Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 26

CONCRETE WORKS - IN-SITU CONCRETE

Location of Concreting = slab


Ready Mixed Concrete Rate
Grade = 35 Grade Rate / m3 Concrete Additives Rate / m3
15 RM 134.62 Rapid Hardened RM 100.00
General Worker wages = RM60.00 /day 20 RM 144.16 Waterproofing RM 120.00
25 RM 151.58 0 RM -
30 RM 165.36
Material Cost 35 RM 172.78

Rate / m3 = RM172.78 B.2 Labour Constant For Concrete Work (Plant)


Description Diesel / hours Lubr.
ITEM Unit Output / hours
Oil /
5/3 size w 1 skilled worker and 2 hours
1 M3 1.50
+ concrete additives 0 = RM0.00 unskilled worker 1.00 0.50
7/5 size w 1 skilled worker and 3
2 M3 2.50
unskilled workers 1.50 1.00
10/7 size w 1 skilled worker and
3 M3 3.50
4 unskilled workers 1.80 1.00
14/10 size w 1 skilled worker and
4 M3 4.50
4 unskilled workers 2.25 1.50
5 % wastages = RM8.64

Plant & Labour Cost Crane Rental Rate Bed/Slab/Base

Item Description Unit Unskilled man-hour (hrs)


Crane rental 30 tonne = RM0.00 Tonne Rate / m3
15 RM 400.00 1 n.e 100mm M3 5.00
5 general worker = 5 nos x RM60.00 = RM300.00 20 RM 450.00 2 exc 100mm b.n.e 150mm M3 6.00
RM300.00 25 RM 500.00 3 exc. 150mm b.n.e 300mm M3 7.00
30 RM - 4 exc. 300mm M3 8.00
Pouring Cost / m3 = RM300.00 = RM30.00
10 RM211.42 Crane output for concrete works
location m3 / hour Column/Beam
Item Description Unit Unskilled man-hour (hrs)
0 % overhead & profit = RM0.00 column RM 15.00
beam RM 15.00 1 Column and Beam M3 8.00
RATE / M3 = RM211.42 slab RM 17.00
staircase RM 13.00

Wall
Unskilled man-hour
Item Description Unit
RM10.57 (hrs)
1 n.e 100mm M3 10.00
2 exc 100mm b.n.e 150mm M3 9.00
3 ecx 150mm b.n.e 300mm M3 8.00
4 exc 300mm M3 7.00

B.5 Labour Constant For Placing Concrete


Unskilled man-hour
ITEM Description Unit
(hrs)
Pad Foundation M3 6.00
Ground Floor
≤ 150mm - 300mm thick M3 7.75
150mm - 300mm thick M3 6.50
> 300mm thick M3 5.00
Upper Floor
≤ 150mm - 300mm thick M3 9.25
150mm - 300mm thick M3 7.50
> 300mm thick M3 6.50
Wall
≤ 150mm - 300mm thick M3 10.00
150mm - 300mm thick M3 8.50
> 300mm thick M3 7.50
Column And Beam M3 8.00
CONCRETE WORKS - READY MIXED CONCRETE
Concrete Rate
Location of Concreting = slab Grade Rate / m3
15 RM 134.62
Grade = 35 20 RM 144.16 Concrete Additives Rate / m3
25 RM 151.58 Rapid Hardened RM 100.00
General Worker wages = RM60.00 /day 30 RM 165.36 Waterproofing RM 120.00
35 RM 172.78 0 RM -

Material Cost

Rate / m3 = RM172.78

+ concrete additives 0 = RM0.00

5 % wastages = RM8.64

Plant & Labour Cost Crane Rental Rate

Crane rental 30 tonne = RM0.00 Tonne Rate / m3


15 RM 400.00
5 general worker = 5 nos x RM60.00 = RM300.00 20 RM 450.00
RM300.00 25 RM 500.00
30 RM -
Pouring Cost / m3 = RM300.00 = RM30.00
10 RM211.42 Crane output for concrete works
location m3 / hour
0 % overhead & profit = RM0.00 column RM 15.00
beam RM 15.00
RATE / M3 = RM211.42 slab RM 17.00
staircase RM 13.00

RM10.57
REINFORCEMENT BAR PRICE
HIGH TENSILE
Y10 Y12 Y16 Y20 Y22 Y25 Y28 Y32 Y40

No. of bars per bundle 138 pcs 96 pcs 54 pcs 34 pcs 28 pcs 22 pcs 18 pcs 14 pcs 9 pcs
Metric ton per bundle 1.020 tonnes 1.023 tonnes 1.023 tonnes 1.006 tonnes 1.003 tonnes 1.017 tonnes 1.044 tonnes 1.061 tonnes 1.065 tonnes
Weight per bar 7.391 kg 10.656 kg 18.944 kg 29.588 kg 35.821 kg 46.227 kg 58.000 kg 75.786 kg 118.333 kg

ZON
TENGAH 2,461.53 2,349.33 2,274.25 2,274.25 2,158.75 2,158.75 2,158.75 2,158.75 2,233.83
TIMUR
UTARA
SELATAN

COSTING
Material Price per Metric Ton
· Government Control Price 1,319.00 1,279.00 1,214.00 1,214.00 1,214.00 1,214.00 1,214.00 1,214.00 1,279.00
· Extra Supplier Charges 456.00 456.00 456.00 456.00 356.00 356.00 356.00 356.00 356.00

