separate compartments so that each box shall
hold cores from e.g. 5 m of the hole. The number of the compartments will however depend on
the core diameter.
2) The core boxes shall be stored in weatherproof sheds of sound construction in the vicinity of the
Works, at locations approved by the Engineer.
3) The core shall be carefully extracted from the core barrel and stored in core boxes in the correct
orientation and sequence. All cores shall be marked with an arrow in the direction of drilling.
Wooden blocks which fit between the longitudinal spacers with a clear and durable inscription of
the depth shall be placed between each core run. Where core is not recovered, or where samples
have been removed by the Engineer, timber blocks of square cross-section shall be placed in the
box. These timber blocks shall be cut to the same length as the missing cores and placed in the
corresponding positions. If these positions cannot be determined, the blocks shall be placed at
the top of the run.
4) No box shall contain cores from more than one hole. Clear designating marks, hole numbers, data
of start and completion, and elevations shall be marked on the boxes and along the lines of cores.
9.4.4 EXPLONATERY HOLE, SAMPLING AND TESTING
9.4.4.1 Introduction
In the course of drilling in overburden, at any time throughout the duration of the Contract, the
Engineer may direct the Contractor to perform:
1. Collection of Undisturbed Samples;
2. Standard Penetration Tests;
3. Cone Penetration Test (CPT) and Cone Penetration Test with pore pressure
measurement (CPTU);
4. Lugeon Tests;
5. Lefranc Test
The Engineer may perform special tests in exploratory holes.
9.4.4.2 Undisturbed Sample
All the equipment and the execution of the test shall be in accordance with ASTM Method D
1587-00. Undisturbed samples as well as split-barrel samples shall be delivered by the
Contractor to the site laboratory, or to a specialized laboratory designed by the Engineer.
9.4.4.3 SPT tests
All the equipment and the execution of the test shall be in accordance with ASTM Method D
1586.
9.4.4.4 CPT and CPTU tests
All the equipment and the execution of the test shall be in accordance with ASTM Method
D5778-95

_______________________________________________________________________________
104
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

9.4.4.5 Lugeon Test


All the equipment and the execution of the test shall be in accordance with BS 5730-ENGL.
a). Allowable Water Pressure
All primary and check holes of the grout curtains shall be water pressure tested. Stage length
for testing shall be the same as for grouting, if not otherwise directed. The Engineer may direct
the performance of water pressure tests in other holes, as he may consider necessary. Double
or single packer shall be applied as necessary to isolate and test zones of high water take.
Water pressure shall be at the following maximum pressures, unless otherwise directed by the
Engineer:
Depth into rock (m) Water Pressure (kg/cm2)
0-5 2
5 - 10 4
10 – 20 6
> 20 8
b).Lugeon Test execution
i.The Contractor shall perform water-pressure tests by the Lugeon Test Method in grout and
exploratory holes or section of holes, as the drilling proceeds or after completion of a drillhole,
as and where directed by the Engineer.
ii.The permeability as measured in the drillholes shall be expressed in Lugeon units, 1 Lugeon unit
being equal to a water take of 1 liter per minute per linear meter of hole at a pressure of 10 bar.
iii.The hole or section of a hole to be subject to testing shall be sealed with single packer placed 3 m
above the bottom of the hole ( descending stages), or with double packers 3 m apart (ascending
steps). The groundwater table, if any, shall be measured and registered before and after each
test.
iv.After the packer is installed, the drillhole shall be thoroughly flushed and the Contractor shall
check that the flow through the packer is not obstructed.
v.Water shall be pumped into the hole through a header and pressure shall be applied in stages up
to the maximum pressure. The maximum pressure shall be determined by the Engineer, but shall in general
not exceed 10 bar. Where water-pressure tests are carried out in grout holes, the maximum
pressure shall not exceed the maximum grouting pressure to be used. Unless otherwise directed
by the Engineer, the pressure at the various stages shall be as follows:
Stage Pressure (Bar)

1 1.0

2 2.0

3 4.0

4 2.0

5 1.0

vi.Discharge measurements shall be started only after a stable pressure has been established. For
each stage of pressure, water absorption shall be measured 3 times for periods of 3 minutes
each. The time for each stage of pressure shall therefore be at least 9 minutes and the total time
for a complete Lugeon test comprising 5 stages of pressure will be at least 45 minutes.
vii.If during discharge measurements the rate of absorption or pressure changes, the test shall be
extended until discharge and pressure remain constant over a period of 5 consecutive minutes.
_______________________________________________________________________________
105
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

viii.If, due to high absorption, it is not possible to maintain the required pressure, the pump shall be
operated at its maximum discharge rate for 10 minutes and the pressure shall be measured at 2
minute intervals.
9.4.4.6 Lefranc Test
In case the permeability is so high that water under pressure is seeping at rates exceeding the
capacity of normal pumps, or in case of the presence of soil, the Contractor shall carry out
permeability tests by the Lefranc’s method. The Engineer may direct the performance of water
tests which could be constant head type or falling head type, as he may consider necessary.
All the equipment and the execution of the test shall be in accordance with BS 5730-ENGL.
9.4.4.7 Laboratory Test
Test Description Procedures

Grain Size Distibution ASTM 421/D422/D1140

Atterberg Limits ASTM D4318

Unit Weight D7263 - 09

Moisture Content ASTM D2216

Triaxial Tests ASTM D2166

ASTM D2850

ASTM D4767

Direct shear ASTM D3080

Consolidation ASTM D2435

The type of tests and the standard procedure to be adopted are shown in the following tables:
The methodology of the testing operations shall be the ISMR (International Society of Rock
Mechanics) standard procedures.

Test Description Procedures


Unit Weight ASTM D1556
UCS + determination of Young Modulus ISRM suggested method for determining
deformability of rock materials in uniaxial
Triaxial compression
ASTM D 2664

9.5 MEASUREMENT AND PAYMENT


9.5.1 GENERAL
1) The estimates of the quantities for drilling, water pressure testing and sampling given in the
Bill of Quantities are to be considered as merely a guide on which the Contractor is to prepare
his Bid and not as an accurate indication of the quantity of the work.
2) The quantities for each of the pay items will be varied to suit the conditions disclosed in the
course of the work, and the Contractor shall not be entitled to any extra payment over and
_______________________________________________________________________________
106
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

above the Unit Prices entered in the Bill of Quantities by reason of changes of the amount and
length of drillholes, by reason of the location of the drilling required by the Engineer, or by
reason of the timing of the drilling in relation to excavation, concrete and other works.
3) The unit prices stipulated hereinafter shall include for all labour, equipment and materials
required for the execution of the work. If for any particular item no separate pay item is
foreseen, the cost shall be included in one of the unit prices entered in the Bill of Quantities.
9.5.2 SETTING UP OF DRILL RIGS
1) Measurement for payment will be made separately for setting up, on the surface, of:
a) Drill rigs to be used for roto-percussion drilling, without core recovery
b) Drill rigs to be used for rotary drilling, without core recovery
c) Drill rigs to be used for rotary drilling, with core recovery.
2) The unit prices shall apply irrespective of the diameter or length of the hole to be drilled.
3) Measurement for payment for setting-up the drilling equipment will only be made once for
each drillhole, irrespective of the number of times the equipment is actually set up, e.g. for
stage grouting. Only in case the drilling method is changed at the requested of the Engineer,
the corresponding new set up will be paid in addition. Payment will be made at the Unit Price
per set-up entered in the Bill of Quantities, which shall include the entire cost of labour,
equipment, and materials for setting-up the drilling equipment.
9.5.3 DRILLING
1) Measurement for payment and payment will be made separately for drilling holes:
a) By different drilling methods:
o Without core recovery by roto-percussion
o Without core recovery by rotary drilling
o With core recovery
b) For drillholes of the following total lengths:
o Not exceeding 10 m
o Exceeding 10 m but not exceeding 25 m
o Exceeding 25 m but not exceeding 60 m
o Exceeding 60 m
c) For drillholes of the following final diameters:
o 38 mm
o 48 mm
o 63 mm
o 89 mm or more.
2) The total length of the drillhole will be paid at the unit price per meter which corresponds to
the location, drilling method, total length and final diameter. No distinction will be made
between holes drilled for different purposes.
3) The Unit Prices for drilling from the surface shall apply for vertical drilling downward to an
inclination of 30° from the vertical. Additional payment will be made for inclined drilling with a
range of 30° to 90° from the vertical and for overhead drilling at the unit prices per linear
meter of hole so drilled entered in the Bill of Quantities.
4) The unit price per meter entered in the Bill of Quantities shall include the entire cost of labour,
equipment and materials for drilling and washing out the holes and for temporary casing, if
required.
5) When drilling of a hole is carried out successively for multiple-stage grouting, the
measurement for payment will only be of the total length of the hole actually drilled in the
rock or concrete. Any redrilling required because of the Contractors failure to clean the grout
out of the hole before it has set shall be at the Contractor's expense.
6) Measurement for payment for any required re-drilling where the grout has been allowed to
set at the direction of the Engineer will be of the actual length of redrilled hole. Payment for
_______________________________________________________________________________
107
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

this length in linear meter will be made at a rate of 50% of the corresponding unit price.
7) Where redrilling of previously drilled drain holes is required after an additional grouting,
measurement for payment will be by the actual length of redrilled hole. Payment for this
length in linear meter will be made at a rate of 50% of the corresponding unit price.
8) Measurement for payment for perforated steel pipe casing left permanently in place with the
approval of Engineer will be made at the unit price per linear meter entered in the Bill of
Quantities, which shall include the entire cost of supply and installation of the casing.
9) The unit price per linear meter of drillholes with core recovery shall include the provision of
core boxes, preservation and storage of cores, preparation of drill logs, provision of colour
photographs of the boxed cores, and any assistance provided by the Contractor to the
Engineer during the geological logging and handling of core boxes.
10) Additional payment will be made for drilling with triple tube core barrels, where directed by
the Engineer, at the unit price per linear meter of hole so drilled entered in the Bill of
Quantities.
11) Measurement for payment and payment for the installation of instruments in exploratory holes
will be made in accordance with the provisions of the relevant section of these Specifications.
9.5.4 SAMPLING AND TESTING
9.5.4.1 UNDISTRURBED SAMPLE
1) Measurement for payment for undisturbed sampling will be of the number of samples.
2) Payment will be at the Unit Price per piece entered in the Bill of Quantities, which shall include
transporting of samples to the site laboratory. No deduction will be made for drilling of that
stage where the sampling was performed.
9.5.4.2 SPT TESTS
1) Measurement for payment for Standard Penetration Tests will be of the number of tests
satisfactorily performed.
2) Payment will be at the Unit Price per piece entered in the Bill of Quantities which shall include
the entire cost of labour, equipment, and materials used for carrying out the test, the provision
of test records and reports to the Engineer and all costs associated with interruptions to the
drilling in case of the test is performed in association with a borehole.
9.5.4.3 CPT AND CPTU TESTS
1) Measurement for payment for CPT and CPTU will be of the length of tests satisfactorily
performed.
2) Payment will be at the Unit Price per meter entered in the Bill of Quantities which shall include
the entire cost of labour, equipment, and materials used for carrying out the test, the provision
of test records and reports to the Engineer, and all costs associated with interruptions to the
drilling in case of the test is performed in association with a borehole.
9.5.4.4 LUGEON TEST
1) Measurement for payment for water-pressure tests will be of the number of tests satisfactorily
performed, irrespective of size, length, or inclination of hole.
2) Payment will be made at the Unit Price per test entered in the Bill of Quantities, which shall
include the entire cost of labour, equipment, and materials used for carrying out the water-
pressure test, the provision of test records and reports to the Engineer, and all costs associated
with interruptions to the drilling caused by the intermittent nature of the testing work.
9.5.4.5 LEFRANC TEST
1) Measurement for payment for Lefranc will be of the number of test performed tests
satisfactorily performed.
2) Payment will be at the Unit Price per piece entered in the Bill of Quantities which shall include
the entire cost of labour, equipment, and materials used for carrying out the test, the provision
of test records and reports to the Engineer and all costs associated with interruptions to the
drilling caused by the intermittent nature of the testing work.

_______________________________________________________________________________
108
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

9.5.4.6 Laboratory Test


1) Measurement for payment for laboratory tests will be of the number of tests satisfactorily
performed.
2) Payment will be made at the Unit Price per test entered in the Bill of Quantities, which shall
include the entire cost of labour, equipment, and materials used for carrying out the test, the
provision of test records and reports to the Engineer.
9.5.5 INSTALLATION IN DRAIN HOLES
1) Measurement for payment of PVC pipe installed in the drainage holes as directed by the
Engineer will be the length of pipe so installed. Payment will be made at the unit price entered in
the Bill of Quantities which shall include the entire cost of supply and installation of perforated
pipes, as well as all necessary coupling.
2) Measurement for payment for the supply and installation of drain holes outlet devices will be
by the number of outlets. Payment will be made at the unit price per piece entered in the Bill of
Quantities which shall include the supply and installation of all required accessories, and
sealing with mortar.
3) Measurement for payment for the supply and installation of pressure gauges will be by the
number of gauges installed. Payment will be made at the unit price per piece entered in the
Bill of Quantities, which shall include the supply, installation and removal of the pressure
gauge, including pressure relief valve and all necessary pipes and fittings, rubber collar etc.,
grouting work around the drain pipe, and eventual redrilling through the concrete and
placement of dry pack mortar when pressure measurements are no longer required.
9.5.6 EXCLUSIONS
1) All costs for provision of embedded steel pipes and fittings for grouting will be measured and
paid for in accordance with provisions of the Section “Grouting”.
2) No extra measurement for payment or payment will be made for the following:
a) Drilling through steel ribs, steel lagging, reinforcing steel or steel lining
b) Installation and removal of grout stub pipes
c) Reaming or redrilling any holes through the concrete lining for the purpose of placing,
and for supplying and placing, the dry-pack mortar
d) Holes which have been blocked and cannot be used because of cave-ins, lost drill
rods or packers, or striking other obstructions (e.g. reinforcement bars), and drilling
the new holes to replace them.

