Subject: Document Submittal For Closeout Submittal Ref.: Rev 0

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

Review Comment Sheet (Project – 1713AC)

Subject : Document Submittal for Closeout


Submittal Ref. : DMC/HSSE/INS/599/2023.
Rev 0

Status: “B” Approved As Noted


1. Ensure that all cables are removed and rerouted from the construction area and safe
from people movement.
2. Ensure hazard signage is provided for all DB’s and other electrical equipment.
3. Ensure emergency contact is displayed for all DB’s and other electrical equipment.
4. Ensure that disciplinary action must be taken against the violators at the same time.
5. Ensure DM HSE Technical Guidelines (whichever appropriate) are
followed/considered.
6. All activities must comply with legal and contractual requirements related to
Environmental Health & Safety.
7. Ensure that Project HSE Plan is perfectly implemented at the site.

Regards,
Date: 16/01/2024

______________________________________________________________________________________________________________
Arif & Bintoak Consulting Architects & Engineers, P.O. Box 3670, Dubai – UAE, Tel: +971 (4) 3372888; Fax: +971 (4) 3370352;