UPR-377-MSRA-MEP-ISG-001 - Site Office & Welfare Facility
UPR-377-MSRA-MEP-ISG-001 - Site Office & Welfare Facility
Project Name Nakheel Mall-Refurb Project Number UPR377 Managing Office: ISG
Satisfactory
(please tick)
Ref RAMS Considerations
Yes No/NA
1 Work activity detailed within the Risk Assessments / Method Statements fully representative of the actual tasks to be undertaken x
2 Sequence of work activity listed in a logical order x
3 Site specific content included with the site actually named and the date / time of the tasks also detailed if relevant x
4 Risks associated with the work activity clearly identified e.g. working at height, dust, exposure to noise / vibration etc x
5 Supporting issue specific risk assessments included as necessary e.g. manual handling, COSHH and MSDS etc x
6 Classification of persons exposed to the risks identified e.g. contractors, client employees, members of public etc x
7 Suitable control measures to mitigate the risks stipulated – e.g. use of scaffolding tower, use of PPE, use of lifting equipment etc x
8 Quoted types of plant and equipment suitable and available on-site with statutory inspection evidence provided where required x
9 Quoted types of materials and / or substances to be used suitable and available on-site x
10 Required competencies of operatives who will be undertaking the work activity identified x
11 Competent persons named, certificates submitted to ISG, i.e. erection, dismantling, inspection of mobile towers x
12 Specific arrangements for the delivery, storing and movement of plant and material considered and planned accordingly x
13 Emergency / rescue plans considered as necessary e.g. work from height / confined spaces x
14 Details of communication outlined within the documentation x
15 Relevant drawings and / or technical information provided as necessary x
16 Sufficient consideration of Environmental issues e.g. waste management, pollution prevention etc x
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 1 of 19
Risk Assessment, Method Statement (RAMS)
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 2 of 19
Risk Assessment, Method Statement (RAMS)
Note: To be submitted at least 5 working Days prior to commencement of work
Other Trade Contractors to receive a copy of RAMS for information, coordination and interface purposes
Name Gypsum Contractor Name Landloard
Company Name GTS Company Name Nakheel Mall -FM
Proposed Start
1.0 Proposed Start Date: 16 Jan 2024 09.00 AM
Time:
1.1 Expected Duration: 2 weeks
Exact Location (S):
1.2 Nakheel Mall, Basement 2
Attach Plan (if necessary)
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 3 of 19
Risk Assessment, Method Statement (RAMS)
SITE PREPARATION
All safety and Authority permits shall be obtained before the commencement of any works.
All workers or site staff shall undergo must undergo daily safety induction, toolbox talk and risk
assessment briefing prior to the initiation of any site activity.
Material shifting shall be done with sufficient manpower and in compliance safe lifting
procedure.
Dilapidation report citing the site conditions and the condition of existing MEP services shall be
submitted in advance to ISG.
It shall be ensured that the source of Electricity, Water and drainage is approved by the
Landlord prior to commencement of connection to the existing services.
The Supervising Engineer / Supervisor / Team leaders shall confirm that all necessary
documentation is in place to proceed with the works.
Site works shall proceed only after the receipt of instruction from the Site Engineer/Project
Manager after ensuring compliance to the project specific requirements.
After the civil clearance advice to proceed with MEP installations, ensure that area is clean and
ready to commence the work.
Contractor shall ensure that the materials are free of any damage or deformity of any kind.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 4 of 19
Risk Assessment, Method Statement (RAMS)
Ladders shall be propped on level surfaces only. Aluminium or metal ladders shall not be used
near the live electrical services in areas exposed to chances of electrocution.
EMKAY will ensure that ladder shall never be placed on a box, bricks or any other thing to
reach the height and that the podium ladders are fully opened and locked before use.
Swing guard is in close position when operatives on the podium working platform.
Proper PPE to be used when working on the top of a ladder.
Ladder inspection tags will be obtained from ISG after submitting ladder inspection report. For
scaffolding inspection tags shall be provided by trained EMKAY employee.
PASMA Certificate of scaffolding inspector will be available at site.
METHOD OF INSTALLATION
Detailed dilapidation report communicating the existing condition of MEP services and the
existing MEP provisions at site shall be submitted to Main Contractor prior to the start of works.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 5 of 19
Risk Assessment, Method Statement (RAMS)
Installation
Mark the location of the MEP installations including Split AC’s, Floor Boxes etc as per the
approved drawings/furniture layouts.
Prior to the final connection of all MEP services necessary permits and written confirmation
shall be obtained from the landlord/main contractor.
All MEP items and ancillaries will be stored and transported to site as per the Supplier’s
recommendations.
Remove Dirt’s/Debris inside and outside the MEP items before assembly.
Hangers and supports installation location shall be coordinated and grouping of services shall
be maintained at site.
Separate supports shall be provided for individual services unless, otherwise there is no option
at site. Hangers or supports will be installed at each end of a junction, bend or any change in
direction of fittings.
Clashes, irregularities and deviations will be brought to the attention of the Engineer & Main
contractor who will direct and officially instruct Emkay on further action.
Drilling will be done at the site after the completion of marking. Fischer’s plugs, anchors will be
inserted at the drilled locations. Threaded rods and supports shall be fixed at the locations.
Support system is installed at site by using 21x21mm and 41x41mm slotted channel (as
applicable), fixed on 2x8mm or 2x10mm threaded rod suspended / anchored on to the
concrete slab.
The technician will cut the required length of the rods appropriate to the elevation of the Tray
specified in the drawing and fix to the anchor/beam clamp.
Channels will be cut to the desired length depending on the size of Tray and assemble and fit
the support system as appropriate in accordance with the approved drawing.
The location and routing of the tray shall be based on the containment drawing prepared for
site purpose. Changes of routing shall be carried out as per the site condition and the same
shall be reflected in the as built drawings.
Fix the cable Tray sections to the support system and join the adjoining lengths in accordance
with the drawing. Purpose made bends and accessories will be utilized as per the site
condition.
