Download as pdf or txt
Download as pdf or txt
You are on page 1of 34

UNIVERSITY OF SAN JOSE – RECOLETOS

Corner P. Lopez & Magallanes Streets, Cebu City

SCHOOL OF ENGINEERING

CONSTRUCTION METHODS AND PROJECT MANAGEMENT:


SUMMARY OF NOTES, TERMINOLOGIES, AND SAMPLE PROBLEMS

In Partial Fulfillment of the Requirements


for the Degree of Bachelor of Science in Civil Engineering

SUBMITTED BY:
LACABA, JOVBEN SHERJAD G
BSCE-4

SUBMITTED TO:
Engr. Yuriy Jose B. Sesican

S.Y. 2023-2024
MODULE 1 - WHAT IS WHO IS A PROGRAM
INTRODUCTION TO MANAGEMENT? MANAGER?
PROJECT Management is a process of The one who is tasked with
MANAGEMENT planning, organizing, management of multiple
leading, and controlling. projects that may require
------------------------------- assignment of additional project
The efforts of organization and managers for support.
Project is a non-routine, non- all other resources to achieve
repetitive undertaking normally the stated goals. The art of In such cases the project
with discrete time, financial and getting things done through manager is taking on the role of
technical performance goals. people. It is the overall a program manager.
planning, control, and
It is made up of a group of coordination of the project from THE PROJECT LIFE
interrelated work activities inception to completion. CYCLE
constrained by a specific:
SCOPE, BUDGET, and WHAT IS - Initiation Phase
SCHEDULE - Planning Phase
CONSTRUCTION?
- Design Phase
CHARACTERISTICS It is the mobilization and - Construction Phase
utilization of personnel, - Commissioning Phase
OF A PROJECT
materials, and equipment. - Closeout Phase
Scope – each project is unique
To assemble them in a specific INITIATION PHASE
and must have a written scope
of works. site in accordance with
- Receives project
drawing, specification, and
authorization
Time – all project must have a contract documents.
- Write project
definitive beginning and end.
requirements
Cost – all projects are WHAT IS document
constrained by limited - Assess capability and
CONSTRUCTION
monetary funding resources. capacity
MANAGEMENT? - Select delivery
THE PROJECT Project team comprising the
strategy
TRIANGLE - Establish project
client, the designer,
organization structure
consultant, and the
- Write project
contractor.
SCOPE management plan
Working together at the
PLANNING PHASE
construction stage of the project
with the common objective to - Functional analysis
best serving the owner’s - Alternative studies
interest. - Site selection
QUALITY - Hazardous material
WHO IS A PROJECT and geotechnical
MANAGER? studies
COST TIME - Utility and third-party
The one who plans and controls coordination
the project execution. - Environmental
The project compliance
manager must
have an
adequate
authority to
exercise the
responsibility
and prior to
experience
managing
similar project in
the past.
DESIGN PHASE engineering seal, are referred to PROGRESS
as the designers of record; and PAYMENTS – management of
DESIGN CRITERIA – will continue to provide the progress payments begins with
Codes, design standards, following design services during the contract specifications
document standard – drawing, construction. clearly stating: how the
specification, estimate, contractor’s work progress is to
schedule, calculation, project Receives and be measured, how payments
requirements definition, design responds to construction are determined based on the
schedule, project budget contractor requests for measured progress, and what
information. Review and documents and reports are
CONCEPTUAL recommend acceptance of required to be submitted by the
DESIGN – code analysis, contractor submittals called for contractor to justify the payment
zoning analysis, topographical, in the drawings and request.
boundary, existing utility, specifications with respect to
geotechnical, environmental the construction deliverables. COMMUNICATIONS
survey. Review change requests and MANAGEMENT – it is important
estimate costs for change for projects that impact the local
PRELIMINARY orders. community or businesses, are
ENGINEERING – layout of potential interest of the
refinement, Archi and SCHEDULE media, and where there are
Engineering definitions, CONTROL – project manager political stakeholder
discipling coordination, focuses in the big picture, the
preliminary analyses and master schedule. To manage
calculation, construction interfaces between contractor,
schedule, staging plan, cost third party, and owner’s
estimates. construction activities. For
larger and more complex
FINAL DESIGN – final projects you will require the cm
plans, elevation, section, and to provide a scheduler to
schedule. Detail development, monitor construction progress
final technical specification, using scheduling software to
discipline coordination. State maintain a master schedule of
and local legal requirements- construction activities. for
bid forms, bonds, prevailing smaller projects the use of hand
wages drawn bar charts worked out
CONSTRUCTION PHASE directly with the re(s) should be
adequate to serve as a master
It is procured by the owner, schedule.
combined with the agency’s
COST AND CHANGE
own forces, construct the
project facilities, and fabricate CONTROL – cost control’s
and install equipment. The work objective in construction is to
is done in accordance with the complete the contracts within
plans and specifications budget.
developed during the design DOCUMENT
phase. The project’s highest CONTROL – it
level of activity, in terms of is the
numbers of personnel and cost management of
incurred per day, occur during records
construction. generated during construction… needed to handle reporting o
construction
ROLE OF THE report of a items
OWNER – make timely and of importance,
decisive decision, retain a conferences
construction manager with the
consultant, delegate levels of contractor or
authority through the project other parties,
team to handle, agreements
made, special
ROLE OF DESIGN
CONSULTANT – one who notes regarding
equipment or
produced the contract drawings
and specifications and “sealed” organization,
labor condition.
them with their professional
COMMISIONING PHASE mark up the drawing as
THIRD PARTY WORK
Is a process for validation of changes occur. The designer of
– involves the relocation or
building equipment and systems the record reviews, approves,
rearrangement of existing
in coordination with operations and documents the changes
facilities that impact project
personnel and third parties. into final as-built drawings and
construction including: utilities
(electric power, gas, telephone, conformed specifications. As-
The owner minimizes – the risk
cable), public infrastructure built drawings will save
of delays, cost overruns,
(highways, bridges, streets, significant life cycle costs and
underperforming heating, air
sewer, water), railroads. avoid potential safety hazards
condition and ventilation
during operations and life of the
system, electrical power system
QUALITY facilities.
failure and faults, and unreliable
MANAGEMENT - • review of
support equipment. PROJECT CLOSEOUT
contract documents to verify
that quality aspects have been PHASE
Things to accomplish during
considered • surveillance of commissioning phase: initiate a Final settlement of:
construction for adherence to commissioning plan, assure project contracts, acceptance of
quality requirements •in process system coordination through contract deliverables, collection
and receiving point quality integration testing, require the of contract documents and
inspections • audits of operation and maintenance records, and approval of final
consultant, contractor, and manuals well in advance of payments, demobilizing the
supplier quality programs for construction completion. Allow project team, closing of funding
adequacy and compliance. adequate time to train the staff and financing agreements, and
with the new equipment, performing an evaluation of
SAFETY
document the as-built project success and lessons
MANAGEMENT – planning of
conditions and become familiar learned.
work to avoid personal injury
with them, accept equipment
and property damage. Activities: prepare a
after it is in operation to assure
Monitoring of work to provide punch list of incomplete
a full warrant period.
early detection and correction of contractor items, lead a final
unsafe practices and conditions. OWNER FURNISHED walk-through inspection of
Protecting adjacent public and EQUIPMENT – almost every job constructed facility, resolve an
private properties to provide for will have some level of owner outstanding changes/claim,
the safety of the public. furnished equipment due to long develop a plan to demobilize
Providing safety education and lead time, specialty equipment, agency and consultant staff,
incentive programs. Complying or unknown requirements at the assess and document lessons
with occupational health and time of bidding. The project learned on project, obtain
safety acts (OSHA). manager is responsible to fully project acceptance from
integrate and account for the principal stakeholders,
owner furnished equipment with celebrate project completion.
the rest of the construction
project work. Requirements:
Manuals and Trainings,
TRAINING AND certificate of beneficial
TRANSITION – under general occupancy, guaranties and
direction of the project manager warranties, as-built drawings,
and through supervision of the final inspection, resolve
commissioning manager, outstanding claim/disputes, final
training is conducted by the payment, commissioning.
contractor or its subcontractors
or suppliers and takes place Administrative:
after the acceptance of demobilization of project team,
equipment and O&M manuals, closure of project funding and
and before operations begin. financing, securing the
The contractor must submit a disposition of project records,
detailed outline of the training conducting a lesson learned
program with the O&M manuals. project evaluation, achieving
closure and acceptance with
AS-BUILT stakeholders, celebrating
DOCUMENTATION – the project success.
construction contractor should
3. Earthwork Estimation specifications, and drainage
requirements.
MODULE 2 – Cut and Fill: Balancing the
quantities of material excavated 3. Material Handling
CONSTRUCTION (cut) and material added (fill) is
METHODS FOR essential to control project Material Sourcing: Efficiently
costs. source and manage materials,
EARTHWORKS including identifying suitable
Software Tools: Modern borrow pits and transportation
------------------------------- software like AutoCAD Civil 3D logistics.
aids in precise earthwork
Earthworks serve various 4. Equipment Selection
calculations and design.
essential purposes in
construction: Appropriate Equipment: Select
Earthwork Equipment equipment suitable for the
Foundation Preparation: project's scale and
Excavators: Versatile
Earthworks provide a stable and requirements to optimize
equipment for digging and
level foundation for structures, productivity.
removing earth material
ensuring their longevity and
efficiently. 5. Safety Measures
safety.
Bulldozers: Used for pushing, Safety Protocols: Implement
Slope Stabilization: They are
grading, and leveling earth strict safety measures to protect
crucial for preventing erosion
surfaces. workers and the environment
and landslides on slopes, which
can damage infrastructure. Loaders: Essential for moving during earthwork operations.
materials and loading trucks 6. Quality Control
Infrastructure Development:
quickly.
Earthworks are integral to
Inspection and Testing:
constructing roads, highways, Graders: Precision equipment Regularly inspect and test
railways, airports, and other for leveling and grading earthwork to ensure it meets
transportation networks. surfaces to desired slopes. specified standards and project
Drainage: Proper grading and Dump Trucks: Transport earth requirements.
earthwork design facilitate materials within the construction
efficient water drainage, site, optimizing logistics.
preventing flooding and erosion. EARTHMOVING
Compactors: Ensure proper MATERIALS AND
Earthwork Methods compaction of fill materials to
enhance stability.
OPERATIONS
1. Mass Diagrams
Earthmoving is the process of
Earthwork moving soil or rock from one
Mass Diagram: A graphical
representation showing Management location to another and
changes in elevation along a processing it so that it meets
1. Site Investigation construction requirements of
linear project route, helping
optimize cut and fill quantities. Soil Analysis: Conduct location, elevation, density,
comprehensive soil and moisture content, and so on.
Benefits: Mass diagrams assist Activities involved in this
geological studies to
in cost estimation and efficient process include excavating,
understand site conditions and
material management. loading, hauling, placing
material properties.
(dumping and spreading),
2. Cross-Sections
Geotechnical Reports: Use compacting, grading, and
Cross-Section: A depiction of geotechnical reports to guide finishing. Efficient
the earthwork profile earthwork design and management of the
perpendicular to the project construction decisions. earthmoving process requires
alignment. accurate estimating of work
2. Design and Planning quantities and job conditions,
Uses: Cross-sections aid in proper selection of equipment,
Precise Earthwork Plans:
visualizing and designing and competent job
Develop detailed plans based
earthwork components management.
on site investigations, including
accurately.
cut and fill calculations, grading
Trafficability is the ability of a at which the soil just begins to EXCAVATING AND
soil to support the weight of crumble when rolled into a
LIFTING
vehicles under repeated traffic. thread 1⁄ 8 in. (0.3 cm) in
Trafficability is primarily a diameter Auger: Drills holes for poles,
function of soil type and posts, soil sampling, and ground
moisture conditions. The plasticity index (PI) is the improvement.
numerical difference between
Loadability is a measure of the the liquid and plastic limits and Booms: Extended booms used
difficulty in excavating and represents the range in for long-reach applications.
loading a soil. Loose granular moisture content over which the
Breaker/hammer: Vibratory
soils are highly loadable, soil remains plastic.
hammer used to break up
whereas compacted cohesive
concrete and rock.
soils and rock have low SOIL VOLUME-
loadability. CHANGE Bucket, 4-in-1: Also called a
multipurpose bucket or
Soil is considered to consist of CHARACTERISTICS multisegment bucket. Such
five fundamental material types: buckets are capable of
gravel, sand, silt, clay, and Bank – materials in its natural
performing as a clamshell,
organic material. Gravel is state before disturbance. dozer, or scraper, as well as a
composed of individual particles Loose – materials that has conventional excavator bucket.
larger than about 1⁄ 4 in. (6 mm) been excavated or loaded. Bucket, articulating clam: A
in diameter but smaller than 3
hydraulic clamshell bucket with
in. (76 mm) in diameter. Rock Compacted – materials after
full rotation.
particles larger than 3 in. (76 compaction
mm) in diameter are called Bucket, cemetery: Used for
cobbles or boulders. Sand is A soil increases in volume when digging straight wall trenches.
material smaller than gravel but it is excavated because the soil Bucket, clamshell: Performs like
larger than the No. 200 sieve grains are loosened during the clamshell described in
opening (0.7 mm). Silt particles excavation and air fills the void Section 5.
pass the No. 200 sieve but are spaces created. As a result, a
unit volume of soil in the bank Bucket, ditch cleaning: Wide,
larger than 0.002 mm. Clay is shallow, and smooth edged
composed of particles less than condition will occupy more than
bucket; may be perforated for
0.002 mm in diameter. Organic one unit volume after
drainage.
soils contain partially excavation. This phenomenon
decomposed vegetable matter. is called swell. Bucket, drop center: Used for
Peat is a highly organic soil trenching. The drop center
When a soil is compacted, some excavates for pipe bedding
having a fibrous texture. It is of the air is forced out of the
normally readily identified by its while the sides excavate to the
soil's void spaces. As a result, required trench width.
dark color, odor, and spongy the soil will occupy less volume
feel. It is generally considered than it did under either the bank Bucket, general purpose:
unsuitable for any construction or loose conditions. This Standard excavator bucket.
use. phenomenon is called
Bucket, muck: Used for
Two principal soil classification shrinkage. excavating mud and muck;
systems are used for design usually perforated for drainage.
A soil’s angle of repose is the
and construction in US: Unified angle that the sides of a spoil Bucket, pavement removal: A
System and the American bank or pile naturally form with forked bucket used for removing
Association of State Highway the horizontal when the and loading pavement slabs.
and Transportation Officials excavated soil is dumped onto
(AASHTO). the pile. Bucket, ripper: The bucket sides
and bottom are lined with ripper
The liquid limit (LL) of a soil is Three principal categories: pit teeth to break up hard soil or
the water content (expressed in excavation, trench soft rock.
percentage of dry weight) at excavation, and excavating or
which the soil will just start to Bucket, rock: A heavy-duty
grading relatively large areas. bucket designed for loading
flow when subjected to a
standard shaking test. The volume of cut or fill between rock.
stations is then calculated,
The plastic limit (PL) of a soil is accumulated, and plotted as a
the moisture content in percent mass diagram.
Bucket, sand: Has a flat bottom SHOVELS (Operation and serving as the casing for the
and tapered sides to reduce the Employment) hole.
chance of soil cave-in.
Hydraulic shovel digs with a • Micro tunneling or utility
Bucket, side tilting: Can be tilted combination of crowding force tunneling is similar to the
for grading slopes and for and breakout (or prying) force. conventional tunneling except
ditching for the tunnel size and use.
Digging face easily formed
Compaction plate/tamper when excavating a bank or Repair and Rehabilitation of
hillside. Pipelines
Compaction wheel Coupler,
quick: Permits rapid exchange Ramping down shovel must Pipe bursting uses a high-
of attachments. dig a ramp down into the powered hydraulic or pneumatic
material until a digging face of piercing tool equipped with a
Cutter/processor: Power jaws suitable height is created. special bursting head to shatter
primarily used for crushing the existing pipe and enlarge
concrete. DRAGLINES (Operation and the opening.
Employment)
Drill, rock: Mounted on the end CRANES
of the stick to drill blast holes. Dragline is a very versatile
machine that has the longest Cranes are primarily used for
Grapple: Equipped with tong- reach for digging and dumping lifting, lowering, and
type arms for handling rock, of any member of the crane- transporting loads.
logs, and other materials. shovel family
Mobile telescoping boom
Pile driver/extractor: Used for CLAMSHELLS crane is capable of lifting loads
driving and extracting piles. to the top of a 24-story building.
Clamshells are commonly used
Shear: Primarily used for for excavating vertical shafts Operating radius is the
processing scrap metal but also and footings. horizontal distance from the
used for demolition. center of rotation to the hook
TRENCHING AND
Thumb, bucket: Attached to TRENCHLESS TECHNOLOGY Outriggers are beams that
bucket to provide a hook widen the effective base of a
capability. It can be retracted Trenching Machines and crane
when not needed Plows
Tipping load is a load that will
Plate line capacity is the bucket • Some of the types of trenching cause the crane to actually
volume contained within the machines available include begin to tip
bucket when following the chain trenchers, ladder
outline of the bucket sides. trenchers, and bucket wheel Heavy Lift Cranes are intended
trenchers. for lifting very heavy loads are
Struck capacity is the bucket usually crawler-mounted lattice-
capacity when the load is struck • Plows can be used to cut a boom models.
off flush with the bucket sides. narrow trench and
simultaneously insert a small Tower crane is widely used on
Water line capacity assumes a diameter cable or pipeline in building construction projects
level of material flush with the because of its wide operating
most soils.
lowest edge of the bucket. radius and almost unlimited
• Vibratory plows deliver a height capability. Major types of
Heaped volume is the maximum
more powerful cutting action tower cranes include horizontal
volume that can be placed in the
than static plows and can be jib, luffing boom cranes, and
bucket without spillage based
used to insert utility lines in hard articulated jib cranes. Types of
on a specified angle of repose
soil or soft rock. tower crane by method of
for the material in the bucket.
mounting include static (fixed
Trenchless Technology
HYDRAULIC EXCAVATORS mount) tower cranes, rail-
(Operation and Employment) • Pipe jacking involves forcing mounted tower cranes,
pipe horizontally through the mobile tower cranes, and
Hydraulic excavator equipped climbing cranes.
soil.
with a hoe front end.
• Horizontal earth boring is a Among these attachments,
Backhoe is an excavator concrete buckets, slings,
horizontal hole is created
designed primarily for special hooks, and load
mechanically or hydraulically
excavation below grade dropping tools (weights) are
with the pipe to be installed
most often used in construction The foundation of a structure supporting soil does not exceed
applications. supports the weight of the soil’s allowable bearing
the structure and its strength.
Skull cracker (wrecking ball)
applied loads. It
is a heavy weight that is hoisted Types of spread footing includes
includes the soil or
by the crane and then swung or individual footing, combined
allowed to drop free to perform rock upon which a
structure rests, as well footing, and mat foundation.
like a huge sledge hammer.
as the structural Mat or raft
Drop hammer is simplest form system designed to foundation consist of a heavily
of pile driver uses a similar transmit building loads reinforced concrete slab
action to drive piles. to support the soil. extending under the entire
LOADING AND A foundation is part of a structure, in order to spread the
building’s substructure – located structure’s load over a large
HAULING area.
below the surrounding ground
Fixed time represents those surface. - Floating
components of cycle time other
FOUNDATION SYSTEM foundation is a
than travel time.
type mat
Spot time moving the unit into Shallow foundation – if the foundation in
position to begin loading width of the foundation is which the weight
greater than the depth of the soil
Variable time represents the
excavated
travel time required for a unit to - Isolated Spread approx. equals
haul material to the unloading Footing, Wall the weight of the
site and return. Footing, Mat structure being
Rolling Resistance is primarily Foundation, erected.
due to tire flexing and Combined
penetration of the travel surface. Footing, and Strap The process of improving soils
Footing in place is called ground
Grade Resistance represents modification or soil
that component of vehicle Deep Foundation – if the width stabilization.
weight which acts parallel to an is smaller than the depth of the
inclined surface. foundation