A MATERIAL 1,775.00 1,735.00 1,670.00 1,670.00 1,570.00 1,570.00 1,570.00 1,570.00 1,635.00
B UNLOADING 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
C TYING WIRE 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
D SPACER BLOCKS 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
E LABOUR / M. TON 340.00 280.00 280.00 280.00 280.00 280.00 280.00 280.00 280.00
F TOOLS& EQUIPMENT RENTAL 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00
G CUTTING & BENDING 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
Sub-Total 2,149.00 2,049.00 1,984.00 1,984.00 1,884.00 1,884.00 1,884.00 1,884.00 1,949.00
Add
5% wastage 88.75 86.75 83.50 83.50 78.50 78.50 78.50 78.50 81.75
Sub-Total 2,237.75 2,135.75 2,067.50 2,067.50 1,962.50 1,962.50 1,962.50 1,962.50 2,030.75
Add
10% profit 223.78 213.58 206.75 206.75 196.25 196.25 196.25 196.25 203.08

GRAND TOTAL 2,461.53 2,349.33 2,274.25 2,274.25 2,158.75 2,158.75 2,158.75 2,158.75 2,233.83

MILD STEEL
R6 R8 R10 R12 R16 R20 R22 R25 R28 R32

No. of bars per bundle 320 pcs 149 pcs 138 pcs 96 pcs 54 pcs 34 pcs 28 pcs 22 pcs 18 pcs 14 pcs
Metric ton per bundle 1.000 tonnes 1.000 tonnes 1.020 tonnes 1.023 tonnes 1.023 tonnes 1.006 tonnes 1.003 tonnes 1.017 tonnes 1.044 tonnes 1.061 tonnes
Weight per bar 3.125 kg 6.711 kg 7.391 kg 10.656 kg 18.944 kg 29.588 kg 35.821 kg 46.227 kg 58.000 kg 75.786 kg

ZON
TENGAH 2,099.90 2,164.58 2,273.15 2,213.09 2,135.71 2,135.71 2,135.71 2,135.71 2,135.71 2,135.71
TIMUR
UTARA
SELATAN

COSTING
Material Price per Metric Ton
· Government Control Price 1,279.00 1,200.00 1,279.00 1,242.00 1,175.00 1,175.00 1,175.00 1,175.00 1,175.00 1,175.00
· Extra Supplier Charges 221.00 356.00 371.00 356.00 356.00 356.00 356.00 356.00 356.00 356.00

A MATERIAL 1,500.00 1,556.00 1,650.00 1,598.00 1,531.00 1,531.00 1,531.00 1,531.00 1,531.00 1,531.00
B UNLOADING 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
C TYING WIRE 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
D SPACER BLOCKS 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
E LABOUR / M. TON 300.00 300.00 300.00 300.00 300.00 300.00 300.00 300.00 300.00 300.00
F TOOLS& EQUIPMENT RENTAL 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00
G CUTTING & BENDING 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
Sub-Total 1,834.00 1,890.00 1,984.00 1,932.00 1,865.00 1,865.00 1,865.00 1,865.00 1,865.00 1,865.00
Add
5% wastage 75.00 77.80 82.50 79.90 76.55 76.55 76.55 76.55 76.55 76.55
Sub-Total 1,909.00 1,967.80 2,066.50 2,011.90 1,941.55 1,941.55 1,941.55 1,941.55 1,941.55 1,941.55
Add
10% profit 190.90 196.78 206.65 201.19 194.16 194.16 194.16 194.16 194.16 194.16

GRAND TOTAL 2,099.90 2,164.58 2,273.15 2,213.09 2,135.71 2,135.71 2,135.71 2,135.71 2,135.71 2,135.71
REINFORCEMENT
C.1 Tying Wire
Bar size = Y10 Reinforcement bar rate ITEM Description Unit wire
size rate / tonne 1 6 – 12 mm diameter kg/t 10.00
Tying wire cost = RM3.50 /kg R6 1,962.00 2 16 – 25 mm diameter kg/t 6.00
R8 1,962.00 3 32 – 50 mm diameter kg/t 5.00
Barbender / cutter wages = RM60.00 /day R10 1,962.00
Y10 2,010.00
General worker wages = RM50.00 /day Y12 1,962.00 C.2 Bending and Cutting (hrs/t)
6 – 8 mm 10 – 12 16 – 20 > 25mm
ITEM Description Unit
Y16 1,884.00 dia. mm dia. mm dia. dia.
Crane rental = RM400.00 /day Y20 1,884.00 1 Straight and bend hrs/t 40.00 30.00 20.00 15.00
2 Links and Stirrups hrs/t 65.00 50.00 30.00 -

Material cost i. Fixing (hrs/t)


6 – 8 mm 10 – 12 16 – 20 > 25mm
ITEM Description Unit
dia. mm dia mm dia dia
i. Rate reinforcement bar per tonne + transport charge RM100.00 = RM2,110.00 1 Foundation and ground slab hrs/t 40.00 30.00 25.00 20.00
2 Upper floor and roof hrs/t 50.00 40.00 30.00 25.00
3 Wall, column, beam and staircase hrs/t 70.00
ii. 5 % wastages and spacer block = RM105.50 50.00 35.00 30.00
4 Links and Stirrups hrs/t 90.00 70.00 60.00 -
iii. Tying wire 6 kg = RM21.00

Labour cost C.3 Fabric Reinforcement


Percentag
ITEM Description Unit
e%
i. Unloading and store bar 1 150mm 0.12
General worker = 1.5 hour x RM50.00 = RM9.38 2 200mm 0.16
8 hour 3 250mm 0.20
4 300mm 0.25
ii. Cut and bend of bar
Barbender / cutter = 20.0 hour x RM60.00 = RM150.00
8 hour i. Fixing (hrs/t)
6 – 8 mm
ITEM Description Unit
diameter
iii. Install bar 1 Floor and roof hrs/t 0.20
Barbender / cutter = 25.0 hour x RM60.00 = RM187.50 2 Foundation hrs/t 0.25
8 hour 3 Wall hrs/t 0.33
4 Staircase hrs/t 0.50