_______________________________________________________________________________
109
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

10 GROUTING
10.1 SCOPE OF WORK
1) The work under this Section includes all labour, materials, equipment, and operations required
for the performance of grouting in the holes from the surface at locations shown on the Final
Design and/or Construction Drawings or where the Engineer may direct.
2) Grouting operations shall include the following:
a) Curtain grouting below the cut-off trench the dam and below other structures (if
necessary), in order to create a high density zone with a low permeability.
b) Fill grouting of drainage trench, around conduits and sump pits, and of
exploratory drillholes and drain holes.
3) The general extent and approximate location of the drillholes are tentatively indicated on the
Final Design Drawings for the purpose of Bid preparation. The final number, length, location
and inclination of the drillholes, as well as the composition and consistency of the grout mixes,
grouting pressures, pumping rates and sequence in which the holes are to be drilled and grouted shall be
governed by actual conditions encountered on Site and shall be at all times subject to approval
by the Engineer.
10.2 DEFINITIONS
10.2.1 CEMENT GROUT
1) Cement grout is defined as a mixture of cement and water with the addition of admixtures,
sand and bentonite, if required, which is forced under pressure into prepared holes or pipes in
order to fill voids or consolidate the rock mass as a whole.
2) Cement grouts are subdivided into stable and unstable mixtures:
a) Unstable mixtures are simple suspensions of cement in water. These suspensions
are only homogeneous as long as they are in movement and the sedimentation
starts as soon as the movement is stopped.
b) Stable mixtures are colloidal suspension dissolved in water which grain size is so
small that no appreciable sedimentation occurs during the grouting operation.
These suspensions are obtained by high speed mixing of cement with addition of
bentonite and/or admixtures and shall be used for all grouting works.
10.2.2 SINGLE-STAGE GROUTING
1) The single-stage grouting (nipple grouting) is carried out by introducing the grout at either the
collar of the hole through a nipple or by means of a grout supply pipe at the bottom of the
hole. The entire length of the hole is grouted in one operation.
2) This grouting method will in general apply for contact grouting and for consolidation grouting of
short holes in stable ground.
10.2.3 MULTIPLE-STAGE GROUTING
1) This grouting method will in general apply for consolidation grouting in holes crossing unstable
ground.
2) Multiple-stage grouting is carried out by introducing the grout into a predetermined section of
the hole which is blocked off by a packer. The grouting of the entire length of hole is
performed in successive stages either in ascending or descending arrangement.
3) The terms ascending or descending arrangement mean only the sequence of the grouting
stages, either from bottom to the collar of the hole or in reverse, irrespective of the effective
direction or inclination of the hole.
4) When grouting is done in ascending arrangement, the hole is drilled to its full depth, washed
out, and the packer is set at the top of the deepest section to be grouted. The section is then
water-pressure tested and grouted at the required pressure through the grout supply pipe. The
packer is allowed to remain in place until there is no back pressure and then withdrawn to the

_______________________________________________________________________________
110
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

top of the next section to be grouted. The water-pressure testing and grouting is repeated
successively section by section until the entire length of the hole is filled with grout.
5) When grouting is done in descending arrangement, the work is accomplished in sections from
the collar of the hole. The hole is drilled to a limited depth, washed out and the packer is set
just above the section to be grouted. The section is then water-pressure tested and grouted at
the required pressure. The grout within the hole is washed out before it hardens while the
grout surrounding the hole is allowed to obtain its initial set, before the hole is drilled to an
additional depth. Repeating thus successively drilling, water-pressure testing, and grouting at
various depths until the entire length of hole is completely drilled and grouted.
10.2.4 WATER-CEMENT RATIO
The water-cement ratio (W/C) is the proportion by weight of water to cement in a water-
cement mixture.
10.3 SUBMITTAL
1) At least 60 days prior to the start of grouting works the Contractor shall submit for approval
fully detailed proposals and a detailed layout of his proposed arrangements for grouting,
including specifications of all equipment, tools and all grouting materials to be used, and
qualification and experience of the proposed personnel.
2) An overall grouting program shall be drawn up jointly between the Contractor and the
Engineer. Grouting mixes, pressures, pumping rates, and sequencing will be selected, subject to
modifications, to meet local conditions encountered during the performance of the work.
Grouting works shall be planned in such a manner that they can be carried out according to
the approved plan concurrently with other activities. Modifications to the grouting program
shall be implemented as directed by the Engineer.
3) Prior to each phase of grouting, the Contractor shall submit for approval a detailed program
for the particular grouting works along with information relating to the methods he proposes
to use and details of grout mixes. No grouting work shall be executed without prior written
approval by the Engineer.
4) During the performance of the grouting works, the Contractor shall keep complete daily
records of all grouting operations which shall include the following:
a) Number and location of the drillholes
b) Results of water-pressure tests
c) Grouting method
d) Date and time of commencement and of each change in grouting operations
e) Rate of pumping
f) Grouting pressures and gauge reference number
g) Water-cement ratio and its variations
h) Separate quantities of cement, sand, bentonite, admixtures and chemicals used
i) Connections, if any, with other holes and cracks, as well as any surface leakage of
water or grout
j) Number of holes and depth of holes left for redrilling
k) Time of completion
l) Name of the foreman in charge
Grouting reports in an approved form shall be compiled from these records and submitted
weekly to the Engineer. Results of water pressure tests and grout takes shall be submitted
graphically.
5) The Engineer reserves the right to require any additional information deemed necessary to be
included in the submitted documents.
10.4 SAMPLING AND TESTING
1) The Contractor shall prepare and test the trial mixes as directed by the Engineer at least 30
_______________________________________________________________________________
111
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

days before commencement of any grouting. Materials for use in grout mixes shall be tested
for compliance with the applicable requirements stipulated in "Materials" of this Section.
2) Following tests shall be required:
a) Laboratory tests:
• Grain size distribution and moisture content of sand
• Atterberg limits
• Chemical analysis of water and solids
• Compressive strength
• Viscosity (by fan-viscosimeter and Marsh cone)
• Density
• Decantation and setting time (by Vicat needle)
• Shrinkage of the grout
b) Field tests:
• Density by hydrometer or mud balance
• Viscosity by Marsh cone
Sampling and testing will be supervised by the Engineer
3) All chemical grouts shall be tested in the laboratory at the Site under conditions identical to
those to which they will be subjected in the field, in order to determine the suitability of
various chemicals and proportion of the ingredients to satisfactorily complete the work.
4) During the actual grouting operations the Contractor shall carry out tests on grout mixes at the
same time as grouting, and shall plot values of viscosity, sedimentation limits, compressive
strength, and maximum viscosity possible for the grouting on a diagram. The frequency of
testing will be once for each grouting jobsite or until acceptance criteria have been met.
However, if a significant change in the cement source occurs, sampling and testing must be
repeated. Acceptance criteria will be determined by the Engineer.
10.5 GROUTING MATERIALS
10.5.1 GENERAL
1) The following kinds of grout mixes may be used:
a) Neat cement grout, possibility with admixture
b) Cement-sand grout, possibility with admixture
c) Chemical grout such as polyurethane, one or two component type
d) Cement-bentonite grout with or without sand
The quantities of sand, bentonite, fly and admixtures will depend on the permeability of the
rock and the size of the voids to be grouted.
2) Cement, sand, water, admixtures and flyash for use in grout mixes shall conform to the
requirements of Section "Concrete", except as specifically amended hereafter.
10.5.2 CEMENT
1) Cement shall have a minimum specific surface of 3,500 cm2 per gram as determined by the
Blaine air-permeability method (ASTM C204). No cement particle shall be retained on US
Standard Sieve No. 200 (0.075 mm).
2) Cement Type I shall be used, pending confirmation that the ground water is not aggressive.
10.5.3 SAND
1) Sand in grout might be required for small portions of the work in highly fissured or fractured
rock zones. Sand shall have the following grading:
US Standard Sieve Square Mesh Sieve Percentage Passing
Opening (by weight)
No. 8 2.360 mm 100
No. 16 1.800 mm 95-100
_______________________________________________________________________________
112
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

No. 30 0.600 mm 60-85


No. 50 0.300 mm 20-50
No. 100 0.150 mm 10-30
No. 200 0.075 mm 0-5
2) Sand shall not contain more than 3% of flat or elongated particles having a maximum
dimension in excess of four times the minimum dimension.
10.5.4 WATER
1) Water shall not contain more than 2,000 ppm of suspended colloidal solids and no particles
larger in size than the cement particles. It shall not be aggressive. The chloride content shall
be less than 50 mg/l and the sulfate content less than 100 mg/l.
2) The temperature of water used for the preparation of grout shall not exceed 25°C.
10.5.5 ADMIXTURES
1) Admixtures shall be added to grout mixes to optimize the strength, viscosity, density,
decantation, setting time and shrinkage.
2) Only admixtures proved by testing prior to the start may be used for grouting. Manufacturer’s
certificates or guarantees will not be accepted as relieving the Contractor of his responsibility
for the suitability of any admixture. Admixtures shall be Sikament 100 with expansion effect,
supplied by SIKA, or approved equal.
10.5.6 BENTONITE
Bentonite shall be as specified by the American Petroleum Institute as follows:
Type Sodium Montmorillonite
Wet screen analysis residue on US Standard max. 2.5%
Sieve No. 200 (0.075 mm)
Moisture max. 13%
Fan Reading min. 30 at 600 rpm
Yield Point max. 3 x plastic viscosity
Filtrate maximum 13.5 cc
Liquid limit not less than 350
Plastic limit not less than 28
10.5.7 FLY ASH OR POZZOLANA
1) For improving the fluidity, stability and sulphate resistance of the grout, finely ground fly ash
or pozzolan may be added to the standard grouting materials and to replace up to 20% of the
cement. Alternatively, Portland Pozzolan cement may be used.
2) Fly ash shall be used only if proved to be compatible with other grouting materials by testing
prior to the start of grouting and approved by the Engineer.
10.5.8 CHEMICALS
1) When chemicals are required or proposed, they shall be accompanied by the manufacturer's
certificates that they have been commercially used with satisfactory service in similar type of
work. The storage, handling and usage shall be strictly with the manufacturers printed
instructions.
2) The use of toxic chemicals such as acrylamide shall not be permitted for use in the Works.
3) When Sodium Silicate is required or proposed it shall meet the following requirements:

_______________________________________________________________________________
113
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

Specific Gravity at 15°C More than 40°Be (Baume gravity meter)


SiO 28% to 30% by weight
Na2O 9% to 10% by weight
Fe Less than 0.02% by weight
Matter insoluble in water Less than 0.2% by weight

10.6 GROUT MIXTURES


10.6.1 GENERAL
1) The type of grout and products for each mixture will be determined by the Engineer according
to design requirements and the purpose of the work.
2) The proportions of various constituents in the grout mixtures shall be selected by the Engineer
in collaboration with the Contractor and shall be constantly adopted to the conditions at the
Site as the Engineer may direct.
3) Any grout mixture not used within one hour after mixing shall be wasted.
10.6.2 UNSTABLE CEMENT MIXTURES
1) Neat cement grouts with a water-cement ratio (W/C) varying from 1 to 0.5 will normally be
used. Admixture may be added to obtain better penetration.
2) Where sand is added to the mix, the weight of sand added shall not exceed twice the weight
of cement.
3) The materials for unstable mixtures may be mixed in the same mixer under condition that
there shall be no appreciable segregation of the grout before setting.
10.6.3 STABLE CEMENT MIXTURES
1) Stable mixtures shall consist of cement, with addition of bentonite as required and as the
Engineer may direct. The water-cement ratio (W/C) may vary from 2:1 to 0.5:1.
2) The preparation of cement-bentonite grout mixture shall be as follows:
a) Phase 1: Mix bentonite and water in a high-speed colloidal mixer and transfer to
a storage reservoir where the mixture is continuously agitated.
b) Phase 2: Transfer the bentonite slurry to a second high speed colloidal mixer and
add cement and additional water. The final mixing shall last for at least 2 minutes.
3) Water used for the preparation of the bentonite slurry shall not contain any suspended cement
particles.
4) Under no circumstances shall the same mixer be used for both phases.
10.6.4 GROUT MIXES FOR DAM/SPILLWAY GROUT CURTAIN
1) The proposed grout mix will start with one part cement/pozzolan to one part water (by
weight) with 1 to 2% super plasticizer (e.g. Sikament). If the grout pressure develops with this
consistency, the hole shall be grouted to refusal point. If there is a pressure drop or take
beyond 200 l/m, the grout mixture shall be thickened with 1:0.7 mixture, to obtain the
development of the desired grout pressure.
2) If after thickening of the mix, the grout take is greater than 200 l/m, intermediate holes shall
be drilled and grouted (secondary, tertiary, etc.).
3) In areas of known high permeability, as interpreted by the Engineer, or where detectable
water loss during drilling occurs, the starting grout mix shall be 0.8 water to 1
cement/pozzolan and 1 to 2% plasticizer.
4) If the take exceeds 0.5 m3/m the mix shall be switched in order to fill the open seams with
mortar composed of one part sand, cement/pozzolan and water (i.e. 1:1:1 ) with plasticizer as
required. Mortar shall be pumped to refusal.

_______________________________________________________________________________
114
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

10.7 EQUIPMENT
10.7.1 GENERAL
1) Only modern, properly operating grouting equipment approved by the Engineer and operated
by trained and experienced crew shall be used for the performance of the work.
2) Grouting equipment shall consist of grout pumps, weighing scale for additives and cement,
grout mixers, water meters, agitator sumps, pressure gauges, packers, pipe lines and fittings,
and miscellaneous tools specifically designated for grouting purposes.
3) Grouting equipment shall be capable of effectively mixing and stirring the grout and forcing it
into the grout holes or grout connections in a continuous, uninterrupted flow at any specified
pressure up to a maximum of 25 bar, and of accurately measuring the grout take. It shall
maintain the specified pressure for at least 5 minutes after the hole refuses to accept further
grout. The equipment shall be capable of accurately controlling grout flows and pressures and
shall be suitable for neat cement and cement-sand grouts.
4) Spare gauges, valves and fittings shall be kept available at the Site, and a two-way
communication system between the mixing plant and place of grouting shall be provided if
the distance exceeds 60 m.
5) Stand-by equipment which can be activated immediately shall be furnished to ensure
continuity of work in the event of main equipment breakdown. The standby equipment shall
be able to operate at pressures up to 10 bar.
6) Graduated water discharge meters shall be accurate to ±5%.
7) Equipment for proportioning grout mixes based on number of cement bags or weighing of
cement from bulk silo, and dosing of bentonite and water shall maintain dosing accuracy of 2
and 5%, respectively.
8) Prior to commencement of work, during the work as specified or as requested by the
Engineer, and at the end of the work, all pressure gauges, recorders and discharge meters
shall be checked and calibrated.
9) The grouting equipment shall always be maintained to Engineer's satisfaction in order to
guarantee continued and efficient performance during grouting work.
10.7.2 GROUT MIXERS AND AGITATOR SUMPS
1) Grout mixers for mixing the stable mixtures shall be of the mechanically operated, high speed
colloidal type of sufficient size, and operating at 1,500 to 2,000 rpm to ensure complete
dispersion and activation of the mix, with electric or pneumatic drive.
2) For mixing the unstable mixtures the paddle mixers may be used.
3) Hand-powered mixers or concrete mixers shall not be permitted for preparation of grout
mixtures.
4) Mixers shall be provided with equipment for measuring weight and volume of mix components
with an accuracy of 2% and a water meter calibrated in liters with a reset switch for zeroing
after each delivery.
5) After mixing, the grout shall be discharged through a 5 mm mesh screen into an agitator
sump equipped with stirring paddle to prevent settling and to remove any air bubbles from
the mix. The stirring paddle shall be of such arrangement to guarantee a complete circulation
of the entire sump content. The agitator sump shall have at least the same capacity as the
mixer so that one batch of grout can be pumped while the next batch is being mixed.
10.7.3 GROUT PUMPS
1) Grout pumps shall be capable of delivering a flow of 50 l/min of thick grout (W/C = 1) at
specified pressure and shall be able to achieve and hold a pressure of up to 25 bar. They shall
deliver grout at constant pressure and flow, without pressure surges.
2) Pumps shall be of the duplex double acting piston-type or a single acting plunger type. The
pump body shall be of high wear and shock resistant material. The plunger unit shall be of
stainless steel, highly resistant to abrasion.
_______________________________________________________________________________
115
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

3) The pump shall have either pneumatic drive or electro-hydraulic drive.