Effective Grade state it as a - Pile Foundation,


grade (%), which would have a Pier Foundation,
grade resistance equivalent to and Caissons
the total resistance actually Foundation
encountered
Methods on describing a
Derating factor expresses
building’s construction based on
percentage of reduction in rated
the location of the lowest
vehicle power at various
building floor: slab-on-grade
altitudes.
construction, crawl space
Rimpull is the pull available at construction, and basement
the rim of the driving wheels construction.
under rated conditions.
Principal types of foundation
Drawbar pull is the power system include spread footing,
available at the hitch of a piles, and piers.
crawler tractor operating under
standard conditions. Spread Footing is the simplest
and the most common type of
------------------------------------------
building foundation. It usually
consists of a square or
MODULE 3 –
rectangular reinforced concrete
SUBSTRUCTURES pad that serves to distribute
AND FOUNDATIONS building loads over an area
large enough so that the
------------------------------------------ resulting pressure on the
Pile is a column driven into the for use where the Piers may be constructed in an
soil to support a structure by lower section would be open excavation, a lined
transferring building loads to a continuously excavation(caisson), or in a
deeper and stronger layer of submerged (hence not drilled excavation.
soil. subject to decay) while
the upper section A caisson is a structure used to
Piles is classified either end- would be exposed to provide all-around lateral
bearing or a friction piles. decay. support to an excavation. It is
- Bulb piles are either open or pneumatic.
TYPES OF PILES: timber,
precast concrete, cast-in-place also known as Drilled piers are piers placed in
concrete, steel, composite, and compacted concrete holes drilled into the soil.
bulb piles. piles, Franki piles, and
pressure-injected Soil identification includes
- Timber piles footings. They are a cohesionless and cohesive.
are inexpensive, easy special form of cast-in-
to cut and splice, and place concrete pile in Cohesionless soil is one
require no special which an enlarged whose grains do not show any
handling. It is also base (or bulb) is tendency to stick together.
subject to insect attack formed during driving.
and decay. The enlarged base
- Precast increases the
concrete piles may be effectiveness of the
manufactured in pile as an end-bearing
almost any desired pile
size or shape.
Commonly used The modern version of the drop
hammer is the pile driver. Cohesive soil, shear strength
section shapes include is provided primarily by the
round, square, and Driving operations consist of: attraction between soil grains.
octagonal shapes. lifting the pile, placing it into the
Advantages of leads, lowering the pile until it no
concrete piles include longer penetrates the soil under
high strength and its own weight, operating the
resistance to decay. drop hammer until the pile is
Heaviest type of pile driven to the required
available for a given resistance.
pile size.
- Cast-in-place Embankment Failures
concrete piles (or shell
piles) are constructed - Subsidence and
by driving a steel shell bulging
into the ground and - Formation of
then filling it with tension crack
concrete.
- Steel piles
are capable of
supporting heavy
loads, can be driven to
great depth without • Head block
damage, and are with guard
easily cut and spliced. • Hammer
Common types of steel • Leads
piles include H-piles • Catwalk
and pipe piles. • Pile
- Composite
piles are piles made up
of two or more different Pier is column, usually of
materials. This would reinforced concrete constructed
be an economical pile below the ground surface.
compacted soil Portland cement, clay
mass (bentonite), fly ash, sand,
lime, and additives.

Protection for Excavation Chemical grouting involves


and Workers the injection of a chemical into
soil. It is used primarily in
o Sloping or benching of sands and fine gravel to
the sides of the cement the soil particles
excavation together for structural support
o Supporting the sides or to control water flow.
of the excavation by
Modes of Embankment shoring Compaction grouting is the
Failures o Placing a shield process of injecting a very stiff
between workers and mortar grout into a soil to
- Face sliding into the sides of the compact and strengthen the
excavation excavation soil. Grouting materials include
- Face toppling into silty sand, cement, fly ash,
excavation additives, and water.

