FILL COMPACTION FOR

KING SALMAN ENERGY PARK - SPARK


INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

METHOD STATEMENT
FILL COMPACTION USING RIC/DC

Page 1 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

METHOD STATEMENT FOR RIC

PROJECT : SPARK INFRASTUCTUR AND


MAINTAINENCE BUILDINGS
CLIENT : ARAMCO
CONTRACTOR : BRANCH OF SINOHYDRO CORPORATION LTD

CONSULTANT : NA

LOCATION : SPARK, ABQAIQ, KINGDOM OF SAUDI


ARABIA

DOC. NO.: GH-SH- MS-RIC-R0-SPARK

This document is property of Geoharbour. Its total or partial reproduction is strictly forbidden by any means, as well as its distribution
to third parties without the express written consent. Any copy of this document in digital or paper support will be considere d a not control
copy. The only valid copy is the last one approves located in the document manager tool.

Issue No. / Date Rev. No. Prepared By Revised By Approved by


00 /17-01-2022 00 Qian Kun Louai Al Jannoun Xu Liang

Page 2 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

AMENDMENT RECORD

This document is reviewed to ensure its continuing relevance to the systems and process that it describes. A record of
contextual additions or omissions is given below.

Revision Date Description of the revisions Elaborated By Revised By Approved By

00 17/1/2022 First Issue Qian Kun LJ Xu Liang

Page 3 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

TABLE OF CONTENTS
1. PURPOSE 7

2. PROJECT DESCRIPTION 7

3. STANDARDS AND REFERENCES 10

4. COMPACTION CRITERIA 10

5. PROJECT ZONING 11

6. SEQUENCE OF WORKS 11

7. GENERAL WORK SEQUENCE 11

8. SPECIFIC SEQUENCE OF WORKS 12

9. POST-TESTING AND REPORTING 13

10. PRE-TESTING FOR CALIBRATION WORKS____________________________________ 13

10.1 Work Preparation 13

11. CALIBRATION WORKS (TRIAL AREA) 14

12. REPORTING 16

13. QUALITY CONTROL-POST-TESTING 16

14. RESOURCES & RESPONSIBILITIES 16

14.1 PERSONNEL 16
14.1.1 Site Management 16
14.1.2 Site Staff 17
Page 4 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

14.2 Compaction Equipment 17


14.3 Approved Third Party 18
14.4 Material Handled 18

15. RECORDS 19

16. HSE

16.1. RISK MANAGEMENT 19

16.2. EMERGENCY MANAGEMENT AND EVACUATION PLAN 19

16.3. SITE SECURITY PLAN AND ACCESS CONTROL 20

16.4. PERMIT TO WORK (PTW) 21

16.5. TRAFFIC MANAGEMENT 22

17. QA/QC 23

17.1. Quality Assurance Records _ 23

17.1.1 Site Engineer In-Charge 23

17.1.2 Quality Control Inspector 24

17.1.3 Project Engineer General 24

17.2 Commencement System 25

17.3 Technical Data Presentation 25

17.4 Examination of Hidden Works 25

17.5 Quality Responsibility and Regular Meetings 26

17.6 Quality Confirmation and Evaluation 26

17.7 Examination of Materials 26

17.8 Records 27

Page 5 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

ABBREVIATIONS
CLIENT ARAMCO
CONSULTANT NA
MAIN CONTRACTOR BRANCH OF SINOHYDRO CORPORATION L.T.D
SUBCONTRACTOR GEOHARBOUR SAUDI CO. LTD
RFI REQUEST FOR INSPECTION
ITP INSPECTION AND TEST PLAN
MS METHOD STATEMENT
NCR NON-CONFORMITY REPORT
GL GROUND LEVEL
PPE PERSONAL PROTECTION EQUIPMENT
RIC RAPID IMPACT COMPACTION
DC DYNAMIC COMPACTION
CPT CONE PENETRATION TEST

Page 6 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

1. PURPOSE

The Purpose of this method statement is to present the methodology of fill compaction using Rapid Impact
Compaction (RIC) is an innovative and alternate method for soil improvement for shallow depths up to 4m
using impact compaction and Dynamic compaction (DC) for lifts more than 4m. The RIC method has been
used successfully in projects with varying soil conditions and depths. The RIC rig is adaptable to most
soils, materials with percentages up to 15% fine content with minimal clay/silt content. This method
statement follows Aramco standard referred as SAES-A-114 which is related specifically to rapid impact
compaction works. Whereas DC technique will follow the standard referred as SABP-A- 073.

