Professional Documents
Culture Documents
Build Quality Guide - 2023
Build Quality Guide - 2023
EPT/ANS/A040
Privacy- None
UNCONTROLLED IF PRINTED
One Fibre Network – Build Quality Guide for Engineers
Author
The author of this document may be contacted at:
E1W 9TD
Telephone:
Fax:
Email: accreditationqualitystandards@openreach.co.uk
Content approval
This is the Issue 41 of this document.
The information contained in this document was approved on 23-Nov-2023
by Marc Henson, Network Quality, Standards & Accreditation Specialist
Page 2 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Version History
Page 3 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 4 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 5 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 6 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 7 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 8 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 9 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Table of Content
1 INTRODUCTION --------------------------------------------------------------------------------------------------------------------- 13
2 FTTP BUILD COMPONENTS ------------------------------------------------------------------------------------------------------ 13
2.1 ONE FIBRE NETWORK (1FN) --------------------------------------------------------------------------------------------------- 13
2.2 LEGACY FTTP AND OFN FTTP COMPARISON -------------------------------------------------------------------------------- 18
3 ONE FIBRE NETWORK (OFN) ---------------------------------------------------------------------------------------------------- 19
3.1 FTTP BUILD ARCHITECTURE ---------------------------------------------------------------------------------------------------- 19
4 PLANNING POLICY CONSIDERATIONS ---------------------------------------------------------------------------------------- 20
4.2 SURVEY MARKERS & SURVEY NETWORK NOTES ------------------------------------------------------------------------------ 21
5 USE OF KOPEX ----------------------------------------------------------------------------------------------------------------------- 21
5.1 COF 205 ------------------------------------------------------------------------------------------------------------------------ 22
5.2 SPINE CABLE LENGTHS FOR TM JOINTS AND CBT’S--------------------------------------------------------------------------- 26
5.3 FIBRE ROUTING AND TRAY ALLOCATION WITHIN TM JOINTS ----------------------------------------------------------------- 29
5.4 TM TRAY SPLICE PROTECTORS -------------------------------------------------------------------------------------------------- 29
5.5 TM JOINTS – QUALITY STANDARDS -------------------------------------------------------------------------------------------- 32
5.6 MOUNTING BRACKETS (MOBRA)-------------------------------------------------------------------------------------------- 35
6 36F CABLES --------------------------------------------------------------------------------------------------------------------------- 38
6.1 36 FIBRE ULTRA-LIGHTWEIGHT CABLE (ULWC) ----------------------------------------------------------------------------- 38
6.2 IDENTIFICATION OF ELEMENTS-------------------------------------------------------------------------------------------------- 39
6.3 36F ULW EXTERNAL LOCKING MECHANISM (ELM) ------------------------------------------------------------------------- 40
6.4 36F ULWC STRENGTH MEMBERS--------------------------------------------------------------------------------------------- 46
6.5 COF 600 UG 36F CABLE ------------------------------------------------------------------------------------------------------ 48
6.6 COF 250 / SST / SLIPPERY FISH CABLE --------------------------------------------------------------------------------------- 48
6.7 SUPPORT AND RESTRAINT CABLES IN THE UNDERGROUND NETWORK -------------------------------------------------------- 49
6.8 SUPPORT AND RESTRAINT OF CABLES IN THE OVERHEAD NETWORK -------------------------------------------------------- 51
6.9 OFN CABLES ON WALL ---------------------------------------------------------------------------------------------------------- 55
6.10 SAFETY WHEN STRIPPING COF ------------------------------------------------------------------------------------------------- 56
7 36F OVERHEAD CABLE VARIANTS (ADSS) ----------------------------------------------------------------------------------- 56
8 CONNECTORISED BLOCK TERMINALS – (CBT) ------------------------------------------------------------------------------ 59
8.1 GENERAL ------------------------------------------------------------------------------------------------------------------------- 59
8.2 CBT MOUNTING GUIDANCE – UG SCENARIO -------------------------------------------------------------------------------- 70
8.3 POLE ENVELOPES & POSITIONING OF JOINTS/CBT’S/CABLES --------------------------------------------------------------- 73
8.4 INSTALLATION OF ULW TAILED CBT------------------------------------------------------------------------------------------- 86
8.5 INSTALLATION OF OVERHEAD SST CABLE -------------------------------------------------------------------------------------- 87
8.6 OVERHEAD FIBRE LENGTH RENEWALS ----------------------------------------------------------------------------------------- 92
8.7 OH FIBRE CABLE SLACK POLICY ------------------------------------------------------------------------------------------------ 96
8.8 CBT POLE MOUNTING BRACKET ---------------------------------------------------------------------------------------------- 106
8.9 MOUNTING ONTO A WALL ---------------------------------------------------------------------------------------------------- 107
8.10 POSITIONING OF TM JOINTS, CBTS & CABLES ON POLES ------------------------------------------------------------------- 108
8.11 FTTP CABLING PLACEMENT ON POLES ---------------------------------------------------------------------------------------- 110
8.12 USE OF D POLES. --------------------------------------------------------------------------------------------------------------- 112
8.13 DNO JOINT USER POLE ALLOWED ATTACHMENTS --------------------------------------------------------------------------- 113
9 SURVEY NETWORK NOTES & SURVEY MARKERS ------------------------------------------------------------------------ 114
Page 10 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 11 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 12 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
1 Introduction
The “One Fibre Network” (OFN) utilises both legacy and new fibre
components. These will be identified, explained and the key quality standards
highlighted in easy to read format. Any governing ISIS documents will be
referenced and should be referred to for detailed or updated information.
It is the responsibility of FBC’s/project managers to ensure their operatives are
aware of any updates, these can be found in the reference section of this
document.
Page 13 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 14 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 15 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Full details and installation practices for the various port kits can be
found at EPT/COF/D945
Page 16 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 17 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 18 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
3.1.1 UG Build
Page 19 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
3.1.2 OH Build
Initially the policy was to provide UG DD cable or rope from the UG CBT to the
customer external capping whenever possible. As of March 2018, this is no
longer required; test rod & rope/cabling of the UG customer lead-in will be
performed in response to a customer order.
Page 20 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
4.1.3 MDUs
4.1.4 Single customers over 150m away from CBT on private land
For single remote premises located between 150m and 350m from the
curtilage of the public maintainable highway, a long reach 350m connectorised
DualDrop cable should be used.
5 Use of Kopex
The table below provides an overview of which cables / blown fibre tubing do
and do not require the use of Kopex to provide additional protection when
installed into the TM series range of nodes.
Page 21 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
COF 209 No
COF 200 No
COF 201 No
COF 600 No
The following provides additional information relating to each of the cables and
tube types detailed above.
