PROGRAM PERUMAHAN RAKYAT (PPR) LORONG SELAMAT/JALAN ZAINAL ABIDIN

UNTUK JABATAN PERUMAHAN NEGARA.

Description :
Allow for the provision of all necessary hydraulic piling equipments, plant, tools and for their
transportation to site, handling, assembling, erecting, dismantling and removal on completion.

1 TRANSPORTATION CHARGES

(a) 2 Lowloader Trips (4 axle) @ RM 2,500 per trip (average)


2 x 2,500.00 =

(b) 2 Cargo Trailer (40'0") @ RM 700.00 per trip (average)


2 x 700.00 =

(c) Mobile Crane Charges (inclusive of 2 Nos of 45 Ton at each time for the 100 Ton Crane
=

Mobilization
Demobilization

RM

2 LABOUR CHARGES

- for assembling and dissembling

1 team of Piling Rig @ RM 7,000 per rig = 1 x 7,000.00 =

3 MAINTENANCE COSTS

Inclusive of :

(a) Servicing including Engine Oil and additives,


Hydraulic Oils, Oils and Air Filters, Bolts and
Nuts, etc
Allow @ RM 5,000.00 per rig for the whole duration =

4 HOLDING COST FOR PLANT AND EQUIPMENT

Each Set of USED Piling Rig is estimated to cost about RM 650,000.00

Assuming the Current Financing Charges at a MINIMUM of


6.5% per Annum, Therefore the minimum Finance Charges
per Piling Rig = 6.5/100 x 650,000.00 = RM 42,250.00 per year
Therefore = RM 3,521 per month

The Duration for the Piling works is 3 month.


Therefore the HOLDING COST for 1 sets/Teams of
Piling Rig = 1 x 3 months x RM 3,521 per month =

Add 15% profit and overhead =

TOTAL =

SAY =
5,000.00

1,400.00

4,000.00

10,400.00
10,400.00

20,800.00

7,000.00

5,000.00
10,563.00

43,363.00

6,504.45

49,867.45

50,000.00
PROGRAM PERUMAHAN RAKYAT (PPR) LORONG SELAMAT/JALAN ZAINAL ABIDIN
UNTUK JABATAN PERUMAHAN NEGARA.

Description :
Allow for moving and handling piling equipments, plants, tools and ancillaries as often and
whenever necessary for the whole operation including any excavation and piling required
for movement of the piling equipment and plant and including idle time

Total Points - 537 points @ RM 72.00 = 38,664.00

Add 15 % profit and overhead = 5,799.60

TOTAL = 44,463.60

SAY = 45,000.00

Description :
Allow for submission of piling record

Cost:
RM 1.60 / sheet x 537 nos x 5 copies = 4,296.00

Add : 15 % Profit and Overhead = 644.40

TOTAL = 4,940.40

SAY = 5,000.00

PROGRAM PERUMAHAN RAKYAT (PPR) LORONG SELAMAT/JALAN ZAINAL ABIDIN


UNTUK JABATAN PERUMAHAN NEGARA.

Pengiraan Kadar Harga untuk item K

Description :
Drive only 400mm Diameter spun pile to all depths and all type of soil.

Operation Cost
Driving Rate @ RM 58.50 per M using hydraulic injectio = 57.20

Add : 15 % profit and overhead = 8.58

TOTAL = 65.78
SAY = 66.00
MEREKABENTUK, MEMBINA DAN MENYIAPKAN KERJA-KERJA MENAIKTARAF SUNGAI KERAYONG SEPANJANG 1.8 KM DARI MUARA SUNGAI KERAYONG
DI SUNGAI KLANG HINGGA TITIK DISCHARGE SISTEM PROJEK SMART, WILAYAH PERSEKUTUAN KUALA LUMPUR.