In this method statement, we state our intentions for managing and supporting the project and the specific
approach that will be taken for certain key aspects. The main content includes the requirements, materials,
equipment and HSE regulations for works, the procedures need to be performed in all operations and the
method to check on site the material, spacing, depth and all other parameters related to RIC works.

The purpose of this method statement is to give details on the Rapid Impact Compaction (RIC)/Dynamic
compaction technique for fill compaction as per project specification and requirements.

2. PROJECT DESCRIPTION

Branch of Sinohydro Corporation LTD awarded the project referred as SPARK infrastructure &
Maintenance at King Salman Energy City (SPARK), located in Abqaiq, Kingdome of Saudi Arabia.
ARAMCO planned to develop the infrastructure phase and maintenance buildings.

This package has been awarded to M/s Branch of Sinohydro Corporation LTD where scope is to execute
the earthwork by cut and fill. The scope of Geoharbour Saudi Co. LTD is to perform compaction for the
proposed backfill areas with various fill thickness using RIC and DC.

Page 7 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

Figure 1: Site location (Google Map) & General layout

The project referred as SPARK INFRASTRUCTURE & MAINTENANCE BUILDINGS with


area around 1.65 million m2 is located in SPARK, ABQAIQ, KINGDOM OF SAUDI ARABIA. As
per the requirement, the main contractor scope is to prepare the site to the final ground level
by cutting and filling.

Page 8 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

Page 9 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

Page 10 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

Figure 2: Cut-Fill General Layout

3. STANDARDS AND REFERENCES

The present Method Statement is based on the following Reference Documents:


a) Geotechnical investigation report prepared by RGF of ref: KHO-GEO-PR-20-27-01
b) SAES-A-114: excavation and backfill
c) SABP-Q-014: Rapid Impact Compaction (RIC)
d) SABP-A-073: Dynamic compaction (DC)
e) Specification: Rough Grading & site preparation specifications of ref: BI - 25-00040 JO – 0013 –
DOC no. SE-010056
f) IFC Drawings

4. COMPACTION CRITERIA

The design criteria for the backfilling compaction activity will be based on following:
For Areas which will be compacted by RIC/DC
70% Relative density (performance line) as per project specification se-010056 section 3.8

Page 11 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

5. PROJECT ZONING

As mentioned before, the project consists of fill and cut areas. The work methodology will follow the
zoning provided in Appendix A. The project will consist of seven zones referred as Zone 1, 2, 3, 4, 5,
6 and 7.

The cut areas are highlighted in red color whereas the fill area is highlighted in green color. Each
Zone will consist of blocks (100m X 100m) and each block will have ID.

6. SEQUENCE OF WORKS

With reference to the type of soil, the fines content, the depth of improvement and the project’s
acceptance criteria, we believe that Rapid Impact compaction technique is the right and most
appropriate methodology to improve the mechanical properties of the fill layers and make it
competent enough to bear the load of the projected developments. This technique as per SAES-A-
114 will be limited to 4m thickness. The thicknesses more than 4m will be compacted using Dynamic
compaction technique.
7. GENERAL WORK SEQUENCE

To execute the compaction and soil improvement works, the following


sequence will be followed:
• Natural grade elevation survey before Filling and compaction
• Clearing and grubbing inspections (if any);
• Establish Grids every 100m x 100m;
• Rough grading activities: Cutting, filling and Inspections;
• Setting out of sectors, compaction points by GPS;
Page 12 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

• Trial areas to be conducted as mentioned in section 9.2.