COF 205 is a mini cable designed exclusively for installation into Sub Duct
Monobore 6 using blown cable techniques only. This cable must not be
Page 22 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
installed using hand pulled cabling techniques as damage to the sheath and
fibres is likely to result.
Instructions for installing the Kopex, SDMB6 seal, SCOP and shrinkdown are
detailed in EPT/COF/D919. Kopex protection is required on COF205 cable
from the SDMB6 connector to the TM port kit.
COF 260 is specifically for overblowing COF 200 series in SDMB 5. Kopex
protection is required on COF260 cable from the Sub Duct connector to the
TM port kit. Details of protecting COF260 are detailed in EPT/COF/D960
25mm Conduit (060631) should be used for all installations of 5mm and 6mm
BFT into the TM series nodes. Please refer to IP 354 (supplied with port kit)
and available within EPT/COF/D945. For attachment of the conduit to the
sheathing of the BFT the appropriate 25mm flexible conduit connector should
be used. The connector required varies depending on the BFT being installed,
the table below details which connector should be used for each BFT type.
Page 23 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
066134 7BFT (2.74/4mm) connector for 4BFT 5mm & 7BFT 4mm
Conduit Flexible 25mm x 10
071195 4BFT (4.5/6mm) connector for 7BFT 5mm and 4BFT 6mm
Conduit Flexible 25mm (BAG OF
10)
Kopex is not required on 2 BFT which is installed directly into the appropriate
port kit (092759)
Due to the rigidity of 8mm BFT it is not advised to install it directly into a TM
series node. A suitable tube joint should be used and 5mm tubing provided
into the TM joint
Kopex is not required on FDC or 36F ULWC, into TM joints either UG or OH.
Page 24 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
There are no requirements for the use of Kopex when installing COF 200, 201
and 209 cables.
There are no requirements for the use of Kopex when installing COF 250 cable
into a TM series node or CBT tail.
Kopex is not required on COF 250, either UG or OH, except for:
◼ When Installing COF 250 into a heat shrink joint e.g. Node Joint 4A, GJ3A etc.
conduit is used to make the cable round at the point of entry into the port and
heatshrink
In these instances please refer to the method detailed in EPT/COF/C005
Caution: When installing the CBT in an underground footway box, ensure
the minimum bend radius of 80mm is maintained
There are no requirements for the use of Kopex when installing COF 600 cable
into a TM series node.
Page 25 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Joint Size Cable Route-A Cable Route-B Cable Route-C Joint Box Size Overall Loop
Length
JF 11
JF 10
Page 26 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
JF 6
JF 4
JF 2
Joint Size Cable Route-A Cable Route-B Cable Route-C Joint Box Size Overall Loop
Length
JF 11
Page 27 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
JF 10
JF 6
JF 4
JF 2
Further information on cable loop lengths and joint box capacity/layout for TM
nodes can be found in NWK/LNK/C573 – TM Node Jointbox Capacity
Note: All UG CBTs must have sufficient feed cable slack to ensure the cable is
supported and restrained within the jointbox. The feed cable must allow the CBT to be
raised/accessed for provision work and also maintain the cable bending radius when
stowed. The chamber size and capacity will govern the cable length required,
additional guidance regarding UG cable lengths and clearance from other plant can be
found in NWK/LNK/C573
Page 28 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Detailed instructions for tray layout and joint configuration can be found at:
CE TM joints tray layout and routing instructions
Page 29 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Note: The above picture is showing the old (yellow) protector splice 5A, the
principles still apply with the new clear 5A.
The new splice protector bays are designed to take a completed 2.2mm splice
protector (5A). Protector Splice 4A are NOT suitable for use in this type of tray
as they have a nominal diameter of 2.4mm when completed and will not be
retained correctly in the bays.
Key points
Small & Medium TM joints
◼ Spare or looped elements stored in the loop storage area at the back of node
◼ In COF 200 fibre elements may not be coloured so would therefore need to be
colleted for future identification
◼ Input fibres routed up L/H raceway, output fibres routed up R/H raceway
◼ Each CBT is to be managed on a dedicated tray, starting from the bottom.
◼ 1 SASA fitted in small joint, up to 2 SASA in medium joint
◼ 1st SASA Blue outputs, 2nd SASA Orange outputs
Page 30 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
◼ Spare or looped elements stored in the loop storage area in the centre of
node.
◼ Plastic sleeve should always be fitted in storage area regardless of
oval/circular port kit used.
◼ In COF 200 fibre elements may not be coloured so would therefore need to be
colleted for future identification
◼ Input fibres routed up L/H raceway, output fibres routed up R/H raceway
◼ Each CBT is to be managed on a dedicated tray, starting from the bottom.
◼ Up to 4 SASAs
◼ SASA Outputs as follows: 1st SASA Blue, 2nd SASA Orange, 3rd SASA
Green, 4th SASA Red
◼ SASA outputs stored in mandrels or spare splicing tray(s)
◼ Each CBT is to be managed on a dedicated tray, starting from the bottom.
◼ Splice through configuration:
⎯ Element/through splicing on tray 1 (side A&B)
⎯ SASA input tray 2&3 (side A&B)
◼ Loop through configuration:
⎯ SASA input tray 1&2 (side A&B)
Page 31 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
5.5.1 Common
Page 32 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
5.5.2 XL & L
Page 33 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
◼ Mid span loops left with 150mm loop diameter on loop. 4 loops in XL and 6
loops in Large
◼ Loops provided in plastic sleeve and twisted in natural position
◼ Loop storage cover/Velcro retaining straps provided over fibres with no kinks
or cable elements protruding
◼ Correct splice protector used for tray type and stored correctly
◼ Manifold cover securely replaced
◼ O ring and surfaces clean
◼ Orange sealing clamp fully engaged and locked in place
5.5.3 M&S
Page 34 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
◼ M – LHS loop fed and stored in clockwise direction under tabs, RHS loop fed
and stored in anticlockwise direction under tabs with final single loop provided
between tabs
◼ S – several loops provided to fill loop storage area diameter, secured with
Velcro with no kinks or bends in loops
◼ Splitter fibres routed and crossed at bottom of mandrel
◼ Correct splice protector used for tray type and stored correctly
◼ Manifold cover replaced
◼ O ring and surfaces clean
◼ Clamp fully engaged and locked in place
Page 35 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
◼ JMF102 – expanding no drill MOBRA is unsuitable for this joint box type.
Page 36 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
◼ Kit Joint Support 1A (grey tube) strapped to chamber iron work to support
CBT/Joints
◼ Where no chamber iron work exists Kit Joint Support to be used as appropriate
Page 37 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
6 36f Cables
6.1 36 Fibre Ultra-Lightweight Cable (ULWC)
This is a small format 36f cable for use in the underground or overhead
network. 36f ULW can be installed directly into underground ducts without the
use of sub-duct. The use of 36f ULW in the underground network should be
Page 38 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
minimised to preserve stock, COF600 is the preferred cable for UG use. When
36f ULW is erected overhead it is to be treated as Dropwire.
