Work Schedule DR Chong Bangsar
Work Schedule DR Chong Bangsar
Work Schedule DR Chong Bangsar
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5
SCOPE OF WORK PROGRESS START END
M T W T F S S M T W T F S S M T W T F S S
PRELIMINARIES
Disassemble work and install a new tiling works and other accessories 80% 16/10/2023 24/10/2023
Soundproofing indicator in every partition wall at the old wing 100% 19/10/2023 19/10/2023
Diassemble existing waterpump and install new waterpump 100% 19/10/2023 19/10/2023
Replace the existing exhaust fan and install new exhaust fan 100% 19/10/2023 19/10/2023
CARPENTRY WORKS
Dissassemble replace to new wood 16mm thickness ramp entrance 0% 24/10/2023 24/10/2023
Feature wall at reception wall area, beige fluted panel 0% 3/11/2023 3/11/2023
Spray paint gun with expoxy filler 1k at reception table area 0% 2/11/2023 3/11/2023
Custom acrylic golden paint alphabet; 7pcs (DR CHONG) 0% 31/10/2023 31/10/2023
Cleaning works with high grade detergent and waterjet 0% 24/10/2023 24/10/2023
FLOORING WORKS
Remove cracked laminate floor and install a new laminate fooring 70% 19/10/2023 19/10/2023
AWNING ROOF
Replace fabric to existing awning and install new awning; 35ft x 2.5m 0% 1/11/2023 1/11/2023
NOTE: This schedule is based on the overall planning of the design and construction phase. Any delays or changes to the renovation works dateline, we will update and inform to the client.