4) The pumps shall be equipped with precise pressure and capacity control valves which allow
the setting of both, the maximum pressure and the flow, independently. The pump shall
automatically stop whenever the preset pressure is reached, and shall maintain that pressure
without fluctuation.
5) For works requiring a small volume of grout, the Contractor may use hand operated grout
pumps approved by the Engineer. These pumps shall be able to achieve a pressure of up to 10
bars.
10.7.4 PRESSURE GAUGES
1) The Contractor shall provide pressure gauges for both low and high pressure ranges (0-15 bar
and 0-30 bar). Two gauges for the appropriate range shall be provided in each grout line, one
at the pump for the use of the pump operator, the other at the hook-up connection directly
at the collar of the hole. The required pressure for each particular hole shall be measured on
the hook-up pressure gauge, not at the pump.
2) Pressure gauges shall have an accuracy of 3%. A minimum of two standardized pressure
gauges for each range shall be calibrated and certified by an independent laboratory prior to
the commencement of grouting works. One gauge for each range shall remain at the disposal
of the Engineer, and the other shall be used by the Contractor for checking and calibration of
working gauges. Working gauges shall be used for no longer than 2 shifts before being
cleaned and recalibrated. All working gauges shall have reference numbers for identification,
which shall be quoted in the grouting reports to be submitted to the Engineer.
10.7.5 CONNECTIONS TO GROUT HOLES AND PACKERS
1) Supply and return lines equipped with quick release couplings shall be able to withstand an
internal pressure greater than the maximum produced by the pump. The internal diameter of
the lines shall be such that no appreciable settlement of grout will take place when pumping
at the minimum discharge capacity of the pump.
2) Valves shall be provided at the pump, in the supply line and at the collar of the hole being
grouted. Suitable screens shall be incorporated in the supply line for removing oversize
particles and foreign matter before injection into the grout hole.
3) Packers shall be the same as used for water-pressure testing as specified in the Section
"Drilling and Water-Pressure Testing".
10.7.6 EMBEDDED PIPES AND FITTINGS FOR GROUTING
1) Standard mild steel pipes and fittings for grouting shall be set in the concrete as the Engineer
may direct, or where shown on the Final and Construction Drawings. The pipes and fittings
embedded in concrete shall be cleaned thoroughly of all dirt, grease, grout and mortar
immediately before embedment and shall be firmly held in position and protected from
damage or displacement while the concrete is being placed. A standard coupling and nipple
wrapped to facilitate eventual removal shall be attached to the grout pipe where embedded
in concrete. No portion of the pipe shall be allowed to remain within 50 mm of the concrete
surface and the resulting recess, after removal of the pipe or fitting, shall be filled with dry-
pack mortar.
2) “Tube-à-manchette" type pipe shall be provided by the Contractor for chemical grouting
operations or where closing the gap between two different concrete stages caused by the
shrinkage is required and as shown on the Construction Drawings. The pipe shall have an
internal diameter of not less than 50 mm and shall be perforated every 30 to 40 cm. Each
series of holes shall be covered by the rubber sleeve, called “manchette”, to allow the grout
under pressure to flow out but not re-enter. In the drillhole the pipe shall be embedded by
means of a cement-bentonite mixture which shall be injected into the space between the
"Tube-à-manchette” and the temporary hole casing while this is being withdrawn. The grout
supply pipe shall have a double packer to allow the grout to following out only from one series
_______________________________________________________________________________
116
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

of holes covered by the "manchette".


3) Care shall be taken to avoid premature blockage of pipes. Any pipe that becomes blocked
before completion of operations shall be cleaned out in a satisfactory manner or replaced by
the Contractor.
10.8 GROUTING OPERATIONS
10.8.1 GENERAL
1) All pressure grouting operations shall be carried out in the presence of the Engineer.
2) Should the Engineer deem necessary to carry out an additional grouting in any section of the
Works, the Contractor shall reinstall the necessary equipment and perform the grouting to
the satisfaction of the Engineer.
10.8.2 CURTAIN GROUTING
1) Curtain grouting shall be performed below the cut of trench of the dam, and as indicated on
the Final and Construction Drawings and/or as directed by the Engineer. Hole depths,
inclinations, sequence of grouting, method of grouting, whether single or multi stage, in
ascending or descending arrangement will be adapted by the Engineer based on information
from exploratory drilling or current operations. The holes shall be drilled and grouted by split
spacing method.
2) The depth of the grout curtain shall be defined according to the results of the water pressure
tests obtained in the primary holes.
3) All primary holes shall be pressure tested before grouting. Based on the results the Engineer
determines the grout mix to be used at the beginning of grouting and the maximum pressure.
4) Normal sequence of grouting shall be ascending from bottom to top of hole in stages
determined from water-pressure tests. Where the permeability exceeds 15-20 Lugeons,
grouting shall generally be performed in descending arrangement.
5) When performing the multiple stage grouting in descending arrangement, the grout that is
within the hole shall be removed from each stage except the deepest one, by washing, or by
the use of a chopping or a “fishtail” bit before it takes a hard set.
6) Stage length shall be a maximum of 5 m.
7) Unless otherwise directed, air, wash water and grout pressures shall not exceed 2 bar plus
0.25 bar per linear meter of the depth measured from the collar of the hole to the
bottom of the packer. Grout pressure shall not be released nor packers moved until the grout
in each successive stage has achieved an initial set.
8) The curtain grouting shall be performed from one or several grout stations. If several such
stations are used, each shall be equipped complete, with mixers, agitator sumps, pumps,
gauges and measuring devices, and shall have a sufficient supply of grouting materials.
9) In case when the required pressure is not reached even when injecting maximum volume, the
Engineer will decide whether the grouting will be interrupted, or the grout mixture is to be
changed, or accelerator added.Where grout is found to be flowing from adjacent holes or
cracks of any kind, such openings shall be capped temporarily by plugging or caulking. If this
does not bring satisfactory results, further grouting shall be interrupted and the injected
material let to harden.
10) Grouting injection will be deemed to be completed when the take has become 0.03 m3/m or
less per stage of hole being grouted during 10 minutes at the specified grouting pressure and
mixture.
11) After the conclusion of the grouting program, the Contractor shall drill control holes as
stipulated in the Section "Drilling and Water Pressure Testing”. Unless otherwise directed,
these control holes shall be drilled generally at a distance of 36 m. These holes shall be fill
grouted. Based on the results obtained in the control holes, the Engineer may order additional
grout holes or a new line of grout holes to be executed.

_______________________________________________________________________________
117
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

12) The general target of permeability of the grouted foundation is 5 Lugeons.


10.8.3 CLOSURE OF HOLES AND CLEAN-UP
Upon completion of grouting work each hole shall be filled with thick grout and connections
not embedded in the concrete shall be removed.
10.8.4 CONTACT GROUTING BETWEEN CONCRETE AND EMBEDDED COMPONENTS
1) Grouting between concrete and embedded components shall not commence until the backfill
concrete has been in place for at least 30 days.
2) Low pressure contact grouting shall be carried out until all voids are thoroughly filled. The
maximum grouting pressure shall be 5 bar or as directed by the Engineer, and the Contractor
shall ensure that the specified pressure is not exceeded.
3) Pre-tapped holes for grouting, complete with threaded steel plugs, will be provided by others
in the steel components. The Contractor shall provide threaded pipes to protect the thread of
the grouting holes during the drilling and grouting operation.
4) After completion of grouting, a knocking test shall be performed jointly by the Contractor and
the Engineer to establish if contact grouting between the steel component and the concrete
has been completely successful. If a "hollow" sound indicates the grouting to be incomplete,
the Contractor shall re-grout, which may include the drilling, tapping and subsequent sealing
of additional holes. All costs associated with regrouting, including those associated with the
drilling, tapping and subsequent sealing of additional holes, shall be borne by the Contractor.
5) After successful completion of the grouting, the Contractor shall clean the threaded holes and
screw the plugs back in position.
10.8.5 GROUTING OF CONTRACTION AND CONSTRUCTION JOINTS
1) All grout shall consist of neat cement/water mix. Cool water not exceeding 30°C shall be used in
the mix to prevent quick setting of the grout.
2) Grouting of the joints shall be completed before the grout takes its set in the grout pipe
system, but the joints shall not be grouted so rapidly that the grout will not settle in the joint.
The time consumed for filling a joint shall be at least 30 minutes.
3) The grout shall be pumped into the bottom headers of the pipe system and the vent or highest
headers shall be left open until the joint is filled with grout of proper consistency for retention
in the joint. Thereupon the system shall be closed and the required pressure applied and held
until the grout has set sufficiently to be retained in place.
4) Nipples in the exposed faces shall be removed and the holes filled with dry pack mortar.
5) Grouting of contraction and vertical construction joints may be specified by the Engineer at
other concrete structures.
10.9 MEASUREMENT AND PAYMENT
10.9.1 GENERAL
1) The estimates of the quantities for grouting given in the Bill of Quantities are to be considered
merely as a guide serving the Contractor to prepare his Bid and not as an accurate indication
of the quantity of the work.
2) The quantities for each of the pay items will be varied to suit the conditions disclosed in the
course of the work, and the Contractor shall not be entitled to any extra payment over and
above the Unit Prices entered in the Bill of Quantities by reason of changes of the amount
and length of holes to be grouted, amount of material absorbed, by reason of the location of
the grouting required by the Engineer, or by reason of the timing of the grouting in relation to
excavation, concrete or other works.
3) The unit prices stipulated herein shall include, but not be limited to, all labour, equipment,
processing, mixing, hooking-up to the hole, injecting grout, hole closures and clearing up, and
shall be independent of the volume or weight of materials injected. Where the multiple-
stage grouting is employed, this item shall also include cleaning grout from the holes at the

_______________________________________________________________________________
118
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

completion of a grouting stage. If for a particular item no separate payment is made, it is


intended that the relevant cost is included in one of the unit prices entered in the Bill of
Quantities.
10.9.2 CONTACT GROUTING BETWEEN CONCRETE AND EMBEDDED COMPONENTS
1) Measurement for payment and payment will be of the number of holes (connections) injected
with grout.
2) Payment will be made at the unit price entered in the Schedule in square meter, which shall
include all labour, materials and equipment required for:
a) Grouting valves where required
b) Grouting materials, irrespective of the quantity actually taken
c) Hook-ups to the grout holes and grouting operation
d) Knocking test after completion of the grouting
e) All repairs and finishing works to the surface after grouting.
3) Should re-grouting be necessary, all relevant costs, including those associated with the
drilling, tapping and subsequent sealing of additional holes, shall be borne by the Contractor.
10.9.3 GROUTING OF CONTRACTION AND CONSTRUCTION JOINTS IN CONCRETE STRUCTURES
1) Measurement for payment and payment for grouting of contraction and construction joints in
concrete structures will be based on the projected area of the joint obtained from the
Construction Drawings.
2) Payment will be made at the unit price per square cubic meter entered in the Bill of
Quantities, which shall include full compensation for furnishing all labour, materials, tools,
equipment and incidentals for mix proportioning, injection, caulking of leaks, clean up, records
and any other costs necessary for doing the work as specified in this Section, shown in the
Final and Construction Drawings and/or directed by the Engineer.
3) Embedded pipes and fitting for the grouting of contracting and construction joints will be paid
for separately, as detailed here below.
10.9.4 EMBEDDED STEEL PIPES AND FITTINGS
1) Measurement for payment for embedded steel pipes and fittings left permanently in place will
be of the weight, regardless of pipe diameter. Payment will only be made for pipes which
installation has been expressly ordered or approved by the Engineer or when shown on the
Detailed Site Execution Drawings.
2) Payment will be made at the Unit Price per kilogram entered in the Bill of Quantities, which
shall include the entire cost of supply, installation, and protection against blockage of pipes
and fittings.
10.9.5 EXCLUSIONS
1) No extra measurement for payment or payment will be made for following:
a) Preparation and testing of trial mixes
b) Grouting materials used in mixture which has been prepared more than one hour
prior to injecting or which have been lost due to improper handling or rejected
due to improper mixing
c) Supply and injection of water
d) Plugging and caulking leaks during grouting
e) Protection of drainage systems, if any, during grouting
f) Communication facilities required during grouting
g) Closure of the holes as specified and clean-up
h) Preparation and submission of records and reports on grouting operations.

