Question 1 0 / 1 point
Explain why an addendum should not be issued too close to the bid closing date.
Because a Bidder requires enough time to ensure that they can meet the new project
requirements,
The correct answer is not displayed for Long Answer type questions.
Hide Feedback
It can put undue hardship on bidders to react to the changes. (M2, L5: Addenda)
Question 2 0 / 1 point
Instruction to Bidders
The correct answer is not displayed for Long Answer type questions.
Hide Feedback
https://learn.sait.ca/d2l/lms/quizzing/user/quiz_submissions_attempt.d2l?isprv=&qi=887618&ai=6708576&isInPopup=0&cfql=0&ou=383786 1/3
9/4/2020 : Quiz Submissions - Quiz 2.5 - Non-Credit 2019-2020 - Principles Constr Document (CNST-002-O4A) - SAIT
Question 3 0 / 1 point
All information required by a bidder to intelligently prepare and submit a bid, including:
Project Identification; Documents; Examination of Documents and Site; Resolution of
Discrepancies and Ambiguities, and Issuing Clarifications; Substitution of Products;
Basis of Bids; Preparation of Bids; Bid Security Information; Requirements for Bonding;
Subcontractor Listing; Identification and Submission of Bid; Modification or Withdrawal
of Bid; Disqualification of Bidders; Governing Laws and Regulation; Opening of Bids;
Award of Contract; and, Execution of Contract.
The correct answer is not displayed for Long Answer type questions.
Hide Feedback
The requirements with which a bidder must comply before and during submission of a
bid.
project identification
information about document availability and returning documents
requirements for examining bid documents and project site
a description for how discrepancies will be dealt with during the bid period, how
questions should be raised, and how clarification will be issued
a description of requirements related to proposed substitutions
a description of the basis of the bid (if required)
a description of how to prepare and submit the bid
bid security requirements
bonding requirements
how to modify or withdraw a bid
what conditions would disqualify a bid
what laws and regulations govern the project
time and place for bid opening; whether it’s private or public
procedures for awarding the contract
requirements related to contract execution (M2, L5: Instructions to Bidders)
https://learn.sait.ca/d2l/lms/quizzing/user/quiz_submissions_attempt.d2l?isprv=&qi=887618&ai=6708576&isInPopup=0&cfql=0&ou=383786 2/3
9/4/2020 : Quiz Submissions - Quiz 2.5 - Non-Credit 2019-2020 - Principles Constr Document (CNST-002-O4A) - SAIT
Attempt Score:0 / 3 - F
Overall Grade (highest attempt):0 / 3 - F
Done
https://learn.sait.ca/d2l/lms/quizzing/user/quiz_submissions_attempt.d2l?isprv=&qi=887618&ai=6708576&isInPopup=0&cfql=0&ou=383786 3/3