NWK/LNK/C541 refers
◼ COF600 should be used when cabling UG from an aggregation node.
◼ COF215 should be used when cabling OH from an aggregation node.
◼ Transitioning from COF600 (UG) to COF215 (OH) should be performed at the
nearest convenient point and only performed to avoid excessive use of
COF215 in the underground network.
Page 39 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 40 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Old type
Current type
Page 41 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 42 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
2. Fit 7mm clamp onto UPB and install 36f ultra-light-weight overhead cable
and feed end of cable down through pole.
Note: Do not secure cable in hollow pole yet
3. Starting from bottom of locking device wrap the cable in a figure of 8, 2 and
a half times around the locking bollards and secure cable at bottom 2 lugs and
top spigot using strap cable fixing 1a Item code 072492.
Note: Ensure that cable minimum bend radius is not compromised
Page 43 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
4. Once cable is secured on locking device the cable can be secured in the
pole on the clamp ring using straps cable fixing 1a
Page 44 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 45 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
These can be terminated with the SSM still in the sheath, but the sheath
diameter may need to be trimmed
Page 46 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
These can be terminated with the SSM still in the sheath, but the sheath
diameter may need to be trimmed.
Page 47 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
⎯ For underground use in duct, CBT tails can be erected overhead (see 8.5)
⎯ Installed directly into ducts (no sub-duct required)
⎯ Hand/mechanised cabling, max pull 1.5kN
⎯ No factory marking, requires yellow tape in jointboxes
Page 48 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Warning: Straps Cable Fixing must be cut flush to prevent injury using the
correct tools (tensioner or nippers miniature 2)
Page 49 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
All cables, lead in’s and main feeds must be supported and restrained on a
bearer, flat bar or Kit Joint Support 1A so it cannot be accidentally pulled from
the box or lose its minimum bend radius. See below examples of fully
supported cables on existing cable support and using Kit Joint Support 1A
(KJS1A)
Note: Copper joints and cables must not be supported by fibre cables and joints and
vice versa. All cables and joints must be supported and restrained as described by the
methods above.
Page 50 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Warning: You must not attach wires or cables to poles carrying high
voltage as per network policy briefing 939.
◼ All engineers MUST be aware of the Overhead Power Glove Box Guide and
have access via the following link. The overhead power glovebox guide.
◼ It is also available by texting PowerGBG to 81192 or via the Linx app.
◼ Any work being carried out in the vicinity of Overhead power and Joint User
Poles (JUP) must be done so in full compliance and understanding of the
Overhead Power Glove Box Guide.
Cables should be cleated where possible on the front or rear of the pole
leaving 50mm clear space around any existing step, taking into account duct &
CBT position. Where possible Cable should not weave/cross/tangle with any
other cable on the pole. It should be possible in most cases for cables to co-
exist side by side supported & restrained by a single aluminium strip across all
of them following the path of existing copper where possible.
Page 51 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
The following key points should be followed when attaching the ULW Fibre
cable to Poles. In all instances, relevant carriageway clearances and
separation distances from power lines must be complied with.
◼ Multiple ULW’s erected along the same line of route, may be attached either
on the sides of the pole using Brackets 22 / UPB, or onto the Ringhead.
◼ Where crossarms are present it is recommended that these are replaced with
Pole Ring Head
◼ Poles with single dropwires, with a through angle of greater than 90 degrees,
can be fitted with single bracket 22.
◼ When attaching on the sides, a 300mm vertical spacing between ULW’s and
Aerial Cables / D/W’s is preferred. However, where existing wires / cables and
ground clearance requirements prove so restrictive that a Pole change (larger
pole) would be required, the vertical spacing may be reduced to a minimum of
150mm.
◼ There is no longer a requirement to use Protector Cable Abrasion (PCA) when
installing double helix clamps for any Round Fibre.
Page 52 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
6.8.2 Routing of 36 fibre ULW cables at DP/CP with Ring Pole Head
All overhead fibre cables must be fed BEHIND the ringhead. The only
occasions where they can be fed in front of the ringhead are listed below.The
list below is not a definitive list but covers most examples.
◼ An incoming overhead 36 Fibre ULWC (COF215) should be routed BEHIND
the ring if feeding into a TM Joint/Splitter
◼ An incoming overhead COF250 (Slippery Fish) should be routed BEHIND the
ring if feeding into a TM Joint/Splitter
◼ An Incoming 36 Fibre ULCW (COF215) with a prefitted CBT can be routed in
FRONT of ring if terminated on DP/CP
◼ An incoming overhead SST COF250 (Slippery Fish) with a prefitted CBT can
be routed in FRONT of the ring if terminated on DP/CP
◼ SST/ULCW going from underground to continuous overhead length between
DP’s & CP’s can be routed in FRONT of Ring (UG to OH)
Page 53 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 54 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
◼ Carrier pole method when 36F clamp with purple flash is used
Page 55 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Type of
36F ULWC BIRLA CDC HFCL
cable
081869
Item Code 081870 092460 092458 092459
or
Diameter 7 mm 7 mm 9 mm 11 mm
Strength
Steel wires Aramid Yarn FRP rod FRP rod
Member
(NB: Only
(NB: Only
RH & UPB
UPB at
at
RH, Road/Rail
Pole RH, UPB Road/Rail
RH, UPB B22 RH, UPB B22 UPB crossings
Attachments B22 crossings
B22 and angle
and angle
pole
pole
positions)
positions)
Page 56 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
XL/L
XL/L – M/S - XL/L – M/S - XL/L – M/S - M/S -
Oval Ports –
082258 088360 082258 088360 090260 088361 088361
None
Circular
088362 088362 082322 082323 082322
Ports
Key
RH – Ring Head
UPB – Universal Pole Bracket
B22 – Bracket 22
ACADSS10 Clamp
Note: There is also a Sterlite 36 Fibre Ultra Light Weight Overhead Cable (item code:
092511) available that has exactly the same technical specification and installation
practices, including clamps, ELMs, HV limit and port kits, as the Prysmian (PGH) 36F
ULW
The Birla 36F 7mm cable FRP rod cannot be used as a strength member in
the dual or 4 port circular kits and the Kevlar Aramid Yarns must be used
General
◼ The FRP strength member diameter is too small for it to be held in the restraint
of either oval or two port circular port kits and is too stiff to be wound in the
restraint of the four port circular port kit.
◼ Therefore, the Kevlar within the cable should to be used for restraining the
cable.