Heaving (or rising) of the Jet grouting employs a


bottom of the cut will occur due rotating jet pipe to remove soil
to the weight of the soil on the around the grout pipe and
sides of the cut. replace the soil with grout. As a
result, the technique is effective
Preventing Embankment over a wide range of soil types
failure to include silts and some clays.

• Side slopes may ------------------------------------------


be stabilized by
cutting them back - Upright MODULE 4 –
to an angle equal - Horizontal SUPERSTRUCTURE:
to or less than the Spacing of
angle of repose of crossbraces
CONCRETE, STEEL,
the soil, or by - Wale WOOD, AND
providing lateral - Crossbrace MASONRY
support for the - Vertical spacing
excavation. of wales and -------------------------------
• Dewatering the crossbraces
soil surrounding Construction Staking or
the excavation otherwise known as Site
• To protect more Layout Survey - is the process
Dewatering is the process of
permanent of interpreting construction
removing water from an
slopes, such as plans and designs and marking
excavation.
highway cuts, in the field the location of
retaining walls are Grouting or pressure proposed new structures such
often used grouting is the process of as buildings, sidewalks, curb
• driving piles or injecting a grouting agent into and gutter, storm sanitary
inserting stone soil or rock to increase its sewer, roads to ensure that the
columns into the strength or stability, protect project is built according to the
soil across the foundations, or reduce designed engineered plans.
potential slip groundwater flow.
plane Staking - refers to points
Grouting methods helping guide the contractor
• soil reinforcement
construct the improvements on
which involves Slurry grouting involves the the site and help ensure the
embedding high injection of a slurry consisting construction project is
tensile- strength of water and a grouting agent completed on schedule –
nonbiodegradable into soil or rock. Common budget – and as designed.
elements in a grouting materials include
Formwork - is temporary or Stay-In-Place Formwork - is
permanent molds into which designed to remain fixed after
concrete or similar materials are the concrete has set, acting as
poured. axial and shear reinforcement.
This formwork is made on-site
Falsework - supports the from prefabricated and fiber-
shuttering molds reinforced plastic forms. It is
TYPES OF FORMWORKS: mainly used in piers and
Traditional Timber Formworks, columns, and also provides
Engineered Formwork System, resistance against corrosion
Re-usable Plastic Formwork, and other types of
Permanent Insulated environmental damage.
Formwork, Stay-IN-Place Coffor – is another type of stay
Structural Formwork System, in place formwork which can be Board Sheathing
and Flexible Formwork used in any type of building Plywood sheath
Timber formwork - was one the Temporary
Permanent Insulated
first types used in the Spreader
Formwork - is one of the most
construction industry. It is Ties
advanced formwork systems,
assembled on site and is the Brace
offering permanent insulation. It
most flexible type. Studs
may also include thermal,
Double walers
Plywood - is often used along acoustic, fire-resistance and
Sill or plate
with timber. It is a manufactured rodent-resistance properties.
wooden material, which is
available in different sizes and
thicknesses.
REQUIREMENT FOR GOOD
Steel formwork - is becoming
FORMWORK: Capable of
more popular due to its long
withstanding dead and live
service life and multiple reuses.
loads, retaining its shape with
Although it is costly, steel
adequate props and braces,
formwork is useful for multiple
leak-proof, must not damage
projects, and it is a viable option
the concrete, reusable material,
when many opportunities for
lightweight, should not warp or
reuse are expected.
distort.
Aluminum formwork - is very
FORMWORK BASED ON
similar to steel formwork. The
- Sheathing STRUCTURAL
main difference is that
- Studs COMPONENTS: Wall
aluminum has a lower density
- Tie Formwork, Beam Formwork,
than steel, which makes
- Braces Foundation Formwork, and
formwork lighter. Aluminum also
- Wales Column Formwork.
has a lower strength than steel,
and this must be considered - Cleat
- Battens
CONCRETE
before using it.
- Side plate Concrete - is one of the world’s
Plastic Formwork - is - Footing most versatile and widely used
assembled from interlocking
construction materials.
panels or modular systems,
made of lightweight and robust Reinforced concrete -
plastic. Because concrete has little
strength in tension, all concrete
Fabric formwork - is also
used for structural purposes
known as flexible formwork.
contains reinforcing material
This system uses lightweight
embedded in the concrete to
and high-strength sheets of
increase the concrete member’s
fabric, designed to adjust to the
tensile strength.
fluidity of concrete and create
interesting architectural forms.
Major elements of a concrete Two-way slabs - provide TWO METHODS FOR
construction cost analysis support in two perpendicular PRODUCING PRESTRESS IN
include the following: directions. CONCRETE MEMBERS

• Formwork costs • Cost of Flat slabs - are supported • Pretensioning - places the
reinforcing steel and its directly by columns without prestressing material
placement. • Concrete edge support. (reinforcing steel or prestressing
materials, equipment, and labor cables) under tension in the
for placing, curing, and finishing One-Way Slabs supporting concrete form before the
the concrete. beams, girders, and slabs may member is poured.
be cast at one time
Since formwork cost may make (monolithically). • Posttensioning - places the
up as much as 60% of total prestressing steel (usually
concrete construction cost, Precast concrete - is concrete placed inside a metal or plastic
every effort must be made to that has been cast into the tube cast into the member)
reduce formwork cost. desired shape prior to under tension after the concrete
placement in a structure. member has been erected.
Walls and Wall Footings - this
method of construction is now STANDARD SHAPES ARCHITECTURAL EFFECTS
used primarily for foundation COMMONLY USED FOR ARE ACHIEVED THRU:
walls, retaining walls, tank walls, PRECAST CONCRETE Shape, Size, Texture, and Color
and walls for special-purpose STRUCTURAL MEMBERS: used.
structures such as nuclear Rectangular, L-
reactor containment structures. MAJOR METHODS USED ON
Shaped, Inverted Tee, I- OBTAINING
Formation of void spaces in the Shaped, and AASHTO ARCHITECTURAL
concrete under blockouts for CONCRETE EFFECT:
windows, pipe chases, and so
on can be prevented by using o exposed aggregate
concrete with adequate surfaces - are
workability accompanied by produced by removing
careful tamping or vibration of the cement paste from
the exterior surface,
the concrete in these areas
exposing the
during placing.
underlying aggregate.
o special surface
designs and textures
achieved - may be
achieved by using form
liners of plastic, rubber,
or wood.
Tilt-up construction - is a special
o form liners
form of precast wall construction
o mechanically
in which wall panels are cast
produced surfaces
horizontally at the job site and
then erected. CONCRETE CONSTRUCTION
PRACTICES:
Bond-breaker - is applied to the
slab to prevent the tilt-up panel Batching, Mixing,
There are a number of from sticking to the slab. Transporting, Placing,
different types of structural
Consolidating, Finishing, and
systems used for concrete PRECAST SLAB SHAPES:
Curing
floors and roofs, such
systems may be classified: Single Tee, Double
EQUIPMENTS USED FOR
Tee, Channel, Flat Slab, and
MOVING CONCRETE FROM
• one-way • two-way slabs. Hollow-Core Slab
THE MIXER TO ITS FINAL
One-way slab - is principally Prestressed concrete - is POSITION:
supported in one direction concrete to which an initial
o wheelbarrows - have a
(i.e.,at each end). compression load has been very limited capacity
applied.
o buggies - are often spraying it onto a surface. accelerated when concrete
employed on building Concrete placed by this temperature is appreciably
construction projects. process is designated higher than the optimum
o push buggies shotcrete. temperature of 50–60°F (10–
- that carry 15.5°C).
6–11 cu ft Tremie - is nothing more than a
o powered vertical tube with a gate at the Heat gain during hydration may
buggies - bottom and a hopper on top. be reduced by adding a
carrying up to retarder.
Consolidation - is the process
1⁄2 cu yd
of removing air voids in USED TO INCREASE
o chutes - widely used
concrete as it is placed. WORKABILITY OF THE MIX
for moving concrete
W/O CHANGING THE W-C
from the mixer to haul Concrete vibrators - are RATIO
units and for placing normally used for consolidating
concrete into forms. concrete Air entraining agent,
o conveyors - are water-reducing agent, and
available to move Finishing - is the process of workability agents
concrete either bringing the surface of concrete
horizontally or to its final position and Accelerator – may be used to
vertically imparting the desired surface reduce concrete setting time
o pumps – capable of texture. during low temperature.
moving concrete from
a truck directly into FINISHING OPERATIONS:
final position.
o Screeding - is the
o buckets - attached to
process of striking off
cranes are capable of
the concrete in order
lifting concrete to the
to bring the concrete
top of high-rise
surface to the required
buildings and of
grade.
moving concrete over
o Floating - smooths
a wide area.
and compacts the
o trucks - are equipped
surface while
with integral retracting
embedding aggregate
chutes that may be Wale
particles.
used for discharging Stud
o Troweling - with a
concrete directly into Brace
steel trowel follows
forms within the radius Spacer for
floating when a
of the chute. anchor, bolt
smooth dense surface
is desired. Footing
MAJOR FACTORS THAT
o Brooming - the Plywood
INFLUENCE THE MAXIMUM
SAFE HAULING DISTANCE: concrete may be
broomed by drawing a
Reinforcing bars - are usually
Temperature, Road stiff broom across the
deformed; that is, they are
Condition, Truck Body Type, surface.
manufactured with ridges that
and Mix Design
Curing – is the process of provide an interlocking bond
Placing – is the movement of providing the required water with the surrounding concrete.
plastic concrete into its final and maintaining a favorable
Welded wire fabric - commonly
position (usually within forms). temperature for a period of time
used for slab reinforcement, is
after placing concrete
The strength, watertightness, available with smooth wire or
durability, and wear resistance Vacuum dewatering - may be deformed wire.
of concrete are largely employed to reduce the amount
Reinforcing steel - is used
determined by the of free water present in plastic
primarily to resist tension and
water/cement ratio of the concrete after the concrete has
thus prevent cracking or failure
concrete mix. been placed and screeded.
of the concrete member under
Concrete may also be Rate of hardening of tension.
pneumatically placed by concrete - is greatly
5 PHASES OF CONCRETE oxide coat on its surface upon clearance when beams connect
QUALITY CONTROL: exposure to the elements so to columns or other beams.
that painting is not required for
- Mix design protection against most Guy ropes and support are
atmospheric corrosion. often used in the process of
- concrete
bringing steel into alignment.
materials quality 5 MAJOR SECTIONS SHAPES
- batching, mixing, OF ROLLED STEEL SHAPES
and transporting
concrete W-Shaped, S-Shaped,
Hp Shape, Channel, and Angle
- concrete placing,
vibrating, Girders are used when regular
finishing, and rolled shapes are not deep
curing enough or wide enough to
- testing of fresh provide the required section
and hardened properties.
concrete at the job
site

Structural Steel Construction


is a specialized task that is
usually performed by specialty
subcontractors.