ANALYSIS ON CONTIGUOUS BORED PILE'S RATE

Ref. Description Supplier's/Sub-Contractor's Price SAKATA's NIKMAT QS RE Recc (27/7/05)


average + 5% + 15% RATE JASA PILING + 5% + 15%
D&B Cont (quote as D&B
rate)
A Provision for piling plant 592,875.00 622,518.75 681,806.25 1,200,000.00 1,120,000.00 566,000.00 620,000.00
B Bore 1200 mm dia. piles 215.25 226.01 247.54 238.00 240.00 217.00 238.00
C Ditto in rocks 1,456.00 1,528.80 1,674.40 1,800.00 1,800.00 1,529.00 1,675.00
D Ditto in concrete 950.00 997.50 1,092.50 1,800.00 1,900.00 998.00 1,093.00
E Supply and place Conc. G35 in 1200 m dia. piles 293.75 308.44 337.81 308.00 300.00 274.00 300.00
F 32mm Dia. HT bar 2.46 2.58 2.83 2.70 2.80 2.35 2.58
G 25mm Dia. HT bar 2.46 2.58 2.83 2.70 2.80 2.35 2.58
H 20mm Dia. HT bar 2.35 2.58
J 12mm Dia. HT bar as helical link 2.48 2.60 2.85 2.70 2.90 2.35 2.58
K Cutt of 1200 mm dia. pile head 334.00 350.70 384.10 330.00 430.00 300.00 330.00
L Pile Integrity Test to 1200 mm dia. pile 200.00 210.00 230.00 720.00 500.00 200.00 230.00
M Sonic Logging Test to 1200 mm dia. pile 2,975.00 3,123.75 3,421.25 4,200.00 4,500.00 3,124.00 3,420.00
N Bore 1000 mm dia. piles 215.00 225.75 247.25 198.00 200.00 180.00 198.00
P Ditto in rocks 875.00 918.75 1,006.25 1,500.00 1,500.00 919.00 1,006.00
Q Supply and place Conc. G35 in 1000 m dia. piles 225.00 236.25 258.75 215.00 210.00 196.00 215.00
R Cutt of 1000 mm dia. pile head 250.00 262.50 287.50 330.00 360.00 262.00 287.50
S Pile Integrity Test to 1000 mm dia. pile 200.00 210.00 230.00 600.00 500.00 210.00 230.00
T Sonic Logging Test to 1000 mm dia. pile 3,000.00 3,150.00 3,450.00 3,500.00 4,500.00 3,150.00 3,450.00
U Bore 900 mm dia. piles 193.00 202.65 221.95 178.00 185.00 162.00 178.00
V Ditto in rocks 785.00 824.25 902.75 1,350.00 1,400.00 824.00 902.75
W Supply and place Conc. G35 in 900 m dia. piles 183.00 192.15 210.45 173.00 168.00 158.00 173.00
X Cutt of 900 mm dia. pile head 225.00 236.25 258.75 297.00 320.00 236.00 258.70
Y Pile Integrity Test to 900 mm dia. pile 200.00 210.00 230.00 540.00 500.00 210.00 230.00
Z Sonic Logging Test to 900 mm dia. pile 3,000.00 3,150.00 3,450.00 3,000.00 4,500.00 2,740.00 3,000.00

727398524.xls Page 7
Mobilisation and demobilisation of piling equipment (7 team)

Utilising 7 units of Base Cranes (40 Tons) and 7 units of Service Cranes ( 50 Ton to 100 Ton ), 7 units of Boring
machine, 7 Generator Sets, 7 Welding Sets, 60 metres of Mild Steel Casing, 7 sets of Drilling
Tools and Acessories.

1 TRANSPORTATION CHARGES

(a) 21 Lowloader Trips ( 4 axle ) @ RM 2,000 per trip (average) 21 x 2,000 =

(b) 26 Cargo Trailer Trip (40 )@RM800 per Trip (average) 26 x 800 =

© Mobile Crane Charges (inclusive of 2 Nos of 45 Ton at each time for the 100 Ton Crane) =
Total Mobilization
Total Demobilisation

2 LABOUR CHARGES

- for Assembling and Dissembling


7 Teams of Piling Rig @ RM 5,000 per Rig 7 x 5,000 =

3 MAINTENANCE COSTS

Inclusive of
(a) Repair of Plant and Equipment
Allow @ RM18,000 per Rig for the whole Duration
i.e. 7 x 18,000 =