Spacing of the supports shall be as per the approved shop drawing which is at 1500mm on
either side if the joints, Tee, Bends and any other such activities.
Ensure that all earth continuity links are correctly fitted. Adjust the support system/ Trunking
fixing to the correct location and alignment. Identification labelling shall be provided at bottom
of Trunking along the run and at every wall crossing.
Installation of Conduits
All the power and other service cables running through floor should be run through Conduit.
Complying to the project specification & approved drawings PVC Conduits shall be utilized at
the predefined areas as per the approved drawings. Conduit shall be fixed directly to the
concrete floor by fastening anchor. The branches to floor outlets will be through flexible
conduits connected using adaptors.
The selection of conduit based on local authority codes and consultant drawings as per the
containment sizing requirements.
Where conduits are connected to trunking/tray, metallic boxes, DB’s or any item having a
tapped entry shall make the connections by long threaded male brass bushes.
Sufficient inspection plates and pulling boxes must be provided to enable inspection, repair
and drawing out of cables throughout the life of the Installation.
The technician will fix the conduits on walls, on beams, on purlins, on steel columns or on open
and closed ceiling using appropriate fixing materials such as saddles, conduit clips for beams
and purlins, channels, and U-bolts.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 6 of 19
Risk Assessment, Method Statement (RAMS)
Joints between PVC conduit + fittings shall be made with suitable adhesive, but expansion
couplings shall be installed where any length of conduit, inclusive of draw in boxes etc.,
exceeds five meters in length.
The minimum and maximum sizes of conduit to be employed shall be 20mm and 32mm
diameter respectively, unless otherwise stated in subsequent sections of the specification.
Conduits in floors shall be routed and installed to avoid the fixings of floor standing equipment
to be installed on the floor.
Ensure conduits to run parallel to each other where crossing is unavoidable it shall be at right
angles. Maintain adequate clearance between conduit and water networks.
Ensure the cable Tanking and cable trays are installed as per the approved drawing.
Once the block wall/dry wall/ Gypsum wall is ready, the technician shall mark the location of
the wiring accessories along with the marking for the conduits.
Standards mounting heights as per the approved shop drawings shall be maintained for the
services @450mm for Sockets & @1200mm for Switches. Proper alignment of the back boxes
will be carried out using spirit level. Adjacent back boxes shall be kept @3cm spacing.
Encased conduits in walls shall be at minimum 50mm depth as per the standards regulation
and extension rings shall be used wherever necessary.
Clearance for plastering/gypsum is issued and protection to installed GI back boxes are
ensured by providing polystyrene foam and tape to avoid any damage during plastering.
After the plastering or gypsum boards are closed, Installation of wires and testing is done. For
GI back boxes ensure proper earth looping is done to the back box device.
Conduits and trunking shall connect to the Distributions Board by adaptors glands, after the
cables, wires are pulled to the DB, through the containment as per the drawings and load
schedules, Further the cables and wires dressed properly and terminated to the assigned
breakers.
Individual circuit wires shall be then grouped properly, and neat dressing shall be done and
then terminated to a particular breaker using proper size Sleeve number ferules / lugs. Each
outgoing will be labelled to identify the circuit number.
Distribution board serving the site temporary loads shall be connected to the spare breaker
facilitated by the Landlord as per the load demand.
Necessary PTW and Isolations will be obtained prior to the connection to existing facility. All
energisations will be carried out in the presence of landlord representative.
On receipt of confirmation from the landlord/main contractor on the feeding point, necessary
isolation permits will be obtained to connect to the existing LV network
Extra care should be taken before pulling the wires and cables; testing will be carried out
before pulling the cable for damage of insulation, continuity of the conductor by Megger. Wires
shall be arranged according to the size and color mentioned in the load schedule for lighting
and power circuits. All wiring of multi-point circuits in a “loop-in” system, and do not use joints
or connections, other than those required for the connection of switches, fuses, socket outlets.
Entire wire roll shall be kept in a safe stand to rotate as free. Wire size, color and quantity shall
be as per the load schedule and tie with insulation tape to the pulling spring and pull from the
other side. Technician will ensure the neutral wire should not come to the switch boxes. If any
difficulties found during pulling apply a small amount of lubricant to the wire. All the boxes and
points are wired with earth continuity conductor.
A slack of at least 200mm of wire will be left at each outlet and 300 mm for lighting points
wherever there is no false ceiling, but inside DB the length is around 800 mm. Put proper
identification for the wires in DB for connection purposes and continuity testing.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 7 of 19
Risk Assessment, Method Statement (RAMS)
The cables and wires shall be in accordance with the approved load schedules and shop
drawings. During installation technician shall pull the cable from one side and push from other
side in a uniform manner until reach the destination.
ECC (Earth Continuity Conductor) of green yellow color equal to half the size of phase
conductor shall be laid with the cable for size including and above 25 Sq.mm2 and of
same for cable equal and below 16 sq.mm.
Leave around a length of 1 meter in DB’s and 2 meter in SMDB’s as loop when pulling the
cable.
Wiring accessories shall be fixed on the back boxes provided on the walls /ceiling /floors etc.
The pulled wires are connected to the wiring accessories like sockets, switches, Isolators, spur
outlets as per the drawings. Continuity test will be carried out after the installation.
All back boxes shall be cleaned properly before fixing of wiring accessories.
Wiring accessories shall be fixed with proper size screws as per approved Shop drawings.
Remove the insulation from the wire and connect it to the terminals provided on it according to
the wiring rules.
The installation of wiring accessories must be done after finishing of second coat of paint by
civil.
Floor outlets will be installed in the locations marked as per the furniture layout on Trunking
due to the non-availability of screed/raised floor. Where possible wall mounted outlets will be
proposed to avoid tripping hazards.
Earth continuity to be ensured by the electrician prior to the energisation of the circuit.