• RIC compaction as per the setting out drawings numbering sequence
• Post-CPT tests for the compacted area as mentioned in section 9
• Final grading and proof rolling means grading at final levels. No grading will be done
if the fill requires two stages or more of filling/compaction. Grading will be at the final
level only. Request for Inspection (RFI’s) for final inspection will be raised only after
post-CPT had been conducted, prior to handing over of the areas to avoid re-work.
• Inspection and Test Plan (ITP) and Inspection Checklist (IC) has to be developed
based on the approved Method Statement as acceptance criteria of each process.

• For areas where Trials & Post CPTs have been completed, the Trial/Calibration reports
including post treatment calculations based on the actual post quality control test in
relation to the project specifications shall be submitted to
• Project Management Representative (PMT).
• Reports submittal including; drawings, post-testing and results.

8. SPECIFIC SEQUENCE OF WORK:


Accordingly, we may identify the following:

For Cut Areas:


Pre-CPT testing will be performed for the verification of sabkha or loose layer.in case CPT shows
loose layer, compaction to achieve as per project requirement. After compaction for loose area,
post-CPT testing will be performed to verify the achieve required compaction.
In case, Pre-CPT achieves the design criteria, no compaction is
required. Final Grading and Proof rolling to be provided before
execution of next activity.
For Fill Areas:
• Clearing & grubbing if needed according to the project requirements.
• Preparation of the fill thickness as per final ground level. However, 0.5m depth of existing
soil to be considered loos due to equipment commuting and fill for first phase shall be
maximum to 3.5m.
• Perform Trial areas for RIC and DC
• Compaction for areas with maximum lift 4m using RIC technique
• Compaction for areas with lifts more than 4m using DC technique

Page 13 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

• Final Grading and Proof rolling


• Carry out Quality control testing by post-CPT tests down to the thickness of fill (1 CPT/
4 ,000 m2), then issuance of handing over reports after rough grading and final ironing
using roller compaction.
• Submission for reports

The post-CPT tests will be witnessed by 3 rd party company and reports will be stamped and
signed by 3rd party company.
To execute the compaction works, the following sequence is to be followed;
1. Full ground survey on each area to be compacted.
2. Establishing grids/blocks and zones for the areas
3. Setting out compaction points by GPS
4. RIC/DC compaction as per the setting out drawings numbering sequence.

9. POST-TESTING AND REPORTING

To ensure the stability of the CPT equipment and trafficability, the top surface of soil shall be
leveled with a maximum acceptable slope of 5 % .
In case of presence of fine-grained materials with a percentage of fines more than 15%, then the
existing soil can’t be used to fill the craters and an imported granular material shall be mixed with
the fine material in order to reach an acceptable fine content percentage. This platform could
be used to backfill the RIC craters during compaction.
All backfilling material required prior, during or after the compaction works should meet the
following specifications:
- Well graded granular material with up to 15% fine contents (passing sieve #200)
- Non-plastic
- Free from organic matter and deleterious substances, physically stable in water.

10. PRE-TESTING FOR CALIBRATION WORK.

GH will perform 1 pre-CPT for fill depth to enable for final design grid spacing and blows number.
The pre-CPT/post-CPT testing will be performed by C PT calibrated machine.

10.1 WORK PREPARATION


• The compaction area will be free obstructions and other trades.
• Survey of the trial area is to be undertaken prior to compaction works,
Page 14 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

• The survey is to be extend to additional width of compaction area as per site


condition.
• The trial area is to be set out by GPS with visible markers on the ground for operator
guidance.
• The locations of the Pre-Compaction CPT’s will be identified and marked and prior to
calibration work.
11. Calibration Works (Trial Area)

Calibration works will be carried out in order to optimize the production parameters by applying
the preliminary compaction parameters with not less than 30m X 30m in plan dimensions with
more than one grid spacing for both techniques RIC and DC. The trial will be done to determine
the grid and spacing in addition to the number of blows for RIC and DC.
The grid and spacing for trials depend on the thickness of the fill.
At the end of the calibration exercise, the following main parameters will be determined:
- Grid spacing which shall be used for all project areas.
- Drop height
- Optimum number of blows per print
- Number of phases
- Type of pounder and its diameter A t r a i l calibration report will be provided including pre &
post CPT-test results, comparison pre/post-tests, analysis of project criteria. The energy
parameters shall be always monitored on site and adjusted when necessary to ensure the
homogeneous improvement all over the site. Detailed RIC/DC prints layout will be prepared
according to the trials output for each Compaction stage.