(b) Servicing including Engine Oil and additives


Hydraulic Oils, Oils and Air Filters, Bolts and Nuts,etc.
Allow @ RM 4,000 per Rig for the Whole Duration
i.e. 7 x 4,000 =

4 FABRICATION OF DRILLING TOOLS

inclusive of modifying existing Tools and Fabricating New DRILLING TOOLS


Allow @RM5,000 per Set Rig for the whole Duration
i.e. 7 x 5,000 =

5 HOLDING COST FOR PLANT AND EQUIPMENT

Each Set of USED Piling Rig is estimated to cost about RM500,000

Assuming the Current Financing Charges at a MINIMUM of 6%


per Annum Therefore the minimum Finance Charges per Piling Rig
6/100xRM500,000 = RM30,000 per year
= RM2,500 permonth
(Compared with the current RENTAL per Piling Rig @ RM40,000 permonth)

Total points = 2241 points @ 1.5 points/day = 1494


Duration (7 team =) 1494 /7 = 213.43 days = 7 months
Add erection & dismantling of temporaray staging = 2 months
Add moving within site = 1 months
Total = 10 months

The average duration for the Piling works is 10 month each of 20 months contract period .Therefore the HOLDING
COST 'for 7 sets/Teams of Piling Rig

= 7 x 10 month x RM 2,500 permonth

=
Add 15% overhead & profit =
TOTAL =
Say =

ITEM BQ 2/5/A

Bore 450mm diameter

I) Operation rate

Qty / m = 0.159 m3
Extra Holes 11% = 0.017 m3
0.176 m3 x 426.00 / m3 =
2) Add 15% profit and overhead =

Quote/m =

ITEM BQ 2/5/B

Extra over excavation in rock

I) Operation rate

Qty / m = 0.159 m3 x 4700 / m3 =

2) Add 15% profit and overhead =

Quote/m =

Notes :

Extra cavity caused by the works during the boring of holes. Extra cavity normally will haappen due to the soil
condition.When the auger operate,the soil will collapes about 11% up to the 20% depend on the soil strata.
In a very good conditions of soil, at least 11% of the soil wall will collapsed.
Tremie concrete Grade 35 in Contiguos bored pile

I) Supply and delivery (tremie mixed) = RM 172.00

ii) Wastage 18% = RM 30.96

iii) Plant and equipment = RM 10.00

iv) Tremie Method = RM 15.00


v) Labour = RM 30.00

vi) Add 15% profit and overhead

A Rate for concrete in 1200 mm diameter pile


Cost per m: RM 296.65 /m3 x 1.13 m/m3 =

B Rate for concrete in 1000 mm diameter pile


Cost per m: RM 296.65 /m3 x 0.785 m/m3 =

B Rate for concrete in 900 mm diameter pile


Cost per m: RM 296.65 /m3 x 0.636 m/m3 =

Notes:

Contractor's quotations for 1200mm RM 308.00 /M3 acceptable

Contractor's quotations for 1000mm RM 215.00 /M3 acceptable

Contractor's quotations for 900mm RM 173.00 /M3 acceptable


ITEM BQ 2/6/A

Temporary Casing

I) 12mm thick x 450mm I/D M.S. Casing

RM 250.00 m.r times uses


50

ii) Cutting to size

RM 5.50 /m x 2 x 3.14 x 0.225 m

iii) Welding Cost

RM 25.00 /m x 2 x 3.14 x 0.225 m

= RM 35.33

Say, for 1 length 12 m need 2 cutting and 1 time of welding

RM 35.33
2 times

iv) Add 15% profit and overhead

QUOTE /M = R
ITEM BQ 2/6/B

Permanent Casing

I) 12mm thick x 450mm I/D M.S. Casing

RM 250.00 m.r times uses

ii) Cutting to size

RM 5.50 /m x 2 x 3.14 x 0.225 m

iii) Welding Cost

RM 26.00 /m x 2 x 3.14 x 0.225 m


= RM 36.74

Say, for length 12m need 2 cutting and time of welding

RM 36.74
2 times

iv) add 15% Overhead + Profit

QUOTE =
ITEM BQ/2/6/C

25mm Diameter Reinforcement Bar In Bored Piles

Trial Piles

I) Supply maretial (Refer Appendices for Bill 2 & 3)

ii) Transport (15 t/trip)

a) Trailer @ RM500.00/ trip

RM 500.00 = RM 33.33
15 mt

iii) Unloading
I Nos - 20t crane @ RM 56.00 / hr
4 Labour @ RM 4.38 / hr
@ RM 60.38 / hr