Plant cost
i. Crane = 0.25 hour x RM400.00 = RM12.50
8 hour
= RM2,595.88

ii. 0 % overhead and profit = RM0.00

RATE FOR 1000 KG RM2,595.88

RATE FOR 1 KG RM2.60


FABRIC REINFORCEMENT

SUMMARY

A63 A98 A142 A193 A252 A318 A393 B196 B283 B385 B503 B636 B785 B1131 C196 C283 C385 C503 C636 C785
MATERIAL A4 A5 A6 A7 A8 A9 A10 B5 B6 B7 B8 B9 B10 B12 C5 C6 C7 C8 C9 C10 DA4 DA5 DA6 DA7 DA8 DA9 DA10

RATE PER M2 3.65 4.52 6.93 8.53 11.34 13.35 17.90 7.06 8.40 10.00 12.68 14.55 18.43 24.32 5.06 6.46 8.13 10.00 12.41 15.42 6.06 7.80 9.74 12.95 16.42 20.44 27.26

NO DESCRIPTION A4 A5 A6 A7 A8 A9 A10 B5 B6 B7 B8 B9 B10 B12 C5 C6 C7 C8 C9 C10 DA4 DA5 DA6 DA7 DA8 DA9 DA10

1 Material cost per m2 1.85 2.50 4.30 5.50 7.60 9.10 12.50 4.40 5.40 6.60 8.60 10.00 12.90 17.30 2.90 3.95 5.20 6.60 8.40 10.65 3.65 4.95 6.40 8.80 11.40 14.40 19.50

2 Laps Allowance 10% 0.19 0.25 0.43 0.55 0.76 0.91 1.25 0.44 0.54 0.66 0.86 1.00 1.29 1.73 0.29 0.40 0.52 0.66 0.84 1.07 0.37 0.50 0.64 0.88 1.14 1.44 1.95

3 Add : Wastage 15% 0.28 0.38 0.64 0.83 1.14 1.37 1.88 0.66 0.81 0.99 1.29 1.50 1.94 2.60 0.44 0.59 0.78 0.99 1.26 1.60 0.55 0.74 0.96 1.32 1.71 2.16 2.93

4 Spacer Block 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10

5 Labour charge per m2 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
3.41 4.23 6.48 7.98 10.60 12.48 16.73 6.60 7.85 9.35 11.85 13.60 17.23 22.73 4.73 6.04 7.60 9.35 11.60 14.41 5.66 7.29 9.10 12.10 15.35 19.10 25.48

6 Add: Profit 7% 0.24 0.30 0.45 0.56 0.74 0.87 1.17 0.46 0.55 0.65 0.83 0.95 1.21 1.59 0.33 0.42 0.53 0.65 0.81 1.01 0.40 0.51 0.64 0.85 1.07 1.34 1.78

7 Total Cost per m2 3.65 4.52 6.93 8.53 11.34 13.35 17.90 7.06 8.40 10.00 12.68 14.55 18.43 24.32 5.06 6.46 8.13 10.00 12.41 15.42 6.06 7.80 9.74 12.95 16.42 20.44 27.26

c:\build-up\costing
FORMWORK

B.5 Labour Constant For Removing Formwork

Fast hardened
ITEM Description Ordinary Portland portland cement
Cement (Day) (Day)

1 3 2
Side of beams, Wall and Column
2 4 3
Floor (penyokong ditinggalkan)
3 5
Menanggal penyokong ke lantai
4 Slab under the beam 8 5
(penyokong ditinggalkan)
5 21 8
Menanggal penyokong ke rasuk

Area to used = sides of foundation / wall


Formwork Support factor
1) 2.4m x 1.2m plywood 12 mm thick = RM55.00 /pcs Area Amount of timber (m3)
2) Timber 2" x 2" size = RM890.00 /tonne = 1.40 m3
3) Nails = RM5.00 /kg Sides of column 0.02
4) No. of cycle = 4 sides of foundation / w 0.04
Sides and soffit of b 0.05
Sides and soffit of sla 0.06
Material Cost

Plywood / m2 = RM55.00 = RM 19.10 Plywood price 2.4m x 4.2m


2.4m x 1.2m plywood Thickness (mm) Price per pcs
12 RM 55.00
Support 0.06 m3 x RM890.00 = RM 38.14 14
1.40 m3 16
RM 57.24 20

Cost for one cycle = RM57.24 = RM 14.31 Timber price


4 Size Price per tonne
2" x 2" RM 890.00
0.35 kg nails = 0.35 x RM5.00 = RM 1.75 2" x 3" RM 680.00
RM 16.06 2" x 4" RM 720.00
2" x 5" RM 890.00
+ 10% wastage = RM 1.61

Labour cost
Fabricate & install - Using times
Carpenter = 1.00 hour x RM70.00 = RM 8.75 ITEM Description Unit using times
8 hour 1 slab, roof, wall m 4-6
2 Column and Beam m 2-3
General worker = 0.75 hour x RM55.00 = RM 5.16
8 hour
- Timbers (Quantity of Timber - m3/m2)
Dissemble & Store ITEM Description Unit QTY
General worker = 0.75 hour x RM55.00 = RM 5.16 1 floor and wall area of floor/wall
8 hour 2 strut for wall, floor M3/m2 0.05
RM 36.73 3 stru for beam and lintel M3/m2 0.06
4 strut for column M3/m2 0.03
Overhead & Profit = 0.00% = RM -
TOTAL RATE = RM 36.73 m2
CONCRETE WORKS
SUPPLIER : PTCK ENTERPRISE

(Project Ref : Pembinaan Rangkaian Paip Pembentungan Di Bunus, KL)