Conducting CPT during the progress of the works will assist in evaluating the compaction process
prior to final testing. CPT Rig and an example of treatment results after compaction are shown in
below figure.

Page 15 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

Page 16 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC-IMB-SH-MS-0004 METHOD OF STATEMENT

TREATMENT OF ONE SITE AS EXAMPLE

Page 17 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC- METHOD OF STATEMENT

12. REPORTING

The Reporting will be done by GEOHABROUR and checked by approved 3rd party engineering
company. The report will include but not limited to the following:
• Introduction
• Layout for the block, Block ID
• Location for the trial areas and coordinates
• Grids used and number of blows
• Presenting Pre-CPT testing
• Presenting Post-CPT testing with detailed analysis
• Calculation for bearing pressure and settlement
• Final Test Results.

13. QUALITY CONTROL-POST-TESTING

GH will perform at fill area 1 post-CPT to fill thickness or maximum 4m, one (1) every 4,000m2 for
verification of results. The post-CPT testing will be witnessed by approved third party company.

14. RESOURCES & Responsibilities

14.1 PERSONNEL

14.1.1 Site Management


• Project Manager/Site Manager
• Reviews and approves project schedule during execution
• Hands on project management and actively manages the project plan, deliverables,
dependencies, and outcomes for selected project.
• Prepares Project Initiation Report and Project Schedule
• Defines and manages overall change control processes and quality assurance aspects of the
project.
• QA/QC Inspector.

Page 18 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC- METHOD OF STATEMENT

14.1.2 Site Staff


• Supervisors
• Ensure compaction rigs are in working order
• Data is loaded to and from the on-board computer
• Check compaction starting and end points are correct as per drawings
• Oversee surveyors on site
• Monitor operators and dolly change team.
• Plan and manage all activities related to plant and machinery.
• Ensure that consumables supplies are in stock during the project duration.
• Ensure that all preventative maintenance is carried out at specified intervals.
• Supervise / oversee any repairs or refurbishments done to the machines and plant.
• Rig Operators
• Draughtsman
• Prepare shop / working drawings for the site team
• Prepare as built drawings at end of project.

14.2 COMPACTION EQUIPMENT


Geoharbour will utilize multiple RIC machines (9 tons) for 4m lifts, The hammer is coupled to CAT
345 crawler excavator (or similar). The machines are equipped with on board computers that
monitor the compaction process. The equipment monitors drop weight height, count and
settlement of the compaction foot.

RIC MACHINE

Fast mobilization and maneuverability of the excavator allow for faster completion times and
Page 19 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC- METHOD OF STATEMENT

adaptation to most site terrains. Import of fill material and placing can follow relatively close to the
compaction work.

For lifts more than 4m, Dynamic compaction technique will be used. The Dynamic Compaction
(DC) method involves compacting the subsurface soils by lifting and dropping a very heavy
tamper. The dynamic impaction energy was generated by the falling tamper to densify the soils in
the influence zone, thus increasing the ground bearing capacity and decreasing the compressibility
of the soils. Here are some dynamic compaction pictures.

14.3 Approved Third party

The approved third party will be supervising the post-CPT including witnessing the tests, and issuance
CPTs reports signed and stamped.

14.4 MATERIAL HANDLED


The Contractor shall use the approved material Source from the site for filling to be used during
compaction process. The material will be used to fill the prints/craters created by the rapid impact

Page 20 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC- METHOD OF STATEMENT

compaction and Dynamic compaction. All other earthworks related to the work, the material shall
comply with SAES-A-114 and according to the project specification.