Per trip = RM 60.38 / hr x 3 hr


15 mt

iv) Wastage and lapping 11%

v) a. Tie wire = RM 25.00


b. Concrete Spacer = RM 5.00
RM 30.00

vi) Plant and Equipment (Placing)

RM 60.38 x 3 hr
15

vii) Bar-bender /mt

viii) Add 15% Overhead + Profit

QUOTE / mt = R
ITEM BQ/2/6/D

10mm diameter Reinforcement Bar In Bored Piles

I) Supply material (Refer Appendices for Bill 2 & 3) =

ii) Transport ( 15t/ trip ) =

iii) Unloading =

iv) Wastage and lapping 11% =

a. Tie wire = RM 25.00


b. Concrete Spacer = RM 5.00
RM 30.00 =

vi) Plant and Equipment (Placing) =

vii) Bar - bender /mt =


viii) Add 15% Overhead + Profit =

QUOTE / mt =

Kg. =

ITEM BQ2/6/E
Strip off 450mm diameter bored piles

1. Trial Piles

a. Labour

I) 1 supervisor x RM 70 days x 2 hrs/no = RM


8

ii) 2 labour x RM 40 days x 2 hrs/no = RM


8 RM

b. Machineries

I) Oxy Cutter RM 225 x 2 hrs/no = RM


8

ii) Jack hammer RM 225 x 2 hrs/no = RM


8

iii) Crane rental RM70.00 / day (Output say 30 nos /day

Cost/no = RM 750 RM
30 nos
RM

c. Add 15% Overhead + Profit

QUOTE / No
ITEM BQ2/7/A

Load Test for 450mm diameter bored piles

I) Working Load = 1250kN (125mt)


Cycle = 2 times
Cost = RM 70 /mt x 125 mt x 2

ii) Add 15% Overhead + Profit

Quote / No

ITEM BQ2/7/B

Intergrity Test

I) Cost from specialist

ii) Add 15% Overhead + Profit

Quote / No
ITEM BQ 2/8/A

Bore 450mm diameter

Unit rate same as per Item BQ/2/5/A RM

ITEM BQ/2/8/B

Extra Over excavation in rock


I) Operation rate

Qty/m = 0.159 /m3 x 4375 /m3 = RM

ii) Add 15% Overhead & profit = RM

= RM

Quote = RM

ITEM BQ/2/8/C

Vibrated reinforced concrete Grade 35 in 450mm Dia. Piles

Unit rate same as per Item BQ/2/5/C RM


ITEM BQ /2/9/A

Temporary casing

Unit rate same as per Item BQ/2/6/A RM

ITEM BQ 2/9/B

Permanent casing

Unit rate same as per Item BQ/2/6/B RM


ITEM BQ/2/9/C

25mm Diameter Reinforcement Bar In Bored Piles

Working Piles

I) Supply material (Refer Appendices for Bill 2&3)

ii) Transport

a) Trailer @ RM500.00/ trip

RM 500 = RM 33.33
15 mt

iii) Unloading
I Nos - 20t crane @ RM 56.00 / hr
4 Labour @ RM 4.38 / hr
@ RM 60.38 / hr
Per trip = RM 60.38 / hr x 3 hr
15 mt

iv) Wastage and lapping 11%

v) a. Tie wire = RM 25.00


b. Concrete Spacer = RM 5.00
RM 30.00

vi) Plant and Equipment (Placing)

