PIN MYINT YAN Construction Co., Ltd.

PMY/HSE-Q/RE/003
Issue Date:
HSE-Q Department 01.01.2023 ISSUE: 1.0
Effective Date:
01.01.2023

REQUEST FOR WORK INSPECTION Page 1 of 1

REQUEST FOR WORK INSPECTION Ref; No: WI / PMY /_______/____

To: From:

Please be informed that the following works have been


completed. We have checked and certified that they are in
order for your inspection Team’s Representative:
Name & Designation: Sign & Date:

Structural /
Civil/
Please specify:
Architectural/
MEP

Work Description / Element: Inspection For……………………………………………….


Floor / Level: ……………… …………..….
Drawing Ref:

Location:

Grid Line: Attached Total: _________ Pages.


Inspection Date & Time Submitted: Requested Date & Time:

Comment:

Conformed all (Structural/ Civil/ Architectural) items are in order for the next stage of work.

Name : Signature & Date


Confirmed all M&E items are in order for the next stage of work.

Name: Signature & Date

Pls tick where applicable