3 MAJOR ELEMENTS ON TYPES OF JOIST END:


PROCESS OF STEEL THREE PRINCIPAL SYSTEM
CONSTRUCTION Underslung end, USED FOR CONNECTING
Square end, and Extended end STEEL MEMBERS:
Advance planning, steel
fabrication and delivery to the USUAL STEEL ERECTION Bolting, Riveting, and
job site, and field operations PROCEDURE: Wielding

Divisioning is the process of Raising crew lifts the steel Interference-body are bolts
dividing a structure into units, member into position and that are driven into place and
which are used to schedule the makes temporary bolted use oversize shanks to prevent
fabrication and delivery of connections that will hold the turning during tightening.
structural steel members to the member safely in place until the
job site. fitting crew takes over. Tension control bolts or
tension set bolts are bolts that
FIELD OPERATIONS Fitting crew brings the member are incorporate a torque control
INCLUDES: into proper alignment and groove so that the stem breaks
tightens enough bolts to hold off under a specified torque.
Receiving and the structure in alignment until
unloading, sorting, inspecting, final connection are made. Bolt tension calibrator is a
storing, and erecting the steel. device that can be used to
Fastening crew makes the final calibrate both impact wrenches
Yarding is the process of connections to meet (used for bolt tightening) and
unloading steel to a temporary specification requirement hand indicator torque wrenches
storage area and then moving it (used by inspectors for
from storage to the point of OFTEN USED ON HANDLING
checking the tension of bolts
erection. STEEL AND LIFTING IT INTO
that have been tightened by
FINAL POSITION:
either method)
Shaking out steel is the
process of sorting it out by Mobile crane & Tower
Wielding is another specialized
identifying each member and crane
procedure that must be
storing it in such a manner that accomplished properly if
Gin pole is one of the simplest
it can be easily obtained during adequate connection strength
types of powered lifting device.
erection. is to be provided.
Guy derrick is probably the
TYPES OF STEELS MAJOR TYPES OF
most widely used lifting device
in high-rise building STRUCTURAL WELDS
A36, A572, and A588
construction.
Fillet welds, groove
Fy is the designated symbol of
Stiffleg derrick is the name welds, and rivet welds
steel strength
applied to notching beams to
Weathering steel is a type of provide the necessary
steel that develops a protective
TEST METHOD AVAILABLE • Construction vehicles The Use and Maintenance of
FOR DETERMINING THE
• Earth moving Construction Safety
QUALITY OF WELDS: Equipment
equipment
Visual Inspection is the • Construction Observing high safety levels in a
quickest, easiest, and most equipment
widely used methods of construction site is very
• Material handling important. It protects site
inspection
equipment workers from different forms of
Destructive Testing is used Conduct Proper Training to injury. Safety equipment such
primarily in welder qualification Equipment Users as industrial ear plugs and hand
procedures
protection like coated gloves
Ensure that the people
Radiographic Inspection should never miss in a site.
designated to handle
involves producing an X-Ray Having them goes miles in
picture of the weld construction equipment are
protecting everyone at the site
extensively trained. Unless
Ultrasonic Inspection uses from any form of danger.
someone can efficiently handle
high-frequency vibration the equipment, he or she Construction equipment plays a
Magnetic-Particle Inspection shouldn’t operate it. huge role in any construction,
utilizes magnetic particles whether big or small. For this
Adhere to Safety Rules
spread on a weld reason, it is prudent to use such
Liquid-Penetrant Inspection To ensure the construction site equipment in the best way
involves spraying the weld remains safe, it’s highly possible. Additionally, make
important to observe safety sure that you maintain your
------------------------------------------ rules religiously. Contrary to equipment regularly. Ultimately,
how it might sound, feel or look, you’ll benefit immensely in
MODULE 5 – terms of reduced maintenance
handling construction
CONSTRUCTION equipment isn’t simple. The and repair costs as well as
EQUIPMENT bedrock of a hazard free increased profits.
OPERATION AND experience is safety.
Maintenance of Construction
MAINTENANCE Always Put on Protective Equipment
Gear
------------------------------- Regular maintenance of
Protected gears such as dipped construction equipment is an
The Use of Construction gloves, fall gear, hard hats, important factor in cost control.
Equipment goggles, etc. are great at Equipment maintenance is an
preventing hazards at the effective way of getting the most
The selection and use of the
appropriate size and type of construction site. Industrial ear out of your investment.
plugs are also a must have on Excellent maintenance helps
construction equipment affect
the needed effort and time of a any construction site. minimize, repair and
maintenance costs, as well as
project. It also highly affects The equipment used at
jobsite productivity. going miles in maximizing both
construction work should be: profit and production, but has
Consequently, it’s not only
the greatest impact on profits.
important to select the right • Ideal for the intended
construction equipment, it’s also use Other benefits you stand to gain
crucial to use it in the right way. • Only used by people from maintaining your
Whether your construction with necessary construction equipment include:
project is paving, drilling, training, adequate
compaction and grading, information and • Maintenance adds
excavation and loading etc training resale value
doesn’t matter. You must use • Safe for use • Maintenance
the equipment in the way that minimizes downtime
• Used based on
it’s supposed to. • Maintenance
specific requirements,
for power presses and lengthens equipment
Construction equipment can be
mobile work life
classified into four main
categories. The groups are equipment • Maintenance helps
based on use and purpose. control service
They are: intervals and costs
Doing this ensures the Bulldozers remove topsoil
Simply put, proper maintenance equipment operates at optimum layers, and graders level soil
of construction equipment can conditions at all times. surfaces, mainly for road
reduce your operating costs Furthermore, you should never construction.
significantly, both indirectly and get tired of performing daily
directly. In terms of direct inspections. It goes miles in Wheel Tractor Scraper provide
operating costs, it’s related to making sure that you’re able to flattened soil surfaces by
costly unscheduled repairs and avoid issues later. Additionally, it scrapping and collecting soil.
machine downtime. extends the life cycle of an Trenchers excavate trenches
Maintenance will help you equipment. Of great to note is for pipeline, cables, and
indirectly in the sense that your that you need to conduct the drainage.
equipment will always be daily inspections in an
functional thus you’ll not organized manner. For Loaders are used to load
experience any shutdowns that example, visual inspections materials onto vehicles.
can harm the entire production usually determine operator
site. That last thing you want is techniques. On the other hand, Tower cranes are fixed cranes
to suffer thousands if not you can conduct a deeper or for hoisting heavy materials
millions of dollars because of more thorough inspection during the construction of tall
equipment failure. depending on operator structures.
suggestions and/or machine Pavers lay asphalt on roads,
Routine is Key performance. and compactors are used to
Adhering to recommended compact soil or asphalt.
Video 1: TYPES OF
maintenance schedules as well
as regular inspections is a major CONSTRUCTION Telehandlers lift heavy
step towards proper EQUIPMENT materials or provide platforms
maintenance of your for construction workers.
construction equipment. Heavy construction equipment
is used for various purposes in Feller bunchers are tree-
Secondly, you must always cutting equipment.
follow the manufacturer’s large projects. These make
recommendations. Remember construction process easier and Dump trucks transports
that nobody knows the faster. materials on construction sites.
equipment better than the Selection of different types of
manufacturer. So it’s important Pile boring and pile driving
heavy equipment depends on equipment are used for making
to adhere to the manufacturer’s the size of the work and
manual. bore holes and installing precast
economy of the project. piles in construction projects.
Have Your Own Application Excavator are important and
Related Maintenance Different types of pile driving
widely used equipment in equipment: piling rigs and
Guide/Rules construction. General purposes hammers, are used to drive
Adding your personal to excavation but other than that piles into the ground.
application-related they are used for many
maintenance items is another purposes such as heavy lifting, Video 2: TYPES OF
demolition, river dredging.
important step to take. For CONSTRUCTION
instance, some harsh Backhoe is another widely used EQUIPMENT USED IN
environments need air filters to equipment which is suitable for CIVIL ENGINEERING
be changed frequently. Also, multiple purposes. The name
undercarriages exposed to itself saying that the whole Types of Equipment:
abrasive or corrosive soils arrangement is provided ton the
require extra attention to detail. • Earthwork Equipment
back side of the vehicle. This is
These are just some of the o Tractor
well for excavating trenches
items that no manufacturer will o Dozers
below the machine level. o Power Shovel
ever know when it comes to
o Dragline
individual job characteristics. Dragline Excavator is
o Clamshells
generally used for larger depth o Hoe
Adhere to Equipment’s excavation, especially o Scraper
Maintenance Schedule underwater. • Trenching Machines
Recommended by the
Manufacturer
o Wheel type laying, cable laying, and • Construction
trenching drainage purposes Equipment
machine • Loaders – used to load the • Material Handling
o Ladder type material onto dumpers, Equipment
trenching trucks, and more.
machine • Tower Cranes – fixed Benefits of Maintenance of
• Truck And Hauling cranes used for hoisting Construction Equipment
Equipment purposes of tall structures
o Rigid Dump Truck - Effective way of getting
• Paver – called as asphalt the most out of your
o Rear Dump Truck paver is used in road
o Bottom Dump investment
construction where it - Helps minimize repair
Truck distributes asphalt evenly
o Side Dump Truck and maintenance costs
on road surface - Maximizes both profit and
• Compaction Equipment
• Compactors – called as production
o Sheepfoot Roller
rollers used to compact - Adds resale value
o Tamping Roller
material or earth’s surface - Minimizes downtime
o Vibrating
Compactors • Telehandlers – hoisting - Lengthen equipment life
o Pneumatic-Tired equipment used to lift - Helps control service
Rollers heavy materials up to intervals and costs
• Concreting Equipment required height
• Feller Bunchers – a tree Rules in Construction
o Mixer
cutting heavy equipment to Equipment Operation and
o Paving Mixer
Maintenance
• Hoisting Equipment remove large trees in the
o Pulley field
• Conduct Proper
o Chain Hoists • Dump Trucks – used in
Training to
o Winch construction to carry the
Equipment Users –
o Cranes material in larger quantities
Make sure the people
from one site to another site
Definition of Some assigned in handling
• Pile Boring Equipment – construction
Equipment:
used to make bore holes in equipment are well
• Excavators – used for the construction sites to
trained
install precast piles
heavy lifting, demolition, • Adhere to Safety
• Pile Driving Equipment –
river dredging, cutting of Rules – always
trees and more used for lifting the pile and
observe safety
• JCB Backhoe – used for holds it in proper position
precautions
and drives into the ground
excavating trenches below • Always Put on
up to the required depth
the machine level and front Protective Gear –
bucket loading, unloading o Different types of
always use protected
and lifting of materials can pile driving
gears such as dipped
equipment:
be done gloves, fall gear, hard
▪ piling
• Dragline Excavator – long hats, goggles and etc.
rigs,
length boom and digging to prevent accidents at
▪ piling
bucket used for larger the site
hammer,
depth excavations
▪ hammer • The Equipment used
• Bulldozers – a soil at Construction work
guides
excavating equipment used should be:
and
to remove top soil layer up o Ideal for the
more
to particular depth intended use
• Graders – called as motor Use of Construction o Only used by
graders used for Equipment trained
construction of roads to people
level soil surface - It affects the needed o Safe for use
• Tractor SCR – earth- effort and time of a project o Used based
moving equipment used to - It highly affects jobsite on specified
flatten surface through productivity requirements
scrapping • The Use and
Classified into Four Main Maintenance of
• Trenchers – used to
Categories Construction Safety
excavate trenches and oil
Equipment – Always
and used for pipeline • Construction Vehicles
observe high safety
• Earth Moving
Equipment
levels to prevent What Is A Construction construct the project’s work
different injuries Scheduler? scope. That work scope is
• Routine is Key – represented by the schedule’s
Following The construction scheduler is work activities, how long they’re
maintenance the person on the project who is going to take, and their
schedules helps in responsible for developing and sequence. One thing to
proper maintenance of updating the project schedule. remember is that a construction
the equipment. Always project schedule is the only
follow what the There are really two types of
schedulers. One is a button project management tool that
manufacturer’s
pusher, someone who takes the can forecast when the project
recommendations are.
will finish.
• Have Your Own information from one party and
Application Related inserts it in scheduling software The construction schedule
Maintenance Guide/ like Primavera, Microsoft should predict, based on the
Rules – Having your Project, or Asta Powerproject. contract, the plan, and how the
own maintenance
The second type is what I would work should progress to
items helps the
individual job call a professional scheduler. forecast, when the project is
characteristics That’s someone who knows and expected to finish.
• Adhere to understands construction Why Do We Need Project
Equipment’s means and methods, as well as Schedules?
Maintenance the capabilities of the software.
Schedule Most importantly, they also Increasingly, over the last 15 or
Recommended by understand what construction 20 years, construction owners
the Manufacturer – scheduling best practices are have required that contractors
This ensures the
and how to incorporate them prepare schedules during the
equipment functions at
into the project schedule. construction project. There are
the optimum level at all
two primary reasons for this
times. Always perform Too often projects don’t have a
daily inspections on trend.
professional scheduler who can
the equipment
pull all those elements together. First, as projects become more
------------------------------------------ Bringing on such a person does complex and have tighter
not guarantee project success. budgets, we need schedules to
MODULE 6 – But the right professional help us manage our
PLANNING AND scheduler can work with the construction projects. As a
project manager and the project construction project
SCHEDULING superintendent to ensure that management tool, a schedule
the plan residing in their heads enables the project participants
-------------------------------
is accurately depicted in the (not just the owner, the
What Is Construction project schedule and will protect contractor, the engineer, or the
Scheduling? the contractor’s risk. architect) to understand the plan
for completion. It allows the
A construction project schedule Construction Scheduling parties to coordinate all the
is either a written or graphical Basics elements of the work.
representation on how the
project is to be completed or In nearly every case, a To some degree, this trend has
constructed. When I say written, construction contract will require also been driven by litigation.
it could be a written narrative. It the contractor to complete the Time is money. Every day a
could be a description. It could project within a specific duration construction project is delayed,
be depicted as a bar chart or by a specified completion either the owner, and/or both the
schedule or a CPM schedule. date. owner and contractor, will incur
For every construction project, additional costs to support that
A construction schedule is project. Therefore, we need a
analogous to a contractor’s bid. there is a lot of work that must
be done before contract way to measure to what extent
Just as a contractor’s bid is an the project is delayed.
estimate of its cost that it completion.
expects to spend to build the The construction project The schedule allows us to