Lighting Fixture
Mark the locations of lighting fixtures on the ceiling or wall, The installation of Light Fittings
shall be done with proper screws and connectors
Pendant or hanging lights shall be installed on the ropes/supports. Lighting circuits from the
Junction box to the lighting fixtures are connected via flexible cable.
Check the alignment of the fixture and connect the wires with connector to the fixture . The
Installation of lighting fixtures shall be done after finishing of final coat paint by the Civil.
Drainage Works
Scope of works of drainage services are limited to the connection of Waste pipes in the pantry
area to the existing Waste lines & Split AC CDP lines.
Split clamps/Rubber hanging clamps is used for ceiling supports. All the supports will be fixed
in place by an approved construction method to suit the elevation of piping as indicated on the
approved shop drawing. Hanger rod sizes will be in accordance with the requirements of the
specification.
The route of the proposed drainpipes which is to be connecting to the existing drainpipes will
be marked as per the approved drawings.
Threaded rods shall be used to fit the pipes into the ceiling and clamps will be provided to
support the drainpipes at an interval of every 800mm installed by using spanners and screw
drivers. Threaded rods will be threaded into fisher plug installed in the ceiling by using drilling
machine and drill bits.
The pipes shall be measured to their required lengths and cut with a hacksaw with frame to
their correct length. The joints of the drain lines after cutting shall be connected properly. Push
type fittings shall be pushed into each other by applying lubricant to the pipe and pushing the
sockets into the pipes.
After the installation has been approved a leak test shall be done for 24 hours to ensure there
is no leak. Slope test also will be conducted for the newly installed CDP lines. Water shall be
poured down the newly installed pipes by use of a water pipe from the nearest water supply
point. The level of the water shall be marked, and tape will be placed over the pipes to prevent
any tampering with the test.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 8 of 19
Risk Assessment, Method Statement (RAMS)
Traps will be provided in the respective drainage lines.
Once the gravity test and slope test is approved, insulation shall be glued onto the drainage
lines as applicable. After the isolation for the main drainage line EMKAY will connect the new
proposed lines to the existing main lines.
Routing of drainage lines are to be avoided above electrical/ELV panels.
On receipt of confirmation from the landlord/main contractor on the tie-in points, necessary
isolation permits will be obtained to connect to the existing Drainage network.
Scope of works of Water supply services are limited to the Sinks in the pantry/temporary
drinking water provision for the site staff.
The marking for the PPR pipe support shall be marked on the wall, floor & ceiling as per
approved shop drawing.
The route of the proposed Water Supply pipes which is to be connecting to the existing pipes
will be marked on the ceiling. Threaded rods shall be used to fit the pipes into the ceiling and
clamps will be provided to support the pipes at an interval of every 800mm installed by using
spanners and screw drivers. Threaded rods will be threaded into fisher plug installed in the
ceiling by using drilling machine and drill bits.
The pipes shall be measured to their required lengths and cut with a PPR cutter. The joints of
the PPR lines after cutting shall be connected properly using PPR welding machine.
Pressure testing of the installed lines will be carried out. Bottle traps below the sinks will be
connected to the floor trap using 50mm waste pipes to the floor traps which will be further
connected to the nearest drain stack.
Expansion type anchors will be used to install the threaded rods which will support the split
clamp supports for the main cold water and hot water supply lines. Insulation will be provided
for the hot water lines.
Further PEX pipes/PPR pipes will be used to connect the main lines to the angle valves from
where it will be extended using GI flexible pipes to taps/mixer.
Once the pipe connections have been completed works will be verified to ensure that the
installation is correct and as per approved drawing.
Location of the final fixes shall be coordinated with the main contractor/architect.
On receipt of confirmation from the landlord/main contractor on the tie-in points, necessary
isolation permits will be obtained to connect to the existing Water Supply network.
SPLIT AC
Mark the location of the indoor units and install supports or brackets for split AC units as per
the approved shop drawing, and site conditions for each individual case (i.e. slab, floors, walls,
etc.). Selection of copper pipe sizes will be as per the manufacturer recommendation.
Supports are to be fixed at the correct levels checking the bracket material is compatible with
the installation.
Indoor-type split units can be installed on the floor or hang from the ceiling or wall. Allow space
for wiring, piping, and service units. For optimum condensate drainage performance, the unit
should be levelled along its length and width.
Align holes with tubing connection and condensate pan connections and reinstall the access
panel and fitting panel.
Ensure that vapours and liquid tube diameters are appropriate to the capacity of the unit and
space is available between the structure and unit to absorb vibration and ensure that tubing
insulation surrounds the vapor tube.
If required hanger straps shall be used. Insulate the hanger strap from insulation by using
metal sleeves bent to conform to the shape of the insulation.
Outdoor unit shall be mounted to pad; tie-down bolts should be used and fastened through
knockout provided in the unit base pan. Arrange supporting members to support the unit and
minimize transmission of vibration.
Sufficient space for airflow clearance, wiring, refrigerant piping, and service should be
available.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 9 of 19
Risk Assessment, Method Statement (RAMS)
Separate power outlet will be provided exclusively for each unit, with a power supply
disconnect and circuit breaker for overcurrent protection in the Distribution Board.
Ensure the installation of an electrical isolator (disconnect switch) for outdoor units and DP
switch for indoor units.
To prevent possible hazards due to insulation failure, the unit must be grounded.
Each wiring connection must be done tightly and in accordance with the wiring system diagram
and in compliance to the local wiring regulations.
Precautions shall be taken to ensure that the wiring shall not touch the refrigerant tubing,
compressor, or any moving parts of the fan.
All installation and construction work required will be undertaken in accordance with
manufacturer instructions, and project requirements.
Supervisor to ensure that there are no dents, distortion, or any possible damage during
installation. Leak test shall be conducted to ensure that there is no leakage in the refrigerant
line prior to the commissioning of the Units.
After completion of Split AC Units installation work, identification of equipment will be
performed.
