Professional Documents
Culture Documents
Piling - Bur
Piling - Bur
Description :
Allow for the provision of all necessary hydraulic piling equipments, plant, tools and for their
transportation to site, handling, assembling, erecting, dismantling and removal on completion.
1 TRANSPORTATION CHARGES
(c) Mobile Crane Charges (inclusive of 2 Nos of 45 Ton at each time for the 100 Ton Crane
=
Mobilization
Demobilization
RM
2 LABOUR CHARGES
3 MAINTENANCE COSTS
Inclusive of :
TOTAL =
SAY =
5,000.00
1,400.00
4,000.00
10,400.00
10,400.00
20,800.00
7,000.00
5,000.00
10,563.00
43,363.00
6,504.45
49,867.45
50,000.00
PROGRAM PERUMAHAN RAKYAT (PPR) LORONG SELAMAT/JALAN ZAINAL ABIDIN
UNTUK JABATAN PERUMAHAN NEGARA.
Description :
Allow for moving and handling piling equipments, plants, tools and ancillaries as often and
whenever necessary for the whole operation including any excavation and piling required
for movement of the piling equipment and plant and including idle time
TOTAL = 44,463.60
SAY = 45,000.00
Description :
Allow for submission of piling record
Cost:
RM 1.60 / sheet x 537 nos x 5 copies = 4,296.00
TOTAL = 4,940.40
SAY = 5,000.00
Description :
Drive only 400mm Diameter spun pile to all depths and all type of soil.
Operation Cost
Driving Rate @ RM 58.50 per M using hydraulic injectio = 57.20
TOTAL = 65.78
SAY = 66.00
MEREKABENTUK, MEMBINA DAN MENYIAPKAN KERJA-KERJA MENAIKTARAF SUNGAI KERAYONG SEPANJANG 1.8 KM DARI MUARA SUNGAI KERAYONG
DI SUNGAI KLANG HINGGA TITIK DISCHARGE SISTEM PROJEK SMART, WILAYAH PERSEKUTUAN KUALA LUMPUR.
727398524.xls Page 7
Mobilisation and demobilisation of piling equipment (7 team)
Utilising 7 units of Base Cranes (40 Tons) and 7 units of Service Cranes ( 50 Ton to 100 Ton ), 7 units of Boring
machine, 7 Generator Sets, 7 Welding Sets, 60 metres of Mild Steel Casing, 7 sets of Drilling
Tools and Acessories.
1 TRANSPORTATION CHARGES
(b) 26 Cargo Trailer Trip (40 )@RM800 per Trip (average) 26 x 800 =
© Mobile Crane Charges (inclusive of 2 Nos of 45 Ton at each time for the 100 Ton Crane) =
Total Mobilization
Total Demobilisation
2 LABOUR CHARGES
3 MAINTENANCE COSTS
Inclusive of
(a) Repair of Plant and Equipment
Allow @ RM18,000 per Rig for the whole Duration
i.e. 7 x 18,000 =
The average duration for the Piling works is 10 month each of 20 months contract period .Therefore the HOLDING
COST 'for 7 sets/Teams of Piling Rig
=
Add 15% overhead & profit =
TOTAL =
Say =
ITEM BQ 2/5/A
I) Operation rate
Qty / m = 0.159 m3
Extra Holes 11% = 0.017 m3
0.176 m3 x 426.00 / m3 =
2) Add 15% profit and overhead =
Quote/m =
ITEM BQ 2/5/B
I) Operation rate
Quote/m =
Notes :
Extra cavity caused by the works during the boring of holes. Extra cavity normally will haappen due to the soil
condition.When the auger operate,the soil will collapes about 11% up to the 20% depend on the soil strata.
In a very good conditions of soil, at least 11% of the soil wall will collapsed.
