ORBITAL FABRICATION & INTEGRATION SERVICES L.L.C.

P.O. Box: 1114, P.C: 611, Sultanate of Oman


Ph:+968 24481397,Fax:+96824481923,Email:info@orbitalgrp.com

AUDIT RESPONSE & CORRECTIVE ACTION

Ref : OFIS-JO-AR&C-Rev 00
Date : 11-02-2024

Subject: L&T/Aramco - Vendor Facility Pre-Audit.


Order Ref:
Equipment:
Scope:

Dear Sirs,

Further to our recent audit meeting on the 11th February 2024 please find below audit findings
and corrective actions required, we will update this report with details of the corrective actions
taken and supporting documentation or evidence.

OFIS LLC is dedicated to continuous improvement, we take this opportunity to thank you for
your valued input and support as we look to implement the action below.

Item Comments Actions Taken


Positive Findings:
1 In the "FIFO System, Traceability Project-wise Noted and Thanks
Followed" welding consumable storage area
2 Temperature control shall be monitored’’. Noted and Thanks
Hygrometer calibrated
3 Gas cylinders that are properly chained and secured. Noted and Thanks
4 Maintenance certificate for Equipment are available Noted and Thanks
5 Piping and Structural fabrication separated and Noted and Thanks
identified with display board.
6 Welders are aware of the WPS requirement. WPS Noted and Thanks
displayed at Work locations

Item Comments Actions Taken


Areas to be improved/Corrected:
1 Quality Manual need to update .

2 Updates must be made to the organogram, and


management approval is needed.

3 Latest Audit report to be submit.

4 Training record need to be maintain

5 NCR procedure need to update .

Rev 00 Date- 1st MAR 2023 727398266.doc Page 1


ORBITAL FABRICATION & INTEGRATION SERVICES L.L.C.
P.O. Box: 1114, P.C: 611, Sultanate of Oman
Ph:+968 24481397,Fax:+96824481923,Email:info@orbitalgrp.com

AUDIT RESPONSE & CORRECTIVE ACTION

6 Cable Management at Shop area can be improved.

7 Pipe End cap to be provide .

8 Colour code to be used for the return electrode to


the store

9 Material Stacking at Shop floor area to be


improved. (As per the ARAMCO requirement )

10 Training certificate for Forklift operator to be


arranged

11 Before the Start the Work readiness matrix to be


prepared .

We will continue to update date you as all points are closed out.

Kind regards,
P. Moretti
QA Director
(ISO 9001:2015 Lead Auditor)