PERSONNEL RESPONSIBILITIES
PROJECT MANAGER
The Contractor / Subcontractor Project Manager is responsible for implementing this method
statement and its associated safety precautions in compliance to the risk assessment.
Project Manager shall be responsible for planning, scheduling and managing the onsite
activities including the arrangement of necessary manpower and equipment’s.
Responsible for ensuring compliance to the project QHSE requirements.
Manages subcontractors/vendors and acts as the single point of management contact between
the main and the subcontractor.
Liaises and coordinates with the Main Contractor/Consultant for commercial and contractual
matters.
Responsible for managing the project schedule, cost baselines and ensuring compliance to
project KPI’s and Metrics.
PROJECT/SITE ENGINEER
QA/QC ENGINEER
He will be overall responsible for the implementations of this procedure and will carry out the
material inspection to ensure that materials received on site are approved materials submittal.
He will monitor the installation works according to the approved shop drawing &method
statement.
Coordinate with the Consultant to carry out the inspection/testing of the completed works.
Responsible for monitoring the work and ensure that all installation or construction works will
be carried out in accordance with the specification’s requirements, approved drawings and
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 10 of 19
Risk Assessment, Method Statement (RAMS)
good engineering practice. QA QC Engineer will carry out internal/preliminary, inspection of
work completed prior to raise an inspection/testing to the Consultant.
He will maintain comprehensive records of inspection and test record (ITP’s) for the purpose of
reference and documentation.
SAFETY OFFICER
He will be overall responsibility for the implementations of the Safety procedure at site.
Safety officer shall be responsible for maintaining the Safety Documentation, Reports.
Audits the site on regular intervals for compliance to HSSE requirements.
Implements control measures in coordination with the site engineer and supervisors.
Leads the implementation of all safety related activities on sites.
SITE SUPERVISOR
Ensure that the construction work is carrying out properly and according to instructions
received from the site engineer.
Coordinating with the site team and subcontractors for the work to be done.
2.3 NOISE: During drilling the soffit for supports with power tools
What activities will generate noise? How During anchoring the stud with hammer
will you minimise noise? How will you During Threaded rod cutting
define noisy areas? Will you undertake a Noisy area can be defined though: -
noise assessment?
Sound pressure, time for distribution sound power and its
See Appendix: 4
frequency.
Noise shall be reduced by using: -
Ear plug if found excessive and zoning of noisy work areas.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 11 of 19
Risk Assessment, Method Statement (RAMS)
2.4 WORK AT HEIGHT: PERSONS Installation of Supports for MEP installations and final fix
Fall prevention: You will need to consider installations on ceilings & soffits.
all site activities that may involve working at All workers using scaffolds will be briefed in safe working
height including loading and unloading procedures.
vehicles, slinging and un-slinging loads,
working adjacent to leading edges etc. Scaffolding tag shall be displayed showing the correct
Provide details of any Work at Height condition of scaffolding set.
Training including harness inspection and Toe Boards will be installed on all scaffolds (Mobile or fixed)
training records.
A-type podium ladders shall be utilized as required.
All ladders and scaffolds shall be inspected & tagged.
WORK AT HEIGHT: FALLING Tools will be Controlled under the following circumstances:
OBJECT PREVENTION
- When working within four metres of an opening or edge
The prevention of tools, articles and of a structure. Where there is possibility of tools falling
materials falling needs to be considered more than one storey. Any location where tools could fall
whenever work at height is undertaken. in PPE free zone area and or a public area
Considerations need to be given to:
The storage of materials and tools at
height
Control/ tethering of tools when
undertaking work at height
Controlling materials and components
during the installation/removal process
Establishing and maintaining exclusion
zones.
Sequencing high-level works to
minimise risks.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 12 of 19
Risk Assessment, Method Statement (RAMS)
4.1 WASTE Management Housekeeping Waste will be removed to the pre-arranged waste collection.
and Storage REMOVAL:
How will waste be removed from the site?
Consider the location of skips, provision of
bins and what collection arrangements will
be put in place.
Disposal of controlled waste?
4.2 HOUSEKEEPING and STORAGE: Site Supervisor shall ensure the works areas are maintained
How will materials be stored on-site?
Ensure that materials are properly stacked and stored.
How will you maintain the required standard
of housekeeping? Excess materials shall be returned to contractors store.
6.0 MANDATORY SITE PPE (AS PER Safety Hard Hat / Safety Shoes / Hi- Visible Vest / Gloves, Eye
BRITISH AND EUROPEAN Protection, Mask
STANDARDS):
6.1 TASK-SPECIFIC PPE: Hearing protection for high noisy activities > 85dB
Identified as per risk assessment.
Respiratory protection (Safety masks)
State grade and standard. Note:
Consideration of working environments will Hand protection, Safety Goggles
need to be included and additional PPE
may be required e.g. cut resistant arm
protection for work in ceiling voids etc.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 13 of 19
Risk Assessment, Method Statement (RAMS)
8.0 RESPONSIBILITY FOR TASK Task lighting for temporary works shall be provided by EMKAY
LIGHTING:
Consideration should be given to site
hours; this may immediately highlight the
need for artificial lighting if work starts
before the first light or continues after dusk.