project, the schedule represents schedule provides a detailed identify not just what the work is,
an estimate of the time required description and representation but the responsibilities of each
to construct the project. of how the contractor plans to
party, and the party responsible mathematical formula allow us Today, there exist many
for each of the activities. to predict when the project will technology platforms and tools
finish. that are designed to streamline
It allows us to track construction project scheduling
performance. Ultimately, having A nice thing about the CPM without necessitating that you
a reasonably accurate schedule is it allows us to model create new workflows from
schedule, be that a bar chart or both the physical and the scratch. The benefits of using
a CPM schedule, will also contractual limitations or software include:
enable the project participants constraints on a project. As an
to identify and resolve project example, especially on larger 1. Less risk and chance
delay as it occurs. and more complex construction of mistakes
projects, we can develop a CPM 2. Better overview of
The last thing you want to do is schedule that integrates clashes
ignore time-related issues contractual limitations on work 3. Ability to track key
during the project and have the during certain time periods, like metrics and milestones
parties kick the can down the environmental restrictions or 4. Improved efficiency
road. This will often result in a winter weather. 5. Streamlined workflows
claim being submitted because and processes
time wasn’t resolved, the project A CPM schedule also enables 6. More adaptable for
finished late, and the parties the project team to prioritize the changes if they occur
can’t agree as to the cause of uncompleted work, based on 7. Increased
the delay. This can and often the activities’ total values, and to transparency and
does result in unnecessary assign the available resources accountability
money spent in litigation. to complete the work in the most This isn’t to say all construction
efficient manner. It also allows software is created equal,
That is not a recipe for success us to:
on construction projects. We though. There are many
want to finish projects on time Assign responsibility, costs, and options, and no one right
and on budget. A way to do that resources to each of the project answer for your team and
is to address delay as it occurs activities. project needs. Before you plunk
during the project. Forecast the expenditure of down your cash and commit to a
costs on an earned value basis. long-term subscription, there
What Is Critical Path Method Forecast the expenditure of are a few essential qualities to
Scheduling? hours, direct labor hours, over consider. Any good construction
the course of the project. project scheduling tool should
The most commonly used be:
construction scheduling Track whether we’re achieving
technique is the CPM approach. those expected rates of Cloud-based: If your software
This approach models or production or earning of the isn’t in the cloud, it becomes
depicts the construction plan in contract amount. much harder to keep teams
what is called a network. This Compared to a bar chart, a CPM updated with central access to
network consists of activities schedule is a much more real-time information, wherever
and logic relationships that comprehensive tool that project they are.
determine the overall sequence teams can use to plan and
of construction. Secure: Any software you
manage projects. I’ve worked consider should have A-class
In a CPM schedule, “activities” on projects where I developed security stands; otherwise, you
depict every element of work in CPM schedules ranging from risk compromising your job site,
the project, be it preparation, 300 activities to 30,000 project, and company as a
submission and review of activities. The number of whole.
submittals, procurement, or activities in your CPM schedule
construction. We connect those often comes down to the level of Accessible on Mobile: Made-for-
activities with “logic detail you choose to represent, mobile solutions to keep your
relationships.” For example, the the project’s size, or its field team always in the loop,
schedule may depict that one complexity. anywhere, and from any device.
activity can start only after Easy-to-Use: If your software is
another is finished. The Tools in Construction complicated, it won’t be used.
combination of the work Scheduling Ensure its easy-to-use and has
activities, their duration, the world-class support staff in case
logic in the schedule, and a you need it down the road.
------------------------------------------ efficiency with better allocation timelines and offer a false sense
of resources of confidence about project
CONSTRUCTION Enhances the visibility of the completion
SCHEDULING impact of any schedule changes Is vulnerable to failure with any
METHODS FOR change in the precedence and
Cons sequential relationships of
PROJECTS
Is burdensome to manage for activities
1. Critical Path Method (CPM) large and complex projects due 3. Gantt Chart
to thousands of activities and A Gantt Chart is another
Perhaps the most widely used
their dependent relationships construction scheduling tool,
construction scheduling method
Fails to account for resource rather than a technique. It is a
in large construction projects,
allocation and might require type of bar chart that
the Critical Path Method (CPM)
other methods to complement it encourages stakeholders to
holds that “your ability to
complete any activity hinges on structure the project with
a few critical resources or 2. Program Evaluation and several levels of details and
constraints. Review Technique (PERT) consider dependencies
between tasks. This helps them
In one of the best metaphors of PERT is one of the most visually estimate the duration of the
all time, they illustrate this accessible construction project and identify the critical
concept using a sandwich, scheduling tools. Essentially, it path to take during construction.
explaining that “might have all is a diagram that “provides a
the butter, ham, and cheese you visual depiction of the major “A Gantt chart is a bar chart
need, but if you don’t have project activities and the used to illustrate a project
bread, you can’t make a sequence in which they must be schedule, that includes some
sandwich. The bread, in this completed.” Each of these steps milestones and it is not as
case, would be the constraint represents the use of time or detailed as a full CPM,”
your sandwich-making project resources or both. Think of it as explains. “It normally includes
depends on.” a road map toward project start/end dates of activities and
completion; only once you pass a summary of activities of a
Due to the critical importance of
all of the milestones will the project.” However, it lacks the
constraints, project managers complexity of more
building have reached its final
study CPM as part of their comprehensive approaches
stages. “PERT charts are often
Project Management (PMP)
constructed from back to front and doesn’t include the
certification. Also, for this resources or materials needed
because, for many projects, the
reason, it’s the legal standard to complete it.
end date is fixed and the
for measuring delays when it
contractor has front-end Gantt Charts are excellent for
comes to project-related
flexibility.” creating a hierarchy among
disputes.
Pros projects, showing which ones
CPM “generates a graphical require immediate attention and
view of a project and calculates Provides a comprehensive which must be completed
how much time and resources activity analysis for events before other, dependent
are required to complete each independently and in projects can follow.
activity. It also determines combination
critical activities requiring Offers a “What-if-Analysis” that Pros
attention so that the project can enables better planning for Creates an accurate picture of
be completed on time.” uncertainties and risk project complexity
Facilitates improved Is helpful to organize thoughts
Pros
coordination for team-wide Indicates clearly what should be
Is widely used and recognized decision-making done, within realistic time
and is the legal standard Takes the deadline into account frames
Is simple and effective at at the start Is easy to build with software or
organizing large and complex on your own
Cons
projects
Encourages project managers Is labor-intensive and expensive Cons
to optimize critical paths and in nature Tends to get complex,
reduce project duration Carries the risk of prediction especially when a project has
Enables the team to improve inaccuracy, which can muck up more than 30 activities
Requires constant updates, fault during litigation, arbitration, ------------------------------------------
which is time-consuming or lawsuit. For example, wall
Might be inaccurate both in foundations have to be MODULE 7 –
displaying information and constructed before the walls CONTRACTS AND
reflecting actual resource themselves, and that must be
DOCUMENTATION
requirements properly represented on the
project schedule. It may seem -------------------------------
Common Construction like a no-brainer, but in a
Project Scheduling Mistakes complex project, it’s easy to Documentation is a major factor
The schedule is often the first overlook these types of in prudent project management.
piece of documentation an mistakes. To avoid delays, Then, too, proper
owner receives demonstrating schedules should be continually documentation is the critical
the contractor’s professionalism checked by multiple element of a risk control system.
in planning and management, stakeholders to ensure all Whether the project manager
so it’s key to establishing dependencies are in the proper, represents the architect, owner,
credibility in an increasingly logical order. or contractor, their
competitive field. Here are four responsibilities are the same on
common construction project 3. Poor resource allocation every construction project.
scheduling mistakes that, when
corrected, can help improve Every company has a set Today, every construction
your company’s success rates amount of resources available project requires detailed
and reputation. for any given project, whether documentation by project
that’s time, budget, materials, or managers. Orderly and
1. Inaccurate project manpower. Problems and conscientious recordkeeping
estimates delays often occur when not only provides the
schedules are set in place with information to effectively and
To ensure your project is set up the assumption that there are efficiently manage a project, but
for success from the beginning, unlimited resources at your is also essential preparation for
it’s important to be as accurate disposal. When creating your contract disputes, delays, and
as possible about project schedule, maintain a realistic litigation. Such preparation
deadlines during the sense of what you’ll have to requires a comprehensive
preconstruction process. work with at any given time, and documentation system to
Estimating the project be sure to remember external defend against or prove
accurately can even be started factors that could impact your entitlement to a number of
in the RFP process. This is the resources, like material damages resulting from a
opportunity where architects, shortages. compensatory claim.
contractors, and owners can 4. Not preparing for the worst Adequate documentation may
express their concerns over the
also satisfy a requirement for a
budget and timelines of the Speaking of material shortages
logical and supportable
project. If either of the parties — there are a lot of factors on
demonstration of cause and
appears to be unrealistic about the job site you simply can’t
effect. Documenting the many
timing or budget, this should be control. That’s why on projects
complicated problems
an immediate red flag that the where just about anything can
developing during a
project is heading straight for an happen, overseeing schedules
construction project is
overrun. Thorough, realistic is a role best suited for the
burdensome. Nevertheless,
estimation and planning will overly cautious. Always plan for
since documentation is
help you avoid scheduling the worst-case scenario,
essential to the success of any
issues down the line, so be allocate extra funds, and include
delay claim, the importance of
willing to listen and adjust buffer time to handle the
creating a paper trail cannot be
course if project stakeholders unknowns that will most likely
overemphasized. Since
express concern over timelines. impact a build, like potential
disputes are not often settled
weather delays.
2. Missing dependencies until after a project is completed,
which may be several years,
If not properly defined from the management policy should
get-go, missing dependencies recognize committing anything
can lead to more than just to memory is only as good as
overshooting deadlines: you the longevity of the
could have difficulty arguing professionals involved both
physically and corporately. • pre-bid site investigation • abnormal weather and
Documentation usually lasts reports; climatologic data;
longer than people and their • pre-construction • transportation or material
jobs. conference minutes; delivery delays;
Most construction contracts • project manager’s daily • unusually severe
reports; and inspections;
require a written change order,
supplemental agreement, or • status project photos. • material and labor
other contract modification for The project manager must shortages;
changed or added work and its maintain a daily record of • defective or deficient and/or
corresponding cost impact. A changes to the project changes to plans and
claim the contract has been schedule, including delays, out- specifications;
constructively changed by the of-sequence, disruptions, • defective owner-furnished
owner may arise in absence of a suspensions, or acceleration of materials;
written and signed change work. These changes may affect • lack of parameters as to
order. either planned work sequence ‘game plan’;
or duration times. The contract
• no field orientation as to
The owner is normally usually contains the overall critical path methodology;
responsible for issuing and project starting date, planned
• poorly defined
approving change orders. duration time, and the
management of CPM
Problems are often encountered anticipated completion date.
schedule philosophy; and
when the owner’s project Milestones or work sequences
manager relies on the architect
• people with whimsical and
are normally found in
procrastination positions on
to review and recommend accompanying special
CPM schedules and
approval or rejection of change conditions. The astute project
documentation.
orders based on ‘unanticipated manager must critique each
Some of the initiatives that can
conditions or some area monthly CPM schedule update
be implemented to avoid
inadequately covered in the and narrative report to know the
problems include:
plans and specifications. This full status of the project.
may cause a conflict of interest • complete daily reports of
for the architect who, by It is imperative for owners,
architects, and contractors to be the scrupulous project
approving such change orders manager;
in a timely manner, maybe problem-oriented while
maintaining documentation • record all project meeting
inappropriately admitting his/her
during construction to be able to minutes;
own negligence with faulty
identify and react to issues • use time impact analysis
omissions.
impacting the contract price or (TIA) to record
Many construction contracts performance time such as: documentation;
contain a differing site • study the project
conditions clause allowing an • lack of meticulous CPM manager’s day timer that
equitable contract price planning; should show proper
adjustment if the physical site or • out-of-sequence activities; documentation;
subsurface conditions are either • lackadaisical attitudes • review all time extensions
different from those represented toward CPM updates; requested and approved;
in the plans and specifications • no project management • document start and
or materially different from communication; completion dates of all
conditions normally inherent in • very little team esprit de milestones;
the type of work performed. corps; • keep complete records of
Prompt notice to the owner’s • delayed approval of shop as-built drawings; and
project manager is required if drawings; • use CPM monthly updates
these differing conditions are
• no timely or adequate input to record as-build CPM
found. Proof of anticipated schedules.
to schedule updates;
conditions may be established
• untimely response to Pre-contract documents
by the following:
information requests;
Documents included in the
• bid specifications; • interference by other owner’s bid package, including
• bid estimate worksheets; contractors or owner;
drawings, specifications, soil
• owner’s boring logs and soil • differing site conditions; and asbestos data, special
reports;
conditions, and specific schedule prepared by the • constraints;
instructions, as well as the contractor and approved by the • pay applications;