_______________________________________________________________________________
119
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

11 DAM EMBANKMENT CONSTRUCTION


11.1 SCOPE OF WORK
1) This section covers all labour, materials, equipment and services required in the construction
of the DAM EMBANKMENT.
2) It does not refer to work on roads or other minor embankment works.
3) The embankment works shall be executed generally in accordance with the Drawings and this
Technical Specification or as the Engineer may direct.
4) Particular attention is drawn to the PREAMBLE of this Technical Specification in respect to the
selection of methods of construction and the modification to these following site testing and
experiments.
5) In addition to any limitations on the gradings of the fill material or any compaction
requirements which may be determined by site testing and experiments, the Engineer
reserves the RIGHT TO MODIFY, during the progress of the work, any other features which he
considers necessary for the proper performance of the completed works.
6) The approval given by the Engineer to the Contractor's plants and equipment or their
operation, or of any construction methods shall not relieve the Contractor of his full
responsibility for the proper and safe execution of Dam embankment works or any
obligations under this Contract.
11.2 SUBMITTAL
11.2.1 SUBMITTALS BEFORE CONSTRUCTION
1) At least 60 days prior to the commencement of the embankment construction the Contractor
shall submit to the Engineer for approval of the proposed quarry working method and results
of trials and tests carried out at the quarry site.
2) During the progress of trial embankments and tests, the Contractor shall submit to the
Engineer copies of all records and results of tests.
3) At least 30 days before starting the construction of dam embankment the Contractor shall
submit for the Engineer's approval, a detailed CONSTRUCTION PROGRAMME and METHOD
STATEMENT for the main dam embankment works.
4) Within 30 days from the date of issue of Notice to Commence and prior to the delivery of the
compaction plant to the Site, the Contractor shall provide the Engineer with all the
manufacturer's data, drawings, and computations to verify compliance with the specified
compaction requirements. The characteristics and efficiency of this equipment shall be subject
to the approval of the Engineer.
11.2.2 SUBMITTALS DURING CONSTRUCTION
1) To enable the Engineer to verify the condition of the prepared foundation surface, the
Contractor shall notify the Engineer in writing, giving at least 7 days notice before the
commencement of placing any embankment fill.
2) At least 7 days prior the commencement of placing of any filter layer the Contractor shall
submit for Engineer's approval details of proposed materials source and methods of placing
and compacting,
11.3 MATERIALS
11.3.1 GENERAL
The construction materials shall be taken from the quarries shown on the Detailed Design,
from the excavation of the other structures or from other approved sources as directed by
the Engineer.
Materials originating from excavation for Permanent or Temporary Works may also be used as
fill materials, but only when such materials have been approved for such use and only within
specified zones.
_______________________________________________________________________________
120
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

11.3.2 DAM BODY (CL/SC)


The principal material to be used in the construction of the dam shall comprise CL/SC material
available from the plain of the dam site area.
Rejection by the Engineer may be made at the source, on the transporting vehicle, or in place.
Final acceptance of earth material will be made only after the materials have been dumped,
spread and compacted in place.
The Contractor shall co-operate with the Engineer to ensure that only acceptable earth
materials be hauled from the source to the work site.
The type of material and grading requirements for the embankment are described in the
Tender Drawings and are separately described below.
The main body of the Dam shall comprise CL/SC material available from the plain of the dam
site area or from other sources as directed and/or approved by the Engineer.
The selected material must be the following gradation:
Percentage passing
size (mm)
100 3 – 25
85 0.6 – 3.8
50 0.2 – 1.3
15 0.001 – 0.025

The material shall be compacted with not less than four full (4) passes of crawler-type tractor
having a min. weight of 18 ton.
The minimum thickness of each layer will be not more of 0.3 m.
11.3.3 UPSTREAM DAM SURFACE (LARGE_STONE)
Upstream dam surface will be protected with stones. This material will be collected from the
borrow areas, resulting from the crushing of the sound material.
The selected material must be the following gradation:
Percentage passing size (mm)

100 460 – 950

85 340 – 700

50 260 - 530

15 170 - 370

The material shall be placed by excavator in order to obtain max interlocking.


11.3.4 COARSE FILTER (GW/GP)
Between upstream facing large stone and fine filter a transition material is present.
This material consists of GW/GP and will be collected from the quarry areas, resulting from the
crushing of the sound material.

The selected material must be the following gradation:


Percentage passing size (mm)

100 165 – 380

_______________________________________________________________________________
121
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

85 100 – 240

50 32 – 85

15 7 – 22

The material shall be compacted with not less than four full (4) passes of vibratory roller min.
weight of 15 ton.
The minimum thickness of each layer will be not more of 0.4 m.
The design of coarse filter layer shall satisfy the following criteria and shall be subject to the
Engineer's approval; calling with the apex B and F respectively the filter material and the base
material, the criteria are:
a) PERMEABILITY CRITERION:
DF15 min ≥ 5
D B15 max
b) RETENTION CRITERION:
DF15max ≤ 5
DB85 max
c) UNIFORMITY CRITERION OF THE FILTER:
1.5 ≤ DF60 ≤ 8
DF10
d) The grain size curves of the filter and base material shall be roughly parallel;
e) Filter does not contain more than 5% of material finer than 0.074 mm after
compaction.
The filter material shall be handled and placed in such a manner as to avoid segregation and
mixing with foundation or backfill material.
11.3.5 FINE FILTER (SM/SC)
Between upstream dam body and coarse filter a transition material is present.
This material consists of SM/SC and will be collected from the quarry areas, resulting from the
crushing of the sound material.
The selected material must be the following gradation:
Percentage passing
size (mm)
100
10 – 30
85
6 – 18
50
1.2 – 4.5
15
0.02 – 0.13
The material shall be compacted with not less than four full (4) passes of vibratory roller min.
weight of 15 ton.
The minimum thickness of each layer will be not more of 0.4 m.
The design of coarse filter layer shall satisfy the following criteria and shall be subject to the
Engineer's approval; calling with the apex B and F respectively the filter material and the base
material, the criteria are:
a) PERMEABILITY CRITERION:
DF15 min ≥ 5
D B15 max

_______________________________________________________________________________
122
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

b) RETENTION CRITERION:
DF15max ≤ 5
DB85 max
c) UNIFORMITY CRITERION OF THE FILTER:
1.5 ≤ DF60 ≤ 8
DF10
d) The grain size curves of the filter and base material shall be roughly parallel;
e) Filter does not contain more than 5% of material finer than 0.074 mm after
compaction.
The filter material shall be handled and placed in such a manner as to avoid segregation and
mixing with foundation or backfill material.
11.3.6 BORROW / QUARRY OPERATIONS
The dam embankment materials shall be obtained by operating the borrows / quarries.
The operation of borrows / quarries shall generally be in accordance with requirements of
Section 6, "Excavation and Filling" and particularly the specification in respect of blasting in that
Section.
Before commencement of embankment construction, the Contractor shall carry out trials as
specified at the designated quarry sites to ascertain the optimum methods for production of
the earth fill materials.
The aim of the trials and tests shall be to establish an efficient system by which to produce fill
material within the specification requirements with the minimum of additional treatment or
screening and to minimize wastage.
As a result of such tests and trials the Contractor shall propose for the Engineer's approval a
quarry working method. If approved, subject to any modifications required by the Engineer, this
method shall become the standard operating procedure for the quarry and shall only be varied
or changed by agreement with the Engineer.
The Contractor shall provide and maintain facilities at the quarry to enable the selection of any
special grading of fill material for particular zones of the dam as specified herein and on the
Drawings or as subsequently instructed by the Engineer. On completion of the Works the
Contractor shall ensure that the quarry is left in a safe and tidy condition to the satisfaction of
the Engineer.
11.3.7 ORGANIC MATTER
No organic matter shall be included in the dam construction and the Engineer reserves the right
to reject complete loads of fill where the organic content is high or mixed with the fill so as to
preclude satisfactory removal.
11.3.8 STOCKPILING OF EMBANKMENT MATERIALS
The Contractor shall stockpile embankment materials, graded or not, in such a manner as to
fulfil the construction programme without delay.
The period, volume, location, etc. of the stockpiling, shall be in accordance with the
requirements of Subsection 6.9 "Disposal of Excavated Material" of the Technical Specification
and shall be entirely the Contractor's responsibility.
11.4 FOUNDATION PREPARATION
11.4.1 GENERAL
1) The foundation for the dam embankments shall be excavated generally in accordance with the
requirements of the Section "Excavation and Filling"
2) All overhanging rock shall be detached by barring or wedging and all loose or semi detached
blocks shall be removed from the foundation surfaces.
3) The exposed rock surface in the foundations shall be cleaned by means of water and/or air
jetting and shall then be inspected by the Engineer. To assess the quality of foundations the

_______________________________________________________________________________
123
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

Engineer may require sampling and testing to be carried out on the material exposed in the
foundations and the Contractor shall provide all facilities to assist the execution of such
sampling and testing (see Section 14.8).
4) Where erodible material is exposed in the foundations, the surface will be compacted according
to the Engineer's instructions and/or specially selected and graded material shall be placed
over the area as directed by the Engineer to provide the filters as shown on the Detailed
Design and/or Construction Drawings, specified herein (see subsection 14.3.2.5) and as directed
by the Engineer.
5) In particular cases, e.g. faults, the removal of soft or decomposed material and surface
protection by shotcrete may be directed by the Engineer.
6) Preparation of foundations shall include the provision of adequate drainage and dewatering to
ensure sufficiently dry working conditions for the operations in progress.
7) The placing of fill to form the embankments may proceed only with the approval of the
Engineer, which will be based on the condition of the foundation determined by inspection
after the completion of all foundation preparation works. The Contractor shall be responsible
for maintaining the foundation surfaces in the approved condition until they have been covered
by fill material.
11.4.2 FOUNDATION FOR OTHER STRUCTURES
For the foundations for all structures and drainage pipelines within the dam embankment
areas, the following special provisions shall apply:
• For the final stages of excavation within 1 m of the foundation levels and slopes, blasting
will not be permitted.
• All abrupt irregularities to line and level shall be removed and graded out.
• Any cracks and joints in the exposed rock surface shall be cleared out to a depth of not
less than three times their width at the surface. The cracks and joints shall then be filled
with cement mortar grout pumped or thoroughly brushed to completely fill the voids.
• Depressions and holes or similar irregularities shall be filled with concrete or selected fill
material as directed by the Engineer. The concrete or fill material shall be thoroughly
compacted by vibration.
• Where such surface treatment occurs on steep slopes or areas of difficult access, gunite
or shotcrete shall be used as the fill material after the cleaning of the surface as specified.
11.5 PLACING
11.5.1 GENERAL
Placing of embankment materials shall be carried out according to the lines, slopes and level as
shown on the Detailed Design and/or Construction Drawings or as directed by the Engineer. The
setting out of the zone limits shall be performed by the Contractor and these limits shall be
strictly observed. The Engineer reserves the right to modify these limits as well as make any
other changes in the dam section as he may decide upon to optimise and/or expedite construction.
The optimum thickness of layers to provide the required degree of compaction and the
specified density of compacted fill shall be determined by the site tests and trials.
The placing methods shall be continuously reviewed by discussion between the Engineer and
Contractor, with the Engineer reserving the right to subsequently modify any arrangements
where this is considered necessary to optimise and/or expedite construction.
The two quality control tests which shall be carried out in situ during construction of the
embankment are the following:
• density tests;
• Sieve Analysis.
The materials shall be placed in such a manner that the top surface of any section under
construction shall remain approximately level.

_______________________________________________________________________________
124
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

The embankments shall be generally raised uniformly in horizontal layers, with variations in
level within and between zones permitted only where essential for the progress of the work
and approved by the Engineer.
11.5.2 WATER CONTENT
The optimal amount of water to be added will be decided on the basis of the site tests and
trials.
11.5.3 INSTRUMENTATION
The requirements for instrumentation within the dam embankment are given in Section 15 of
the Technical Specification and the location of the instrumentation is shown on the Detailed
Design.
The Contractor shall make allowance, in his spreading and compacting operations, for the
works of positioning of the instrumentation and any connecting cables and for avoiding any
damage to this equipment during subsequent works.
11.6 TESTS AND QUALITY CONTROL
During the construction of the trial embankments and the main dam embankment, tests shall
be carried out to measure the achievement of the specified requirements for all zones of the
embankments.
All tests will be specified by the Engineer in advance with sufficient time for the Contractor to
organise the appropriate equipment and personnel.
The standard tests to be performed shall be as follows:
Specific weight: measurement of the density of the material in the laboratory. 5 Samples per
test.
Grading: the grading of soil material samples in the
laboratory and production of grading curves.
Settlement: Measurement of settlement of layers in situ by topographic levels over a defined
grid for each pass of compaction plant. Each test comprises a set of
measurements for each layer and a report on results.
Field Density: excavation to the complete depth of the in situ layers of soil material, the
measurement of the void volume by water contained by plastic sheet lining
and the measurement of the weight of the removed soil material.

The frequency of the tests for each embankment shall be as follows:


NUMBER OF TESTS
TYPE OF TEST
Trial Embankments Dam
Specific Weight 5 25
Grading 5 25
Settlement 5 every layer of zone 1 and zone 2
Density 5 75
11.7 TOLERANCE
The following tolerances to dimensions of the embankment shall be observed in respect of the
finished works:
• Slope of upstream face, Zone 1: H:V ± 0.05:1
• Crest level (including camber): ±5 cm
• Maximum penetration of Zone 1 into Zone 2: 0.5 m in horizontal width

_______________________________________________________________________________
125
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

11.8 MEASUREMENT AND PAYMENT


11.8.1 TRIAL EMBANKMENT AND TESTS
No separate measurement or payment will be made for the trial embankments and standard
tests.
The unit rates for the embankment fill materials shall include for all works on the trial
embankments as specified, together with the regular measurement recording and standard
testing as specified and the reinstatement of embankments after testing.
11.8.2 FOUNDATIONS
The preparation of foundations to the embankments shall be measured as the net area of
surface prepared as specified and the payment under this item will be made at the Unit Price per
square meter entered in the Bill of Quantities which shall include all the works necessary.
For the foundations at the cut off, walls and other structure, conduits, etc., the preparation as
specified shall be measured by the net area of finished surface.
Any additional concrete or shotcrete shall be measured and paid for as similar work covered in
Section “Concrete Work” and Section “Sprayed Concrete” respectively.
11.8.3 EXCAVATED MATERIALS
Where suitable material is obtained from excavations on the Works its use as fill will be
measured separately by volume of such material placed and compacted in the embankment.
The payment for this item will be made at the Unit Price per cubic meter entered in the Bill of
Quantities which shall include costs of excavations (where necessary) loading and transporting
the material from the relevant excavation or disposal area and for its placing, spreading and
compaction in the embankment as specified.
Any work of stockpiling of this material shall also be included for in the unit rates of the placed
material.
11.8.4 EMBANKMENTS
The measurement of quantities of fill in the embankments shall be based on the agreed survey
of the foundation area after its preparation to receive fill. The measurement of the
embankments will be made to the specified lines.
The payment for embankment material shall be made on the basis of the net volume of
compacted material in the embankments, placed in layers of thickness as specified, spread,
water added when necessary and compacted to the required performance criteria, according to
the Unit Prices per cubic meter entered in the Bill of Quantities for the following category of fill
embankment.
The rates shall be deemed to include the entire cost of, but not limited to, the following:
a) the excavation at the specified borrows / quarries including blasting and any
selection at the quarry face, stockpiling, crushing, screening, washing in order to
obtain the required grading, together with all loading and transporting of the
material to the embankments, and the disposal of waste, placing, spreading and
compacting the material as specified herein and directed by the Engineer;
b) any disturbance to the placing and compaction works occasioned by the placing
of the instrumentation system (see Section “Dam Instrumentation”);
c) all delays during embankment works resulting from placing of instrumentation
system and carrying out of standard or special tests;
d) surveying, setting out, checking of embankment profile and alignment, and any
subsequent rectification works resulting from undue or incorrect survey; provision
of suitable equipment for, and delays due to carrying out this work.
11.8.5 EXCLUSIONS
No extra measurement for payment or payment will be made for the following:
a) extra work caused by Contractor's negligence;
b) all costs of dewatering and keeping the foundation surface dry;
_______________________________________________________________________________
126
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

c) surveys to verify the foundation area;


d) extra work or material required to repair damages to the final embankment surface caused
by erosion or travel of the construction equipment;
Any additional work in areas where surface embankment has already been completed, which
the Contractor may be directed by the Engineer to carry out, will be measured and paid for at
the same Unit price entered in the Bill of Quantities as for the original item. No increase in Unit
Price for such additional work will be allowed.
Any alteration or adjustment to the construction methods to be adopted following the results
of site tests or trials, will not allow increasing the unit rates and price for the works unless it has
been demonstrated that the relevant materials or conditions are significantly different from
those that could have been foreseen at tender stage by an experienced Contractor (as defined
in Conditions of Contract).

