3.1.3.
3.1.2.2. _ Install geotechnical instrumentation to monitor and validate the
performance of the works.
3.1.2.3. Removal and disposal of excess material on completion of
specified surcharge period or as shown in Drawing or when
directed by the S.0..
3.1.2.4. Removal and disposal of excess material of the embankment to
the line, level and grade in accordance to details as shown in
the Drawing to complete the works.
The Contractor shall be responsible for the provision of surcharge material
and the removal and disposal of excess material on completion of the
specified surcharge period or when directed by the S.O.
3.2. Materials
3.21
3.2.2
Materials for use in surcharging shall be suitable material conforming to
Standard Specification for Building Works SECTION B: EXCAVATION
AND EARTHWORKS.
The filling material shall be laid in layer and compacted as per SECTION
B: EXCAVATION AND EARTHWORKS.h Surcharge
3.1. General
3.1.1. The execution of surcharging works shall be in accordance with this
Specification and details as shown in the Drawing.
3.1.2. The scope of works shall cover the following:
BA 2A. Spread, level and compact surcharging material in accordance
with SECTION B: EXCAVATION AND EARTHWORKS and
details as shown in the Drawing.
‘COPYRIGHT JKR MALAYSIA87.
Filling on Soft Ground
87.1.
87.2.
8.7.3.
Foundation treatment
8744
8.7.1.2,
8.7.1.3,
ly
Where soft ground under embankment is to be treated as shown
on the Drawings or as directed by the S.O., the foundation soil
shall be improved as specified in SECTION V: GROUND
IMPROVEMENT.
The first layer of fill materials shall be deposited over the full
width of the embankment and berms in thicknesses not more
than 500mm or as approved by the S.O. to sufficiently support
earthwork machineries
If fill materials are required to be placed under standing water,
hard clean crushed rock, natural gravel or sand having grading
within the respective limits specified in Table B4 shall be used
to backfill the embankment not less than 300mm above the
standing water to receive compacted suitable fill thereafter.
Surcharge and staged construction
Where indicated in the Contract or directed by the S.O., the embankment
shall be built to different heights in stages with or without surcharge and
with allowance for consolidation time periods in between stages, all in
accordance with the Contract. Where surcharge is specified, the work
shall be carried as specified in SECTION V: GROUND IMPROVEMENT
WORKS. The Contractor shall be responsible for the provision of
surcharge material and the removal and disposal of excess material on
completion of consolidation or when directed by the S.0...
8.7.3.4
Geotechnical instruments shall be provided and installed by the
Contractor in the positions as shown on the Drawings or as