RENOVATION WORKS AT DR CHONG CLINIC, BANGSAR KL

PROJECT START: 13/10/2023 RENOVATION START 16/10/2023 RENOVATION END 4/11/2023


WEEK & DATE Oct 16, 2023 - Oct 22, 2023 Oct 23, 2023 - Oct 29, 2023 Oct 30, 2023 - Nov 5, 2023

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5
SCOPE OF WORK PROGRESS START END
M T W T F S S M T W T F S S M T W T F S S

PRELIMINARIES

Site Mobalisation 100% 16/10/2023 16/10/2023

TOILET AREA AND TREATMENT ROOM AT OLD WING

Disassemble work and install a new tiling works and other accessories 80% 16/10/2023 24/10/2023

Soundproofing indicator in every partition wall at the old wing 100% 19/10/2023 19/10/2023

Diassemble existing waterpump and install new waterpump 100% 19/10/2023 19/10/2023

Replace the existing exhaust fan and install new exhaust fan 100% 19/10/2023 19/10/2023

CARPENTRY WORKS

Dissassemble replace to new wood 16mm thickness ramp entrance 0% 24/10/2023 24/10/2023

Feature wall at reception wall area, beige fluted panel 0% 3/11/2023 3/11/2023

Spray paint gun with expoxy filler 1k at reception table area 0% 2/11/2023 3/11/2023

Custom acrylic golden paint alphabet; 7pcs (DR CHONG) 0% 31/10/2023 31/10/2023

Cleaning works with high grade detergent and waterjet 0% 24/10/2023 24/10/2023

Signage; DR CHONG CLINIC PREMIUM 50% 31/10/2023 31/10/2023

FLOORING WORKS

Remove cracked laminate floor and install a new laminate fooring 70% 19/10/2023 19/10/2023

AWNING ROOF

Replace fabric to existing awning and install new awning; 35ft x 2.5m 0% 1/11/2023 1/11/2023

NOTE: This schedule is based on the overall planning of the design and construction phase. Any delays or changes to the renovation works dateline, we will update and inform to the client.