(Eiscon Construction Sdn Bhd)

LABOUR COST
Labour for mixing and placing concrete
i. Concretor RM 160.00 / 8 hrs x 1.00
ii. 1 Unskilled Labour RM 100.00 / 8 hrs x 1.00

Supply &
Description Unit wastage crane
Delivery

RM/m3 RM/m3 RM/m3

26.10.2023 5%
Normal Mixed Slump 75+-
25mm
Concrete G15 lean conc M3 263.00 13.15 20.00
Concrete G20 Normal Mix M3 268.00 13.40 20.00
Concrete G25 Normal Mix M3 277.00 13.85 20.00
Concrete G30 Normal Mix M3 287.00 14.35 20.00
Concrete G35 Normal Mix M3 299.00 14.95 20.00
Concrete G40 Normal Mix M3 313.00 15.65 20.00
Concrete G45 Normal Mix M3 329.00 16.45 20.00
Concrete G50 Normal Mix M3 347.00 17.35 20.00

CONCRETE WORKS
SUPPLIER : MAJOR DUAL SDN BHD

(Project Ref : Avenue 3 (As-Syaff Resources)

Supply &
Description Unit wastage crane
Delivery

RM/m3 RM/m3 RM/m3


31.7.2023 5%
Normal Mixed Slump 75+-
25mm
Concrete G15 lean conc M3 215.00 10.75 20.00
Concrete G20 Normal Mix M3 220.00 11.00 20.00
Concrete G25 Normal Mix M3 229.00 11.45 20.00
Concrete G30 Normal Mix M3 239.00 11.95 20.00
Concrete G35 Normal Mix M3 250.00 12.50 20.00
Concrete G40 Normal Mix M3 263.00 13.15 20.00
Concrete G45 Normal Mix M3 - - -
Concrete G50 Normal Mix M3 - - -

CONCRETE WORKS
SUPPLIER : EVER MIXED CONCRETE SDN BHD

(Project Ref : Bukit Raja (Sri Mansang)

Supply &
Description Unit wastage crane
Delivery

RM/m3 RM/m3 RM/m3


11.7.2023 5%
Normal Mixed Slump 75+-
25mm
Concrete G15 lean conc M3 206.00 10.30 20.00
Concrete G20 Normal Mix M3 211.00 10.55 20.00
Concrete G25 Normal Mix M3 220.00 11.00 20.00
Concrete G30 Normal Mix M3 230.00 11.50 20.00
Concrete G35 Normal Mix M3 - - -
Concrete G40 Normal Mix M3 - - -
Concrete G45 Normal Mix M3 - - -
Concrete G50 Normal Mix M3 - - -

CONCRETE WORKS
SUPPLIER : DATA QS RATE ONLINE

Supply &
Description Unit wastage crane
Delivery

RM/m3 RM/m3 RM/m3


Nov-23 5%
Normal Mixed Slump 75+-
25mm
Concrete G15 lean conc M3 230.00 11.50 20.00
Concrete G20 Normal Mix M3 235.00 11.75 20.00
Concrete G25 Normal Mix M3 245.00 12.25 20.00
Concrete G30 Normal Mix M3 256.00 12.80 20.00
Concrete G35 Normal Mix M3 268.00 13.40 20.00
Concrete G40 Normal Mix M3 281.00 14.05 20.00
Concrete G45 Normal Mix M3 295.00 14.75 20.00
Concrete G50 Normal Mix M3 - - -

REINFORCEMENT
bender +
Unit supply wastage cutter

5%
Rebar @ 16,20 dia tonne 3,220.00 80.00
Rebar @ 25,32 dia tonne 3,220.00 80.00
Rebar @ 10,12,40 tonne 3,370.00 80.00
Rebar @ R6,R8,R10 tonne 3,370.00 80.00

Rate_Collect from data 2021/2022 + 2023 (Mid)


an Di Bunus, KL)

hrs / m³ RM 20.00
hrs / m³ RM 12.50
RM 32.50

labour + COST
pump truck tools + RATE Total Cost including Profit
curing (RM)
RM/m3 RM/m3 RM/m3 RM/m3 RM/m3 RM/m3

7.5% 10.0% 15.0% increment

3%
5.00 301.15 346.32 356.71 83.32 32%
15.00 32.50 348.90 401.23 413.27 133.23 50%
15.00 32.50 358.35 412.10 424.47 135.10 49%
15.00 32.50 368.85 424.18 436.90 137.18 48%
15.00 32.50 381.45 438.67 451.83 139.67 47%
15.00 32.50 396.15 455.57 469.24 142.57 46%
15.00 32.50 412.95 474.89 489.14 145.89 44%
15.00 32.50 431.85 496.63 511.53 149.63 43%

labour + COST
pump truck tools + RATE Total Cost including Profit
curing (RM)
RM/m3 RM/m3 RM/m3 RM/m3 RM/m3 RM/m3
7.5% 10.0% 15.0%

5.00 250.75 288.36 73.36 34%


15.00 32.50 298.50 343.28 123.27 56%
15.00 32.50 307.95 354.14 125.14 55%
15.00 32.50 318.45 366.22 127.22 53%
15.00 32.50 330.00 379.50 129.50 52%
15.00 32.50 343.65 395.20 132.20 50%
- - - -
- - - -

labour + COST
pump truck tools + RATE Total Cost including Profit
curing (RM)
RM/m3 RM/m3 RM/m3 RM/m3 RM/m3 RM/m3
7.5% 10.0% 15.0%