contractor’s calculations and owner and architect after the • field issues;
bid-preparation documents, are issuance of the contract will be
• request for information
generally admissible evidence an integral part of the
(RFI) requirements and the
as to what was intended by a documents. Anything else
need for clarifications of
construction contract. prepared at a later date, except
plans and specifications;
for formal change orders, is not
A reasonable contractor and
part of the contract. It is
prepares his or her bid or • inspection and testing
essential to keep a clean,
proposal to provide what the reports.
unchanged set of original
contract requires—no more and Oral directives versus written
contract drawings and
no less. A prudent contractor will documentation
specifications for future
seek clarification to ambiguities reference to prove changes In the daily routine of conducting
in the bid documents, occurring during the project. It is business at a construction site,
particularly if they have any cost also important to note drawings many directives are conveyed
impact or risk. However, when and/or specifications issued at orally. There are several
disputes develop over such the contract-award stage may dangers in instructing activities
ambiguities or alleged changes be different from those in the orally—one being that the
in the contract requirements, an bid, and the contractor should directive may not be clearly
examination of the bid verify such changes before understood and, therefore, not
documents and the contractor’s accepting the contract. The carried out accurately. To guard
backup information may be the notice to proceed is also a against such errors, all oral
only way to resolve these significant contract-related item directives must be substantiated
issues. A comparison of the as- in that its date may in writing to help clarify the
bid drawings with the as-built unexpectedly follow contract information conveyed.
drawings should disclose any award by several weeks or more
changes, variances, or and could delay the project from In addition to the order of
dissimilarities. the beginning. precedence of the contract
document for a construction
Forensic investigation into the Correspondence project, there is also an order of
reason for these differences
precedence for the forms in any
may reveal some owner action All correspondence of any kind
contract based on general legal
or inaction (e.g. defective on a project should be
principles. This order from the
design) for which a contractor preserved in a chronological
least to the most important is as
may be entitled to recover any master file with each letter, fax,
follows:
related additional cost. and e-mail numbered and
cataloged for convenient • the printed form;
Soil data supplied by the owner, reference. Coordination
in the owner’s possession, or • the typed form;
meetings should cover items
obtained by the contractor • the handwritten form; and
such as:
during a site investigation visit • the oral directive.
prior to contract are important • approval of last meeting Contemporaneous
evidence in decisions that minutes; documentation
regard to differing site • construction progress Contemporaneous written
conditions. Reliance on this (reference CPM activities
expressions of work progress,
data by a contractor when such by node numbers);
CPM schedule updates, site
information is found to be in • contractor’s plan for the conditions, and damages
error is critical to determining coming month; entered into a job log, or daily
entitlement for this type of claim.
• any delays including report can provide a valuable
Contract documents weather and strikes; and factual evidentiary
• status of material foundation, particularly if it is
Only those documents in deliveries; done by a punctilious project
existence at the time the • schedule narrative report; manager in the form of a regular
contract • status of change orders business record.
is awarded are part of the and items on submittal log
agreement. There is, however, Design professionals who are
as to submissions to date
one exception. Special providing field observation
and approvals;
conditions may state the CPM reports should be encouraged
to take photographs of site direct result of contractor Essential Contract
conditions and the work in mismanagement. Documents for Construction
progress on a routine and Projects
systematic basis, concentrating Although cost records on each
on problem areas critical to the project and between contractors Construction Contract
procedures and scheduling. A vary, the following list is a typical Agreement
picture is worth a thousand spectrum of cost data that
should be preserved by the This is the principal agreement
words, or a thousand dollars, between the construction
especially in matters involving project manager for potential
use in proving damages: contractor and the private
impacts or delays on property owner or the
construction projects. Changes
• project cost budget; contracting officer for a
and additions to the work often
• weekly labor distribution business. It's the essential
cause delays. Although the component of the bundle of
reports;
reason for the change or various contract documents—
addition usually cannot be • labor timecards coded to
CPM work activities; the main document to which
photographed, the resulting most of the other documents
delay, such as idle equipment or • overtime labor records;
attach or refer.
lack of daily progress, can be • labor fringe agreements;
documented visually. • certified payroll reports; Scope of Work (SOW)
• canceled payroll checks;
Cost Documentation Having a clearly defined scope
• daily equipment cost
of the work involved for a project
Providing the actual dollars lost records, including hours
is helpful during the bidding
is critical to a construction claim. operated and idle, work
process and later on during the
Use and maintenance of performed by CPM activity,
construction sequence.
effective accounting methods and repairs made;
can provide the proof of • purchase orders; The Scope of Work document,
damages necessary to support • contractors bid analysis; sometimes known as the
additional compensation. All • paid invoices; Statement of Work, should
project managers must study • material receiving tickets; enumerate all of the work to be
current accounting systems tied done, who is responsible for the
• canceled accounts payable
to a time impact analysis (TIA) checks; work, how the work should be
of the project CPM schedule. performed (techniques used),
• monthly job cost reports;
and what materials will be used.
Since delay, acceleration, and • subcontractors cost
This is the document that will
impact claims frequently involve reports;
detail how change orders are
inefficiency claims and loss of • revenue records; handled.
productivity factors, which are • progress payment reports;
difficult to segregate under • ‘S’ curve of projected Construction Schedule
traditional accounting systems, collections and actual
a method of isolating cost not The construction schedule is an
collections
covered by the contract is important component of the
• of work in place by CPM larger document and second
especially needed. schedule (a dollar value is only to the construction contract
A system allowing for given agreement. This component
concurrent segregation of • to each CPM scheduled allows the contracting client to
unanticipated costs is not only activity to show projected know how and when the project
easier and less expensive than • monthly cost); will be completed and offers
the after-the-fact breakdown, • record of stored materials them leverage when schedule
but also more convincing in the billed monthly; problems arise. It is also the
courtroom. • change order request and document that helps the
approved; contractor schedule the work.
Reports are often prepared to
• bank loans; and Construction contracts
study costs or production units
• cost assigned to each delay sometimes require updated
as the project progresses. schedules throughout the
and will advise the owner of
Analysis of such cost reports construction progress, and they
current request for the cost
may show where the might form the basis for the
on the project.
contractor’s estimating application for payments by the
department was incorrect or contractor.
when inefficiencies were the
General Conditions will be part of the construction Item 1: Weather
project. This document is
The General Conditions portion essential for allowing a You want a complete weather
of an overall construction contractor to properly bid a report for the day. Was it sunny,
contract is the portion that sets project. Sometimes this cloudy, rainy, or snowing? What
forth the right, responsibilities, document is omitted since it is were the temperatures morning,
and relationships between the not always required by the noon, and at the end of the day?
client and contractors. Most contracting officer. How did the weather change
important is the delineation of throughout the day?
rights and responsibilities of Cost Estimate
each party. Item 2: The Location of Work
This portion of the construction On-Site
The General Conditions portion contract agreement provides a
of the contract offers the legal breakdown of all items being Who was working and where
framework for the overall incorporated into the were they working? Location
construction contract. It includes construction project and their can be defined by sectors on the
stipulations for how any costs. The cost estimate can be plans, column lines, or using
disputes will be resolved. detailed per item in a document north, south, east, or west
that combines specifications directions.
Special Conditions and costs, or in a lump sum form Item 3: Work Accomplished
This is usually an extension of that doesn't specify individual
the contract and an addendum items. Sometimes an itemized Who is performing what scope?
to the General Conditions. The Cost Estimate is combined with In this section, it is important to
Special Conditions document the Specifications in a single tie the daily report to the
should specify certain section. activities on the schedule. Note
conditions and clauses that which activities are starting,
Drawings completing, making progress,
pertain to specific portions of the
job. For example, if there are All contracts should include a and which work activities should
specific instructions that apply set of whatever drawings that be progressing but are not. For
to only one portion of the job, the are applicable to the work being your project manager or
Special Conditions section is performed. This might include superintendent to do this, they
where this will be described. the actual blueprints for the must have access to and be
project, or it may be one or more familiar with the schedule.
Specifications simpler drawings that provide a Item 4: Quantities
The Specifications section of a graphic representation of the
contract is where all the scope, extent, and character of How many pieces of steel were
technical data and requirements the work that will be performed set today? This is essential data
are listed. Information should by the contractor. to evaluate productivity. We
detail all the materials and know there are 500 pieces of
Construction Insurance steel in the building, and the
techniques that are expected to Coverage
be used. steel erection activity was 20
This is an essential part of the days. We can calculate the
These specifications should be agreement because it provides contractor’s planned progress
discussed and negotiated at the a guarantee to the owner that for the steel erection as 25
time the contract is developed, the contractor has the means pieces per day. In the event of a
and later changes to the and the economic backup to dispute, you may need to note
specifications are often handled perform under the terms of the whether or not the steel erection
under whatever conditions are construction contract. It will subcontractor was meeting its
laid for change orders in the include details on specific types production rate. On the flip side,
Scope of Work section. of coverages, including general if you’re in construction and that
liability insurance, performance subcontractor was on the site
Bill of Quantities two days, but has only set 15
bonding, and builder's risk
This document comprises lists insurance. pieces…you already know it is
of diverse trades and materials behind. The contractor needs to
that will form part of the As a Contractor, These Are step it up and you may ask him
construction. It includes an Things You Need To to accelerate.
itemized list on the costs of Document On Your
Construction Daily Reports Item 5: Workforce
materials, parts, and labor that
Document each subcontractor graduation ceremony are Deliveries need to be
on the site that day, as well as examples of significant events. documented, such as what and
the number of workers provided. If you are working on a school how much material was
project, and school authorities delivered. Even as the general
Item 6: Hours Worked request that no loud work be contractor, and you are not
Document the hours the crew performed during the graduation signing for it, you should
worked. Also, record the hours ceremony, that request needs to document the delivery, who
the crew did not work and why be noted. signed for it, and where it was
the crew did not work. Again, placed.
Item 10: Third Party Activity
this will be important when Item 15: Record of Visitors
evaluating productivity. Any type of third-party activity
that impacts the project should Keep track of when the
Item 7: Equipment In Use also be documented in this inspector, owner, designer, or
and/or Idle section of your daily report. insurance representative visited
You want to document what the site.
Item 11: Safety Issues and
equipment is being used by Toolbox Talks Item 16: Signature
each subcontractor and what
equipment is sitting idle. Also, All injuries should be thoroughly Every daily report should have a
identify when major pieces of documented, not just on a daily signature.
equipment are mobilized and report. Most insurance policies
demobilized from the project will have their own forms to fill A prime contractor, who is
site. Again, this information is out as well. As the writer of the typically a general contractor, is
essential for a productivity daily report, you want to a fi rm that contracts directly
evaluation, or to support a document the time and location with the owner for the
change order. of the incident, as well as what construction of a project, either
actions took place. in its entirety or for some
For example, if the site work designated portion thereof. In
subcontractor submits a change Item 12: Meetings this regard, the owner may
order for unforeseen field choose to use a single prime
conditions, such as rock, and if Decisions are still occasionally contract or several separate
the change was not made in the field. These prime contracts.
preapproved, it is important that meetings and decisions should
both the site work subcontractor not only be documented in the Competitive Bidding
and the general contractor have daily report but should also be
followed up with an email at the -The owner selects a prime
daily reports documenting the contractor on the basis of
conditions and the equipment end of the day.
competitive bidding,
that were used to excavate that Even if no decisions were made negotiation, or some
rock. at the meeting, the meeting combination of the two.
Item 8: Potential Delaying itself should still be
documented. If it was a brief -When bidding a project, the
Events contractor estimates how much
coordination meeting between
Is the job being impacted by the mechanical and plumbing the project will cost using the
weather? Who was scheduled subcontractors, it is still architect‐engineer’s drawings
to work, but couldn’t? Are there important to document the and specifications as a basis for
access problems? Was an meeting and any plans that the calculations. The contractor
underground tank found that were discussed. then adds a reasonable profit to
was not indicated on the plans this cost and guarantees to do
to be there and did that stop the the entire job for the stated
excavation operation? Did the price.
Item 13: Directions
carpenter not show up to -Bid prices quoted by the
complete his work and delay the Direction from authorities bidding contractors most often
start of paint? Any potential having jurisdiction needs to be constitute the principal basis for
delay should be documented. documented, as well as selection of the successful
inspections passed or contractor, with the low bidder
Item 9: Significant Events inspections failed. usually receiving the contract
A road closure that prohibited Item 14: Deliveries award.
material deliveries or a
-Most bidding documents - Competing contractors are usual arrangement is for a
stipulate that the work shall be often interviewed, in addition to private architect‐engineer firm
awarded to the “lowest submitting the bid and the to perform the design in contract
responsible bidder.” qualifications statement. with the owner.