Page 57 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
◼ In order to use the Kevlar for restraining the cable in the port kits its volume
needs to be reduced to approximately a 5th. If the volume is not reduced the
Kevlar is too bulky to be installed into the restrain mechanisms.
◼ Once the volume is reduced restrain the Kevlar follow the guidance in the
relevant port kit IP guide with the following advisories.
Page 58 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 59 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
The CBT is supplied in 4, 8 and 12 port variants with the ports being factory
terminated to the fibres in the fibre cable tail.
Points of reference:
EPT/COF/C005 - FTTP Single Split Non FDP Connectorised Block Terminal
Build Installation Practices
If you are installing a CBT into the legacy blown fibre network as a retro build
activity please refer to ISIS document
EPT/COF/C006 - FTTP Connectorised Retro Build Practices
EPT/OHP/B039 - SST Cable with Pre-Terminated CBT
8-1 shows the original Commscope CBT’s
8—1
8-2 shows the Commscope NOVUX CBT’s
Page 60 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
8—2
8-3 Shows the corning CBT’s
Page 61 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
8—3
8-4 Shows Sterlite CBT’s
Page 62 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
8—4
◼ The CommScope CBT utilises the same body regardless of port count, with
ports being positioned in rows of four, whereas the Corning product uses
different sized enclosures for each port count.
◼ All CBTs must have the node ID written on the top face of the CBT with the C
code. When mounted on a MOBRA where possible label the rear face of the
CBT to aid identification
◼ Overhead CBTs must be fitted in the top pole envelope and black plastic
mounting brackets must be used on Corning CBTs when fitted on poles.
◼ CBTs with a 36f ULW tail (COF 215), where the cable can be spanned
overhead require an ELM at both the CBT and jointing position. The ELM
should be co-located with the CBT in the top pole envelope.
◼ COF250 SST cable can be erected overhead for end of route CBTs
Page 63 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
The Pushlok Miniature CBT is around a quarter of the size of the standard
CBTs that are currently used for Overhead (OH) and Underground (UG)
deployment.
The current zones in which the Pushlok CBTs are permitted to be installed are
all wall mounted scenarios, Newsites & Congested UG Boxes.
Caution: At present, Pushlok must not be installed on poles, this is due to
the breaking strain of the L2C cables.
Various cable colour codes exist depending on CBT manufacturer and date of
issue.
A visible light source (red light) should be used to confirm the correct
cable/port allocation where required.
Page 64 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
It is important to keep cables restrained so as they are not free to flap in the
wind causing possible faults or hamper the engineer when working at the pole
top. Below are a set pictures showing how to arrange Hybrid Dropwires
terminating on CBT and copper BT.
Page 65 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Caution: Back to back brackets must not be fitted in the lower envelope.
Point of reference EPT/COF/C005
Caution: Back to back brackets must not be fitted to walls
Where a back to back bracket is fitted, washers should be used to spread any
future load (prevent smaller screw heads pulling through due to metal fatigue).
Where the back to back bracket does not come with washers included,
washers galvanised 19 (I/C 073202) are an acceptable alternative.
Page 66 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 67 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 68 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 69 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 70 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
◼ Place supplied Unistrut channel nuts the channel approximately 350mm apart,
the actual spacing will vary depending on the CBT being installed.
◼ Attach the CBT to the top unistrut nut using an M6X40 posidrive set screw
through the top mounting hole.
Rotate the CBT to the side to enable the Corning stand-off adapter to be
attached to the bottom channel nut using penny washer and second set screw
Page 71 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Attach 2 x SCF1A to large cable entry & tighten onto stand-off adaptor.
If installing a CommScope CBT attach the CBT bracket to the unistrut using
the supplied posidrive machine screws. Then Install the CBT onto the bracket
from the bottom first and click into place.
Page 72 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 73 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 74 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Figure 2
Envelopes of Space
The safe climb zone must be kept clear. No equipment is allowed in this area
due to the requirement to safely position the climber’s belt and to avoid
potential damage to equipment.
Page 75 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Fig 3
Page 76 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 77 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
In most cases the 800mm line will be at the position of the lowermost Bass
step.
Where the Bass steps are higher than 800mm, equipment can be attached
below them providing the attachment point is a minimum of 800mm above the
‘working steps.
Likewise, where the Bass steps are exceptionally low, the 800mm clear space
rule still applies.
Please see the examples below.
Page 78 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 79 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 80 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 81 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 82 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Fix the CBT bracket in the correct position within the top pole envelope
Install the CBT base into the bracket and click the top into place,
When fixing the SST fibre tail on a pole use Strip Aluminium at 450mm
intervals fixed with 2 x Nails Bonding (072034) & Washers Galvanised 19
(073202). The aluminium strip can also be formed into a “C” clip and using 1 x
nails bonding and washer galvanised & must be dressed as close to the pole
as possible.
Page 83 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 84 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
When installation is complete ensure the tail is protected on the pole with
appropriate sized capping from ground level to a minimum of 2 metres up the
pole.
Page 85 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
When attaching fibre equipment to DNO poles the new labels (shown below)
must be used.
The new labels can be ordered with immediate effect using the item codes
below:
◼ Label Item code 112099 for wooden poles - bag of 10
◼ Pin Steel No.2 7/8 inch Item code 070864 – box of 100
◼ Sticky label item code 112100 for hollow poles - bag of 10
In the main the process for installing the ULW tailed CBT on a pole follows the
same process as the mounting of the SST cabled CBT above.
The ULW tailed CBT is drummed in reverse to an SST tailed CBT so that the
CBT is accessed first, this allows the CBT to be mounted on a pole or OH
structure, the ULW tail can then be installed into network.
To mount the ULW tailed CBT to the pole top follow the process detailed for an
SST tail.
Page 86 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Once the CBT has been mounted to the pole the installation of the ULW cable
into the overhead network should follow the standard practices detailed in
EPT/COF/D932
Remember to lock off the ULW cable in an ELM, item code 066611 on the first
and last poles of any continuous overhead span. See EPT/COF/D932 for
details.
When fixing the 36f ULW fibre tail on a pole use Strip Aluminium at 450mm
intervals fixed with 2 x Nails Bonding (072034) & Washers Galvanised 19
(073202). The aluminium strip can also be formed into a “C” clip and using 1 x
nails bonding and washer galvanised & must be dressed as close to the pole
as possible.
Page 87 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Hypoclamp
The item code for the new clamp is 104593 which are supplied in a box of 10.
Once all existing Corning clamps (095296) have been used up, orders will be
re-directed to the new Telenco clamp.
The Telenco Hypoclamp is composed of a metallic body, a plastic shim and
plastic wedge with an integrant opening bail. The key difference is that this
clamp does not require a Pole Top Link to form an attachment between the
clamp and the pole ring. See figure 1 below:
Attachment to Poles
The pictures shown below are taken from the manufacturer’s installation guide
and as such, the bracket shown is not something that Openreach use. The
attachments will be to a Pole Ring or Universal Pole Bracket, etc.