15. RECORDS

All test reports related to Rapid Impact Compaction (RIC) will be submitted to the project quality
department for submittal to Project Management Representative (PMT). Upon completion of each
activity box, detailed reports including post quality control test and analysis shall be submitted to PMT.
A report will be prepared after all compaction works and testing is completed.

• Survey data for the RIC points


• Post-compaction CPT data.
• On board machine output
• Analysis of post-compaction data and calculations

16. HSE

16.1 RISK MANAGEMENT

Prior to any work commencing on site, GH will ensure that the application of risk assessment and
method statement are in place, as per procedure
GH has produced a Risk Register which are the main risks pertaining to the project from inception
to completion. See Attached-Risk Register. All risk assessment shall be checked by the site safety
department. Any anomalies within the documents shall be amended prior to work commencing.
Risk assessments shall be reviewed annually, unless required to do so after any changes to the
task, incidents or other, added control measures and any other inputs / outputs.

All Subcontractors shall conduct risk assessment on all of their activities, and take appropriate
actions to mitigate the risk to an acceptable level.

16.2 EMERGENCY MANAGEMENT AND EVACUATION PLAN

All emergency situations will be dealt with as per GH-Emergency Preparedness Procedure.
The emergency preparedness plan shall be completed before work commences on site. This plan
shall be communicated to all personnel working on site via the induction process and updated
through toolbox talks. All emergency telephone numbers shall be displayed at various locations

Page 21 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC- METHOD OF STATEMENT

around the site.

The emergency preparedness plan shall be reviewed and updated at regular intervals not
exceeding 6 weeks.

BASIC ACTIONS:

Accident:

• Immediately inform others who may be in danger


• If people are injured call for the appointed first aiders to help in dealing with the casualty
• Assess the situation, call for relevant emergency services and guide them to the area.
• Inform Site Management of the situation.

Fire:

• Immediately inform others who may be in danger, sound the fire alarm
• Call the emergency services and ensure that they are guided to the scene.
• Assess situation and with minimal personal risk, fight the fire with the appropriate equipment.
• If the fire cannot be extinguished or contained, evacuate the area using the designated
exits signs, and move to the assembly point.

16.3 SITE SECURITY PLAN AND ACCESS CONTROL

GH shall take all reasonable steps to ensure that only authorized persons are allowed onto site or
into areas where construction work is taking place.

A typical list of those persons would include:

• Contractors or employees carrying out construction work


• Those who need to enter the work area for purposes connected with the work (e.g.
architects, engineers and representatives of the client).
• Individuals or organizations that have a statutory right to enter the work area (e.g.
enforcing authorities).

Page 22 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC- METHOD OF STATEMENT

Visitors (see below):


• A perimeter fence/ hoarding will be erected around the whole site to protect client staff,
visitors and members of the public from the construction work being carried out. The fence
will be at approximately 2.4 meters in height with vehicular and pedestrian accesses. To
achieve protection for the workforce from any contact with vehicles, a separate pedestrian
access will be created.
• GH will continually assess the measures adopted to protect the public.
• Suitable and enough warning signs will be displayed on the perimeter fence/hoarding and on
the approaches to the site.
• Site Security will be placed at all entrances to site to ensure that control is being implemented.
Security guards shall be in place at all time and the security supervisor shall monitor their
performance. The security guard will register all personnel and vehicles that enter onto the
site and ensure that the driver is informed where to report to.
• During night security, guards will patrol the site at regular intervals.
• Suppliers will park their vehicles in the designated areas on site when loading / unloading of
materials is taking place, and shall never leave their vehicles unattended.
• All visitors or subcontractors shall be directed to make themselves known to the site security
and site safety department.

16.4 PERMIT TO WORK (PTW)

In high-risk activities where additional control measures are required GH shall implement a
permit to work system, based upon a suitable risk assessment.

The PD / PM shall be the overall permit to work control manager

A permit to work appointed person (PTW AP) shall be nominated by the PD / PM.

