Professional Documents
Culture Documents
Bur 3 - Concrete Works
Bur 3 - Concrete Works
Wall
Unskilled man-hour
Item Description Unit
RM10.57 (hrs)
1 n.e 100mm M3 10.00
2 exc 100mm b.n.e 150mm M3 9.00
3 ecx 150mm b.n.e 300mm M3 8.00
4 exc 300mm M3 7.00
Material Cost
Rate / m3 = RM172.78
5 % wastages = RM8.64
RM10.57
REINFORCEMENT BAR PRICE
HIGH TENSILE
Y10 Y12 Y16 Y20 Y22 Y25 Y28 Y32 Y40
No. of bars per bundle 138 pcs 96 pcs 54 pcs 34 pcs 28 pcs 22 pcs 18 pcs 14 pcs 9 pcs
Metric ton per bundle 1.020 tonnes 1.023 tonnes 1.023 tonnes 1.006 tonnes 1.003 tonnes 1.017 tonnes 1.044 tonnes 1.061 tonnes 1.065 tonnes
Weight per bar 7.391 kg 10.656 kg 18.944 kg 29.588 kg 35.821 kg 46.227 kg 58.000 kg 75.786 kg 118.333 kg
ZON
TENGAH 2,461.53 2,349.33 2,274.25 2,274.25 2,158.75 2,158.75 2,158.75 2,158.75 2,233.83
TIMUR
UTARA
SELATAN
COSTING
Material Price per Metric Ton
· Government Control Price 1,319.00 1,279.00 1,214.00 1,214.00 1,214.00 1,214.00 1,214.00 1,214.00 1,279.00
· Extra Supplier Charges 456.00 456.00 456.00 456.00 356.00 356.00 356.00 356.00 356.00
A MATERIAL 1,775.00 1,735.00 1,670.00 1,670.00 1,570.00 1,570.00 1,570.00 1,570.00 1,635.00
B UNLOADING 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
C TYING WIRE 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
D SPACER BLOCKS 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
E LABOUR / M. TON 340.00 280.00 280.00 280.00 280.00 280.00 280.00 280.00 280.00
F TOOLS& EQUIPMENT RENTAL 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00
G CUTTING & BENDING 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
Sub-Total 2,149.00 2,049.00 1,984.00 1,984.00 1,884.00 1,884.00 1,884.00 1,884.00 1,949.00
Add
5% wastage 88.75 86.75 83.50 83.50 78.50 78.50 78.50 78.50 81.75
Sub-Total 2,237.75 2,135.75 2,067.50 2,067.50 1,962.50 1,962.50 1,962.50 1,962.50 2,030.75
Add
10% profit 223.78 213.58 206.75 206.75 196.25 196.25 196.25 196.25 203.08
GRAND TOTAL 2,461.53 2,349.33 2,274.25 2,274.25 2,158.75 2,158.75 2,158.75 2,158.75 2,233.83
MILD STEEL
R6 R8 R10 R12 R16 R20 R22 R25 R28 R32
No. of bars per bundle 320 pcs 149 pcs 138 pcs 96 pcs 54 pcs 34 pcs 28 pcs 22 pcs 18 pcs 14 pcs
Metric ton per bundle 1.000 tonnes 1.000 tonnes 1.020 tonnes 1.023 tonnes 1.023 tonnes 1.006 tonnes 1.003 tonnes 1.017 tonnes 1.044 tonnes 1.061 tonnes
Weight per bar 3.125 kg 6.711 kg 7.391 kg 10.656 kg 18.944 kg 29.588 kg 35.821 kg 46.227 kg 58.000 kg 75.786 kg
ZON
TENGAH 2,099.90 2,164.58 2,273.15 2,213.09 2,135.71 2,135.71 2,135.71 2,135.71 2,135.71 2,135.71
TIMUR
UTARA
SELATAN
COSTING
Material Price per Metric Ton
· Government Control Price 1,279.00 1,200.00 1,279.00 1,242.00 1,175.00 1,175.00 1,175.00 1,175.00 1,175.00 1,175.00
· Extra Supplier Charges 221.00 356.00 371.00 356.00 356.00 356.00 356.00 356.00 356.00 356.00
A MATERIAL 1,500.00 1,556.00 1,650.00 1,598.00 1,531.00 1,531.00 1,531.00 1,531.00 1,531.00 1,531.00
B UNLOADING 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
C TYING WIRE 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
D SPACER BLOCKS 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