5.00 241.30 277.50 71.50 35%


15.00 32.50 289.05 332.41 121.41 58%
15.00 32.50 298.50 343.28 123.27 56%
15.00 32.50 309.00 355.35 125.35 55%
- - - -
- - - -
- - - -
- - - -

labour + COST
pump truck tools + RATE Total Cost including Profit
curing (RM)
RM/m3 RM/m3 RM/m3 RM/m3 RM/m3 RM/m3
7.5% 10.0% 15.0%

5.00 266.50 306.48 76.48 33%


15.00 32.50 314.25 361.39 126.39 54%
15.00 32.50 324.75 373.46 128.46 52%
15.00 32.50 336.30 386.75 130.75 51%
15.00 32.50 348.90 401.23 133.23 50%
15.00 32.50 362.55 416.93 135.93 48%
15.00 32.50 377.25 433.84 138.84 47%
- - - -
labour + COST
spacer wire RATE Profit
(RM)
7.5% 10.0% 15.0%
25.00 550.00 4,036.00
25.00 550.00 4,141.00
25.00 550.00 4,193.50
25.00 550.00 4,193.50
average/tonne
SAY, PER KG
SUMMARY Table 1 Table 2 Table 3
Supplier 1 Supplier 2 Supplier 3
Normal Mixed Slump 75+-25mm

Concrete G15 lean conc M3 346.32 288.36 277.50


Concrete G20 Normal Mix M3 401.23 343.28 332.41
Concrete G25 Normal Mix M3 412.10 354.14 343.28
Concrete G30 Normal Mix M3 424.18 366.22 355.35
Concrete G35 Normal Mix M3 438.67 379.50 -
Concrete G40 Normal Mix M3 455.57 395.20 -
Concrete G45 Normal Mix M3 474.89 - -
Concrete G50 Normal Mix M3 496.63 - -
Table 4
QS Rate
Online
306.48
361.39
373.46
386.75
401.23
416.93
433.84
Summary of prices for READY MIXED CONCRETE - NORMAL MIXED

Supply & Delivery Built Up Rate


Item Type Of Materials Rate (RM) Unit Material Labour Plant & Machineries Sub -total
1 Concretor =
: RM 226.80+RM16.87
1 Concrete Grade 10 216.00/M3 M3 Concrete Grade 10 RM110.00/8hrs x 0.75/ Tools: Tile cutter = RM 650.00
=RM 243.67
m³ = RM 10.31/m³
= RM 216.00 1 unskilled = life ± 3 yrs, say 8 times
RM70.00/8hrs x 0.75/ m³ maintenance cost = RM 60 x 8 =
Wastage 5% = RM 6.56/m³ RM 480
=RM 10.80 Total
RM 10.31+6.56 Total cost for 3 yrs = RM 480 + RM
Total = RM 16.87 650.00 = RM 1130.00
RM 216.00 + RM 10.80
= RM 226.80 : say, 200 days using in 1 year & 8
hrs/day & 0.67hrs / m²

2 Concrete Grade 15 216.00/M3 M3

= RM 216.00
sample
Concrete Grade 15
1 Concretor =
RM110.00/8hrs x 0.75/
m³ = RM 10.31/m³
1 unskilled =
RM70.00/8hrs x 0.75/ m³
Tools: Tile cutter = RM 650.00

life ± 3 yrs, say 8 times


maintenance cost = RM 60 x 8 =
: RM 226.80+RM16.87
=RM 243.67

Wastage 5% = RM 6.56/m³ RM 480


=RM 10.80 Total
RM 10.31+6.56 Total cost for 3 yrs = RM 480 + RM
Total = RM 16.87 650.00 = RM 1130.00
RM 216.00 + RM 10.80
= RM 226.80 : say, 200 days using in 1 year & 8
hrs/day & 0.67hrs / m²
1 Concretor =
: RM 239.40+RM22.50
3 Concrete Grade 20 228.00/M3 M3 Concrete Grade 20 RM110.00/8hrs x 1.00/
=RM 261.90
m³ = RM 13.75/m³
= RM 228.00 1 unskilled =
RM70.00/8hrs x 1.00/ m³
Wastage 5% = RM 8.75/m³
=RM 11.40 Total
RM 13.75+8.75
Total = RM 22.50
RM 228.00 + RM 11.40
= RM 239.40

: RM 1130.00 / 3yrs/ 200days/8 hrs


x 0.67hrs / m²
= RM 0.16

1 Concretor =
: RM 239.40+RM22.50
4 Concrete Grade 25 232.80/M3 M3 Concrete Grade 25 RM110.00/8hrs x 1.00/
=RM 261.90
m³ = RM 13.75/m³
= RM 232.80 1 unskilled =
RM70.00/8hrs x 1.00/ m³
Wastage 5% = RM 8.75/m³
=RM 11.64 Total
RM 13.75+8.75
Total = RM 22.50
RM 228.00 + RM 11.40
= RM 239.40

: RM 1130.00 / 3yrs/ 200days/8 hrs


x 0.67hrs / m²
= RM 0.16
Profitt & Attendances Total Cost

: RM 243.67 + RM
: RM 243.67 x 15%
36.55
=RM36.55 =RM 280.22
say
=RM 280.20

: RM 243.67 x 15% : RM 243.67 + RM 36.55

=RM36.55 =RM 280.22


say
=RM 280.20

: RM 261.90 x 15% : RM 261.90 + RM39.29

=RM39.29 =RM 301.19


say
=RM 301.20

: RM 261.90 x 15% : RM 261.90 + RM39.29

=RM39.29 =RM 301.19


say
=RM 301.20
ARMPSB

BUILT-UP RATE LEAN CONCRETE G10


TRADE : CONCRETOR *Note : Please fill in the green area before proceed.
CODE :
Description : Lean concrete G10 under pad footing. Unit : M3