A number of activities have been identified, which require having a safe system of work, including
permits to work. The permits to work shall include the following:

a. Hot works

b. Excavation
Page 23 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC- METHOD OF STATEMENT

c. Lifting permit

Each of these can be operated only when the correct safe system of work is in

place. All records will be kept in the safety department office.

Periodical monitoring of the designated task will be done by the site safety department.

All other hazardous activities identified which may require having a permit to work issued will be
dealt with in line with the consultant.

Subcontractors, when working in high-risk activities shall either use their own safety system of
work, including permit to work or adhere to GH safe system of work.

Only the PTW AP’s can issue any permit to work.

PTW AP Names:

No1: Name:

No 2: Name:

16.5 TRAFFIC MANAGEMENT

• The Police will summarily deal with traffic incidents on the Employees properties. Conviction
of a Traffic Violation may result in a disciplinary action against the individual.
• Traffic routes that pass near or through the construction site shall be clearly identified.
• All traffic routes through the construction site shall be segregated from pedestrians to avoid
contact.
• All plant operators which include both GH and Sub-Contractors shall have a valid driving
license for the class of vehicle they are tasked to operate.
• All plant / vehicles operators shall provide proof of competency, vehicle and equipment
worthiness through 3rd party certificate, before commencing work.
• All access and egress onto site shall be controlled by site security.
• The site management team shall identify areas for lay down of equipment and ensure that
Page 24 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC- METHOD OF STATEMENT

adequate routes to these areas are available.


• The site shall endeavor to create a one-way system to adequately control the flow of traffic
through the site.
• Maximum permitted speed on site will be 20km/h and subject to change dependence of risks,
and all construction plant vehicles shall have reversed horn and flashing amber warning light
on when maneuvering around the site.
• Adequate signage shall be in place to warn of traffic dangers, speed and any other risks.

17. QA/QC
17.1 QUALITY ASSURANCE RECORDS

RIC is a real time adjustment technique, whereby all production parameters are fully recorded,
controlled and adjusted during execution stage according to soil behavior during production, and soil
conditions for every area. A detailed quality assurance procedure is implemented during RIC works,
which relies on:
✓ An automated record of all production parameters
✓ A continuous record of ground response during compaction

This systematic control will guarantee that the required degree of compaction and project
requirements are reached at every treated point. Following our quality assurance system, all below
listed information and others being related to the RIC/DC procedure will be recorded and reported to
the client on daily basis

17.1. 1 SITE ENGINEER IN-CHARGE

a. Take Full responsibility for construction quality.


Page 25 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC- METHOD OF STATEMENT

b. Organize to execute the quality system documents. Ensure the efficient implementation of
the quality system.
c. Control quality goal.
d. Specify the duties within project department.
e. Take charge of the contract modifications Forward the modifications to operation division
and clients, and coordinate between these two parties.
f. Stipulate and implement quality benefit-penalty rules. Deny any quality doubt.
g. Organize regular examinations, critiques, reconstructions and appraisals.

17.1.2 QUALITY CONTROL INSPECTOR

a. Supervise the implementation of quality duties by personnel and report to QC


Supervisor/Manager.
b. Assist Construction Manager to implement quality system. Produce the construction
organization design, quality plan and construction scheme of key constructions.
c. Assist Construction Manager to control, manage and supervise the construction quality.
Organize the regular examinations, critiques, reconstructions and acceptance on quality.
Guide and supervise the quality documenting by people on site.

17.1.3 PROJECT ENGINEER GENERAL

d. Well informed on quality system, quality plans, and quality standards, regulations and
specifications, and implement it.
e. Well informed on drawings and design requirements, and implement quality plans. In each
phase, supervise and guide key procedures, control the nodes construction. Identify and
correct quality doubts and troubles timely, and be advisable. Deny quality affairs if
necessary.
f. Organize team chiefs to implement self-examination and document the results.
g. Take charge of the data analysis collected in construction, and provide modifications on
construction techniques and parameters.
h. Leaders and chiefs should carry out the respective duties specified in the company’s
handbook. Establish and improve quality guarantee system. Strive for a clearly defined duty,
executed supervision, implemented rules and ensured quality.