Additionally, the requirement for general
site lighting and specific task lighting would
be inserted here
NO PORTABLE HALOGEN LIGHTS
ALLOWED
9.0 TO WHOM THE INFORMATION All the personnel involved in this works shall be briefed prior to
WILL BE COMMUNICATED AND works. Briefing shall be recorded on RAMS briefing sheet, copy given
HOW? to Main Contractor HSE. For Non–English speaking personnel,
(to include non-English speaking provide translation in to the local language familiar to the employee.
operatives)
9.1 CONFIRMATION OF OPERATIVES Signed briefing sheets are to be submitted prior to the commencement of
BRIEFING: works
10.0 PERSON RESPONSIBLE FOR Jagath.M Phone No: 050 365 3569
MONITORING/REVIEW OF THE
SAFE SYSTEM OF WORK AND
ENSURING COMPLIANCE:
Show here who is responsible for this
operation/task, and their contact
numbers.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 14 of 19
APPENDIX 1
Risk Assessment
Please refer to Document Reference:
HSQE-RAMS-006 Risk Assessment Template with Guide List
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS-001 HSQE Manager HSE February 2023 04 Page 15 of 19
APPENDIX 2
COSHH Assessment
This form provides details of the hazards and risks associated with the task/substance identified below. You must read
the information provided and implement the measures specified on the form.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS-001 HQSE Manager HSE February 2023 04 Page 16 of 19
APPENDIX 2
COSHH Assessment
Relevant Risk Assessment RA-02
form number:
Medical advice: Consult doctor if problem persists
Name, address and Refer MSDS
telephone number of
supplier of substance:
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS-001 HQSE Manager HSE February 2023 04 Page 17 of 19
APPENDIX 3
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS-001 HQSE Manager HSE February 2023 04 Page 18 of 19
APPENDIX 3
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS-001 HQSE Manager HSE February 2023 04 Page 19 of 19
Risk Assessment
Death 5 Frequently 2 10 8 6 4 2
1 5 4 3 2 1
Nakheel Refurbishment
Persons 1. Employees 2. Contractors 1. ISG 2. TC Supervisor
Responsibility
Affected 3. Client Employees 4. Public 3. TC Operator 4. TC Workforce
3 Work at Height - Damaged scaffold parts; Fall from height, scaffold 2 5 4 20 - Double width towers must be given preference – narrow width towers only to be used in areas where it is 5 2 10 2,3,4
more than 3m - incompetent persons; collapse, property not possible to place a double width or in very limited spaces
- Assembly, dismantling or altering must be carried out by PASMA trained person/s
Mobile Scaffold - uneven surfaces; damage.
- The ratio of the minimum base dimension to the height of the working platform shall not exeed 1:3 ratio.
(Working at height - uninspected scaffolding; - Access up and down from working platforms should never be from outside the scaffold, only by the internal
on mobile - Failure to erect as per Serious injury, fatality, ladder frame and through the trap doors.
aluminium tower manufacturers multiple fatalities. - Trap doors must be closed when using the platform.
recommendations - PASMA trained inspector must inspect and tag tower from first use, at 7-day intervals and when major
scaffold (more than
alterations have been made
3m) - All brakes deployed and functional prior to work is carried out on the platform
- If complete guardrails have been correctly installed, It is recommended NOT to use a safety harness when
working on lightweight aluminium mobile towers (in line with PASMA recommendations).
- Constructed as per manufacturer’s instructions
- 3T (Through the Trap) method implemented when assembling/dismantling towers
- ISG Visual Standards should be posted on all towers
- Towers must meet the requirements of EN1004
- Narrow width towers 2.4m and above must deploy 4 stabilisers
- Double width towers 3m and above must deploy 4 stabilisers
- Where the deployment of stabilisers in the manufacturer’s instructions is more stringent than stated above,
the manufacturer's instructions will be followed.
- Should the scaffold require repositioning, this must be done when no personnel are on the working
platform.
- Exclusion zones deployed with physic barriers prior to work commencement
- All tools must be tethered when working at height.
- A fiberglass mobile tower must be used for electrical work being completed at height as it is non-conducted
and spark resistant.
FORM REF: HSQE-FOR-045a AUTHORISED BY: HSQE Manager | DEPARTMENT: HSQE | DATE OF ISSUE: November 2023 | ISSUE NUMBER: 06 Page 1 of 5
RA RISK RATING RESIDUAL RISK
Risk & Persons
Item Activity Hazard Control Measures Required Responsibility
Concequences Affected Severity Likelihood Risk Severity Likelihood Risk
No.
4 Manual Handling - Wrong body posture - Major or minor body 1,2,3 4 4 16 - All involved persons for the activity of manual handling needs to undergo safety induction, task briefing, 4 1 4 2, 3, 4
- Uneven Surfaces injuries TBT and awareness training before starting the task;
- All activities involving manual handling must have appropriate planning;
- Poor housekeeping - Fracture
- Pre-check of the route to be taken to identify and clear any obstructions;
- Sharp edges - Hand injuries - Ensure that the work area is free from any obstruction before starting any manual handling activity;
- Failure of lifting - Head and eye injuries - All materials to be lifted must be assessed and checked before starting any manual lift;
- Lack of physical space - Foot and leg injuries - Appropriate manual handling technique must be followed accordingly to avoid back injuries;
- Repetitive movements - Bruises and cuts - Use the power of your legs rather than you back to avoid any back injuries;
- Poor workplace design - Strains and Sprains - If doing manual tandem lift, assess and do trial lift first for the material before proceeding;
- Back injuries - Ensure that the manual handling activity is competently supervised;
- Do not overexpose a person to a manual handling activity. Plan the activity and assign a workers rotation;
- Ensure that all sharp edges have been safely covered or protected before starting any manual lifts;
- Assess the work space if needed before starting manual handling. Do not push through the activity if the
space or access is obstructed with unwanted materials;
- Conduct regular housekeeping around the work area before and after the task;
- Ensure that all operatives who are involved in manual handling are using the standard 5-point PPEs and
task specific PPEs.
5 Use of Hand Tools A- Misuse of hand tools Damaged Tools, 2 3 3 9 - Hand tools shall not be kept on walkways. 3 1 3 2, 3, 4
B- Improper maintenance Improvised Tools, Sharp - Hand tools shall be kept in tool boxes, specific & designated areas for storage whenever not in use &
should not be kept unattended at any time.
C- Homemade handtools Edges, Fall of Tools
- All tools shall be inspected for any damages on daily basis and at regular intervals.
from Height - Tie off tools with a tool teather to prevent their fall while working at height.
- Ensure that no homemade/makeshift or any altered tools are used at the site.