DATA : Date : 8/12/2016


MATERIAL Supply (RM) LABOUR Labour Constant Labour Rate PLANT RATE
RM / bag Concretor 0.75 hrs /m³ RM 110.00 / day
Conc. G10 RM 216.00 / m³ Unskilled 0.75 hrs /m³ RM 70.00 / day
RM / m³

A MATERIAL COST

1. Concrete G10 RM 216.00 / m³


RM 0.00 / m³
RM 0.00 / m³
RM 216.00 / m³
add : 5% wastage RM 10.80
RM 226.80 / m³

B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 0.75 hrs / m³ RM 10.31
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 0.75 hrs / m³ RM 6.56

RM 16.87 / m³

SUB-TOTAL RM 243.67 / m³

Adjustment for small PROJECT


Standard 15% Say, = RM 0.00 RM 0.00 / m³
RM 243.67 / m³
Adjustment for LOCATION
Perlis, Kedah, Penang 30% Say,
Johor, N.9, Melaka 25% Say,
Pahang 30% Say,
Kelantan, Terengganu 30% Say, 0% = RM 0.00 RM 0.00 / m³
Perak 25% Say,
Klang Valley 0% Say, 0%
Sabah / Sarawak 45% Say,
RM 243.67 / m³

Add : PROFIT & OVERHEAD


Competitive, 10% Say, 15%
Selective, 20% Say, 15% = RM 36.55 RM 36.55 / m³
Direct Negotiation, 30% Say,
TOTAL COST RM 280.22 / m³
Say, RM 280.20 / m³

BUR_Concrete/17
ARMPSB

BUILT-UP RATE LEAN CONCRETE G15


TRADE : CONCRETOR *Note : Please fill in the green area before proceed.
CODE :
Description : Lean concrete G15 under pad footing. Unit : M3

DATA : Date : 8/12/2016


MATERIAL Supply (RM) LABOUR Labour Constant Labour Rate PLANT RATE
RM / bag Concretor 0.75 hrs /m³ RM 150.00 / day RM / day
Conc. G15 RM 206.00 / m³ Unskilled 0.75 hrs /m³ RM 100.00 / day
RM / m³ RM / day

A MATERIAL COST

1. Concrete G15 RM 206.00 / m³


RM 0.00 / m³
RM 0.00 / m³
RM 206.00 / m³
add : 5% wastage RM 10.30
RM 216.30 / m³

B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 150.00 / 8 hrs x 0.75 hrs / m³ RM 14.06
ii. 1 Unskilled labour RM 100.00 / 8 hrs x 0.75 hrs / m³ RM 9.38

RM 23.44 / m³

SUB-TOTAL RM 239.74 / m³

Adjustment for small PROJECT


Standard 15% Say, = RM 0.00 RM 0.00 / m³
RM 239.74 / m³
Adjustment for LOCATION
Perlis, Kedah, Penang 30% Say,
Johor, N.9, Melaka 25% Say,
Pahang 30% Say,
Kelantan, Terengganu 30% Say, 0% = RM 0.00 RM 0.00 / m³
Perak 25% Say,
Klang Valley 0% Say, 0%
Sabah / Sarawak 45% Say,
RM 239.74 / m³

Add : PROFIT & OVERHEAD


Competitive, 10% Say,
Selective, 20% Say, 15% 15% = RM 35.96 RM 35.96 / m³
Direct Negotiation, 30% Say,
TOTAL COST RM 275.70 / m³
Say, RM 275.70 / m³

BUR_Concrete/18
ARMPSB

BUILT-UP RATE CONCRETE G20


TRADE : CONCRETOR *Note : Please fill in the green area before proceed.
CODE :
Description : Vibrated reinforced concrete G20 in external steps. Unit : M3

DATA : Date : 8/12/2016


MATERIAL Supply (RM) LABOUR Labour Constant Labour Rate PLANT RATE
RM / bag Concretor 1 hrs /m³ RM 110.00 / day RM / day
Conc. G20 RM 228.00 / m³ Unskilled 1 hrs /m³ RM 70.00 / day
RM / m³ RM / day

A MATERIAL COST

1. Concrete G20 RM 228.00 / m³


RM 0.00 / m³
RM 0.00 / m³
RM 228.00 / m³
add : 5% wastage RM 11.40
RM 239.40 / m³

B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 1.00 hrs / m³ RM 13.75
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 1.00 hrs / m³ RM 8.75

RM 22.50 / m³

SUB-TOTAL RM 261.90 / m³

Adjustment for small PROJECT


Standard 15% Say, = RM 0.00 RM 0.00 / m³
RM 261.90 / m³
Adjustment for LOCATION
Perlis, Kedah, Penang 30% Say,
Johor, N.9, Melaka 25% Say,
Pahang 30% Say,
Kelantan, Terengganu 30% Say, 0% = RM 0.00 RM 0.00 / m³
Perak 25% Say,
Klang Valley 0% Say, 0%
Sabah / Sarawak 45% Say,
RM 261.90 / m³

Add : PROFIT & OVERHEAD


Competitive, 10% Say, 15%
Selective, 20% Say, 15% = RM 39.29 RM 39.29 / m³
Direct Negotiation, 30% Say,
TOTAL COST RM 301.19 / m³
Say, RM 301.20 / m³

BUR_Concrete/19
ARMPSB

BUILT-UP RATE CONCRETE G25


TRADE : CONCRETOR *Note : Please fill in the green area before proceed.
CODE :
Description : Vibrated reinforced concrete G25 in upper floor slab. Unit : M3

DATA : Date : 8/12/2016


MATERIAL Supply (RM) LABOUR Labour Constant Labour Rate PLANT RATE
RM / bag Concretor 1 hrs /m³ RM 110.00 / day RM / day
Conc. G25 RM 232.80 / m³ Unskilled 1 hrs /m³ RM 70.00 / day
RM / m³ RM / day