E LABOUR / M. TON 300.00 300.00 300.00 300.00 300.00 300.00 300.00 300.00 300.00 300.00
F TOOLS& EQUIPMENT RENTAL 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00
G CUTTING & BENDING 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
Sub-Total 1,834.00 1,890.00 1,984.00 1,932.00 1,865.00 1,865.00 1,865.00 1,865.00 1,865.00 1,865.00
Add
5% wastage 75.00 77.80 82.50 79.90 76.55 76.55 76.55 76.55 76.55 76.55
Sub-Total 1,909.00 1,967.80 2,066.50 2,011.90 1,941.55 1,941.55 1,941.55 1,941.55 1,941.55 1,941.55
Add
10% profit 190.90 196.78 206.65 201.19 194.16 194.16 194.16 194.16 194.16 194.16
GRAND TOTAL 2,099.90 2,164.58 2,273.15 2,213.09 2,135.71 2,135.71 2,135.71 2,135.71 2,135.71 2,135.71
REINFORCEMENT
C.1 Tying Wire
Bar size = Y10 Reinforcement bar rate ITEM Description Unit wire
size rate / tonne 1 6 – 12 mm diameter kg/t 10.00
Tying wire cost = RM3.50 /kg R6 1,962.00 2 16 – 25 mm diameter kg/t 6.00
R8 1,962.00 3 32 – 50 mm diameter kg/t 5.00
Barbender / cutter wages = RM60.00 /day R10 1,962.00
Y10 2,010.00
General worker wages = RM50.00 /day Y12 1,962.00 C.2 Bending and Cutting (hrs/t)
6 – 8 mm 10 – 12 16 – 20 > 25mm
ITEM Description Unit
Y16 1,884.00 dia. mm dia. mm dia. dia.
Crane rental = RM400.00 /day Y20 1,884.00 1 Straight and bend hrs/t 40.00 30.00 20.00 15.00
2 Links and Stirrups hrs/t 65.00 50.00 30.00 -
Plant cost
i. Crane = 0.25 hour x RM400.00 = RM12.50
8 hour
= RM2,595.88
SUMMARY
A63 A98 A142 A193 A252 A318 A393 B196 B283 B385 B503 B636 B785 B1131 C196 C283 C385 C503 C636 C785
MATERIAL A4 A5 A6 A7 A8 A9 A10 B5 B6 B7 B8 B9 B10 B12 C5 C6 C7 C8 C9 C10 DA4 DA5 DA6 DA7 DA8 DA9 DA10
RATE PER M2 3.65 4.52 6.93 8.53 11.34 13.35 17.90 7.06 8.40 10.00 12.68 14.55 18.43 24.32 5.06 6.46 8.13 10.00 12.41 15.42 6.06 7.80 9.74 12.95 16.42 20.44 27.26
NO DESCRIPTION A4 A5 A6 A7 A8 A9 A10 B5 B6 B7 B8 B9 B10 B12 C5 C6 C7 C8 C9 C10 DA4 DA5 DA6 DA7 DA8 DA9 DA10
1 Material cost per m2 1.85 2.50 4.30 5.50 7.60 9.10 12.50 4.40 5.40 6.60 8.60 10.00 12.90 17.30 2.90 3.95 5.20 6.60 8.40 10.65 3.65 4.95 6.40 8.80 11.40 14.40 19.50
2 Laps Allowance 10% 0.19 0.25 0.43 0.55 0.76 0.91 1.25 0.44 0.54 0.66 0.86 1.00 1.29 1.73 0.29 0.40 0.52 0.66 0.84 1.07 0.37 0.50 0.64 0.88 1.14 1.44 1.95
3 Add : Wastage 15% 0.28 0.38 0.64 0.83 1.14 1.37 1.88 0.66 0.81 0.99 1.29 1.50 1.94 2.60 0.44 0.59 0.78 0.99 1.26 1.60 0.55 0.74 0.96 1.32 1.71 2.16 2.93
4 Spacer Block 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
5 Labour charge per m2 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
3.41 4.23 6.48 7.98 10.60 12.48 16.73 6.60 7.85 9.35 11.85 13.60 17.23 22.73 4.73 6.04 7.60 9.35 11.60 14.41 5.66 7.29 9.10 12.10 15.35 19.10 25.48
6 Add: Profit 7% 0.24 0.30 0.45 0.56 0.74 0.87 1.17 0.46 0.55 0.65 0.83 0.95 1.21 1.59 0.33 0.42 0.53 0.65 0.81 1.01 0.40 0.51 0.64 0.85 1.07 1.34 1.78
7 Total Cost per m2 3.65 4.52 6.93 8.53 11.34 13.35 17.90 7.06 8.40 10.00 12.68 14.55 18.43 24.32 5.06 6.46 8.13 10.00 12.41 15.42 6.06 7.80 9.74 12.95 16.42 20.44 27.26
c:\build-up\costing
FORMWORK
Fast hardened
ITEM Description Ordinary Portland portland cement
Cement (Day) (Day)
1 3 2
Side of beams, Wall and Column
