ET Road KM 4.0-14.2 EB Pole Shifting Undertaking
And WHEREAS the Chengalpattu Division has undertaken the work of “Widening
from Intermediate Lane to Two Lane with Paved Shoulders and Strengthening in Km
4/0 - 6/2, 7/4 -10/2, 13/6 - 14/2 and Strengthening with Paver Block for Shoulders
from km 6/2 - 7/4 & 10/2 - 13/6 of Echur - Thiruporur Road inculding CD Works in Km
4/6(i), (ii), 4/8, 5/2,4,6, 6/8,10, 7/6,10, 8/4,6,10, 9/2, 10/2,4, 10/8(i), (ii), 11/8,10,
13/4 & 13/8” and has requested the TANGEDCO to shift the EB Poles at Echur –
Thiruporur Road Km 4/0 -14/2 that fails in the above said work.
2. Chengalpattu Division and their appointed authorities shall only use high
quality materials conforming to the standards approved by the
TANGEDCO and as per relevant ISS.
4. All the work shall be carried out under direct supervision of TANGEDCO
officials and their decisions in this regard shall be final and binding on
Chengalpattu Division.
6. The work shall be carried out without causing any incontinence to the
operation and maintenance of Sub-Station and other Department works of
the TANGEDCO in all matters.
consider their request and arrange for LC (Line Clear) depending upon
the exigencies. This has to be strictly adhered to.
13. Chengalpattu Division and there appointed authorities are responsible for
smooth execution of work and if any dispute arises during execution of
the work in regard to property / passage and labours, TANGEDCO shall
not be responsible or involved in such dispute.
14. Chengalpattu Division undertakes to ensure free flow of traffic during
execution of the works and shall also be responsible for any accident /
15. The source of supply materials used and the guarantee for the materials
lines.
18. Authority undertake to resolve all local problem and connected legal issue