Page 88 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
The installation process is very similar to the existing SST clamp but is
described below for completeness.
Step 1
Fit Hybrid Cable Grip (Come Along), item code: 069586 onto the pole or ring
head ensuring there is enough length for the clamp to be fitted to the SST
cable without interference.
Step 2
Fix the SST cable into Come Along ensuring correct tension is on the cable.
Due to its flat profile, this cable requires twists to be inserted into each Span
during installation.
Insert a minimum of 1 twist per 10 metres – preferably 10 twists per span. As
this cable is very light, the twists can be inserted by hand, by simply rotating
the Cable using both hands.
Page 89 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Step 3
Step 4
Page 90 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Step 5
Step 6
Page 91 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Step 7
Step 8
Page 92 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Warning: You must inspect all of any damaged span that is to be re-used
to create a new joint and ensure that there is enough cable to splice at
ground level
Page 93 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
The diagrams below show examples of how the policy should be applied.
These will not cover every scenario and the policy rules stated in 8.6 above
must be followed.
8.6.2.1 Span renewal + 1 span either side
When a span of OH is damaged (e.g. by tree falls), the damaged span plus 1
span each side should be renewed to avoid re-using damaged fibres in the
clamped areas of the cable.
Page 94 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 95 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
8.6.3 References:
AEI/AEC/B347
EPT/COF/R001
Page 96 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
If the CBT is to be pole mounted, where possible store 2-4 metres of cable
slack in the joint box closest to the CBT. This leaves sufficient length to
reposition the CBT if a pole change out is required at some stage in the future.
Page 97 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
Page 98 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
The cable coiling bracket (pictured) has been introduced to enable build &
splice work on a node in the rear of a vehicle, or to provide a safe & secure
method of storing coils of cable on the pole when it is not possible to complete
the build at the pole due to other obstructions or adverse weather conditions.
Before installation of a cable coiling bracket ensure there is space in the lower
pole envelope to install it. EPT/ANS/A011 Sect. 4.2 refers.
Note: There are now maximum extended dimensions for coil brackets: 500mm in
horizontal plane and 600mm in the vertical (see below)
Note: These brackets may only be used on BT poles. They must not be used on
DNO owned Joint User Poles.
Page 99 of 150
EPT/ANS/A040, ISSUE 41 (23-NOV-2023)
One Fibre Network – Build Quality Guide for Engineers
◼ The bracket must be fitted in the lower pole envelope above the capping or a
minimum height of 2m above the ground & a minimum of 450mm below the
first climbing step & not projecting above or below these points.
◼ The arms of the cable coiling bracket shall not project into the highway/footway
or any other area of hazard.
◼ Any pole fixture will be easily removable for the purpose of pole testing.
◼ The overriding requirement is that safe ladder placement & SAFE climbing
must not be impeded.
◼ In addition to the usual site activities, before starting on the pole always:
◼ Carryout the standard pre-work check on the pole (hammer test etc).
SFY/HSH/D040
◼ Ensure the ground area surrounding the pole is fully guarded off.
◼ Ensure that the ladder is safely tied to the pole or use TETRA if trained.
◼ Ensure you adopt a safe working position on the ladder/pole using the safety
belt 11, fall arrest lanyard & work positioning belt. SFY/HSH/D042 or TETRA
system if trained.
Following the assembly instructions included with the bracket, assemble the
cable coiling bracket (100846) loosely tightening the retaining bolts of the
arms.
Mount the bracket on the pole with 1 x coach screw (014700) using a coach
screw brace (112089). Consideration should be given to the mounting position
of the fibre node on the pole in relationship to the lower envelope of space. It
may be above, below or on the opposing face of the pole as long as these
requirements are met.
Feed the cable or cables around the arms of the bracket – it may be easier to
bunch the cable together first with straps cable fixing or tape to keep the coils
more manageable.
Push the cable bracket arms inwards to secure the cable coils & form a circle,
it is also permissible to extend the top & bottom arms further than the
horizontal arms to form an oval coil if required. Minimum bend radius of the
cables being coiled must NOT be compromised.
Tighten the securing bolts of the bracket to lock the arms in position.
Secure the cable coils to the bracket arms with straps cable fixing.
Secure the cables leading from the coiling bracket to the pole with aluminium
strips. These can be attached either using 1 nails bonding & washer to form a
“C” clip or with 2 nails bonding & washers.
8.9.1 CBT
The following steps should be followed for mounting the block to a wall:
◼ Determine the location for the block – above reachable height (3m)
◼ Protect any cable below 2m with appropriate capping
◼ Corning CBT:
⎯ Screw to wall using appropriate fixings using top mounting hole and 1 x
mounting bracket with 2 x SCF 1A
◼ CommScope CBT:
⎯ Screw CBT mounting bracket to the wall using appropriate wall fixings
⎯ Clip the CBT into the bracket.
8.9.2 TM Joint
◼ When all splicing is complete fit cap and remove the Node and clamp from the
bracket.
◼ Refit bracket and joint at the selected position in the bottom pole envelope
Note: UG feed cable (e.g. COF600) may be brought into the joint, this should be
measured off to the final joint position to ascertain cable length before jointing in the
temporary position. On completion the cable will feed directly into the joint with no
excess slack.
There are several DILOR methods to consider when erecting new fibre cables
for further information see AEI/AEC/B335 or EPT/ANS/A014
Where Dropwires are run together in line of route, they begin to act together
and can apply a more significant, combined load onto Poles which left
unchecked, may threaten the stability of a Pole. Because of this, we limit the
number of wires running in line using the DILOR rule.
Where additional Dropwires are to be added alongside an un-stayed Aerial
cable, the loading will be beyond permitted limits and so an evaluation should
be carried out by a suitably trained Planner / Surveyor to ascertain the
requirements to strengthen the route in order to accommodate the new
loading.
Tables below are to show loading limits of poles with or without stays or wires
applying opposing loads
8.11.1.1 Where a pole has no Stay or wires in an opposing arc
Max 3 4 5 4 5 6
permitted
wires
8.11.1.2 Where the Pole has a Stay fitted, or wires applying an opposing load
All newly provided cables (copper & fibre) should, where achievable, avoid the
ladder placement area on the pole. Standard ladder placement is for the V
shaped pivot plate to rest between 1st and 2nd climbing steps leaving the top
rung almost level with first step.
Consideration must be given to existing plant, pole orientation and likely ladder
location(s) as to the best route for new cables.
