PTW Test

Total Marks – 100

1. This Procedure is applicable to Operations carried out by


a) contractor workers
b) company or contractors / sub-contractor workers
c) contractors or sub-contractor workers
2. Authority, that will be affected by any work executed in the vicinity of the area under his
responsibility and therefore can be affected by any possible hazardous events as outcome of
the authorized work.
a) AUTHORIZED ENTRANT
b) AREA OF OPERATIONAL OWNERSHIP
c) AFFECTED PARTY
d) AFFECTED EMPLOYEE
3. PTW is mandatory for _________________ activities.
a) Non Routine, SIMOPS and CONOPS
b) Routine, SIMOPS and CONOPS
4. PTW is applicable to operations carried out by _____________________
a) Company & Contractor
b) Contractor & Sub-contractor
c) Company & Contractor / Sub-contractor
5. How many supplementary certificate do have additional to Permit to Work?
a) Five
b) Three
c) Six
d) Seven
6. A person formally authorized in writing by his Employer after formal training and assessment
to aid in the facilitation of the PTW procedure for particular type of job is called
a) Authorized Fire Watcher
b) AREA AUTHORITY
c) COMPETENT PERSON
7. During SIMOPS activity at Bhit wellhead between E&C and maintenance team _____________
will act as Affected party for E&C related permits.
a) Resident Engineer
b) Shift Engineer
c) Maintenance Superintendent
d) Production Superintendent

8. The Performing Authority of one discipline shall act as Performing Authority for another
discipline;
PTW Test

Yes No
9. For appointment of Authorizing Authority for Non-SIMOPS Cold Work Permit,
______________ the shall nominate personnel
a) Discipline Superintendent
b) Site Manager
c) Site HSE Representative
10. Selection and Appointment of Issuing Authority for Maintenance In-house Permits shall
appoint by
a) MS& UH
b) PS & UH
c) E&C Resident Engineer
11. There are ____ types of the permit to work that company shall implement on its worksites;
a) Two
b) Five
c) Threee
12. No one can authorize / issue a work permit for work that he will carry out by himself.

Yes No

13. Contractor’s manpower may be authorized as _______ to accept all Work Permits after
fulfilling the requirements of this procedure.
a) AREA AUTHORITY
b) Performing Authority
c) AFFECTED PARTY
14. An entry into a Confined Space where breathing apparatus shall be worn is
a) Class A
b) Class B
15. Confined Space Entry Certificate revalidation shall complete by _________________________
a) Performing, Issuing and Area Authorities
b) Performing, Issuing and Area Authorities
c) Performing, Issuing and Area Authorities
16. Permit to Work Dossier to be maintained and update by ___________________________
a) HSE Coordinator
b) Shift Engineer
c) Document Controler.
17. Incase active Work Permit (e.g. Cold or Hot) and / or certificate (e.g. Energy Isolation, Safety
Defeat, Vehicle / Equipment, Radiography, Excavation Clearance, Medium Voltage, Confined
PTW Test

Space Entry) is lost during the execution of work the __________________________ shall
immediately stop the work.
a) Area Authority
b) Performing Authority
c) Issuing Authority
18. Gas tests should be made for:
a) Oxygen deficiency or enrichment.
b) Weather condition.
c) Gas Leakage
19. A _________________ Permit is required for work not involving hot work or naked flame work
that is also potentially hazardous, which may expose personnel, equipment or the environment
to hazard.
a) Hot Permit
b) Confined Space Permit
c) Vehicle Permit
d) Cold Permit
20. Electrical potential difference that is equal to or greater than 50 volts and is less than 1000 volts.
a) Low Voltage
b) High Voltage
c) Medium Voltage
21. Rescue plan is mandatory to be attached with_____________
a) Cold Work Permit
b) Hot Work Permit
c) Confined Space Entry Permit
22. Sequence of Hot Work Permit Issuance, Approval & Authorization and Acceptance signatures is
as follows:
A
a) Requesting Authority;
b) Permit Issuing Authority;
c) Authorization Authority;
d) Authorizing SIMOPS Authority (SOA) (shall countersign PTW in case of SIMOPS/ CONOPS);
e) Affected Party (shall sign as per guidelines mentioned under section 5.13, Otherwise N/A);
f) Area Authority;
g) Performing Authority.

