Professional Documents
Culture Documents
CIRIA Waterproofing Basements Pt8
CIRIA Waterproofing Basements Pt8
The effect of the new building on surrounding buildings and services must be
considered and damage assessments, condition surveys, etc., must be carried out.
In the case of metallic and plastic pipework (or more usually sleeves around pipes)
subjected to hydrostatic pressure, a caulking groove may be formed around the pipe on
the inside face of the box. The groove is sealed, normally with a bitumastic sealant,
internal render, if used, may be butted up to the pipe.
Non-metallic pipes (and, in particular, salt-glazed earthenware) may have their surfaces
specially prepared before casting into the concrete. Provided a sufficient length of
prepared pipe projects beyond the concrete face it may be possible to bond an internal
render direct to the surface.
the building services engineer must make known to the structural engineer any
provisions affecting the structure, at an early stage in the design. Likewise, the
structural engineer must advise on the risk of any differential settlement occurring
which may affect services passing through or outside the structure.
Every effort must be made by the design team to pre-plan all service entries. Duct
openings that have to be provided at the last moment because of lack of planning
II:140
frequently present a leakage risk. Additional reinforcement may be required,
particularly at comers of openings’ to counteract the concentration of shrinkage stresses
at such positions.
Services that pass through the wall at high level and are grouped together in one or
two large openings isolate the potential problems of leakage. When this is not possible,
and individual pipes are required to pass through the wall, a number of points of
weakness may be formed in the passive protection. Good-quality concrete, well
compacted around pipes, may provide sufficient water-resistance, but puddle flanges
may be used on individual pipes at this point. However, there is some difference of
opinion on this subject, as a badly placed flange can form a channel for moisture
ingress. The final decision must be the responsibility of the designer. Particular care
must be given to the detailed design at these points to ensure that congestion of
reinforcement is avoided so that concrete can be easily poured and compacted around
the pipe.
Wherever piped services run from an external duct or loosely filled surface excavation
into the basement, surface water can collect at this point. The simple precaution of
providing a puddle clay dam (or half brick wall) at the junction between the duct and
wall may be an effective countermeasure. This is one of the points of particular
sensitivity for ingress of water into the basement.
Sufficient access to all services, including pipes, cables, and mechanical and electrical
plant, will probably be required both during construction and subsequently for
maintenance.
Problems with services passing under a basement may occur due to water ingress into
ducting, which can be particularly hazardous for electric cables, as access for
maintenance is difficult.
Domestic cable support brackets, if they are light, may be attached to timber battens
bonded to the rendered surface (see Figure 8.3).
For car parks, plant rooms, etc., the floor should be provided with adequate falls for
drainage. Particular attention is required to avoid ponding at the foot of ramps and
staircases.
II:141
Preformed pockets
i.e. when position of
fixing is known before
concrete is poured
Note:
It is assumed that pockets
for bolt fixings would be
preformed in in-situ
concrete work
.after
Mortar fill to pockets
positioning of bolt
Finish if required
Cable
1
Fixings to batten
II:142
Where a drained cavity is included in the construction, access doors provided in the
inner wall at regular intervals for inspection and cleaning of the cavity may be
advantageous. Where possible, such doors should coincide with downpipes.
Automatic pump switches in sumps may malfunction and regular inspection, testing
and maintenance are essential to ensure that they work satisfactorily. Multiple switches
should be considered by the designer.
Void formers, provided below some basement floors to counter the effects of ground
heave, should be prevented from expanding until required. This may be achieved by
wrapping them in polythene, with the water introduced in a controlled manner through
a pipe.
Care should be taken with the use of compressible filler boards (of the clay/paper type)
below basement constructions, which in certain ground environments can rapidly
generate large quantities of methane. This may migrate into poorly ventilated
basements and build up to reach the lower explosive limit.
II:143
Core Programme Members (June 1995)
Consultants Contractors