2 4 3
Floor (penyokong ditinggalkan)
3 5
Menanggal penyokong ke lantai
4 Slab under the beam 8 5
(penyokong ditinggalkan)
5 21 8
Menanggal penyokong ke rasuk
Labour cost
Fabricate & install - Using times
Carpenter = 1.00 hour x RM70.00 = RM 8.75 ITEM Description Unit using times
8 hour 1 slab, roof, wall m 4-6
2 Column and Beam m 2-3
General worker = 0.75 hour x RM55.00 = RM 5.16
8 hour
- Timbers (Quantity of Timber - m3/m2)
Dissemble & Store ITEM Description Unit QTY
General worker = 0.75 hour x RM55.00 = RM 5.16 1 floor and wall area of floor/wall
8 hour 2 strut for wall, floor M3/m2 0.05
RM 36.73 3 stru for beam and lintel M3/m2 0.06
4 strut for column M3/m2 0.03
Overhead & Profit = 0.00% = RM -
TOTAL RATE = RM 36.73 m2
CONCRETE WORKS
SUPPLIER : PTCK ENTERPRISE
LABOUR COST
Labour for mixing and placing concrete
i. Concretor RM 160.00 / 8 hrs x 1.00
ii. 1 Unskilled Labour RM 100.00 / 8 hrs x 1.00
Supply &
Description Unit wastage crane
Delivery
26.10.2023 5%
Normal Mixed Slump 75+-
25mm
Concrete G15 lean conc M3 263.00 13.15 20.00
Concrete G20 Normal Mix M3 268.00 13.40 20.00
Concrete G25 Normal Mix M3 277.00 13.85 20.00
Concrete G30 Normal Mix M3 287.00 14.35 20.00
Concrete G35 Normal Mix M3 299.00 14.95 20.00
Concrete G40 Normal Mix M3 313.00 15.65 20.00
Concrete G45 Normal Mix M3 329.00 16.45 20.00
Concrete G50 Normal Mix M3 347.00 17.35 20.00
CONCRETE WORKS
SUPPLIER : MAJOR DUAL SDN BHD
Supply &
Description Unit wastage crane
Delivery
CONCRETE WORKS
SUPPLIER : EVER MIXED CONCRETE SDN BHD
Supply &
Description Unit wastage crane
Delivery
CONCRETE WORKS
SUPPLIER : DATA QS RATE ONLINE
Supply &
Description Unit wastage crane
Delivery
REINFORCEMENT
bender +
Unit supply wastage cutter
5%
Rebar @ 16,20 dia tonne 3,220.00 80.00
Rebar @ 25,32 dia tonne 3,220.00 80.00
Rebar @ 10,12,40 tonne 3,370.00 80.00
Rebar @ R6,R8,R10 tonne 3,370.00 80.00
hrs / m³ RM 20.00
hrs / m³ RM 12.50
RM 32.50
labour + COST
pump truck tools + RATE Total Cost including Profit
curing (RM)
RM/m3 RM/m3 RM/m3 RM/m3 RM/m3 RM/m3
3%
5.00 301.15 346.32 356.71 83.32 32%
15.00 32.50 348.90 401.23 413.27 133.23 50%
15.00 32.50 358.35 412.10 424.47 135.10 49%
15.00 32.50 368.85 424.18 436.90 137.18 48%
15.00 32.50 381.45 438.67 451.83 139.67 47%
15.00 32.50 396.15 455.57 469.24 142.57 46%
15.00 32.50 412.95 474.89 489.14 145.89 44%
15.00 32.50 431.85 496.63 511.53 149.63 43%
labour + COST
pump truck tools + RATE Total Cost including Profit
curing (RM)
RM/m3 RM/m3 RM/m3 RM/m3 RM/m3 RM/m3
7.5% 10.0% 15.0%
labour + COST
pump truck tools + RATE Total Cost including Profit
curing (RM)
RM/m3 RM/m3 RM/m3 RM/m3 RM/m3 RM/m3
7.5% 10.0% 15.0%
labour + COST
pump truck tools + RATE Total Cost including Profit
curing (RM)
RM/m3 RM/m3 RM/m3 RM/m3 RM/m3 RM/m3
7.5% 10.0% 15.0%
= RM 216.00
sample
Concrete Grade 15
1 Concretor =
RM110.00/8hrs x 0.75/
m³ = RM 10.31/m³
1 unskilled =
RM70.00/8hrs x 0.75/ m³
Tools: Tile cutter = RM 650.00
1 Concretor =
: RM 239.40+RM22.50
4 Concrete Grade 25 232.80/M3 M3 Concrete Grade 25 RM110.00/8hrs x 1.00/
=RM 261.90
m³ = RM 13.75/m³
= RM 232.80 1 unskilled =
RM70.00/8hrs x 1.00/ m³