A- Cuts, lacerations, - Ensure the operatives are wearing hand gloves during the activity.
bruises - Ensure to isolate the area below scaffolding when using hand tools on at height.
B- Frequent / prolonged - Ensure hand tools are in good condition when received from store or supplier.
use of hand tools can - Provide Appropriate PPE.
- Choose the Safest Tools for the task.
cause soreness, aches,
- Conduct regularly training and workshops on the safe use of Hand Tool
pains, and fatigue. - Never carry sharp tools with a pointy end in pocket.
- Always be aware of people around you when using hand tools
- Always use the right tools for the job
- Only operate tools according to manufacture instructions
6 Housekeeping - Scattered Materials - Major and minor Head 1,2,3,4 3 4 12 - Provision of approved, dedicated and secured materials storage area. 3 1 3 2, 3, 4
- Dust Injuries - Training and awareness to all workforce and staff regarding the importance of housekeeping;
- Ensure that material storage entry and exit points are visible and free from any obstruction;
- Accumulated cut materials - Eye Irritation
- Cut small materials must be stored in safe designated area or inside a safe skip box;
- Combustible Materials - minor/ major Eye - Appropriate segregation of materials must be done as per item and away from open access;
- COSHH Materials Injuries - Waste management and segregation must be as per approved site plan;
- Fumes - Fire - Designated COSHH/ chemical room must be established on site;
- Spills/ stagnant water - Asphyxiation - All COSHH materials must be segregated as per item with visible labeling;
- Obstructed Access - Shortness of breath - Used COSHH materials must be securely covered and stored in designated safe area only;
- minor or major Head - Provide the MSDS and COSHH assessment for all available Chemicals on site, and ensure the availability
when needed;
Injuries
- Liquid chemicals must be stored on top of a portable drip tray or might be provided with a dedicated storage
area, safe and secured 110% Fireproof bund to avoid any spillage.
- Chemical waste must be disposed and be collected by approved collection local authority;
- If all combustible materials cannot be collected immediately, it must be initially secured or identified with
visible barrier and warning signage;
- Ensure the availability of Spill kits nearby works involving chemicals;
- Avoid accumulation of combustible materials and secure it on separate collection skip for further removal;
- No Brooms are to be used when cleaning floor, vacuum cleaners must be used to avoid accumulation of
dust and airborne particles.
- Conduct regular housekeeping and removal of unwanted materials before and after the task.
- Adopt a 'clean as you go' policy at all times.
7 Cutting Stations/ - Trailing cables - Head and body injuries 1,2 4 4 16 - All stationary cutting and work stations must be identified/ installed rigidly safe only in designated secured 4 1 4 2,3,4
work station (e.g. - Open and cut cables - Amputation area with exclusion zone;
- Only competent and trained persons are allowed to work or use the cutting/ work stations;
Benchsaw, Bench - Unguarded machine - cuts and laceration
- Provide all necessary permit-to-work, TBT, and task briefing before starting any works;
drill, Chop saw, - Rotating parts - Major or minor finger - Awareness training must be done to all involved persons for safe operation of cutting/ work stations;
steel benchsaw) - Loose machine parts injuries - Avoid un-authorized entry around the work area and keep the station visibly accessible to the assigned
- Scattered cut materials - Eye injuries operator at all times;
- Noise and Dust - Electrocution - Ensure All machines to be used are fully inspected by a competent electrician before deployment for safe
- Saw dust - Asphyxiation and usage on site;
- Moving cut blade shortness of breath - Operator to Ensure the emergency stop button for the machines are operational before starting job;
- Avoid overexposure of operators and follow safe manual handling technique while using cutting stations to
- damaged, uninspected - Asthma
avoid any accidents and injuries;
blade/ drill bit - Puncture wounds - Regular inspection (Monthly) must be done to all work/ cutting station machines;
- Unsecured electricity - Fire - Source of electricity to where the machine will be plugged must be identified and secured;
- Avoid trailing electrical cables. Keep the cables hanged or permanently secured away from open access.
- Safe operation manual and operator's details must be posted or be available in the work/ cutting station;
- All damaged rotating and moving parts must be removed immediately from duty to avoid re-usage;
- All timber chop saws must be provided with appropriate vacuum extraction;
- Avoid accumulation of saw dust around the work area to prevent any possible fire;
- Keep and use the safety guard for the machine as an additional protection regularly;
- Use regularly the designed push-stick if cutting small materials to avoid sudden finger injuries;
- Provide separate waste skip for accumulated cut material waste;
- Provide nearby and accessible Fire Extinguisher/ fire point for the work/ cutting stations;
- Conduct regular housekeeping before and after the task;
- Persons involved for the task must use the 5-point PPEs and specific PPEs (earplug, faceshield) at all
times.
FORM REF: HSQE-FOR-045a AUTHORISED BY: HSQE Manager | DEPARTMENT: HSQE | DATE OF ISSUE: November 2023 | ISSUE NUMBER: 06 Page 2 of 5
RA RISK RATING RESIDUAL RISK
Risk & Persons
Item Activity Hazard Control Measures Required Responsibility
Concequences Affected Severity Likelihood Risk Severity Likelihood Risk
No.
26 Scaffolding - Poor workmanship - Falling from height, 1,2,3 5 3 15 - All tube and fitting scaffolds are to be designed in line with the requirements of NASC guidance TG20. 5 1 5 2,3,4
Erection and - untrained erector, - Collision with - All types / brands of system scaffolding used shall conform to the relevant BS EN 12810/12811 standards,
- All scaffolds are to be designed by a competent person, in accordance with the ISG Temporary works
Dismantling - Poor standard of lighting, scaffolding,
procedure
- Weather condition. - Collapse of the - Ensure the scaffolding is erected and dismantled by trained and competent persons
- Lack of edge protection, platform, - All scaffolds shall be erected, modified or dismantled in accordance with the requirements of NASC
- Unstable ground surface. - Cuts/severe injuries. guidance SG4
- Where scaffolding works are to be completed over public areas, these shall be subject to a robust
exclusion zone with interconnected red pedestrian barriers and clear warning signage, with a marshal to
secure the zone.