Two methods of ladder avoidance exist:
Method 1: Ladder “loop” as defined in: EPT/OHP/B073
Cables must be routed away from climbing steps as not to interfere with the
climber’s foot/hand placement or risk entanglement. Cables may pass through
the stepped section of the pole but must be correctly fixed to the pole and not
be in contact with any steps.
has been subject to a successful on the day hammer test and is accessed
using a MEWP.
◼ Additional connectivity items may be added to Shallow Depth “SD” Class
Poles, providing that the Pole in question has been subject to a successful on
the day hammer test and is accessed using a MEWP.
Summary of Rules
Equipment Type Policy D Poles Non Policy D
(Dec and Dam) and SD Poles
Pole mounted components in a green metal housing i.e. DSB’s are not
acceptable as they are too large.
◼ Ensure the pole has a ‘J’ marking indicating this pole is licenced as a joint user
pole
◼ The number following the ‘J’ indicates the permitted number of attachments
e.g. ‘J10’ means the pole is licensed for 10 attachments
◼ If not, you will need to check we have a licence in place with the wayleave
team.
◼ If no licence exists or a new license is required, the license application site can
be found via the ORWFMT system under Wayfinder
To confirm the OTH status for an exchange you currently need to send a SMS
that includes “OTHtest” followed by either the 1141 or exchange name, to
81192.
The reply will confirm which testing procedures you are required to follow.
For testing at a Tactical OTH please refer to section 10.3.1 of this document.
For testing at a Strategic OTH please refer to section 10.3.2 of this document.
For testing on sites with no OTH please refer to section 10.4 of this document.
Testing is to be completed by the build teams as they build each Splitter and
CBT. A reflector is to be left in each CBT only once testing has been
completed.
Warning: Reflectors must not be left in the network before any type of
testing has started.
All testing on tactical OTH sites will be carried out by logging into https://onmsi-
server.dyndns.biz/field using a phone, tablet, or laptop.
In the Spine – Use the OTH to verify the correct spine and no faults in the
cable.
At the Splitter – Using the OTH, mobile/desktop app and a reflector, run an
Auto Toggle test to confirm correct Headend equipment is connected to the
Splitter. Confirm the Test Head can see the reflector connected to the cable,
after using Auto Toggle.
At all Intermediate Joints – Confirm at each intermediate joint using the OTH
you have correct light and it has been connected through to the correct CBTs
as per the Job Pack.
At the CBT – On all ports on the CBT run a test using the Optical Test head
via the Mobile App. Attach a single reflector at a time, one port after another
and run the tests until the whole CBT has been tested. Each port spliced
through should have a test recorded on the system to show reflector detected
and port within test limits.
All testing on strategic OTH sites will be carried out via FastTest+ or CANDID’s
Openreach Test Centre.
Warning: All the below steps are mandatory – Do not perform any OTH
tests prior to the SASA being connected, this will create an incorrect
result for testing which will need to be removed from the system to
allow testing.
Warning: It is essential that both the port of the test equipment and the
connectors of the OptiTap power patch lead are cleaned before they are
terminated to take a power reading. Failure to do so can cause damage to the
port / connector and or provide incorrect power levels.
11 Fibre Cleaning
Contamination within the fibre network will have a severely negative impact on
the services carried, resulting in potential loss of service. To mitigate against
this, we need to ensure the fibre network is cleaned every time it is worked
upon. It is now mandatory that each and every connection is cleaned using the
approved Sticklers cleaning kit.
◼ Before testing, each end of the test patch cord and endface connector must be
cleaned.
◼ After testing the endface connectors should be re-cleaned.
◼ After cleaning the endfaces must be protected by replacing the dust caps
◼ In between tests the dust cap must be used to protect the endface of the
connector.
◼ Every time you connect to a new test port or cable both end face connections
must be cleaned.
◼ Test leads must be inspected monthly with a Microscope or digital inspection
device.
◼ If at any point the endface connector of a test lead is in question for
contamination, the lead should be quarantined, and an alternative lead used
whilst it is checked.
◼ Any test lead connector which cannot be cleaned following inspection should
be scrapped.
◼ For further information on the fibre cleaning process please refer to
AEI/AEC/B331.
Warning: It is essential that both the port of the multiport block and the
connector of the drop cable are cleaned before they are terminated
together. Failure to do so can cause damage to the port / connector,
result in high transmission losses, degradation in service or faults.
This section details the practices required for completing the termination of the
connectorised drop cable into the CBT for both the OH and UG installations.
◼ Identify the correct block port according to the routing information provided in
the job pack. See figure 4_9 for port identification.
◼ Remove the dust caps from both the CBT port and drop cable connector.
◼ Clean the port (wet and dry clean) using a 2.5mm Clean Clicker Optical Fibre
Cleaner (i/c 100205).
◼ Clean the connector of the drop cable using a 2.5mm Clean Clicker Optical
Fibre Cleaner (i/c 100205).
◼ Align the arrow on the connector body with the notch on the port, and insert
the connectorised drop cable into the block port
◼ Screw the threaded shroud of the connector onto the thread of the port
◼ Screw the protective caps of the connector and the port together
Port 1 has been highlighed for all CBT types, by default it is the bottom left
hand port. The protective dust cap must be replaced after testing.
12 Tools
12.1 36F Stripping tool
FTTP 36F ULW AC Sheath Cutter Item Code: 066613 (OFS 36F)
FTTP 36F ULW AC Sheath Cutter Item Code: 088338 (PGH 36F)
Any unplanned track joints must be sent for ILC (in life change) for a node ID
to be created, in the interim, joint must be marked with a minimum of estimate
number/date/UIN
All newly provided cables must be labelled using Cable Marker Label
OPT/COP (Code 108548). All fields on the label should be legibly completed in
black indelible marker pen as below and attached with Strap Cable Fixing and
the straps cable fixing 1A at each end should be wrapped in Tape Plastic
Adhesive 25mm in the U/G network.
Note: There is no requirement to tape the SCF 1A on walls or poles.
On cables less than 25mm diameter a 3rd zip tie can be fitted. This will be free
to slide and not obscure any lettering this helps with cable management.
However, this is no longer mandatory.
Warning: Straps Cable Fixing must be cut flush to prevent injury using the
correct tools (tensioner or nippers miniature 2)
◼ For all cables, the labels may be ‘wrapped’ or applied as a ‘flag’, depending
on the diameter of the cable (shown below). Ensure the cable is clean and
dry beforehand.
Below pictures show attachment of label and punching using Letter and
Number punch Kit:
This work will be carried out by Chief Engineers, FND and partners at build
stage and retrospectively by Service Delivery (SD) on Lead 2 Cash (L2C)
installation visits.
This new process will run alongside the existing process of labelling
CBT’s using gold pen on body of CBT and the fixing of the yellow label
on cable at base of CBT shown below.