RM 60.38 x 3 hr
15

vii) Bar-bender /mt

viii) Add 15% Overhead + Profit

QUOTE / mt = R
ITEM BQ/2/9/D

10mm diameter Reinforcement Bar In Bored Piles

I) Supply material (Refer Appendices for Bill 2 & 3) =

ii) Transport =

iii) Unloading =

iv) Wastage and lapping 11% =

a. Tie wire = RM 25.00


b. Concrete Spacer = RM 5.00
RM 30.00 =

vi) Plant and Equipment (Placing) =

vii) Bar - bender /mt =

viii) Add 15% Overhead + Profit =

QUOTE / mt =

Kg. =
ITEM BQ2/6/E

Strip off 450mm diameter bored piles

1. Working Piles

a. Labour

I) 1 supervisor x RM 70 days x 2 hrs/no = RM


8 /hrs

ii) 2 labour x RM 40 days x 2 hrs/no = RM


8 /hrs RM

b. Machineries

I) Oxy Cutter RM 225 x 2 hrs/no = RM


8 hrs

ii) Jack hammer RM 225 x 2 hrs/no = RM


8 hrs

iii) Crane rental RM70.00 / day (Output say 30 nos /day

Cost/no = RM 750 RM
30 nos
RM

c. Add 15% Overhead + Profit

QUOTE / No

d Discount

ITEM BQ /2/9/A

Load Test for 450mm diameter bored piles

Unit rate same as per Item BQ/2/7/A RM


ITEM BQ 2/14/A

Allow for Moving of Piling Equipment

Cost ( for 3 Blocks )

IT Block, Student Centre and Admin Block

Total Points - 583 pts x RM 40.00 /pt =

Add 15% profit and overhead =

Total for 3 blocks =

1 block =

QUOTE =
ITEM BQ 2/14/B

Submission of piling record

Cost ( for 3 Blocks )