- Where an exclusion zone cannot be provided, a climbing fan shall be employed and shall rise and lower
with the erection or dismantling respectively.
- All tools shall be tethered. Materials shall be tethered in high-risk environments.
- A separate documented safe system of work for dismantling shall be in place. This shall clearly detail the
striking sequence, methodology and works-specific rescue plan.
- Only electric winch or braked pulley wheels are permitted and shall be subject to a lifting plan.
- Lapped boards are not permitted without justification.
- Gaps are not permitted between boards (including between inside standards).
- Twisted boards are not permitted.
- Horizontal protruding tubes are not permitted.
- Materials may only be stored vertically when restrained and the scaffold has been designed to
accommodate the load.
- Scaffold sheeting and debris netting shall be branded wherever possible and shall be fire retardant to the
LPS 1215 specification for external materials;
- Scaffolding must be erected on level or smooth ground; avoid sloping, uneven surfaces, overhead wires or
other obstructions when erecting scaffolding.
- Adequate guardrails must be fitted on the scaffold to prevent personnel from falling.
- All scaffold components, including the operating platforms and planks, must be carefully inspected before
and after use. Check for rust, breakage, cracks, and any warping or deterioration.
- Overloading of the platform must be avoided.
- Extra care should be taken, and workers should wear appropriate fall protection equipment when
dismantling any scaffold. In addition, each platform tier should be taken entirely apart before progressing to
the next.
- Adequate lighting must be provided/fitted around the scaffolding for proper illumination.
- The scaffolding must be inspected upon first use, at 7-day intervals, and following any modification by
competent inspector.
27 Cabling - Untrained personnel, - Severe injuries 1,2,3 4 2 8 - The operative must be trained and competent. 4 1 4 2,3,4
- Working at height, - Death to the personnel, - Ensure complete isolation of connected live services before such cabling activity.
- Proper or appropriate working at height equipment, such as podium step, and mobile tower, must be
- Cable pulling, - Fall from height,
selected for such cabling activity.
- Working at height, - Cut/abrasion, - The cables must be adequately managed to prevent trips of fall hazards.
- Damaged hand tools. - Shock/electrocution. - Appropriate PPE must be thoroughly worn by the operatives engaged in the activity.
- Energised system. - Do not leave the hand tools unattended on the ground when not in use.
- Hand tools to be stored directly in a toolbox when not in use.
- All tool used during work at height needs to be tethered and secured to avoid a sudden drop.
- Tools shall be of good quality and replaced if the fault is broken.
- No homemade tools shall be used. Tools shall only be used for the purpose they are designed for.
28 DB Installation - Working at height, - Back injury, 1,2,3 4 3 12 - Don’t work on live equipment; isolation and multi-lock system shall be followed. 4 1 4 2,3,4
- Shifting of materials, - Hand injuries/cuts, - Don’t hang cloth or any material on electrical equipment.
- Electrical DB or switchgear should not be handled with wet hands or bodies.
- Manual handling, - Flying debris,
- Electrical switches or access to them shall not block by any material.
- Cable pulling, - Fire and explosion. - Use appropriate PPE while working on electrical DB.
- Overloading, - Use safe work practices every time electrical equipment is used.
- Energised System. - Know the location and how to operate shut-off switches and/or circuit breaker panels. Use these devices to
shut off the equipment during a fire or electrocution.
- Limit the use of extension cords. Use only for temporary operations and then only for short periods. In all
other cases, request installation of a new electrical outlet.
- Place exposed electrical conductors (such as those sometimes used with electrophoresis devices) behind
shields.
- Ensure any electrical equipment brought to work by employees, or any hired or borrowed, is suitable for use
before use and remains appropriate by being maintained as necessary.
- Ensure there are no trailing cables that can cause people to trip or fall
- Ensure workers know how to use the electrical equipment safely while working on DB installation.
33 Installation Chilled A- Inadequate working A- Cuts, lacerations, 1,2,3 4 3 12 - Ensure the area is well ventilated, adequate lightening arrangements are in place and free from obstruction 4 1 4 2,3,4
Water Pipes and platfrom i.e. poor lighting, bruises - The area is clean and clear
- Operatives involve in the task are competent and trained for the job
FCU’s ventilation B- frequent / prolonged
- Power tools are PAT tested, color coded and in good condition
B- Insufficient work use of hand tools can - Right tools are used for the job
area/space cause soreness, aches, - Competent supervision in place
C- Incompetent workforce pains, and fatigue - Lifting gears and equipment used are load tested and certified
D- Inadequate handtools or C- Dehydration - All the hot work activity is controlled by permit to work system
power tools D- Fall from - Well maintain site and housekeeping on site all the time
E-incompetent height/scaffolding - Ensure workers are aware of the area, workers working nearby and services in area
- Daily activity briefing is conducted and recorded
supervision/monitoring collapse
- Content of permit is implemented as per the work permit requirement
D- Uninspected lifting gear E- Fall of tools and - Signs and posters are in place.
F- Welding/Grinding equipment
activities F- Failure of lifting gear
G- Inadequate G- Fire/Burn, electrical
housekeeping shock
H- Collision/striking with H- Damage to existing
existing services services
FORM REF: HSQE-FOR-045a AUTHORISED BY: HSQE Manager | DEPARTMENT: HSQE | DATE OF ISSUE: November 2023 | ISSUE NUMBER: 06 Page 3 of 5
RA RISK RATING RESIDUAL RISK
Risk & Persons
Item Activity Hazard Control Measures Required Responsibility
Concequences Affected Severity Likelihood Risk Severity Likelihood Risk
No.