Currently no labels to be attached to DNO poles.
◼ White Cable Marker Optical label fitted to SST cable (Yellow still permissible
until stocks run out)
◼ Top section above the ports labelled with node ID using permanent marker
◼ If mounted on a MOBRA, where possible label the rear face of the CBT to aid
identification (not mandatory)
◼ SST cable marked with yellow tape in UG network only.
◼ Yellow tape is not required on pole/wall mounted joints and cables.
When attaching fibre equipment to DNO poles the new labels (shown below)
must be used.
The new labels can be ordered with immediate effect using the item codes
below:
◼ Label Item code 112099 for wooden poles - bag of 10
◼ Pin Steel No.2 7/8 inch Item code 070864 – box of 100
◼ Sticky label item code 112100 for hollow poles - bag of 10
Note: The requirement for a yellow fibre label on the pole DOES NOT currently apply
in example 3.
15 Quality tips
Warning: On completion of any work/testing, all remaining sharp ends
MUST be cut off and disposed of correctly.
15.1 Build
Fibre Top Tips and Reminders
◼ Always look for an overhead solution, rather than an expensive civils solution.
◼ The Connectorised Block Terminal (CBT) must be provided in the top pole
envelope, if this is not possible a network re-arrangement will be required.
◼ Remember to use joint user poles – except in Electricity North West.
◼ CBTs provided along route in all positions to enable a maximum of 150 metre
length of OH or UG dual drop cable to be required between the CBT and the
customers entry position.
◼ Use external locking mechanisms (locking bollards) on first and last poles of a
36F ULW route and when cable is routed down the pole to a transition joint
(One ELM on each input / 36F output).
◼ Stand-off adaptors must be fitted on Overhead Connectorised Block
Terminals.
◼ Overhead Fibre labels to be provided on fibre enabled poles.
◼ Joint to be mounted at a maximum of 750mm below lowest pole climbing step,
enabling
◼ The bottom of the cable loop being between 2 – 2.4 metres above ground
level.
◼ Always use 36F ULW or other fibre cable options – do not provide new BFT
lengths.
◼ In TM joints the 36F ULWC strength member is the steel wires within the
sheath. For the circular ports use the bare wires stripped from one side of the
sheath. For Oval ports use this method or one side of the sheath with the wires
included.
◼ In UG TM joints only COF 205, COF 260 and 4 & 7 BFT (from existing TIJ
joint) need Kopex providing into the TM joint (with yellow tape).
◼ Always update the survey markers and survey network notes using the valid
combinations.
◼ Provide a toggle test, OTDR trace and power reading on port 1 of every CBT
provided.
◼ Remember to use the fibre optic connector cleaner SC first.
◼ Use armoured fibre cables in locations where (1) No duct network currently
exists (2) No subsequent copper demand exists (3) Limited demand for fibre
can be fulfilled by a single cable (4) An armoured cable solution is a more cost
effective solution than duct and cable.
If these conditions cannot be met, solutions such as mole ploughing duct
should be investigated.
◼ Field Based Co-ordinator (FBC) Role: The FBC(s) who oversees the build of
any FTTP structure whether this has been built by DL, contractor or any other
project, will be responsible for the quality of the structure they release for
commissioning. They shall ensure that the L2C journey is deliverable within
the SNN that has been set. Prior to release, the FBC should amend if
required, any SNN which could lead to an on the day L2C failure
Where defects are observed, the FBC will record these on a quality checking
system, consult with key stakeholders, including any DL or contractor, to
inform them of outcomes and ensure these are resolved within 30 days. Any
red flag items should be communicated to PM and operatives alike. These are
to be resolved prior to commissioning taking place.
◼ Independent Audit (IA) Role: Independent audit is undertaken to quality
check compliance of FTTP build and the work of all stakeholders. It ensures
governance and reporting for FTTP quality of build. Independent audit will be
recorded on a quality checking system where the PM of the build programme
will be informed of the outcome of any audit and tasked with resolving any
issues that arise. Defects to be resolved by build team within 30 days of issue
and red flags cleared by build team prior to commissioning, or withing 30 days
if the FTTP structure is already commissioned.
flags
◼ Defects: FTTP structures can be released with known defects if remedial work
is in progress and this will not become service affecting, or a safety issue. This
can be measured by FBC’s when undertaking final PON audit using a quality
checking system and fed back to suppliers for remedial works. Defects picked
up at independent audit will be fed back to the PM of the build programme to
arrange resolution.
◼ Red Flags: Red Flags are capturable by both FBC and IA teams. These are
defects which are highly likely to cause a L2C failure. FBC’s should not allow
FTTP structures to pass to commissioning with red flag issues. Independent
audit will likely observe red flag issues post commissioning, whereby the
information will be passed to the PM for resolution.
◼ Red Flag issues are accepted as:
⎯ CBT is located in a position that will stop the L2C engineer completing the
provision
⎯ Plant missing, and/or location not planned/supplied
⎯ Plant missing, and/or service not planned/provided to a NAD
⎯ No toggle test result/light test for CBT, indicating fibres have not been
spliced
⎯ CBT provided for wayleaves scenario where track joint should have been
provided
⎯ CBT provided in a location “more complex” than the copper provision, to
avoid obtaining a wayleave.
⎯ Internal MDU Plant in poor position to feed all apartments, or insufficient
capacity to serve all properties
⎯ Cables not terminated, or fibres not spliced through in trays
⎯ Safety issue that will lead to network being removed to overcome the issue
and severely delay L2C
⎯ Direct in Ground (DiG) not built to the curtilage – excludes shallow build
projects/areas
⎯ Joint User Pole identified as not licenced, or insufficient D/W allowance to
serve volume of NAD addresses associated with CBT
15.4.1 Introduction
Where a Red Flag has been raised and there is a disagreement to all or part of
it’s content, the following process should be followed.
15.4.2 Process
When appealing a Red Flag, please create an email titled “Red Flag Appeal -
[insert PON ID]”. This should be sent to the RQM (Regional Quality Manager -
manager of issuing network assessor) copying in the QAP (Quality Assurance
Professional) and your regional PM. The appeal content within the email
should have a clear rationale with supporting evidence.
The quality manager will investigate the content of your appeal and respond to
all with an Accept or Reject.
If accepted, the QAP will log the appeal and remove this from the Red Flag
Report, marking this ‘Removed After Appeal’.
All appeals need to follow this process to ensure the correct removal of the
Red Flag.
Caution: Incorrect use of ‘removed after appeal’ will result in Red flag
being re-opened.