Wastage 5% = RM 8.75/m³
=RM 11.64 Total
RM 13.75+8.75
Total = RM 22.50
RM 228.00 + RM 11.40
= RM 239.40
: RM 243.67 + RM
: RM 243.67 x 15%
36.55
=RM36.55 =RM 280.22
say
=RM 280.20
A MATERIAL COST
B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 0.75 hrs / m³ RM 10.31
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 0.75 hrs / m³ RM 6.56
RM 16.87 / m³
SUB-TOTAL RM 243.67 / m³
BUR_Concrete/17
ARMPSB
A MATERIAL COST
B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 150.00 / 8 hrs x 0.75 hrs / m³ RM 14.06
ii. 1 Unskilled labour RM 100.00 / 8 hrs x 0.75 hrs / m³ RM 9.38
RM 23.44 / m³
SUB-TOTAL RM 239.74 / m³
BUR_Concrete/18
ARMPSB
A MATERIAL COST
B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 1.00 hrs / m³ RM 13.75
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 1.00 hrs / m³ RM 8.75
RM 22.50 / m³
SUB-TOTAL RM 261.90 / m³
BUR_Concrete/19
ARMPSB
A MATERIAL COST
B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 1.00 hrs / m³ RM 13.75
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 1.00 hrs / m³ RM 8.75
RM 22.50 / m³
SUB-TOTAL RM 266.94 / m³
BUR_Concrete/20
ARMPSB
A MATERIAL COST
B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 1.00 hrs / m³ RM 13.75
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 1.00 hrs / m³ RM 8.75
RM 22.50 / m³
SUB-TOTAL RM 285.84 / m³
BUR_Concrete/21
ARMPSB
A MATERIAL COST
B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 1.00 hrs / m³ RM 13.75
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 1.00 hrs / m³ RM 8.75
RM 22.50 / m³
SUB-TOTAL RM 299.70 / m³
BUR_Concrete/22
ARMPSB
A MATERIAL COST
B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 1.00 hrs / m³ RM 13.75
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 1.00 hrs / m³ RM 8.75
RM 22.50 / m³
SUB-TOTAL RM 314.82 / m³
BUR_Concrete/23
ARMPSB
A MATERIAL COST
B LABOUR COST
1. Labour for mixing and placing concrete
i. 1 Concretor RM 110.00 / 8 hrs x 1.00 hrs / m³ RM 13.75
ii. 1 Unskilled labour RM 70.00 / 8 hrs x 1.00 hrs / m³ RM 8.75
RM 22.50 / m³
SUB-TOTAL RM 331.20 / m³
BUR_Concrete/24
ARMPSB
BUILT-UP RATE
TRADE : CONCRETOR
CODE :
Description : Vibrated reinforced concrete G25 in upper floor slab.
DATA : Date :
MATERIAL Supply (RM) LABOUR Labour Constant Labour Rate PLANT RATE
Cement RM 12.00 / bag Skilled 1.75 hrs /m³ RM 90.00 / day Conc. mixer RM 380.00
Sand RM 32.00 / m³ Unskilled 1.75 hrs /m³ RM 50.00 / day (rental)
Aggregate RM 30.00 / m³ Operator RM 50.00
A MATERIAL COST
Mixing material for concrete G25 is 1:1½:3
1. Cement 1m³ = 28 bags RM 336.00 / m³
2. Sand 1.5 m³ RM 48.00 / 1.5m³
3. Aggregate 3 m³ RM 90.00 / 3 m³
Sub-Total RM 474.00 / 5.5 m³
add : 5% wastage RM 23.70
RM 497.70 / 5.5 m³
add : 33.33% shrinkages RM 165.88
MATERIAL COST FOR 5.5 m³ RM 663.58 / 5.5 m³
COST PER m³ RM 120.65 / m³ RM 120.65
B LABOUR COST
Labour for wheeling, hoisting and placing
1. 1 Concretor RM 90.00 / 8 hrs x 1.75 hrs / m³ RM 19.69
2. 1 Unskilled labour RM 50.00 / 8 hrs x 1.75 hrs / m³ RM 10.94
RM 30.63
SUB-TOTAL RM 205.03
BUR_Concrete/25
ARMPSB
PLANT RATE
/ day
/ day
/ m³
/ m³
/ m³
/ m³
/ m³
/ m³
/ m³
/ m³
/ m³
/ m³
/ m³
BUR_Concrete/26