35 Installation of A- Inadequate working A- Cuts, lacerations, 1,2,3 4 4 16 - Ensure the area is well ventilated, adequate lightening arrangements are in place and free from obstruction 4 1 4 1,2,3
Water Supply PPR platfrom i.e. poor lighting, bruises. - The area is clean and clear
- Operatives involve in the task are competent and trained for the job
Piping ventilation. B- frequent / prolonged
- Power tools are PAT tested, color coded and in good condition
B- Insufficient work use of hand tools can - Right tools are used for the job
area/space cause soreness, aches, - Competent supervision in place
C- Incompetent workforce pains, and fatigue. - Lifting gears and equipment used are load tested and certified
D- Inadequate hand tools or C- Dehydration - All the hot work activity is controlled by permit to work system
power tools D- Fall from - Well maintain site and housekeeping on site all the time
E-incompetent height/scaffolding - Ensure workers are aware of the area, workers working nearby and services in area
- Daily activity briefing is conducted and recorded
supervision/monitoring collapse
- Content of permit is implemented as per the work permit requirement
D- Uninspected lifting gear E- Fall of tools and - Signs and posters are in place.
F- Welding/Grinding equipment
activities F- Failure of lifting gear
G- Inadequate G- Fire/Burn, electrical
housekeeping shock
H- Collision/striking with H- Damage to existing
existing services services
38 Pressure Testing A- Incompetent workforce A- Major/minor injuries 1,2,3 3 3 9 - Trained and skilled workers are assigned to the task 3 1 3 1,2,3
of PPR Water B- Lack of supervision to workers due to - Workers are familiar with the use of a compressor and other equipment used during the test
- Activity is supervised and monitored by a competent person
Supply Pipes C- Uninspected equipment pressure release
- All power tools and other equipment’s are third-party inspected and certified
D- Use of gauges without B- Failing to exert actual - Pressure gauges are calibrated and calibration certificates are available
collaboration pressure - Whip lashes are used for the temporary discharge lines
E- Insecure joints C- Slip, trip and fall - Area is barricaded and signs and posters are displayed
F- Failure to comply with the D- Contamination, the - A watcher is assigned during the breaks
permit system release of contaminated - Permit to work system is implemented if required
G- Water spillage on the water - Conduct regularly training and workshops on the safe use of Hand Tool
- Access to the site is controlled all the time.
floor E- Unauthorized workers
H- Unprotected/barricaded accessing the location
areas
15 Testing and Energized system, Electrocution, 1,2,3 4 4 16 - Ensure that the testing activity is only as per the approved plan. 4 2 8 2,3,4
commissioning Untrained personnel, Poor quality, - Conduct task briefing and TBT to all involved persons before starting any testing and commissioning works
on site.
Activity Un-authorized persons, Severe burns,
- Additional awareness will be given to all operatives and staff regarding the testing activity.
PPE, False alarm, - PTW and NOC (if required) must be issued and available on site for verification.
Working at height, Falling from height, - Team involved for the testing needs to identify the location of the testing and source panel/ operation board
Working with a rotating Cuts or severe injury, or DB to ensure that everybody is aware of the planned testing.
machine Open and unsecured - Ensure that the area of testing and commissioning is having exclusion zone, isolation and identified entry
panels, point with warning signage to avoid any un-authorized entry.
Noise - Implement the LOTO (Lockout/ Tagout) system to ensure safe process of testing (minimum two locks)
- All panel sources must have dedicated supervision to avoid un-authorized operation.
- Inform the building premises about the test to be done as an additional awareness.
- Ensure that all persons involved are using the mandatory 5-point PPEs and task specific PPE (e.g. earplug,
etc.) with facemask while or during the operation.
- Only suitably experienced or qualified competent personnel to be used to carry out testing
- Suitable height equipment must be selected, such as fibreglass podium step to avoid electrocution.
30 Hot Works - Confined - Fire & 1,2,3 5 3 15 - All involved persons in the activity must be trained and competent. 5 1 5 2,3,4
space, explosion, - The operator must be experienced/trained in using the power hand tools.
- The grinder machine must be pre-inspected before deployment to the site.
- PPE, - Burns,
- Ensure that the grinding or welding machine is PAT tested and colour coded.
- Lack of - Property - The welding or grinding machine must have a dedicated guard and handle.
permit to damage, - Do not remove the handle and guard when in use.
work - Fatality. - Ensure the cables for the machine are secured and free from any cuts.
system, - The distribution board for the machine must be secured entirely as per standard (e.g., with RCD, safely
- Access cover, can be used for 110V tools, etc.) before usage.
and - Ensure the hot work or grinding area is free from combustible materials.
- Full-time fire watchman to be deployed for the activity.
egress.
- Hot work Permit to be furnished, and precautions must be verified commencing.
- PTW copy to be available visibly onsite for cross-checking.
- Assess the hot work area safely before starting.
- The hot work area must have a dedicated exclusion zone with visible warning signage.
- Prepare and install a dedicated fire point/Fire extinguisher and additional Fire blanket nearby the hot work
area.
- All involved persons must know the importance of onsite fire points.
- Tools shall be of good quality and replaced if the fault is broken.
- No homemade tools shall be used. Tools shall only be used for the purpose they are designed for.
- Adequate access and egress free from obstruction must be provided.
- There must be adequate lighting in the working area.
- Miniumum 1-hour fire watch must be in place following hot works completion.
FORM REF: HSQE-FOR-045a AUTHORISED BY: HSQE Manager | DEPARTMENT: HSQE | DATE OF ISSUE: November 2023 | ISSUE NUMBER: 06 Page 4 of 5
RA RISK RATING RESIDUAL RISK
Risk & Persons
Item Activity Hazard Control Measures Required Responsibility
Concequences Affected Severity Likelihood Risk Severity Likelihood Risk
No.
FORM REF: HSQE-FOR-045a AUTHORISED BY: HSQE Manager | DEPARTMENT: HSQE | DATE OF ISSUE: November 2023 | ISSUE NUMBER: 06 Page 5 of 5