-This gives the owner the right - The owner then scores the bid -Under this arrangement, the
to reject the proposal of a and the qualifications, awarding design professional acts
bidding contractor if the the project to the contractor with essentially as an independent
contractor is judged to be the best score. design contractor during the
unqualified for some reason. If design phase and as an agent
its bid is selected, the contractor Subcontracting of the owner during construction
is obligated to complete the -When the prime contractor operations.
work in exchange for the engages a specialty firm to
contract amount. -The architect‐engineer acts as
accomplish a particular portion a professional intermediary
Negotiated Contracts of the project, the two parties between the owner and
enter into a contract called a contractor and often represents
- At times it can be subcontract. the owner in matters of
advantageous for an owner to construction contract
negotiate a contract for its -No contractual relationship is
thereby established between administration.
project with a preselected
contractor or small group of the owner and the -Under such contractual
contractors. subcontractor. When a general arrangements, the owner,
contractor sublets a portion of architect‐engineer, and
-It is common practice for an its work to a subcontractor, the contractor play narrowly defined
owner to forgo the competitive prime contractor remains roles, and the contractor is
bidding process and to handpick responsible under its contract basically in an adversarial
a contractor on the basis of its with the owner for any negligent relationship with the other two.
reputation and overall or faulty performance by the
qualifications to do the job. A subcontractor. Design‐Construct
contract is negotiated between
the owner and the chosen -The prime contractor assumes -When the owner contracts with
contractor. complete responsibility to the a single firm for both design and
owner for the direction and construction and possibly
-Such contracts can include any accomplishment of the total procurement services, this is
terms and provisions that are work. referred to as a design‐
mutually agreeable to the construct project.
parties. -An important part of this
responsibility is the coordination -This form of contract is usually
Combined Bidding and and supervision of the various negotiated, although
Negotiation subcontractors. occasionally it is competitively
bid.
- An owner sometimes will Construction Contract
combine elements of both Services -Usually, the contractor has its
competitive bidding and own design section with
negotiation into an approach -The selection of the proper
architects and engineers as
known as best value. contract form appropriate to the
company employees.
situation is an important
-In this approach, a portion of decision for the owner and is -In other cases, however, the
the decision is based on price one deserving of careful architect‐ engineer can be a
and the rest on qualifications. consideration and consultation. contractor’s corporate affiliate or
subsidiary, or the contractor can
- In the best‐value approach, the -The construction contract can
enter into a joint venture
competing contractors are be made to include
arrangement with an
required to submit their construction, design construct,
independent architect‐ engineer
qualifications along with their or construction management
firm for a given project or
bids and are encouraged to services.
contract.
tender suggestions as to how
the cost of the project could be Construction Services
Turnkey
reduced. -Where the contractor provides
construction services only, the
-A turnkey contract is similar to -Cost‐plus‐fee contracts provide - In a turnkey arrangement, the
a design‐ construct contract. that the owner reimburse the owner provides the facility
contractor for all construction design requirements to the
-The difference lies in the costs and pay a fee for its contractor, which designs and
greater range of responsibilities services. constructs the facility under a
that the contractor undertakes single contract. The single
on behalf of the owner under a -How the contractor’s fee is contract eliminates the need for
turnkey arrangement. determined is stipulated in the owner coordination and reduces
contract, and a number of project duration. Upon
- For example, a turnkey different procedures are used in
contract often includes such completion, the key to the
this regard. project is turned over to the
services as land selection and
acquisition, project financing, -Commonly used are provisions owner and the contract is closed
project equipage procurement, that the fee shall be a stipulated out.
and leasing of the completed percentage of the total direct Integrated Project Delivery
facility. cost of construction or that the
fee shall be a fixed sum. -A new type of project delivery
Project Management system is emerging with the
Work‐by‐Force Account development of BIM.
-The term project management
is applied to the provision of -The owner may elect to act as -In BIM environment, all data for
professional management its own constructor rather than the project go into a massive
services to the owner of a have the work done by a database that is shared by all
construction project with the professional contractor. If the stakeholders in the project.
objective of achieving high project is being built for the
quality at minimum cost. owner’s own use, this method of -Because the data are
construction is called the force‐ integrated into a single entity, all
-Such services may encompass stakeholders who contribute
account system.
only a defined portion of the and use the data become active
construction program, such as -In such a situation, the owner participants in the entire project.
field construction, or they may may accomplish the work with The result is shared risk and
include total project its own forces and provide the shared reward across all
responsibility. supervision, materials, and stakeholders, which, in turn,
equipment itself. requires a new type of contract
-The objective of this approach
is to treat project planning, that integrates all stakeholders
-Or the owner may choose to
design, and construction as into a single operational
subcontract the entire project,
integrated tasks within a structure.
assuming the responsibility of
construction system. coordinating and supervising -Individual contracts between
the work of the subcontractors. various stakeholders are no
Fixed‐Sum Contract
longer efficient in a BIM
Turnkey and BOT Contracts
-A fixed‐sum contract requires environment.
the contractor to complete a Fixed‐sum, cost‐plus‐fee, and
-Integrated Project Delivery
defined package of work in work‐by‐force account
(IPD) ties all stakeholders
exchange for a sum of money contracting methods all require
together based on a single
fixed by the contract. Should the owners to coordinate initial
contract that is signed by each
actual cost of the work exceed planning, design, construction,
stakeholder.
this figure, the contractor and facilities start‐up. These
absorbs the loss. tasks distract the owners from Speculative Construction
their core business
-The owner is obligated to make -When owners build structures
responsibilities.
only such total payment as is for sale or lease to other parties,
stipulated in the contractual -For this reason, some owners they engage in what is
agreement. also contract these commonly referred to as
responsibilities to the contractor. speculative construction.
-A fixed‐sum contract may be Turnkey and build‐operate‐
either lump sum or unit price. - Housing and commercial
transfer (BOT) contracts provide
a vehicle for complete project properties like shopping centers
Cost‐Plus‐Fee Contracts
delivery by the contractor. and warehousing facilities are
common examples of such
construction. In tract housing, conditions, watch employees for area where the hazard
for instance, “merchant” unsafe actions and take prompt was observed.
builders develop land and build action to eliminate any hazards. Supervisor Responsibilities
housing for sale to the general
public. Management must do its part by 1. Ensure that each
devoting the resources employee has
- This is a form of speculative necessary to form a safety and received initial
construction through which health committee composed of orientation before
developers act as their own management and elected beginning work.
prime contractors. They build employees. A system must be 2. Ensure that each
dwelling units on their own developed for identifying and employee is
account and employ sales correcting hazards and competent or has
forces to market their products. foreseeable emergencies. The received training on
In much speculative housing, company must provide initial the safe operation of
contractors build for unknown and ongoing training for equipment or tasks
buyer employees and supervisors and before starting work.
we will establish a disciplinary 3. Ensure that each
------------------------------------------ policy to ensure that company employee receives
safety and health policies are required personal
MODULE 8 – followed. protective equipment
CONSTRUCTION (PPE) before starting
Safety and Health
MANPOWER SAFETY work on a project
Responsibilities requiring PPE.
------------------------------- Manager Responsibilities 4. Perform a daily safety
check of the work
Safety and Health Policies
1. Ensure that sufficient area. Promptly correct
All companies must place a high employee time, any hazards you find.
value on the safety and health of supervisor support and 5. Observe the
its employees. It should be funds are budgeted for employees you
committed to providing a safe equipment, training supervise while they
workplace for all employees and and carrying out the are working. Promptly
have developed this program for safety and health correct any unsafe
injury prevention to involve program. behavior. Provide
management, supervisors and 2. Evaluate supervisors additional training and
employees in identifying and each year to make take corrective action
eliminating hazards that may sure they carry out as necessary.
develop during our work their responsibilities as 6. Document employee
process. described in this evaluations.
program. 7. Set a good example for
It is the basic safety and health 3. Ensure that incident employees by
policy that no task is so are fully investigated following the safety
important that an employee and corrective action is and health rules and
must violate a safety and health taken to prevent the attending required
rule or take a risk of injury or hazardous conditions training.
illness to get the job done. or behaviors from 8. Investigate all
happening again. incidents in your area
Employees are required to and report findings to
4. Ensure that a record of
comply with all company safety management.
injuries and illnesses is
and health rules and are 9. Talk to management
maintained and posted
encouraged to actively about changes to work
as described in this
participate in identifying ways to practices or equipment
program.
make our company a safer that will improve
5. Set a good example by
place to work. employee safety and
following established
Supervisors are responsible for safety and health rules health.
the safety and health of their and attending required Employee Responsibilities
employees and, as a part of training.
6. Report unsafe 1. Follow the safety and
their daily duties, must check health rules
the workplace for unsafe practices or conditions
to the supervisor of the established by your
company, Report Employees from each represent on safety
unsafe conditions or operational unit, division or area and health issues.
actions to your may volunteer or be nominated 3. Encouraging safe work
supervisor or safety from among themselves to be a practices among co-
and health committee representative on the workers.
representative committee. If there is only one 4. Reviewing the injury,
promptly. volunteer or nomination, the illness and first aid logs
2. Report all work-related employees may approve the for trends and
injuries and illnesses person by voice vote at a short conducting a separate
to your supervisor meeting called for that investigation of any
promptly, regardless of purpose. If there is more than incident (if determined
how minor they may one volunteer or nomination, a appropriate).
seem. secret paper ballot may be used 5. Providing any
3. Report all near-miss to elect the representative. recommendations to
incidents to your management for
supervisor promptly. Elected representatives will consideration.
4. Always use personal serve for 2 years before being
protective equipment re-elected or replaced. If there The safety and health
that is in good working is a vacancy then an election committee should meet at a
condition when it is will be held before the next regular interval. Each area
required. scheduled meeting to fill the committee member should bring
5. Do not remove or balance of the term. information from the monthly
bypass any safety In addition to the employee- inspections of their areas and
device or safeguard elected representatives, any concerns from the
provided for your management should designate employees in the area they
protection. no more than three represent. Using this
6. Encourage your co- representatives but a minimum information, the committee can
workers to use safe of one who will serve until help identify safety and health
work practices on the replaced by management. problems, develop solutions,
job. Management representation review incident reports, provide
7. Make suggestions to should not outnumber employee training, and evaluate the
your supervisor, safety representation. If the company effectiveness of the safety and
and health committee employs a medical professional health program.
representative, or on staff, it is recommended that
management about A committee member will be
this individual serve on the designated to keep minutes. A
changes that will safety and health committee as
improve employee copy of the minutes will be
well but at least an individual posted in a place where all
safety and health. who manages the workers’ affected employees have
compensation, injury and access to them. The company
Employee Participation illness, and first aid logs, such should archive meeting minutes
Safety and Health as the company safety and for a specified period of time
Committees and Meetings health manager. such as one year for follow-
A chairperson should be up/review purposes. (The
Employers can form safety and company may choose to post
health committees to help selected by a majority vote by
the committee members each minutes on employee bulletin
employees and management boards, on an intranet, etc.
work together to identify safety year. If there is a vacancy, the
same method should be used to Additionally, the company may
and health problems, develop choose to archive such records
solutions, review incident select a replacement.
electronically.)
reports, and evaluate the The duties of safety and health
effectiveness of the safety and committee members include: General Employee Safety
health program. The committee Meetings
should be made up of 1. Conducting a monthly
management-designated self-inspection of the All employees are required to
representatives and employee- area they represent. attend a monthly safety and
elected representatives from all 2. Communicating with health meeting. This meeting
areas within the company. the employees they will help identify safety and
health problems, develop
solutions, provide training, and within three days of the duration of employment plus 30
evaluate the effectiveness of the incident. years.
safety and health program. The safety and health
manager/company medical First aid records (not including
An employee will be designated professional/HR or personnel medical histories) of one-time
each month to keep the manager will: treatment and subsequent
minutes. A copy of the minutes observation of minor scratches,
will be posted in a place where • Determine from the cuts, burns, splinters, and the
all affected employees have Employee’s Incident like that do not involve medical
access to them. The company Report form, Incident treatment, loss of
should archive meeting minutes Investigation Report consciousness, restriction of
for a specified period of time form and any claim work or motion, or transfer to
such as one year for follow- form associated with another job, if made on-site by a
up/review purposes. (The the incident. nonphysician and if maintained
company may choose to post • Enter any recordable separately from the employer's
minutes on employee bulletin incident within seven medical program and its records
boards, on an intranet, etc. calendar days after and the medical records of
Additionally, the company may becoming aware of the employees who have worked for
choose to archive such records injury/illness/fatality. less than one year for the
electronically). • If the injury is not employer need not be retained
recorded on the OSHA beyond the term of employment
Recordkeeping and if they are provided to the
log, add it to the first
Reporting employee upon the termination
aid log, which is used
Injuries and Illnesses to record non-OSHA of employment.
Reporting recordable injuries and
Exposure Records
near misses.
Employees are required to • The employer may Background data to
report any injury or work-related need to fill out and file environmental (workplace)
illness to their immediate a Workers’ monitoring or measuring, such
supervisor regardless of how Compensation Form, as laboratory reports and
serious. Minor injuries such as “Employer’s Report of worksheets, need only be
cuts and scrapes will be entered Employee’s Injury,” retained for one year so long as
on the first aid log. The with the Industrial the sampling results, the
employee will use an Commission within five collection methodology
“Employee's Incident days of learning of an (sampling plan), a description of
Report” form to report more injury or allegation. the analytical and mathematical
serious/compensable injuries. Employee Access to Medical methods used, and a summary
The supervisor will: and Exposure Records of other background data
relevant to interpretation of the
Whenever an employee or
• Investigate all injuries results obtained are retained for
designated representative at least 30 years.
and illnesses in their
requests access to a record, we
work area, including
must ensure that access is Material safety data sheets and
serious first-aid cases
provided in a reasonable time, records concerning the identity
and near miss
place, and manner. If we cannot of a substance or agent need
incidents. Complete an
reasonably provide access to not be retained for any specified
“Incident Investigation
the record within 15 working period as long as some record
Report” form and “Sup
days, we will apprise the of the identity (chemical name if
ervisor’s Incident
employee or designated known) of the substance or
Investigation” form
representative requesting the agent, where it was used, and
immediately following
record of the reason for the when it was used is retained for
the incident.
delay and the earliest date when at least 30 years.
• Provide all incident the record can be made
investigation Biological monitoring results
available.
report forms to the designated as exposure records
safety and health The medical record for each by specific occupational safety
manager/company employee will be preserved and and health standards must be
medical professional maintained for at least the preserved and maintained as
or HR/personnel office
required by the specific of equipment and any anything DOLE (Department of Labor
standard. else in the work area that may and Employment) Department
be relevant. The team will Order 13 - Construction Safety
Analyses using exposure or complete a written incident
medical records must be investigation report. The report /content/enforced/17067-
preserved and maintained for at will include a sequence of FirstSem2021-
least 30 years. events leading up to the 4101/DO13+Seriesof1998
incident, conclusions about the CONSTRUCTION SAFETY.pdf
Training Records
incident and any DOLE (Department of Labor
Some standards require training recommendations to prevent a and Employment) Frequently
records to be maintained for similar incident in the Asked Questions
three years and some do not future. This report will be given
require training records. to [insert appropriate name/job /content/enforced/17067-
Records of employees who title] for corrective action. The FirstSem2021-4101/FAQs 1.pdf
have worked for less than one report will be reviewed by the
year need not be retained after safety and health committee at /content/enforced/17067-
employment, but we are its next regularly scheduled FirstSem2021-4101/FAQs 2.pdf
required to provide these meeting.
records to the employee upon
termination of employment. When a supervisor becomes
aware of an employee injury
Accident / Incident where the injury was not serious
Investigation enough to warrant a team
investigation as described
Accident/Incident above, the supervisor will write
Investigation Procedures an incident investigation report
If an employee dies while to accompany the employee’s
working or within 30 days of the report and forward them to
initial accident/incident causing In addition, whenever there is
an injury or illness, or when an incident that did not result in
three or more employees are an injury to an employee
admitted to the hospital as a (a near-miss), the supervisor
result of a work-related will investigate the incident. The
accident/incident, the company incident investigation report
must contact DOLE within eight form will be filled out to
hours of becoming aware of the investigate the near-miss and to
accident/incident. establish any corrective action
Whenever there is an incident as applicable. The form will be
that results in death or serious clearly marked to indicate that it
injuries or illnesses, a was a near miss and that no
preliminary investigation will be actual injury occurred.
conducted by an accident Below are Links to
investigation team made up of Documents and Files Related
the immediate supervisor of the to Construction Safety
injured person(s), a person
designated by management, an Sample Safety Programs
employee representative of the
safety and health committee, /content/enforced/17067-
and any others whose expertise FirstSem2021-4101/SAMPLE
would help in the investigation. SAFETY PROGRAMS.doc