A MATERIAL COST

1. Concrete G25 RM 232.80 / m³


RM 0.00 / m³
RM 0.00 / m³
RM 232.80 / m³
add : 5% wastage RM 11.64
RM 244.44 / m³

B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 1.00 hrs / m³ RM 13.75
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 1.00 hrs / m³ RM 8.75

RM 22.50 / m³

SUB-TOTAL RM 266.94 / m³

Adjustment for small PROJECT


Standard 15% Say, = RM 0.00 RM 0.00 / m³
RM 266.94 / m³
Adjustment for LOCATION
Perlis, Kedah, Penang 30% Say,
Johor, N.9, Melaka 25% Say,
Pahang 30% Say,
Kelantan, Terengganu 30% Say, 0% = RM 0.00 RM 0.00 / m³
Perak 25% Say,
Klang Valley 0% Say, 0%
Sabah / Sarawak 45% Say,
RM 266.94 / m³

Add : PROFIT & OVERHEAD


Competitive, 10% Say,
Selective, 20% Say, 15% 15% = RM 40.04 RM 40.04 / m³
Direct Negotiation, 30% Say,
TOTAL COST RM 306.98 / m³
Say, RM 307.00 / m³

BUR_Concrete/20
ARMPSB

BUILT-UP RATE CONCRETE G30


TRADE : CONCRETOR *Note : Please fill in the green area before proceed.
CODE :
Description : Vibrated reinforced concrete G30 in ground beam. Unit : M3

DATA : Date : 8/12/2016


MATERIAL Supply (RM) LABOUR Labour Constant Labour Rate PLANT RATE
RM / bag Concretor 1 hrs /m³ RM 110.00 / day RM / day
Conc. G30 RM 250.80 / m³ Unskilled 1 hrs /m³ RM 70.00 / day
RM / m³ RM / day

A MATERIAL COST

1. Concrete G30 RM 250.80 / m³


RM 0.00 / m³
RM 0.00 / m³
RM 250.80 / m³
add : 5% wastage RM 12.54
RM 263.34 / m³

B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 1.00 hrs / m³ RM 13.75
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 1.00 hrs / m³ RM 8.75

RM 22.50 / m³

SUB-TOTAL RM 285.84 / m³

Adjustment for small PROJECT


Standard 15% Say, = RM 0.00 RM 0.00 / m³
RM 285.84 / m³
Adjustment for LOCATION
Perlis, Kedah, Penang 30% Say,
Johor, N.9, Melaka 25% Say,
Pahang 30% Say,
Kelantan, Terengganu 30% Say, 0% = RM 0.00 RM 0.00 / m³
Perak 25% Say,
Klang Valley 0% Say, 0%
Sabah / Sarawak 45% Say,
RM 285.84 / m³

Add : PROFIT & OVERHEAD


Competitive, 10% Say,
Selective, 20% Say, 15% 15% = RM 42.88 RM 42.88 / m³
Direct Negotiation, 30% Say,
TOTAL COST RM 328.72 / m³
Say, RM 328.70 / m³

BUR_Concrete/21
ARMPSB

BUILT-UP RATE CONCRETE G35


TRADE : CONCRETOR *Note : Please fill in the green area before proceed.
CODE :
Description : Vibrated reinforced concrete G35 in retaining wall. Unit : M3

DATA : Date : 8/12/2016


MATERIAL Supply (RM) LABOUR Labour Constant Labour Rate PLANT RATE
RM / bag Concretor 1 hrs /m³ RM 110.00 / day RM / day
Conc. G35 RM 264.00 / m³ Unskilled 1 hrs /m³ RM 70.00 / day
RM / m³ RM / day

A MATERIAL COST

1. Concrete G35 RM 264.00 / m³


RM 0.00 / m³
RM 0.00 / m³
RM 264.00 / m³
add : 5% wastage RM 13.20
RM 277.20 / m³

B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 1.00 hrs / m³ RM 13.75
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 1.00 hrs / m³ RM 8.75

RM 22.50 / m³

SUB-TOTAL RM 299.70 / m³

Adjustment for small PROJECT


Standard 15% Say, = RM 0.00 RM 0.00 / m³
RM 299.70 / m³
Adjustment for LOCATION
Perlis, Kedah, Penang 30% Say,
Johor, N.9, Melaka 25% Say,
Pahang 30% Say,
Kelantan, Terengganu 30% Say, 0% = RM 0.00 RM 0.00 / m³
Perak 25% Say,
Klang Valley 0% Say, 0%
Sabah / Sarawak 45% Say,
RM 299.70 / m³

Add : PROFIT & OVERHEAD


Competitive, 10% Say, 15%
Selective, 20% Say, 15% = RM 44.96 RM 44.96 / m³
Direct Negotiation, 30% Say,
TOTAL COST RM 344.66 / m³
Say, RM 344.70 / m³

BUR_Concrete/22
ARMPSB

BUILT-UP RATE CONCRETE G40


TRADE : CONCRETOR *Note : Please fill in the green area before proceed.
CODE :
Description : Vibrated reinforced concrete G40 in retaining wall. Unit : M3

DATA : Date : 8/12/2016


MATERIAL Supply (RM) LABOUR Labour Constant Labour Rate PLANT RATE
RM / bag Concretor 1 hrs /m³ RM 110.00 / day RM / day
Conc. G40 RM 278.40 / m³ Unskilled 1 hrs /m³ RM 70.00 / day
RM / m³ RM / day

A MATERIAL COST

1. Concrete G40 RM 278.40 / m³


RM 0.00 / m³
RM 0.00 / m³
RM 278.40 / m³
add : 5% wastage RM 13.92
RM 292.32 / m³