_______________________________________________________________________________
127
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

12 DAM INSTRUMENTATION
12.1 SCOPE OF WORK
The work to be done under this Section shall comprise the supply of all labour, materials and
plant, except as provided herein, and the performance of all work necessary for supplying and
installing instruments, as shown on the Detailed Design, as required by the Engineer and as
specified herein.
The location of all instruments shall be as shown on the Detailed Design or as otherwise
required by the Engineer.
12.2 SUPPLY
1) The instruments and equipment shall be assured to be of high quality, realized according to the
best practice and according to international standards prescriptions. It shall be manufactured
by well known reputable international company, with experience in large dam instrumentation.
2) All the instruments and equipment shall be subject to Engineer’s acceptance procedure of
inspection and testing at their arrival at dam site. The verification of the material shall be in
accordance with the manufacturer’s specifications.
3) Acceptance of the instrumentation devices (sensors, cabling and communication facilities) after
installation, is to be subject of special procedures to be defined by the manufacturer/supplier
and agreed with the Engineer. The proper functioning of every instrument, and satisfactory
cabling and all connections to junction boxes, data loggers, computers and relevant
identifications, is to be checked carefully. In case of malfunction the faulty instrument or
connection shall be replaced.
4) Activities of supplying, testing, calibrating, installing and commissioning of the monitoring
system shall be provided with by supplier’s skilled and qualified personnel, under the
Contractor’s coordination.
5) All instruments and equipment shall be accompanied by documents providing the following
information:
a) Technical documentation (purpose of instrument, principle of measurement general
characteristics and performances in terms of accuracy, sensitivity, range, etc., in
compliance with these Technical Specifications).
b) Proceeding for installation and use (list of materials and tools needed for installation,
detailed procedure of installation, calibration, use and results interpretation of the
instrument, measurement forms and files, etc.).
c) Calculations and interpretation results (calibration curve, calculation formula and
form, example of calculation).
d) Acceptance and maintenance instructions (detailed proceedings of the instrument’s
acceptance, calibration and tests procedures, frequency of calibration where neces-
sary, list of recommended spare, identification and description of possible failures,
breakdown indicators, etc.).
12.3 INSTALLATION
1) All work in connection with the installation of instrumentation shall be done under the direct
supervision of the Engineer. Every precaution shall be taken to ensure that installations are true
and plumb and that the various instrumentation components are in no way damaged.
2) The Contractor shall protect all instruments and connections from damage and displacement
during the progress of the work, and markers and barricades shall be provided as required by
the Engineer. Any damage to, or displacement of, the instruments and connections shall be
repaired immediately to the satisfaction of the Engineer, at no additional cost to the Employer.
3) Tubes shall be installed without joints in the maximum lengths practicable as determined by the
Engineer and where necessary, splicing and coupling shall be performed in accordance with the
_______________________________________________________________________________
128
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

manufacturer’s requirements. Open ends of all incomplete lines of tubing and casing shall be
kept capped and the Contractor shall, at all times during installation, keep the insides of casing
and tubes free from foreign matter. All tubing shall be flushed and pressure tested after
installation of each section or joint, and prior to backfilling.
4) The methods and procedures for installation of instruments shall be in accordance with the
various manufacturer’s instructions and under the supervision of the supplier’s representative.
5) Cabling installation shall be done where prescribed according to the manufacturer’s
requirements, disposing the cables in pits and galleries (where necessary encased in sleeve
pipes) in safe and stable location.
6) Such works shall be carried out as and when required by the Engineer and in any stages as may
be necessitated by the progress of the construction of the Dam embankment.
7) Instruments shall be provided, where necessary, with protective device against lightning and
associated over voltage.
12.4 TYPE OF INSTRUMENTS
The instrumentation systems to monitor the behaviour of the Dam embankment and the
reservoir levels will be as follows and the approximate quantity and probable locations are
shown on the Detailed Design. This specification covers the supply, installation and/or
construction of the dam safety instrumentation systems for the, dam embankment and their
foundations, survey and water level recorder instrumentation.
For the purpose of this Contract, the following instrumentation shall be installed:
I. Weather station
II. Radar Level Meter
III. Reservoir water level staff
IV. Seepage flow weir.
V. Open standpipe piezometer
VI. Vibrating wire piezometer
VII. USBR settlement gauge
VIII. Inclinometer
IX. Target (Levels)
X. Automatic total station
XI. Meteorological Station
XII. River gauge and discharge station
XIII. Data acquisition units

I. WHETHER STATION
1) The Contractor shall be responsible for providing a fully equipped automatic weather station to
be located within the drainage area subject to approval by the Engineer. The weather station
shall be able to measure the following climate parameters:

(a) Rainfall and duration of storm


(b) Real time evaporation
(c) Real time ambient temperatures
(d) Maximum temperature
(e) Minimum temperature
(f) Real time wind speed and wind direction
(g) Real time humidity
(h) Real time pressure
(i) Cloud height.
2) Apart from the instrumentation requirements, the weather station will have to be provided

_______________________________________________________________________________
129
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

with the following:

(a) The weather station will receive power from a solar panel connected in parallel
with rechargeable batteries. Solar output should be at its optimum for minimum
5 hours a day
(b) A mast minimum 10m high
(c) The weather station instruments will be provided with data loggers and will have
the facility to be upgraded to send real time data to a central operations station
(d) The weather station instruments will be protected against lightning strikes
(e) The weather station will be fenced in by a 2 m high vandalized-free hot-dipped
galvanized steel security palisade fence with a 1.0 m wide gate of similar height
that can be locked with Chubb security lock. The fence will be constructed on a
300 mm wide x 400 mm deep Grade of reinforced concrete foundation. The
foundation shall protrude 100 mm above the surrounding ground level. The
palisade fence poles shall be of robust design and no member of the fence will
have a thickness of less than 3.0 mm. The bottom of the palisades shall not be
more than 50 mm above the concrete foundation. The plan dimensions of the
fenced area and height will not negatively impact on the automatic weather
station manufacturer’s clear distance requirements for safe operation.
(f) All instrument read-out points will be housed in a properly designed structure of
which the floor, roof and walls are all constructed with suitable Grade of
concrete. The Contractor will be responsible for the design of the structures
which shall be submitted to the Engineer for approval. These structures will all be
provided with lockable Grade 304 stainless steel plate doors and frames.
(g) All enclosures to be the highest grade of stainless steel provided by the
manufacturer.
3) The Contractor is required to submit a method statement to the Engineer, prior to
commencement of this part of the works for the supply and installation of the automatic
weather station in accordance with the above specification. This should include manufacturer’s
details, technical specifications a priced bill of quantities and drawings. The Engineer shall
assess the method statement in conjunction with the Employer. The Contractor shall only
proceed with construction upon approval by the Engineer.

II.RADAR LEVEL METER


Use:
A radar water level measurement device shall be installed in proximity of the spillway in the
position shown in the Detailed Design and as directed by the Engineer.
Technical description:
The instrument must be connected to the Control Room for automatic data acquisition and
transmission and must respect the following specifications:
• Measurement field : 20 m
• Feeding : 9,6-36 V
• Accuracy :  2 mm
• Sensitivity : 1 mm
• Temperature Range : -40° to 80°C
• Pressure Range : -1 to +2 bar
This instrument will be installed to measure the water level in the reservoir until the elevation
+1359 msl. Below this elevation the water level in the reservoir will be measured by one
piezometric water level measurement device.

_______________________________________________________________________________
130
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

PIEZOMETRIC WATER LEVEL MEASUREMENT DEVICE


Use:
One vibrating wire piezometer will be installed on the u/s dam face to measure the water level
in the reservoir in the positions indicated in the Detailed Design and according to the Engineer’s
instructions on site. This device is able to measure the level when reservoir water level is below
+1359 msl.
The instruments must be positioned in a suitable pit at a level lower than the minimum
reservoir level so that they are always submerged and must be linked via cable to the data
acquisition instrumentation situated on the dam crest for transmission and recording of data.
Technical description:
The vibrating wire piezometer shall have the following basic characteristics:
• Accuracy: ±0.5% Full Scale
• Resolution: 0.025% Full Scale
• Temperature Range: -20° to 80°C

III. RESERVOIR WATER LEVEL STAFFS


Use:
This instrument is aimed at indicating the reservoir levels by means of elevation direct reading
on a sign.
The water level staffs must be installed as shown on the Detailed Design for optical reading of
the water level in the reservoir.
The position of the water level staffs must allow the maximum visibility from several
observation points and will be agreed together with the Engineer.
The Contractor shall ensure that the water level staffs are fixed in a solid manner to the
Engineer’s satisfaction.
Technical description:
Reservoir level measuring staff will be enameled iron plates 180 x 1000 mm (combined to
obtain the total depth of the reservoir and suitably disposed to record the river tail water level)
the elevation character will be 400 x 800 mm. with 100 mm resolution in height, and elevation
marking each 2 m of elevation.
Staff Gauges shall be rust resistant, corrosion or discoloration from the water and any other
environmental agent.
Staff Gauges shall be marked in metric units, with graduation marks every centimeter and
showing every decimeter with alternate black and white 10 cm high bands. The staffs shall be
located in places where water movement does not affect the level and where they can be easy
read.

IV. V-NOTCH FLOW MEASUREMENT WEIR


Use:
The purpose of the weirs is to measure seepage water through the dam and from the
foundations of the dam. Two (2) V-notch weirs shall be installed at downstream toe drain as
indicated in the Drawings or as directed by the Engineer.
The flow measurement devices must be installed in respect of the following specifications and
according to the Engineer’s instructions on site.
Technical description:
It is composed by a movable sharp-edged stainless steel plate (about 450 x 600 mm) provided
with a 30° or 90° triangular opening for low and medium flows, or with an upper rectangular
opening for large flows, installed in the existing reinforced concrete manholes.
It is composed by a movable sharp-edged stainless steel plate (about 450 x 600 mm) provided
_______________________________________________________________________________
131
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

with a 30° or 90° triangular opening for low and medium flows, or with an upper rectangular
opening for large flows, installed in the existing reinforced concrete manholes.
The plate slides into a milled guide, which is anchored by bolts to the drain gutter walls with the
interposition of a rubber gasket to make the coupling water tight.
Otherwise, a steel frame is bolted to the drain gutter walls. On its upstream side, the frame is
coupled with a rubber gasket: the plate is juxtaposed to the frame and water tightly anchored
by clamps.
The V notch shall be removable, being equipped with a steel handle. According to the
measurement volume it shall be possible to change the V-notch type ( 30° triangular shape, 90°
triangular shape, rectangular shape) inserting it in the milled guide.
Graduated gauge staff are installed at each V-notch for water level measurements, as described
at above.
The graduated gauge staff instrument shall allow the reading of the water level with ±1
millimeter accuracy.
The flow shall be then calculated from the u/s level readings.
The range of flow for which the instrument can work shall be provided by the supplier in the
flow- level curve characteristic of the v-notch, and shall be at least:
• Min. Range: from 0 to 15 l/s (30° triangular shape)
• Min. Range: from 0 to 43 l/s. (90° triangular shape)
• Min. Range: from 0 to 120 l/s. (rectangular shape)

V. OPEN STANDPIPE PIEZOMETER


Use:
Twelve (12) standpipe piezometers shall be installed along the downstream the dam axis and in
the downstream berms as shown in the drawings to measure and monitor the uplift pressures,
seepage and the water table level.
Technical description:
The standpipe piezometer consist of a 100 mm diameter hole drilled by rotary drilling (with or
without core recovery as instructed by the Engineer) until a depth of 15 m beneath the
foundation level as instructed by the Engineer. The hole shall host a 54 mm diameter PVC pipe.
The last 4 m of the PVC pipe shall be slotted and a layer of geotextile shall be applied around
the slotted bottom pipe over a length of 4 m.
The space between the pipe and the hole shall be filled with a water cement grout with an
expanding agent over the entire length except for the bottom 4 m where it shall be filled with
sand. The Contractor should verify is the bottom of the hole is stable.
The pipe must be straightened and fitted inside the hole with extreme care so that the pipe is
not bent, broken or damaged any way.
The depth of the sand should be measured and confirmed prior applying the grout.
After verifying that the pipe is installed properly and the sand has been applied to the correct
depth, all to the Engineer’s approval, a small quantity of the grout material should be applied.
This amount of the grout must be allowed to initially set so that a proper seal is formed before
applying the rest of the grout over the reminder of the hole’s length. This will ensure that the
grout will not penetrate the sand at the bottom of the hole.
To complete the installation a small concrete slab and a protective cap with a 3 way connector
with 2 valves one of which is fitted with a manometer shall be foreseen.
In the case of any deviation from the process described above, the Contractor should, at his
expanse, repeat the installation and construction process accordingly as specified herein
subject to the Engineer’s approval.
The Contractor shall execute extreme care during construction process so that the pipe or other
apparatus are not damaged in any way.
_______________________________________________________________________________
132
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

The water level should be read by portable acoustic water level meter and automatically with a
vibrating wire piezometer inserted in the standpipe. In case of the water is pressurized in the
piezometer, the pressure will be measured by a manometer device.