B
PTW Test

a) Requesting Authority;
b) Issuing Authority;
c) Authorization Authority;
d) Authorizing SIMOPS Operations Authority (SOA) (shall countersign permit in case of
SIMOPS);
e) Affected Party (shall sign as per guidelines mentioned under section 5.13; otherwise Not
Applicable - N/A);
f) Area Authority;
g) Performing Authority.
23. Authorized Gas Tester (AGT) shall be nominate and approved
by_________________________________
a) Issuing Authority
b) Authorization Authority;
c) Performing Authority.
24. ________________ and ______________ Authorities shall ensure that Emergency Rescue Plan is
tested prior to start the activities in the Confined Space;
a) Area & Issuing Authority
b) Area & Authorization Authority
c) Area & Performing Authority
25. Hot Work in Confined Spaces shall be controlled through the Cold Work Permit, Hot Work
Permit and Confined Space Entry Certificate together.
a) True
b) False
26. For working in confined space flammability shall be less than of Lower Flammable / Explosive
Limit (LFL/LEL).
a) 1.5%
b) 2%
c) 1%
d) 0%
27. Vehicle / Equipment Entry certificate will be required if the vehicles fitted with spark arrestors
remain out of the range of the Plant areas marked with the Hazardous area identification.
a) True
b) False
28. Energy Isolation certificate is required when any work is being carried out so that all sources of
hazardous energy associated with the equipment shall be locked and tagged in the position that
isolates personnel from the hazardous energy.
a) True
b) False
PTW Test

29. Process, mechanical and instrumentation Isolations shall be carried out by the Isolation
Authority (IA) under the supervision of the respective site ___________________________
where necessary;
a) Shift Engineer (Permit Issuer)
b) Discipline Engineer (Requesting Authority)
c) Electrical Engineer (Competent Person)
30. ___________________ shall be acted as “Competent Person when excavation beyond 1.5
meter.
a) Electrical Engineer
b) Resident Engineer
c) Civil Supervisor
31. Who will signed off PTW at completion of job in working area.
a) Performing Authority and Area Authority
b) Performing Authority and Issuing Authority
c) Performing Authority and Authorizing Authority
32. If an emergency alarm sounds, all work permits are suspended, work will cease, and the work
site left in a safe condition, so far as is reasonably practicable and time allows;
a) True
b) False
33. __________________ Shall sign PTW when activities to be performed by another party i.e. E&C
and Drilling in his area of Responsibility (i.e. Site Manager)
a) Issuing Authority
b) Area Authority
c) Affected Party
34. The Performing Authority of one discipline can be Performing Authority for another discipline;
a) True
b) False
35. SIMOPS and CONOPS are routine activities, risk assessment is required and PTW is not
mandatory.
a) True
b) False
36. Operational owner of drilling wells for the Contractor PTW system is,
a) Drilling Manager
b) Drilling Engineer
c) Company Man
d) Field Manager
37. Work on or Adjacent to Live Electrical Conductors shall not be undertaken on;
a) Low Voltage Electrical Equipment
b) Medium Voltage Electrical Equipment
c) High Voltage Electrical Equipment
PTW Test

38. A Safety Defeat Certificate defines the requirements and guidelines for all activities requiring
temporary overrides, inhibits, links and bypasses applied over the process safeguarding systems
and process alarms in order to manage the workflow.
a) True
b) False
39. Sequence of Confined Space Entry Certificate Issuance and Acceptance signatures is as follows:

A
 Requesting Authority;
 Issuing Authority;
 Area Authority;
 Performing Authority;

B
 Authorized Authority
 Issuing Authority
 Affected Party
 Accepting Authority
40. The color of Radiography Certificate is _____________________.
a) Yellow
b) Blue
c) Pink
d) Grey
41. All underground services shall be regarded as “live”.
a) True
b) False
42. Before Issuance of excavation clearance certificate, inspection of excavation area shall be
performed by_______________ along with ______________ Area Authority and Competent
Person when excavation deeper than 1.5 meter
a) Performing Authority along with Authorized Person
b) Performing Authority along with Issuing Authority
c) Performing Authority along with Area Authority
43. Deep excavations ________________ shall be carefully designed and planned under the
responsibility of Competent Person;
a) (≥1.5-meter-deep)
b) (≥1.7-meter-deep)
c) (1.5-meter-deep)
PTW Test

44. _______________________ shall act as Radiation Protection Supervisor in Radiography


Certificate.
a) Performing Authority
b) Issuing Authority
c) Discipline Engineer
45. When servicing and/or maintenance is performed by different discipline, department crew or
other group and they are operating on the same piece of equipment or where energy isolation
or de-isolation from one job may affect the safety of another job, _____________________shall
be used
a) Group Lockout/Tagout devices
b) Temporary Removal
c) Long Term Isolation (LTI)
46. Energy Isolation Procedure is provided in _______________________
a) Annex - D
b) Annex - C
c) Annex – H
47. The permit will specify the time in which it is valid. Its validity will be no more than the normal
working shift. If the work is not completed within the time specified, the permit may be
extended as long as it does not over run the initial shift time;
a) True
b) False
48. In case of loss of the Original Active Work Permit and / or the certificate, the Performing
Authority shall immediately stop work and force close the active Work Permit.
a) True
b) False
49. On completion of work, the issued copy (hard or card copy) of the permit shall be signed off by
the Performing Authority, and the Area Authority at site to indicate completion, subject to a
satisfactory inspection of the worksite.
a) True
b) False
50. Prior to signing off the permit, __________ shall conduct an inspection of the worksite to
confirm that it has been left in a satisfactory condition;
a) Area Authority
b) Performing Authority
c) Issuing Authority