B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 1.00 hrs / m³ RM 13.75
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 1.00 hrs / m³ RM 8.75

RM 22.50 / m³

SUB-TOTAL RM 314.82 / m³

Adjustment for small PROJECT


Standard 15% Say, = RM 0.00 RM 0.00 / m³
RM 314.82 / m³
Adjustment for LOCATION
Perlis, Kedah, Penang 30% Say,
Johor, N.9, Melaka 25% Say,
Pahang 30% Say,
Kelantan, Terengganu 30% Say, 0% = RM 0.00 RM 0.00 / m³
Perak 25% Say,
Klang Valley 0% Say, 0%
Sabah / Sarawak 45% Say,
RM 314.82 / m³

Add : PROFIT & OVERHEAD


Competitive, 10% Say, 15%
Selective, 20% Say, 15% = RM 47.22 RM 47.22 / m³
Direct Negotiation, 30% Say,
TOTAL COST RM 362.04 / m³
Say, RM 362.00 / m³

BUR_Concrete/23
ARMPSB

BUILT-UP RATE CONCRETE G45


TRADE : CONCRETOR *Note : Please fill in the green area before proceed.
CODE :
Description : Vibrated reinforced concrete G40 in retaining wall. Unit : M3

DATA : Date : 8/12/2016


MATERIAL Supply (RM) LABOUR Labour Constant Labour Rate PLANT RATE
RM / bag Concretor 1 hrs /m³ RM 110.00 / day RM / day
Conc. G45 RM 294.00 / m³ Unskilled 1 hrs /m³ RM 70.00 / day
RM / m³ RM / day

A MATERIAL COST

1. Concrete G45 RM 294.00 / m³


RM 0.00 / m³
RM 0.00 / m³
RM 294.00 / m³
add : 5% wastage RM 14.70
RM 308.70 / m³

B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 1.00 hrs / m³ RM 13.75
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 1.00 hrs / m³ RM 8.75

RM 22.50 / m³

SUB-TOTAL RM 331.20 / m³

Adjustment for small PROJECT


Standard 15% Say, = RM 0.00 RM 0.00 / m³
RM 331.20 / m³
Adjustment for LOCATION
Perlis, Kedah, Penang 30% Say,
Johor, N.9, Melaka 25% Say,
Pahang 30% Say,
Kelantan, Terengganu 30% Say, 0% = RM 0.00 RM 0.00 / m³
Perak 25% Say,
Klang Valley 0% Say, 0%
Sabah / Sarawak 45% Say,
RM 331.20 / m³

Add : PROFIT & OVERHEAD


Competitive, 10% Say, 15%
Selective, 20% Say, 15% = RM 49.68 RM 49.68 / m³
Direct Negotiation, 30% Say,
TOTAL COST RM 380.88 / m³
Say, RM 380.90 / m³

BUR_Concrete/24
ARMPSB

BUILT-UP RATE

TRADE : CONCRETOR
CODE :
Description : Vibrated reinforced concrete G25 in upper floor slab.

DATA : Date :
MATERIAL Supply (RM) LABOUR Labour Constant Labour Rate PLANT RATE
Cement RM 12.00 / bag Skilled 1.75 hrs /m³ RM 90.00 / day Conc. mixer RM 380.00
Sand RM 32.00 / m³ Unskilled 1.75 hrs /m³ RM 50.00 / day (rental)
Aggregate RM 30.00 / m³ Operator RM 50.00

A MATERIAL COST
Mixing material for concrete G25 is 1:1½:3
1. Cement 1m³ = 28 bags RM 336.00 / m³
2. Sand 1.5 m³ RM 48.00 / 1.5m³
3. Aggregate 3 m³ RM 90.00 / 3 m³
Sub-Total RM 474.00 / 5.5 m³
add : 5% wastage RM 23.70
RM 497.70 / 5.5 m³
add : 33.33% shrinkages RM 165.88
MATERIAL COST FOR 5.5 m³ RM 663.58 / 5.5 m³
COST PER m³ RM 120.65 / m³ RM 120.65

B LABOUR COST
Labour for wheeling, hoisting and placing
1. 1 Concretor RM 90.00 / 8 hrs x 1.75 hrs / m³ RM 19.69
2. 1 Unskilled labour RM 50.00 / 8 hrs x 1.75 hrs / m³ RM 10.94
RM 30.63

C PLANT & MACHINERY

1. Concrete mixer RM 380.00 / 8 hrs x 1 hr / m³ RM 47.50


2. Operator RM 50.00 / 8 hrs x 1 hr / m³ RM 6.25
COST per m³ RM 53.75

SUB-TOTAL RM 205.03

Adjustment for small PROJECT


Standard 15% Say, 30% = RM 61.51 RM 61.51
RM 266.54
Adjustment for LOCATION
Perlis, Kedah, Penang 30% Say, 20%
Johor, N.9, Melaka 25% Say,
Pahang 30% Say,
Kelantan, Terengganu 30% Say, 20% = RM 41.01 RM 41.01
Perak 25% Say,
Klang Valley 0% Say,
Sabah / Sarawak 45% Say,
RM 307.55

Add : PROFIT & OVERHEAD


Competitive, 10% Say,
Selective, 20% Say, 20% 20% = RM 61.51 RM 61.51
Direct Negotiation, 30% Say,
TOTAL COST RM 369.06
Say, RM 369.10

BUR_Concrete/25
ARMPSB

PLANT RATE
/ day

/ day

/ m³

/ m³

/ m³

/ m³

/ m³
/ m³

/ m³

/ m³

/ m³

/ m³
/ m³

BUR_Concrete/26

You might also like