VI. VIBRATING WIRE PIEZOMETER


Use:
For the observation of pore water pressures within the dam foundation, twelve (12) vibrating
wire piezometer shall be installed in boreholes as shown in the Drawings or directed by the
Engineer.
The requirements of this Specification include the supply of pore pressure meters with cables
and ancillaries, the installation of the meters and cables during construction of the dam, the
connection of the cables to the monitoring terminal and monitoring of the pore water
pressures.
Vibrating wire piezometers shall be installed within the raised portion of the main
embankment, within the foundation. Locations will be indicated on the drawings.
Technical description:
The VW piezometer consists of a vibrating wire sensing element enclosed in a protected
stainless steel housing.
The sensing element shall be hermetically sealed.
The pressure cell shall be protected from surrounding material with a specific porous filter with
openings of 0.02 mm.
All the parts of the sensing element, other than the wire, shall be made of stainless steel.
The VW shall be fitted with a surge protector and resistant to electrical and radio frequency
interferences.
It shall be designed to withstand a max pressure of 10 bar (100 m water pressure) with an
accuracy of ± 0.1 % F.S and resolution 0.025% F.S. Temperature Range -20° to 80°C.
The vibrating wire piezometers shall be installed in a slotted PVC pipe 60 80 borehole
atprotected by a REPS type net in an appropriate/specified locations according to the
drawings, and, where multiple installation is required, preferably in close but separated
boreholes/places.

VII. USBR SETTLEMENT GAUGE


Use
Three (3) USBR settlement systems shall be installed in the dam embankment as shown in the
drawings to measure and monitor settlement and deformation in the dam embankment.
The USBR settlement gauge must be installed in respect of the following specifications and
according to the Engineer’s instructions on site.
Measurement is performed using a special probe and its stainless steel tape graduated in
centimetres, with precision vernier; measurement is facilitated by a suitable device with a
winch.
The USBR settlement system is the most robust and reliable system for monitoring settlement
during the construction phases of embankments.
Technical description:
The system is constituted by a column of tubes of two different diameters, partially inserted
one into the other and able to slide like a telescope (it is constituted by an access pipe with
telescopic sections). On the smaller diameter tube, steel profiles are anchored and fixed to the
ground, these form the measuring point for each layer.
The system will consist of:
• Bottom element: tubular element in galvanized steel, blind, with bottom device
for the recovery of the probe (standard Length =1.5m):;
_______________________________________________________________________________
133
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

• One head Element: Tubular element in stainless steel, complete with special head
for the application of different measuring devices (standard Length = 1m)
• Intermediate Element: Two tubular elements in galvanized steel to form a column
element with a length of 1.5 ÷ 1.7 m; other dimensions available on request
• USBR Probe: in stainless steel
• Dimensions:
➢ Diameter = 35mm;
➢ Length = 225mm
• Tape holder support: in steel and varnished and galvanized brass, complete with
locking bush to the settlement column
• Measuring Tape: Stainless steel, L=50m or L=100m

VIII. INCLINOMETER
Use:
A total number of 3 inclinometers shall be installed in the embankment at each cross section as
shown in drawings in order to monitor movements in the embankment.
The Inclinometer must be installed in respect of the following specifications and according to
the Engineer’s instructions on site.
The control system is generally composed of multiple IPI sensors, connected to each other via a
single cable for the version with output signal, or with independent cables for the version with
analogue output, inserted into an inclinometer column which forms the reference element and
guide for the entire system.
Thanks to the pairs of guide wheels on the body of each instrument, the chain is lowered into
the column, bringing the various sensors in the chain to the pre-established level.
The inclinometer column follows the ground’s movements, consequently causing a change in
inclination of the individual IPI sensors which automatically provide data revealing the
deformation of the column.
Technical description:
The inclinometer shall have the following basic characteristics:
• Range:
➢ X=Y=±15° (digital)
➢ X=Y =± 5° or ±20 ° (analogue)
• No linearity : (digital) ±0.0125% f.s. (±0.002°) (0.03 mm/m)
• Diameter of the probe
➢ 25.4 mm (digital)
➢ 30 mm (analogue)
• Length of the probe
➢ 710mm (digital)
➢ 1400 mm (analogue)
• Weight of the probe : 1,2 Kg
• Material of the probe : Stainless steel
• Resolution of data : 0.001
• Accuracy : +/- 2mm for 25m
• Temperature : -40 up to 70 °C
• Type of the sensor : MEMS Accelerometer, biaxial type

IX. AUTOMATIC TOTAL STATION


Use:
One automatic totals station shall be foreseen to monitor the dam displacements with respect

_______________________________________________________________________________
134
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

to reference point located outside the dam. The system will be composed by:
• No. 1 automatic total station;
• About 28 targets installed on the dam crest and on the downstream face of the
dam;
• No 1 concrete pillar downstream the dam.
All targets shall be installed on a concrete footing according to the Engineer instructions. An
identification number and other details of the beacon will be inscribed on each concrete
footing.
Bi reflex targets: A convergence bolt made of 12mm x 170 mm galvanized steel rebar with SS
threaded stud shall be securely attached to the exposed rock or shortcrete surface. The bolt
shall be provided with a plastic cap with a breaking point serving as an adopter for the
mounting a reflector with a marked centre point. This device shall be designed for high
precision measurements with two axis of rotation and to be observed from both sides. The
manufacture accuracy must be better than +0.1mm to achieve an overall accuracy +/- 1mm
within the measuring section.
Technical description:
• Angle measurement:
➢ Accuracy: 0.5”;
• Distance measurement:
➢ Range 1.5 m to 3500m
➢ Accuracy 0.6 mm + 1ppm
• Long Range Automatic Aiming (ATR):
➢ Range ATR mode 1500/3000m
➢ Accuracy 0.5”;
X.DATA ACQUISITION UNITS
1) All instruments or sensors shall maintain the ability to be read manually or by portable Data
Acquisition Units before entering the network.
2) Where necessary, according to design drawings and manufacturer’s instructions, the automated
instruments shall be provided with:
• data base management computers and software
• power supply
• measurements records communication and transmission systems
3) The instrumentation supply shall include, where necessary, the whole set of cabling (individual
cables to de-centralized data loggers, communication cables, power supply cables), that shall be
provided in order to assure a proper, durable and safe connection and functioning according to
the manufacturer’s requirements and to the international standards prescriptions.
4) The connection, where required, shall be extended up to the control panel dedicated to the
visualization and acquisition of all records.
5) The layout and disposition of the control panels and relevant connection systems (supply,
communication and transmission) shall be fixed by the Contractor according to the type of the
measurements and to the manufacturer’s instructions, taking into account the need of reliable
and easy control and elaboration of the acquired data, to monitor in good time the dam
stability.
6) A specific automated data acquisition system (ADAS) shall be installed before the impounding
of the dam for the following measurements:
• Piezometers
• Water level indicator and data loggers
• Reservoir level recorder
• Meteo Station

_______________________________________________________________________________
135
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

7) This automated system will have a central network monitoring station to manage the field
system, collect and store the data in electronic format, print the data and relevant graphs, and
provide an external communication interface.
8) Cabling for this system will be installed through dam galleries and shafts up to reaching the
location where the acquisition units will be installed.
12.5 USE OF INSTRUMENTS
1) The Contractor shall take records of the data to be obtained from all the instruments to monitor
the behaviour of the Works during the construction, impounding and commissioning periods.
2) During the construction period it shall be possible to monitor the data recorded by the
instruments already installed, collecting and gathering the data directly at instrument’s location
by means of portable PC and/or portable devices.
3) Type of records, duration (continuous or spot measurements), filing and elaboration of all the
measurements shall be defined by the Contractor in the Operation and Maintenance Manual of
the Plant, in compliance with the manufacturer’s instructions.
12.6 MEASUREMENT AND PAYMENT
1) Measurement for payment of the Dam Instrumentation shall be made by number of the
particular instrument installed as shown on the Drawings and as directed by the Engineer.
2) Payment for the Dam Instrumentation shall cover purchase, delivery to Site, installation in
accordance with suppliers instruction and protection until completion of the maintenance
period, and payment will be made at the Unit Price for the following items entered in the Bill of
Quantities.
3) Any services by the Contractor, on the instructions of the Engineer, for using the
instrumentation systems and recording results shall be deemed to be included in the payments for
operation of the Site Testing Laboratory.

_______________________________________________________________________________
136
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

13 ROAD WORKS
13.1 GENERAL
1) The dam site area is accessible from Mbarara by a road of 90 km approximately length. The first
65 Km stretch is the road Mbarara-Kikagati, which is paved and in fair conditions and seems
indicated for heavy vehicle traffic. The remaining 25 Km, from the branch out from the main road
Mbarara-Kikagati, must be rehabilitated. The road shall be enlarged and stabilized in order to
transport heavy construction materials and machineries.
2) The Contractor must build a permanent road approximately 2 km long, including the access to
the dam site, to the management’s camp, to the raw pumping stations and the road running
from the dam site to North on the left side of the river, about 190 m, and inundated by the
reservoir.
3) The Contractor must also build the additional temporary roads that he deems necessary, and
maintain the road system for the entire duration of the works.
13.2 PERMANENT ROADS
13.2.1 GENERAL
1) Permanent roads relevant to this Contract are shown on the Detailed Design and include:
a) the access Road to the dam, coming from the junction with the Mbarara-Kikagati
road in proximity of the Kikagati;
b) the access road to the management’s camp and to the raw pumping stations.
2) The Contractor shall:
a) build the permanent road which connects the dam, the management’s camp and
the raw pumping stations
b) rehabilitate to the road reaching the dam and appurtenances structures from
Mbarara- Kikagati road;
c) build the temporary roads deemed necessary for the execution of the works;
d) maintain these roads for the entire duration of the work.
3) The detailed design of the additional permanent roads shall be prepared by the Contractor, on
the basis of general arrangement drawings shown on the Detailed Design and submitted to the
Engineer for approval.
13.2.2 SCOPE OF WORK
1) This section covers all labour, materials, equipment and services required for the construction of
the permanent roads.
2) Work related to the roads, such as excavation, culverts, drain ditches, retaining walls, slope
protection etc. is covered by the respective sections of these Specifications.
3) Work for the pavement construction shall include the following elements:
a) Excavations and construction of the road embankment
b) Construction of sub-base
c) Construction of base course
13.2.3 CONSTRUCTION MATERIAL SOURCES
1) The materials for sub-base and base course shall be obtained from the excavation of the works
and from the approved borrow and quarry areas. Materials shall be composed of hard, dense,
durable particles in conformity with the quality specified for concrete aggregates.
2) All sub-base and base materials shall be approved by the Engineer.
13.2.4 SUB-BASE MATERIAL
1) The material shall meet the following grade requirements:
US Standard Sieve Percentage by Weight Passing
3" 100

_______________________________________________________________________________
137
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

2½ 90-100
No.4 35-70
No.200 0-20

2) If the material does not contain a sufficient quantity of natural cementitious material to bond
readily under the action of traffic, there shall be added to, and incorporated in it, a binder
consisting of rock screening or other cementitious materials. The sources from where the
binder will be obtained, together with the method to be used for adding it to the sub-base
material, will be approved by the Engineer.
13.2.5 BASE COURSE MATERIAL
1) The material shall meet the following grade requirements:
US Standard Sieve Percentage by Weight Passing
1½ 100
3/4 50-75
No.4 25-50
No.200 0-12

2) If the material does not contain a sufficient quantity of natural cementitious material the
Contractor shall add a binder as previously specified for the sub-base.
13.2.6 SUB-GRADE PREPARATION AND COMPACTION
1) The areas to be covered with aggregate shall be carefully cleaned so that no objectionable
material shall be incorporated in the future aggregate course.
2) If necessary, the surface which will be in contact with the aggregate course shall be so treated as
to fill the fissures, cavities, pockets, hollows and depressions.
3) The sub-grade shall be made to conform to prescribed lines and grades, and the loose material for
a thickness of 30 cm shall be compacted to 95% of the maximum dry density, or as directed by
the Engineer.
13.2.7 PLACING
1) The surfacing materials shall be spread on the prepared sub-grade to such depth that, when
thoroughly compacted, it will conform to the prescribed grades and dimensions. Segregation of
coarse and fine particles shall be avoided, and any segregation material shall be remixed by
harrowing and blading.
2) The depositing and spreading of the material shall start at the point nearest to the point of
loading and the Contractor shall route the hauling equipment over the surfacing material
already in place and shall distribute the travel evenly over the entire width of the surfacing so as
to distribute the compacting effect of the equipment.
3) The hauling and spreading shall be accompanied by blading and/or dragging, and the surfacing
shall be free from corrugations and waves. If necessary, to produce proper compaction, water
shall be incorporated with the surfacing material, either at the source or after it is spread on
the roadway, at the option of the Contractor.
4) The method of incorporating water in the surfacing material shall be subject to the approval of
the Engineer.
5) Immediately following final spreading and grading, each layer shall be compacted to full width by
means of smooth wheel power rollers or pneumatic tired rollers.
6) The compaction corresponding to each layer of compacted sub-base and base material shall not
be less than obtained with 5 complete passes of a smooth-wheel vibrating roller of 8 tons
minimum weight.
_______________________________________________________________________________
138
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

7) Rolling shall progress gradually from the sides to the center, and shall continue until the whole
surface has been rolled. Any irregularities or depressions that develop shall be corrected by
loosening the material at these places and adding or removing material until the surface is
smooth and uniform. Along curbs, header and walls and at all places not accessible to the roller
the base material shall be tamped thoroughly with mechanical tampers.
13.3 MAINTENANCE
1) The Contractor shall be responsible for the maintenance of all permanent and temporary roads on
the Site that he will construct or improve until the completion of the Works.
2) The Contractor shall maintain the roads in such a way that the surface never has undulations,
hollows ruts or other damages which limit the speed of the vehicles.
3) Unpaved roads shall be frequently sprayed with water during the dry weather season to
prevent the formation of dust clouds.
13.4 TEMPORARY ROADS
1) The Contractor shall design, construct and maintain all temporary roads, bridges, parking areas
and other access facilities within the site that he deems necessary for the construction of the
Works, including all borrow, quarry and stockpile areas. Where necessary, the roads shall be
wide enough to allow heavyweight traffic in both directions. To prevent excessive erosion, no
steeper longitudinal slopes than 10% shall be designed, except when specifically approved by
the Engineer.
2) Except where rock is encountered, the back slopes of cut banks shall be stable and compatible
with existing topography, and shall be flattened and rounded as far as practicable into natural
ground surface.
3) The Contractor shall construct suitable drainage structures in sufficient numbers to prevent
accumulation of excessive water and erosions along the roadways.
4) Roads shall be frequently sprayed with water during the dry weather season to prevent the
formation of dust clouds. Site roads shall be graded as necessary to ensure a firm and even
surface.
5) Upon Completion of Works the temporary construction roads shall be turned over to the
Employer. Those roads which the Employer does not choose to keep shall be made impassable to
vehicular traffic and the surfaces shall be scarified and left in a condition which will facilitate
growth of natural vegetation, removing the granular material, if any.
13.5 MEASUREMENT AND PAYMENT
13.5.1 PERMANENT ROADS CONSTRUCTION
13.5.1.1 Earthmoving and Structures
1) Measurement and payment for the clearing, grubbing, excavation, fills, backfill, concrete works,
culverts, supports and slope protections will be made in accordance with the corresponding
sections of these Specifications.
2) All costs of de-watering and keeping the sub-grade surface dry during construction will be
included in the unit price for excavation.
3) No extra payment will be made for the preparation of the sub-grade and protection or
maintaining excavated surfaces in satisfactory conditions until the sub-base is placed, and the
cost thereof shall be deemed to be included in the unit prices for the materials to be placed
upon it.
13.5.1.2 Sub-base and Base Course
1) Measurement for payment of sub-base and base granular material, including that for shoulders,
will be of the in-situ volume of the material placed and compacted.
2) Payment will be made at the appropriate unit prices per cubic meter entered in the Bill of
Quantities, which shall include the entire cost of, but not limited to, the following:

_______________________________________________________________________________
139
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

a) Excavation in the borrow and quarry areas including all clearing, grubbing and
stripping in, and trimming, levelling and draining thereof, as stipulated in the Section
"Excavation and Filling"
b) Provision of all labour, equipment and materials required for the preparation,
segregating, grading, blending and mixing, wetting or drying of the materials in order to
obtain the required gradation, moisture content and other properties
c) Loading the materials in the borrow and quarry areas, processing plants, or in
stockpiles including any rehandling of suitable materials from the required excavations
d) Transport of materials from the source to the final location
e) Provision of all labour, equipment and materials required for the placing, spreading,
compacting watering or reduction of the water content as needed of the materials
f) Quality control and performance of tests as required
g) Surveying, setting-out, checking of profile and alignment, and any subsequent
rectification works resulting from undue or incorrect surveys, provision of suitable
equipment for, and delays due to carrying out this work.
13.5.1.3 Exclusions
No extra payment will be made for the following:
a) Extra work caused by the Contractor's negligence in setting out the structures and
slopes
b) Rectification, removal and replacement of the materials which during the placement
or afterwards have been contaminated with foreign matters, mixed with unsuitable
materials, or lost due to erosion
c) Extra work or material required to repair damages to the temporary or final surfaces
caused by erosion or travel of the construction equipment
d) Stockpiling, rehandling, reloading and transport of materials which cannot be directly
placed in the final locations after being excavated
e) Damages to concrete structures caused by Contractor's operations
f) Additional passes of the compacting equipment ordered by the Engineer if he
determines that a higher degree of compaction than specified is required.
13.5.2 PERMANENT ROADS MAINTENANCE
Payment for permanent road maintenance will be made at the unit price entered in the Bill of
Quantities per month, which shall cover all labour, construction equipment and materials for
satisfactorily maintain all roads.
13.5.3 TEMPORARY ROADS CONSTRUCTION
1) Payment for construction of the temporary roads will be made as Lump Sum entered in the Bill
of Quantities, which shall cover all labour, construction equipment and materials for carrying
out all necessary works.
2) Payment of the Lump Sum will be made according to the actual construction progress obtained
dividing the total amount by the total length shown on the Contractors approved drawings and
multiplying for the works done in the month corresponding to the statement of account.
13.5.4 TEMPORARY ROADS MAINTENANCE
1) Payment for maintenance of the Temporary Roads will be made at the Lump Sum entered in
the Bill of Quantities, which shall cover all labour, construction equipment and materials.
2) Payment of the Lump Sum for maintenance will be made in equal monthly installments for each
of the month during which the facility is maintained by the Contractor according to the
Contractor's approved detailed construction schedule. Each monthly installment will be
calculated as the total Lump Sum divided by the number of months of maintenance according to
the Contractor's approved construction schedule.
3) In the event that the Contractor is entitled to an extension of time for the Completion of Works,
the payment will continue at the same rate per month as stipulated above.

_______________________________________________________________________________
140
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

14 MISCELLANEOUS and ANCILLARY WORKS


14.1 SCOPE OF WORK
This section covers all labour, materials, equipment and services required for the following
Miscellaneous items necessary for minor construction works and finishing:
• Roofing
• Plastering
• Painting
• Flooring and Tiling
• Windows and Doors
• Ceilings
• Plumbing
• Electrical System
• Water Treatment Plant
• Demolitions of structures
• Non-shrink grout for the installation of permanent equipment where shown on
the Drawings
14.2 ROOFING
The works covered by this sub section shall include the complete delivery of materials, their
temporary storage and protection on Site and the execution of all roofing together with
ancillary works.
The climatic conditions on Site shall be taken into account with regard to wind force,
impermeability and corrosion protection.
Roofing work by means of corrugated steel sheets shall be carried out as shown on the Drawing
or as directed by the Engineer.
Supports to steel sheet roofing shall be in steel, either in the form of trusses or beams.
14.3 PLASTERING
The work covered by this sub section shall include the supply and storage of all materials and
the execution of the plastering work, its protection and final cleaning up as indicated on the
Construction Drawings, or as directed by the Engineer.
The completed work shall be covered and kept damp until final setting has taken place.
The required mortar shall be mixed from clean aggregates, free of organic matter, and first
quality building lime with an admixture of cement, or shall consist of pure cement mortar,
as required.
Mixed mortar shall be stiff and shall not flow from the trowel. Prepared mortar which is not
immediately applied cannot be used again and shall be rejected.
The materials of mortars shall be measured out in their correct proportions and shall first
be thoroughly mixed together in a dry state until they are of a homogeneous appearance in
consistency and colour.
Clean water shall then be added while the mixture is being turned over until it attains a
suitable consistency.
Mixing by hand will be allowed only if the Engineer gives specific approval. Mixing by
machine, using the same sequence of operations described above shall be carried out
whenever possible.
Surfaces to receive plaster shall be properly cleaned and the surfaces shall be moderately
wetted shortly before applying plaster.
All internal plastering shall be finished to an even and polished surface with a float, trowel
or other suitable tool, special care being taken to obtain perfectly smooth and glazed faces.

_______________________________________________________________________________
141
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

Finished plaster work with cracks, blisters, discolouration or similar defects will not be
accepted and shall be removed and replaced to the Engineer's satisfaction.
Patching of defective surfaces shall only be carried out with prior approval of the Engineer.
Windows, doors, their frames and glazing, floors, fittings, and all other building
components shall be protected against soiling and damage before starting plastering.
14.4 PAINTING
14.4.1 GENERAL
The works covered by this sub section shall include the supply and storage of all material and
the application of all paint work as shown on the Construction Drawings or as directed by the
Engineer, including protection and finish painting of metal surfaces, except those metal surface
specified under the Technical Specifications for Permanent Equipment supplied by others.
All interior surfaces of ceilings and interior and exterior surfaces of walls shall be painted as
shown on the Detailed Drawings or as directed by the Engineer.
The Contractor shall provide all labour, materials, supplies, equipment and scaffolding to
perform all operations necessary to complete the work.
All painting work shall be applied strictly in accordance with the Manufacturer’s instructions
and only under favourable atmospheric conditions.
Paint shall be delivered in undamaged original containers bearing the Manufacturer's
trademark, colour, instructions for storage, handling and application. Paint shall be kept in
closed original containers until used.
The Contractor may choose the method for paint applying (manual or spraying) but a skillful
performance shall be guaranteed, excluding soiling of adjacent parts. Where damage due to
spraying may occur, paint shall be hand applied.
The Engineer may direct the method to be used to achieve the required results to his
satisfaction. Surfaces to be painted shall be thoroughly cleaned and be dry before applying any
paint. Metal parts shall be cleaned of rust by sandblasting where directed by the Engineer.
Previously primed surfaces, soiled with oil or grease shall be cleaned without affecting the
quality of the primer.
14.4.2 MATERIALS
1) The painting materials shall be of quality as available from CARBOLINE COMPANY (USA), or
KELLER (Switzerland), or SIKKENS (Holland) or an equally qualified supplier.
2) Colour of paints shall be in accordance with the colour schemes selected by the Engineer. Exact
tones of the colour selected shall be in accordance with the samples supplied and applied on
test areas in the Works approved by the Engineer.
3) All paint materials shall be delivered to the Site in their original containers, with labels intact
and seals unbroken. All paints shall be of well known registered brands.
4) All tinting colours and thinning materials shall be of the same brand as the oil paint specified for
the particular area. Tinting colours for oil paint shall be colours-in ground in pure linseed oil for
the best grade.
5) With the exception of ready mixed materials in original containers, all mixing shall be done at
the Site.
6) The Contractor is responsible to ensure that the storage and handling of paint material
complies with the requirements of pertinent codes and fire regulations. Proper containers
placed outside of the building shall be provided and used for painting wastes, which shall be
properly disposed of or removed from the premises at the close of each days work. No
plumbing fixture shall be used for this purpose.
14.4.3 PREPARATION OF SURFACES
1) Concrete and masonry work shall be left to cure for one month and any surface defects
repaired before painting.

_______________________________________________________________________________
142
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

2) Cracks, holes and other defects in plaster shall be filled or patched with an approved filling
compound. The filling shall finish flush with and in the same plane as the adjoining surface.
Where patches in cement plaster are required, the surfaces shall be coated with an approved
bonding agent, the defects filled with an approved mortar mix for patching, and the patched
areas finished to match the texture of the cement plaster. Plaster surfaces that will be painted for
the first time shall be uniformly coated with a solution composed of 1 kg of zinc sulphate to 41
of water, to which shall be added 28 g of dry sienna to each 41 of zinc sulphate solutions, 24 hours
after application of the zinc sulphate solution, the surfaces shall be thoroughly washed with
clear water and allowed to dry thoroughly.
3) Metal welds and blisters shall be ground and sanded smooth, pits and dents filled and
imperfections corrected so as to leave a smooth surface.
4) Metal surfaces to be painted shall be clean and thoroughly dry before painting. Prior to
painting, black steel surfaces shall be sand-blasted down to rust degree SA 2-112 according to
SIS-standard 055 900, to remove all mill scale, weld splatter, rust and any other deleterious
material. Oil and grease shall be removed by an approved solvent. The surface shall be wiped
clean of any dust prior to priming.
5) The Contractor shall be responsible for and shall rectify any surface finish which in the opinion of
the Engineer is unsatisfactory to receive paint.
14.4.4 WORKMANSHIP
1) All paint shall be applied by brush unless spray painting or other method is specifically
approved by the Engineer.
2) Material shall be applied in accordance with the manufacturers printed directions. Any thinning
that may be required shall be added only with the approval of the Engineer and then with an
approved type of thinner and in the amount recommended by the paint manufacturer.
3) One liter of paint as originally supplied by the manufacturer shall not cover a greater area when
applied by spray gun than when applied unthinned by brush. Deficiencies in film thickness shall
be corrected by the application of additional coat(s). Application on masonry surfaces may vary
according to surface texture but in no case shall the manufacturers coverage rate be exceeded.
On porous surfaces, it shall be the Contractor’s responsibility to achieve a finish comparable to
the manufacturers coverage rate by decreasing the coverage or applying additional coats of
paint.
4) Painting shall be equal in quality to the samples as submitted to and approved by the Engineer.
5) The Contractor shall remove all lighting fixtures, including canopies, surface hardware and
similar items before painting, safely store them and replace them when painting is complete.
Dripped, spilled or splattered paint shall be cleaned up promptly. Drop cloths shall be laid to
completely cover flooring and all other work items during painting, and shall remain in position
until the paint work is dry, finished and inspected.
6) The premises shall at the times be kept free from an accumulation of waste material and
rubbish. On completion of the painting, all tools, scaffolding and surplus materials shall be
removed from and about the building, ready for inspection by the Engineer.
7) Any primer or finish applied on steel surfaces that shows signs of rusting, flaking, powdering or
peeling, shall be sand-blasted to remove the paint bare to the metal and repainted.
14.4.5 PAINTING SCHEDULE
1) Prime shall consist of one coat unless otherwise specified. Finish shall consist of two coats
unless otherwise specified.
2) The following paints shall be applied, unless otherwise shown on the Drawings or directed by
the Engineer.
a) Steel works (not galvanized):
Primer: inorganic zinc based on zinc silicates with good resistance to acid and
alkalis TDFT (*) >=60 microns
_______________________________________________________________________________
143
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

Finish: epoxy-polyamide with good resistance to acid and alkalis TDFT >=250
microns
b) Steelworks (galvanized):
Solvent: modified neoprene adhesive or equivalent solvent TDFT>=20 microns
Primer: inorganic zinc based on zine silicates with good resistance to acid and
alkalis TDFT >= 60 microns.
Finish: epoxy-polyamide with good resistance to acid and alkalis TDFT >= 250
microns
c) Interior doors:
Primer: alkyd based resin TDFT >=80 microns Finish: alkyd based enamel TDFT>=
200 microns
d) Acid Resistant Paint:
Primer: epoxy-polyamide with very good resistance to acid TDFT >=125 microns
e) Indoor Concrete and Plaster:
Primer: impregnation compatible with finish
Finish: water resistant acrylic resin. Consumption=approx. 220 g/m2
f) Outdoor Concrete and Plaster:
Primer: impregnation compatible with finish
Finish: water resistant acrylic resin specific for outdoor. Consumption = approx.
250 g/m2.
(*) Total Dry Film Thickness
14.5 FLOORING AND TILING
The works in this sub section shall include the supply of all materials for, and all finishing and
covering works to floors and walls, together with incidental preparatory work and ancillary
items asdescribed.
Before applying cement finish to already hardened or cured concrete slabs, the surfaces shall
be thoroughly cleaned of all rubbish, concrete and mortar droppings. Oil and grease soiled parts
shall be cleaned with oil removing agents.
For a good bond, surfaces shall be rough and where necessary they shall be roughened either
by sandblasting or by chipping, followed by a complete removal of all detached particles of
concrete and dust. The surface shall be washed thoroughly with water under pressure and be
kept wet for 24 hours prior to placing the concrete finish, but no free water shall remain on the
surface during placing of surfacing.
Cement finishes shall be carried out perfectly level or sloped towards drains, in accordance with
the Construction Drawings.
A bonding course of pasty, rich cement mortar scrubbing shall be applied with a stiff brush prior
to placing the cement surfacing on the cleaned, roughened and wetted concrete surfaces.
Before the applied mortar has thickened appreciably, the top course shall be added, tamped or
rolled and levelled to the required thickness and slope. The surface shall be tested for high or
low spots, which shall be levelled.
Surfaces shall be smooth, have a dense finish and be free from defects and blemishes.
All cement floor finishes shall be protected from damage, especially that due to quick drying.
Floors shall be covered completely with clean, airtight, impermeable coverings such as plastic
sheets to prevent against a quick loss of moisture. During curing time (minimum 2 weeks), no
use shall be made of the floor.
Surfaces to receive P.V.C. tile work shall have a floated finish, perfectly smooth and level.
Where cement finishes are to be carried out with a tile like pattern, the Engineer will
indicate the exact layout of lines in situ.
Ceramic tiles or single fired tiles shall be laid on walls and floors in the bathrooms and