16 Retro Build
16.1 Installing 36F & SST into Splitter Node 2A HS joint
ISIS EPT/COF/C005 refers
The photographs show SST, but it is the same method for 36F ULW cable
Trays
◼ HCSC trays replaced with individual HCSE
◼ HCSE hinge and locking tabs engaged
◼ Input fibres re- routed to new trays
◼ All individual CBT tail fibres stored in tray central storage areas or spliced as
per FNC
SST tail
◼ Port 3 used to install SST cable
◼ All SST cables provided in port 3 (up to 4) simultaneously
◼ 10mm split Kopex provided from duct mouth up to butt of SST cable
◼ Single SCOP and cable foil provided over all SST cables
◼ Heat shrink correctly provided
◼ Sealant 10B provided
◼ SST Strength members terminated in anchor directly above port 3
◼ Element support tube 3A provided from cable butt to tube holder
◼ Element stripped between element marks on tube holder and fibres routed up
RHS raceway
◼ Allocated input fibres for CBT located and re-routed to tray
◼ Spliced and stored correctly as per FNC
◼ Fibres and splice protectors routed and stored correctly on tray
◼ SDMB6 seal & SCF provided at duct mouth,
◼ Yellow adhesive tape provided on Kopex as fibre cable indicator
◼ Outside of trays labelled with CBT ID details
Trays
◼ 32 FDP do not need trays changing
◼ SDP trays replaced with new 8 or 16 way VTU with back plane
◼ SDP incoming fibres spliced in splitter device tray
◼ SDP output fibres routed to allocated CBT trays
◼ SDP CBT tail fibres routed up RHS raceway and stored or spliced in allocated
CBT tray
SST Tail
◼ 2 way SST port kit provided in correct port – preferred order is 8, 7, 6 then 5
◼ SST secured in port cable clamp
◼ Port kit locked in position in correct orientation (screws facing back of FDP)
◼ SST cable cap fitted and locked in place.
◼ SST cables provided in cable guide positions (cable 1 in empty port in base)
◼ Cable cleaned and abraded 100 mm below butt - IP
◼ Butt positioned level with top of SST cable guide.
◼ Strength members cut off at butt
◼ Sealant 10B provided in the cavities with SST cable in only
◼ Spare cavity blank not removed or sealant 10B provided if unused
◼ SST fibre element stripped 25-35mm above SST cable cap
◼ 3mm – 3mm connector provided between element and allocated transport
tubing
◼ Old blue water block replaced with black water block
◼ Tray water block trimmed for 8F & 12F CBT fibre elements (not needed for 4F
CBT element)
Trays
◼ 12/32 FDP do not need trays changing
◼ SDP trays replaced with new 8 0r 16 way VTU with back plane
◼ SDP incoming fibres spliced in splitter device tray
◼ SDP output fibres routed to allocated CBT trays
◼ SDP CBT tail fibres routed up RHS raceway and stored or spliced in allocated
CBT tray
SST Tails
◼ SST cable from a CBT may be brought into a pole mounted FDP via an
overhead or underground feed. PMFDP number/size of ports vary depending
on the chassis size and age, the chassis should be checked to ensure port
capacity exists.
Cable entry and preparation
◼ Cable entry via ports 1 – 3, 5 & 6 for OH entry and port 12 for UG entry
16.7.4 Incremental Build of 128 SPN using 16F per splitter O/P
◼ Fit splitter device tray (SSTA) into SD2 position, remove the 32 splitter legs
from the SSTA (These should be in bundles of 8)
◼ Route first bundle of 8 fibres down and onto tray D05, then route second
bundle of 8 fibres down and onto tray D05. Mark 2nd bundle of 8 fibres with
Tape Yellow Plastic 12mm
◼ Route third bundle of 8 fibre down and onto tray D06, then route final 4th
bundle of 8 fibres down and onto tray D06. Mark 4th bundle of 8 fibres with
Tape Yellow Plastic 12mm
Adding splitter device 3
◼ Fit splitter device tray (SSTA) into SD3 position, remove the 32 splitter legs
from the SSTA (These should be in bundles of 8)
◼ Route first bundle of 8 fibres down and onto tray D03, then route second
bundle of 8 fibres down and onto tray D03. Mark 2nd bundle of 8 fibres with
Tape Yellow Plastic 12mm.
◼ Route third bundle of 8 fibres down and onto tray D04, then route final 4th
bundle of 8 fibres down and onto tray D04. Mark 4th bundle of 8 fibres with
Tape Yellow Plastic 12mm
Adding splitter device 4
◼ Fit splitter device tray (SSTA) into SD4 position, remove the 32 splitter legs
from the SSTA (These should be in bundles of 8)
◼ Route first bundle of 8 fibres down and onto tray D07, then route second
bundle of 8 fibres down and onto tray D07. Mark 2nd bundle of 8 fibres with
Tape Yellow Plastic 12mm.
◼ Route third bundle of 8 fibres down and onto tray D08, then route final 4th
bundle of 8 fibres down and onto tray D08. Mark 4th bundle of 8 fibres with
Tape Yellow Plastic 12mm.
Incremental Build of 128 SPN using HCSC to HCSE tray replacement (No
Customers present)
◼ Note: both HCSC sub-trays on a VTU must not be connected to a customer as
this process effects both sub-tray 1 & 2.
◼ Stored fibres within the SPNs HCSC trays to be replaced which are routed to
the FDPs removed
◼ HCSC trays removed from backplane within the SPN and replaced with HCSE
tray (IC: 060625)
◼ Fibres removed from tray 1 & 2 routed and stored into the new HCSE tray
◼ HCSC fibres within the SPN which terminate in the target Fibre Distribution
Point & newly installed CBT moved to the newly installed HCSE tray
◼ Fibres spliced through as required for the splitter output fibres to the CBT
◼ SD1 & SD3 splitter output fibres routed and stored in VTU 31 - 34 and 35 – 38
respectively on side A (8 fibres per tray)
◼ SD2 & SD4 splitter output fibres routed and stored in VTU 31 - 34 and 35 – 38
respectively on side B (8 fibres per tray)
SIDE A SIDE B
17 Legacy Components
Legacy FTTP components are detailed in component specific ISIS documents;
these are available from the Technical Library - FTTP page or CANDID
Information Centre.
18 References
18.1 Build
Most of the relevant FTTP documents are held in the Technical Library - FTTP
page
Some of the most commonly used OFN FTTP Build documents are:
18.3 Safety
SFY/HSH/D040 – Working on the Overhead Network
SFY/HSH/D042 – Safety Belt 11 & MEWP Harness. Use & Maintenance
19 Videos
19.1 CBT Installation
This FTTP video, is also available in chapters and gives easily accessible
foundation knowledge on the new FTTP components plus top tips on how to
install them efficiently and to a high standard.
Corning web site
https://opcomm.corning.com/EMEA_Openreach_BT-Landing-Page-
Overview.html
END OF DOCUMENT