RM 1.60 /sheet x 583 nos x 5 copies =

Add 15% profit and overhead =

Total for 3 blocks =


Therefore,
1 block =

QUOTE =
ITEM BQ 2/15/A

Bore 450mm diameter

Unit rate same as per Item BQ/2/5/A RM

ITEM BQ 2/15/B

Extra Over excavation in rock

Unit rate same as per Item BQ T 2/5/B RM

ITEM BQ 2/8/C

Vibrated reinforced concrete Grade 35 in 450mm Dia. Piles

Unit rate same as per Item BQ/2/5/C RM


ITEM BQ 2/16/A

Temporary casing

Unit rate same as per Item BQ/2/6/A RM

ITEM BQ 2/16/C

Permanent casing

Unit rate same as per Item BQ/2/6/B RM

ITEM BQ 2/16/C

25mm Diameter Reinforcement Bar in Bored Piles

Unit rate same as per Item BQ/2/6/C RM


ITEM BQ 2/16/D

10mm Diameter Reinforment Bar in Bored Piles

Unit rate same as per Item BQ/2/6/D RM

ITEM BQ 2/16/E

Strip off 450mm Diameter Bored Piles

Unit rate same as per Item BQ/2/6/E RM


ITEM BQ 2/17/A

Load Test for 450mm diameter bored piles

Unit rate same as per Item BQ/2/7/A RM

ITEM BQ 2/17/B

Intergrity Test

Unit rate same as per Item BQ/2/7/B RM


ITEM BQ 2/18/A

Bore 450mm diameter

Unit rate same as per Item BQ/2/5/A RM

ITEM BQ 2/18/B

Extraover excavation in rock

Unit rate same as per Item BQ/2/8/B RM

ITEM BQ 2/18/C

Vibrated reinforced concrete Grade 35 in 450mm Dia. Piles

Unit rate same as per Item BQ/2/5/C RM


ITEM BQ 2/19/A

Temporary casing

Unit rate same as per Item BQ/2/6/A RM

ITEM BQ 2/19/B
Permanent casing

Unit rate same as per Item BQ/2/6/B RM

ITEM BQ 2/19/C

25mm Diameter Reinforcement Bar in Bored Piles

Unit rate same as per Item BQ/2/6/C RM

ITEM BQ 2/19/D

10mm Diameter Reinforment Bar in Bored Piles

Unit rate same as per Item BQ/2/9/D RM

ITEM BQ 2/19/E

Strip off 450mm Diameter Bored Piles

Unit rate same as per Item BQ/2/9/E RM


ITEM BQ2/20/A

Load Test for 450mm diameter bored piles

Unit rate same as per Item BQ/2/10/A RM

ITEM BQ/2/20/B

Intergrity Test

Unit rate same as per Item BQ/2/7/B RM


n ), 7 units of Boring

RM 42,000.00

RM 20,800.00

RM 8,000.00
RM 70,800.00
RM 70,800.00
141,600.00

RM 35,000.00

RM 126,000.00

RM 28,000.00

RM 35,000.00
herefore the HOLDING

RM 175,000.00

RM 540,600.00
RM 81,090.00
RM 621,690.00
RM 620,000.00

RM 74.98
RM 11.25
RM 86.22

RM 86.25

RM 747.30

RM 112.10
RM 859.40

RM 860.00

en due to the soil


n the soil strata.
RM 257.96

RM 38.69
RM 296.65

RM 335.22

RM 232.87

RM 188.67
= RM 5.00

= RM 7.77

= RM 17.67

RM 30.44

RM 4.57
35.00

QUOTE /M = RM 35.00
= RM 250.00

= RM 7.77
= RM 18.37
RM 276.14

RM 41.42

RM 317.56

QUOTE = RM 320.00
RM 1150.00

= RM 33.33

= RM 12.08

RM 1195.41

= RM 131.50

RM 1326.90

= RM 30.00

= RM 12.08

= RM 600.00
RM 1968.98

RM 295.35

RM 2264.33

QUOTE / mt = RM 2264.00
kg = RM 2.26

RM 1250.00

RM 33.33

RM 12.08

RM 1295.41

RM 142.50

RM 30.00

RM 12.08

RM 600.00

RM 2079.99
RM 312.00
RM 2391.98

RM 2392.00

RM 2.39
###

###
### RM 37.50

56

56

###

### RM 137.50

RM 175.00

RM 26.25

RM 201.25

= RM 200.00
times RM 17,500.00

= RM 2,625.00

= RM 20,125.00

Quote / No RM 20,000.00

RM 520.00

= RM 78.00

RM 598.00

Quote / No RM 600.00
86
###

###

###

###

47
###

###
= RM 1150.00

= RM 33.33
= RM 12.08

RM 1195.41

= RM 131.50

RM 1326.90

= RM 30.00

= RM 12.08

= RM 600.00
RM 1968.98

RM 295.35

RM 2264.33

QUOTE / mt = RM 2264.00

kg = RM 2.26
RM 1250.00

RM 33.33

RM 12.08

RM 1295.41

RM 142.50

RM 30.00

RM 12.08

RM 600.00

RM 2079.99

RM 312.00
RM 2391.98

RM 2392.00

RM 2.39
###

###
### RM 37.50

56

56

###
### RM 137.50

RM 175.00

RM 26.25

RM 201.25

= RM 200.00

RM 10.00

RM 190.00

###
RM 23,320.00

RM 3,498.00

RM 26,818.00

RM 8,939.33

RM 8,940.00
RM 4,664.00

RM 699.60

RM 5,363.60
RM 1,787.87

RM 1,790.00
86

###

47
###

###

2.26
2.39

###
###

###
###

###

###
###
###

2.26

2.39

###
###

###
PILING WORK (As per 24/05/2002)

A. Supply only the following diameter pile - Metre

Diameter (mm) 250 300 400 500 600

37.60 41.80 71.10 - 75.58


K.L. Ex Stock 83.00 112.00

B. Handle, transport and pitch the following piles - No

Diameter (mm) 250 300 400 500 600

10.00 12.00 14.00 - 17.00


K.L. Ex Stock 16.00

C. Drive only the following diameter pile to all depth and type of soil

Diameter (mm) 250 300 400 500 600

9.00 10.00 10.00 - 12.00


K.L. Ex Stock 12.00

Concrete Engineering Products Berhad


Lot 63, Kawasan Perindustrian Bakar Arang
0800, Sungei Petani
Kedah Darul Aman

Tel: 04 - 421 0891


Fax: 04 - 422 1263 Miss Lee

Concrete Engineering Products Berhad


Tingkat 2, Wisma IJM,
Jalan Yong Shook Lin
P.O. Box 191
46720, Petaling Jaya

Tel: 03 - 7955 8888 Encik Ridzuan

PILING WORK (As per 24/05/2002)