_______________________________________________________________________________
144
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

kitchens.
P.V.C. tiles shall be laid in other rooms, corridors etc.
Tiles shall be of first class quality, perfect in shape and colour.
Samples of all tiles must be submitted to the Engineer for approval, whereafter no
changes shall be introduced.
The surface on which the single fired, ceramic and "gres'' tiles are to be laid shall be
thoroughly cleaned and all traces of building materials removed and the surface shall then
be thoroughly wetted with water before the screed is laid.
Joints of single fired tiles on floors shall be pointed with lean grey Portland cement, unless
otherwise specified by the Engineer.
Ceramic tiles for walls shall be glazed and shall by supplied with the necessary corners,
channels and ends together with all matched special units, such as soap dishes, brackets
for towel bars and glass shelves, toilet paper holders, etc.
Joints shall be pointed with white lean Portland cement.
Wall tiles shall fit perfectly around all pipes. Connections to all sanitary appliances must be
well arranged and be neatly carried out.
P.V.C. tiles shall be laid strictly in accordance with the Manufacturer's recommendations for
the specific material and be glued only with the appropriate recommended glues.
Finished floor covering shall not contract or expand nor warp, or become detached.
Completed floor coverings shall be thoroughly protected against soiling and damage.
Samples of proposed materials shall be submitted to the Engineer for approval in advance
of any ordering of material.
14.6 WINDOWS AND DOORS
The works covered in this sub section shall include the supply and erection of the windows and
doors as described and in the locations shown on the Final and/or Construction Drawings, together
with their relevant hardware and glazing.
The Contractor shall verify the exact dimensions of each item before ordering and shall supply
for the Engineer's approval full details including, where necessary, drawings of each item,
components and fixing arrangements.
Durable packing and protection shall be provided to prevent damage during transportation and
handling up to delivery to the Site of all the materials.
The windows and doors shall be in accordance with their description on the Detailed Drawings.
All windows and doors and their fixtures and fittings shall be carefully handled and stored on Site
prior to erection. They shall be stored within an enclosed storage building and covered to protect them from
all weather conditions. They shall be supported to prevent bending or twisting stresses.
Holes in structures for embedding the anchors of frames shall be carried out by the Contractor,
and care shall be taken not to damage any finished surroundings.
All door frames shall have a minimum of two anchor fixings on each side of the door opening,
but the distance between fixing points shall not exceed 400 mm.
Windows and doors shall open as indicated on the Detailed Drawings and/or schedules.
Joints between walls and window and door frames and between the frames and windows and
doors shall be perfectly airtight.
All surfaces shall be smooth and crack free.
All windows and doors shall be rigid and safe against warping. When closed, all windows and
doors shall fit perfectly.
All glazing shall be performed by skilled workmen. The Contractor shall strictly follow the details
indicated on the Drawings, or, if none exist, shall prepare his own working details and have
them approved by the Engineer.
Glass panes shall nowhere be rigidly fixed. They shall be set on supports in such a way that their

_______________________________________________________________________________
145
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

weight will be well distributed and no warping can occur which would impair the operation of
windows and doors.
Glass pane edges shall nowhere touch the framework.
Exterior glazing shall resist wind pressure and weathering and be set rainproof and airtight.
Only heavy-duty standard-type hardware, well resistant to humidity (rustproof), shall be used
for windows and doors.
A sample of each type shall previously be approved by the Engineer. Ready-installed hardware
shall be well protected against damage.
All windows and door frames shall be fitted with mosquito netting.
14.7 CEILINGS
The works covered by this subsection include the supply and erection of suspended ceilings as
shown on the Construction Drawings, including all ancillary works.
The required detailed drawings shall be provided by the Contractor, following his check of all
measurements on site. Any discrepancies shall be referred to the Engineer for confirmation
before commencing with the work.
Hangers, fasteners and other assembling means shall be chosen according to type and weight
of the material to be suspended or fixed.
14.8 PLUMBING
The Works covered by this sub section include the supply and installation of pipes, appliances
and ancillary fittings and equipment for the complete water supply from the elevated water
tank, and sanitary drainage systems to septic tanks.
Prior to acceptance, the systems shall be tested to above normal working pressures and
conditions, and any defects or leakages shall be rectified.
Local rules and regulations for the installation of plumbing and the quality of materials shall be
observed.
The hot and cold water systems shall be constructed in accordance with the shown on the
Construction Drawings or as directed by the Engineer.
Hot and cold water pipes shall be of adequate size to serve the sanitary units concerned.
Pipes shall be fitted with clips, plugged and screwed to walls or built into plaster or other
surfacing as specified by the Engineer.
The sanitary drainage system shall be constructed in accordance with the layout, shown on the
Construction Drawings or as directed by the Engineer.
Pipes for the conveyance of sewage and wastes shall be obtained from an approved
manufacturer. The pipes and fittings shall be fixed to walls using correctly sized brackets and clips
of a type designed for the purpose, and all fixings shall be at sufficiently close centres as to
prevent any deflection of the pipe resulting in a back-fall in the pipe.
Connections to water closets and floor mounted soil fittings shall be made using the correct
sized socket for the outlet of the fitting.
All pipework for water supply and drainage shall be firmly fixed and supported to resist
movement under internal pressure.
Pipes passing through walls and floor slabs shall be protected with sleeve pipes and proper
insulation. There shall be no direct contact between wall or floor and the pipe. The insulation
wrapping shall allow for free movement of the pipeline.
Plumbing installations shall be complete, with hand basins, sinks, W.C. units, water heaters and
showers, as shown on the Drawings or as directed by the Engineer.
A sewerage system shall be provided to collect all foul drainage in septic tanks and soak-aways
in accordance with the Drawings prepared by the Contractor and approved by the Engineer.

_______________________________________________________________________________
146
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

14.9 ELECTRICAL SYSTEMS


The works covered by this sub section shall include the supply and installation of all materials
and equipment necessary for the proper and efficient operation of the electrical systems
specified herein, as indicated in the Bill of Quantities, as shown on the Contractor’s Construction
Drawings or as directed by the Engineer on Site.
The works shall be executed in accordance with local regulations.
14.10 WATER SUPPLY PLANT
The water supply plant will provide drinking water and service water to the Sites of
Installations. The Contractor shall submit for the Engineer’s approval the detailed drawings for
the entire plant and details of the proposed treatment plant for drinking water.
The water supply plant will generally comprise:
• one submersible pump to be installed upstream of the diversion works at a
lower than the minimum river level, with a discharge greater than 1 litre/sec,
head greater than 45 m and power about 1 HP ( 0.75 kW);
• elevated water tank, in concrete, steel or glass-fibre, divided into two sections
for service water and drinking water and comprising all necessary pipelines and
valves;
• a steel pipeline, of at least 2” diam., complete with bends, valves, vents, etc.
necessary for the supply of water to the elevated water tank situated near the
Installations;
• system allowing automatic or manual operation of the pump;
• water treatment plant with a capacity of 20 to 40 m3/day. The treatment
process shall be principally electrical. Any chemicals shall be commercially
available in Uganda and of a type with a shelf life of at least 5 years.
• the plant shall be complete with all accessories necessary to guarantee state-
of-the-art automatic operation.
14.11 REQUIRED DEMOLITIONS
14.11.1 GENERAL
1) Demolition works refer to plain concrete and reinforced concrete.
2) The works under this paragraph shall concern the structures to be demolished by written
instruction of the Engineer due to changes of the original design.
14.11.2 EXECUTION METHOD
3) Demolitions shall be carried out with hammers and/or hand held type paving breakers unless
different approval by the Engineer.
4) Demolition works shall be performed in an orderly manner and the Contractor shall take any
necessary precaution and measure to avoid damage to adjacent structures as well as to prevent
dust, labour accidents and minimize interference with the activities of others contractors.
5) Materials resulting from demolition works shall be disposed of as specified for the unloading of
excavated materials in these Specifications.
14.12 NON-SHRINK GROUT
14.12.1 GENERAL
1) The non-shrink grout shall consist of a special compound formulated with catalyzed metallic
fine-elements, water reducing agents and other components which, by producing a void-filling
action, completely overcomes any shrinkage which may be caused by water evaporating from
the grout.
2) The grout shall be used for bearing plate beds, blockouts, filling of recesses and the like, second
stage fillings and similar works shown in the Drawings or directed by the Engineer in connection
with the installation of the Permanent Equipment.
_______________________________________________________________________________
147
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

14.12.2 MATERIAL AND PLACING


1) The mixture shall be composed of one (1) part of non-shrink compound, one (1) part of
Portland cement, one (1) part of sand or fine gravel (8 mm max size) and sufficient water for
obtaining a self-leveling mortar.
2) The non-shrink compound shall be the Kemox-B produced by Sika, or equivalent material
approved by the Engineer.
3) Mixing and placing of the grout shall be in accordance with the instructions supplied by the
manufacturer of the compound and/or by the Engineer.
14.13 MEASUREMENT AND PAYMENT
14.13.1 ROOFING
Measurement for payment for roofing will be of the horizontal projected area of finished roof.
Payment will be made at the Unit Price per square meter entered in the Bill of Quantities which
will include the supply and placing of all materials.
Gutters and corner pieces will be measured by length including gutter ends and slip joints.
Downpipes, elbows and bends will be measured by length along the centre line of finished pipe.
The rates for payment shall include all cutting and jointing and wasted materials.
These rates shall also include the extra cost of bends and fittings together with all brackets and
fixings.
14.13.2 PLASTERING
Measurement for payment for plastering will be of the area of finished work regardless of the
kind of surface, height and extension to which coatings are applied.
Payment will be made at the Unit Price per square metre entered in the Bill of Quantities,
which will include for all materials and activities necessary for the work. No additional payment
will be granted for scaffolding.
Openings of an area less than 1 m2 will not be deducted from measured areas. No separate
measurement will be made for joints, returns, rounded-off corners, forming of square corners
and similar kinds of finishing to plastering.
14.13.3 PAINTING
Payment for paintwork will be made at the Unit Price per square meter entered in the Bill of
Quantities, according to the following provisions:
1. No direct payment will be made for furnishing and applying paint for steel works and wooden
elements, the entire cost of this work being include in the Unit Prices entered for the various
items in the Schedule.
2. Measurement for payment for painting works on plaster and concrete will be based on the area
covered with the paint of the required type.
3. Payment of painting works on plaster and concrete will be made at the appropriate Unit Price
per square meter entered in the Schedule, which shall also include material supply, surface
preparation, scaffoldings, application and protections and completion of the finishes
4. The rates shall also include for the supply to the Employer’s store on Site of 1% of each type and
colour of paint, supplied in un-opened containers.
14.13.4 FLOORING AND TILING
Measurement for payment for all floor finishes, tiling and floor coverings will be of the net area
of completed work for each material.
Payment will be made at the Unit Price per square metre entered in the Bill of Quantities.
Openings of less than 0.10 m2 will not be deducted.
The rates for payment of the items for floor finishes, tiling and floor coverings shall include for
all materials and fixings, fitting to corners and edges, cutting and jointing and for all wasted
materials. 0.5% of each flooring material, but a minimum of 1 m2 shall be supplied as spare
material and the rates for measured items shall include for such.

_______________________________________________________________________________
148
KABUYANDA BIDDING Section-VII
PART 2 - WORKS REQUIREMENTS
DOCUMENTS Vol 3 - Specifications

14.13.5 WINDOWS AND DOORS


Measurement for payment of windows and doors will be by Unit Price per square meter
entered in the Bill of Quantities.
Unit prices shall include all glazing, required fittings and miscellaneous material. 10% of each
particular type and size of glass pane, but minimum one full pane, shall be supplied as spare
material and the rates for the measured items shall include for such.
14.13.6 CEILINGS
Measurement for payment of ceiling work will be of the net surface area of the finished work.
Payment will be made at the Unit Price entered in the Bill of Quantities which shall include all
material for suspending and fixing of ceilings, as well as all wall connections and material for
setting-in of electrical appliances, joint covers, cutting and adapting the material to shapes and
dimensions and for any wasted materials.
As spare parts, 2% of each type of ceiling material, but minimum one full panel, shall be supplied
and the rates for measured items shall include for such.
14.13.7 PLUMBING
Pipelines supply and installation, including appliances and ancillary fittings, bends, valves, all
fixing and connection material, labels, etc., will be paid in relation to the net installed pipeline
length.
Items such as W.C., Wash Basins, Showers etc., will be paid per supplied and installed unit.
Payment will be made at the Unit Price entered in the Bill of Quantities.
The rates of payment for pipework and appliances and equipment shall include for all pipe
fittings (bends, valves, etc.) and fixings and the insulation and protection as specified.
The rates shall also include for testing of the pipework and appliances to the appropriate pressure
and conditions.
14.13.8 ELECTRICAL SYSTEM
Payment for the supply and installation of the electrical system as indicated on the
Construction Drawings, performed by the Contractor and approved by the Engineer, will be
made at the lump sum amount entered in the Bill of Quantities.
14.13.9 WATER SUPPLY PLANT
Payment for the supply and installation of the Water Supply Plant as indicated on the Drawings
will be made at the lump sum amount entered in the Bill of Quantities.
14.13.10 REQUIRED DEMOLITIONS
1. Measurement for payment for required demolitions will be based on the in-place volume
obtained from the Engineer's instructions.
2. Payment will be made at the appropriate Unit Price per cubic meter entered in the Bill of
Quantities, which shall also include re-steel cutting and transport of resulting material to spoil
areas.
14.13.11 NON-SHRINK GROUT
1. Measurement for payment for non-shrink grout will be based on the volume obtained from
the Drawings.
2. Payment will be made at the appropriate Unit Price per cubic meter entered in the Bill of
Quantities, which shall also include material supply, mixing, surface preparation, placing and
formworks.

_______________________________________________________________________________