Page 26 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC- METHOD OF STATEMENT

17.2 COMMENCEMENT SYSTEM

Prior to the commencement of construction, checks should be conducted on preparations.


Preparations are met, commencements are allowed. The commencement reports are
managed by Project Department. Commencements should own the following conditions.

1. Contract presentation. Leaders organize administrative personnel to familiarize with


contract stipulations, e.g., schedule, quality requirements, quantities and special requirements.

2. Satisfactory materials, machineries, apparatus and labors.

17.3 TECHNICAL DATA PRESENTATION

Technical data presentation is taken by Engineering Division and prepared by Engineer General. Prior
to the production, Engineer General should understand the design data, familiarize with design
specifications and requirements, and then present data to the subordinators, teams and relevant
departments. Project Engineers are responsible for producing construction data documents and
guidelines of key procedures. Contents include engineering features, engineering conditions,
geological conditions, structure details, construction techniques, construction material specifications,
construction methods, operation requirements, quality criteria and safety attentions.

The documents should be distributed to chiefs of each tier. Documents are saved and controlled by
Engineering Division. Upon commencements, Chiefs should organize personnel to go through the
documents and to inform their quality.

Standards and requirements. If necessary, technical staff should present the documents on site. The
documents should be standardized, clear and signed by checkers and relevant units.

17.4 EXAMINATION OF HIDDEN WORKS

Examinations of hidden works are taken by Engineering Division. Once the Chief Technician
approves the examination, notify Project Engineer to examine and approve. If construction
ceases for a long period after the checks, recheck and re-approve the works before restart the
constructions. After the rechecks, report to Inspectors for signatures.

Page 27 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC- METHOD OF STATEMENT

17.5 QUALITY RESPONSIBILITY AND REGULAR MEETINGS

17.5.1 After an individual completion, team chief is responsible for the self-examination of the
works quality. No movement into the next step without approved quality.

17.5.2 Administrative and technical staff examine on site regularly. Examination contents
include the abidance of operators with specifications, procedures, criteria and data
presentations.
17.5.3 Quality Regular Meetings. A monthly full-scale examination is leaded by Project
Manager and involved by relevant departments. Through the examination, identify doubts
and problems timely, propose advices, specify people in charge of reconstruction and
times.
17.6 QUALITY CONFIRMATION AND EVALUATION

17.6.1 Quality evaluation determines the completion level of construction units.


17.6.2 Quality confirmation and evaluation should be objective and conducted in a timely
manner. The evaluators should be responsible for the evaluations.
17.6.3 Well informed on and abide by mandatory construction regulations. Supervise the
examination and quality confirmation in accordance with the mandatory regulations.
17.6.4 Accident investigation should abide by three "should", i.e., should investigate the
causes, should talk to the people at fault, and should cope with countermeasures,
and prepare the investigation reports. The people at fault should be subjected to
appropriate penalty or accusation.
17.6.5 17.6.5 Administrative punishments are executed on the following cases, including
intentions to cover, lie and delay the accidents, to process the accidents by itself, to
process the site without abiding the three should, to destroy the site, to impede the
investigations, to resist inquiries, to refuse to surrender relevant documents, and to
supply faked documents. If a crime is committed, the case should be handed over
to justice authorities.
17.7 EXAMINATION OF MATERIALS

All raw materials, products and semi-products should bear quality certificate. The materials
are subjected to appearance check, type and model examinations.

Page 28 of 29
FILL COMPACTION FOR
KING SALMAN ENERGY PARK - SPARK
INFRASTRUCTURE & MAINTENANCE BUILDING
KINGDOM OF SAUDI ARABIA

DOC- METHOD OF STATEMENT

17.8 RECORD

Each probe is going to be recorded manually and with an electronic data-logging based

system. The following data is recorded manually on the daily record sheet:

a. Project name and location


b. Rig number
c. RIC Print
d. Date and time of commencement and completion of area
e. Settlement
f. Record all abnormalities and their reasons accordingly
g. Actual Platform Level

Page 29 of 29