A. Supply only the following bored pile - Metre

Diameter (mm) 400 600 700 800 1000

37.60 41.80 71.10 - 75.58


K.L. Ex Stock 83.00 112.00

B. Handle, transport and pitch the following piles - No

Diameter (mm) 250 300 400 500 600

10.00 12.00 14.00 - 17.00


K.L. Ex Stock 16.00

C. Drive only the following diameter pile to all depth and type of soil

Diameter (mm) 250 300 400 500 600

9.00 10.00 10.00 - 12.00


K.L. Ex Stock 12.00

Concrete Engineering Products Berhad


Lot 63, Kawasan Perindustrian Bakar Arang
0800, Sungei Petani
Kedah Darul Aman

Tel: 04 - 421 0891


Fax: 04 - 422 1263 Miss Lee

Concrete Engineering Products Berhad


Tingkat 2, Wisma IJM,
Jalan Yong Shook Lin
P.O. Box 191
46720, Petaling Jaya

Tel: 03 - 7955 8888 Encik Ridzuan

PRECAST CONCRETE PILES AS PER 24/06/1999

HUME STANDARD Delivered to site Excluding UNLOADING (RM/M)


Starter Piles Extension Piles
200MM SQ JKR (CLASS1) 12M 9M 6M 12M
(4Y12)T1 0.00 0.00 33.41 0.00
250MM SQ JKR (CLASS1)
(8Y10)T1 39.43 41.80 46.30 38.49

HUME CONCRETE MARKETING Tel No: 03

Ng Boon Pion

HUME STANDARD Delivered to site Excluding UNLOADING (RM/M)


Starter Piles Extension Piles
200MM SQ JKR (CLASS1) 12M 9M 6M 12M
(4Y12)T1 0.00 0.00 0.00 0.00
250MM SQ JKR (CLASS1)
(8Y10)T1 27.83 28.62 30.16 28.74

PANEX MARKETING SDN BHD Price as per 21/05/1999


405C, Jalan Pahang
53000, Kuala Lumpur Tel No. 03-4249585, 03-4249588
Miss Chua

HUME STANDARD Delivered to site Excluding UNLOADING (RM/M)


Starter Piles Extension Piles
200MM SQ JKR (CLASS1) 12M 9M 6M 12M
(4Y12)T1 0.00 0.00 22.56 0.00
250MM SQ JKR (CLASS1)
(8Y10)T1 30.14 31.54 34.04 31.14

SEJATI CONCRETE SDN BHD Price Per 23/4/1999


37C, Jalan SS 29/23 Damansara Jaya
Petaling Jaya 47400, Selangor Tel No.: 03- 7183082
Mr Chak Hee Tong

HUME STANDARD Delivered to site Excluding UNLOADING (RM/M)


Starter Piles Extension Piles
250MM SQ JKR (CLASS1) 12M 9M 6M 12M
(4Y12)T1 36.66 38.77 43.40 37.68
300MM SQ JKR (CLASS1)
(8Y10)T1 51.78 54.64 60.17 54.09
BESPILE SDN BHD
6Th Floor West Tower Tel No. 03-732 8108
Wisma Consplant, No 2 Pauline Teng
Jalan SS 16/4, Subang Jaya
ADING (RM/M)
Extension Piles
9M 6M 3M
0.00 29.60 40.74

40.55 44.42 59.43

ADING (RM/M)
Extension Piles
9M 6M 3M
0.00 0.00 0.00

29.88 32.05 41.14

ADING (RM/M)
Extension Piles
9M 6M 3M
0.00 23.66 29.64

32.75 35.84 44.73

ADING (RM/M)
Extension Piles
9M 6M 3M
40.14 45.25 60.26

57.73 64.79 86.41


PROGRAM PERUMAHAN RAKYAT (PPR) LORONG SELAMAT/JALAN ZAINAL ABIDIN
UNTUK JABATAN PERUMAHAN NEGARA.

Description :
Allow for High Strain Pile Dynamic Test / Low Strain Pile Intergrity Test

Testing cost
Cost per point @ RM 1,700.00 = 1,700.00

Add : 15% Profit and Overhead = 255.00

TOTAL = 1,955.00

SAY = 2,000.00