The accident investigation team DOLE (Department of Labor


will take written statements from and Employment) Occupational
witnesses and photograph the Safety and Health Standards
incident scene and equipment /content/enforced/17067-
involved. The team will also FirstSem2021-4101/OSH-
document, as soon as possible Standards-Amended-1989.pdf
after the incident, the condition
FORMULAS
SAMPLE PROBLEMS
Compacted Volume =

1700𝑘𝑔/𝑚3
458,823.5 × = 410,526.32
1900 𝑘𝑔/𝑚3

1
4(120)
Base width= ( )2 = 7.56𝑚
12 tan 35

Height =7.56tan 35 = 2.65𝑚


2

𝑚3 𝑐𝑦𝑐𝑙𝑒𝑠 60𝑚3
Productivity Rate = . 5 × 120 =
𝑐𝑦𝑐𝑙𝑒 ℎ𝑟 ℎ𝑟
𝑃𝐻𝑃
4500
Unit Cost of Production = ℎ𝑟
𝑚3
= 75 𝑃𝐻𝑃
3
60 𝑚
ℎ𝑟
3
𝑚3
Net Productivity Rate = 60𝑚 × .69 = 41.4
ℎ𝑟 ℎ𝑟

60𝑘𝑔
A . Rolling Resistance = 25,X10^3𝑘𝑔 × =
𝑡𝑜𝑛
Moisture Content = 50 𝑘𝑔−40𝑘𝑔 = .25 × 100% = 25% 1,500 𝑘𝑔
40 𝑘𝑔
Grade Resistance = 25,000𝑘𝑔 × 15% = 3,750𝑘𝑔

Total Resistance = 1,500 𝑘𝑔 + 3,750𝑘𝑔 = 5,250𝑘𝑔

Rimpull = 15,000 𝑘𝑔 × .35 = 5,250𝑘𝑔

Rimpull = 5,250𝑘𝑔 − 5,250𝑘𝑔 = 0


55𝑘𝑔
B . Rolling Resistance = 27,400𝑘𝑔 × =
𝑡𝑜𝑛
1,507 𝑘𝑔

Grade Resistance = 27,400𝑘𝑔 × 15% = 4,583𝑘𝑔


1700𝑘𝑔
3
Swell = ( 𝑚 − 1) × 100 = 30.8% Total Resistance = 1,500 𝑘𝑔 + 3,750𝑘𝑔 = 6,090𝑘𝑔
𝑘𝑔
1300
𝑚3
Rimpull = 17,400 𝑘𝑔 × .35 = 6,090𝑘𝑔
1700𝑘𝑔
3
Shrinkage = (1 − 𝑚
𝑘𝑔
) × 100 = 10.5% Rimpull = 6,090𝑘𝑔 − 6,090𝑘𝑔 = 0
1900
𝑚3

3
Load Factor = 1300𝑘𝑔/𝑚 = .76
1700 𝑘𝑔/𝑚3
3
Shrinkage Factor = 1700𝑘𝑔/𝑚 = 0.89
1900 𝑘𝑔/𝑚3

Loose Volume = 600X10^3 m3

Bank Volume =
1300𝑘𝑔/𝑚3
600,000 × = 458,823.5 𝑚3 10 × 6 × 20 × 2.5 × .75
1700 𝑘𝑔/𝑚 3 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 = = 10𝑝𝑎𝑠𝑠𝑒𝑠
𝑐𝑐𝑚
225
ℎ𝑟

You might also like