Tremie concrete Grade 35 in Contiguos bored pile
Notes:
Temporary Casing
= RM 35.33
RM 35.33
2 times
QUOTE /M = R
ITEM BQ 2/6/B
Permanent Casing
RM 36.74
2 times
QUOTE =
ITEM BQ/2/6/C
Trial Piles
RM 500.00 = RM 33.33
15 mt
iii) Unloading
I Nos - 20t crane @ RM 56.00 / hr
4 Labour @ RM 4.38 / hr
@ RM 60.38 / hr
RM 60.38 x 3 hr
15
QUOTE / mt = R
ITEM BQ/2/6/D
iii) Unloading =
QUOTE / mt =
Kg. =
ITEM BQ2/6/E
Strip off 450mm diameter bored piles
1. Trial Piles
a. Labour
b. Machineries
Cost/no = RM 750 RM
30 nos
RM
QUOTE / No
ITEM BQ2/7/A
Quote / No
ITEM BQ2/7/B
Intergrity Test
Quote / No
ITEM BQ 2/8/A
ITEM BQ/2/8/B
= RM
Quote = RM
ITEM BQ/2/8/C
Temporary casing
ITEM BQ 2/9/B
Permanent casing
Working Piles
ii) Transport
RM 500 = RM 33.33
15 mt
iii) Unloading
I Nos - 20t crane @ RM 56.00 / hr
4 Labour @ RM 4.38 / hr
@ RM 60.38 / hr
Per trip = RM 60.38 / hr x 3 hr
15 mt
RM 60.38 x 3 hr
15
QUOTE / mt = R
ITEM BQ/2/9/D
ii) Transport =
iii) Unloading =
QUOTE / mt =
Kg. =
ITEM BQ2/6/E
1. Working Piles
a. Labour
b. Machineries
Cost/no = RM 750 RM
30 nos
RM
QUOTE / No
d Discount
ITEM BQ /2/9/A
1 block =
QUOTE =
ITEM BQ 2/14/B
QUOTE =
ITEM BQ 2/15/A
ITEM BQ 2/15/B
ITEM BQ 2/8/C
Temporary casing
ITEM BQ 2/16/C
Permanent casing
ITEM BQ 2/16/C
ITEM BQ 2/16/E
ITEM BQ 2/17/B
Intergrity Test
ITEM BQ 2/18/B
ITEM BQ 2/18/C
Temporary casing
ITEM BQ 2/19/B
Permanent casing
ITEM BQ 2/19/C
ITEM BQ 2/19/D
ITEM BQ 2/19/E
ITEM BQ/2/20/B
Intergrity Test
RM 42,000.00
RM 20,800.00
RM 8,000.00
RM 70,800.00
RM 70,800.00
141,600.00
RM 35,000.00
RM 126,000.00
RM 28,000.00
RM 35,000.00
herefore the HOLDING
RM 175,000.00
RM 540,600.00
RM 81,090.00
RM 621,690.00
RM 620,000.00
RM 74.98
RM 11.25
RM 86.22
RM 86.25
RM 747.30
RM 112.10
RM 859.40
RM 860.00
RM 38.69
RM 296.65
RM 335.22
RM 232.87
RM 188.67
= RM 5.00
= RM 7.77
= RM 17.67
RM 30.44
RM 4.57
35.00
QUOTE /M = RM 35.00
= RM 250.00
= RM 7.77
= RM 18.37
RM 276.14
RM 41.42
RM 317.56
QUOTE = RM 320.00
RM 1150.00
= RM 33.33
= RM 12.08
RM 1195.41
= RM 131.50
RM 1326.90
= RM 30.00
= RM 12.08
= RM 600.00
RM 1968.98
RM 295.35
RM 2264.33
QUOTE / mt = RM 2264.00
kg = RM 2.26
RM 1250.00
RM 33.33
RM 12.08
RM 1295.41
RM 142.50
RM 30.00
RM 12.08
RM 600.00
RM 2079.99
RM 312.00
RM 2391.98
RM 2392.00
RM 2.39
###
###
### RM 37.50
56
56
###
### RM 137.50
RM 175.00
RM 26.25
RM 201.25
= RM 200.00
times RM 17,500.00
= RM 2,625.00
= RM 20,125.00
Quote / No RM 20,000.00
RM 520.00
= RM 78.00
RM 598.00
Quote / No RM 600.00
86
###
###
###
###
47
###
###
= RM 1150.00
= RM 33.33
= RM 12.08
RM 1195.41
= RM 131.50
RM 1326.90
= RM 30.00
= RM 12.08
= RM 600.00
RM 1968.98
RM 295.35
RM 2264.33
QUOTE / mt = RM 2264.00
kg = RM 2.26
RM 1250.00
RM 33.33
RM 12.08
RM 1295.41
RM 142.50
RM 30.00
RM 12.08
RM 600.00
RM 2079.99
RM 312.00
RM 2391.98
RM 2392.00
RM 2.39
###
###
### RM 37.50
56
56
###
### RM 137.50
RM 175.00
RM 26.25
RM 201.25
= RM 200.00
RM 10.00
RM 190.00
###
RM 23,320.00
RM 3,498.00
RM 26,818.00
RM 8,939.33
RM 8,940.00
RM 4,664.00
RM 699.60
RM 5,363.60
RM 1,787.87
RM 1,790.00
86
###
47
###
###
2.26
2.39
###
###
###
###
###
###
###
###
2.26
2.39
###
###
###
PILING WORK (As per 24/05/2002)
C. Drive only the following diameter pile to all depth and type of soil
C. Drive only the following diameter pile to all depth and type of soil
Ng Boon Pion
ADING (RM/M)
Extension Piles
9M 6M 3M
0.00 0.00 0.00
ADING (RM/M)
Extension Piles
9M 6M 3M
0.00 23.66 29.64
ADING (RM/M)
Extension Piles
9M 6M 3M
40.14 45.25 60.26
Description :
Allow for High Strain Pile Dynamic Test / Low Strain Pile Intergrity Test
Testing cost
Cost per point @ RM 1,700.00 = 1,700.00
TOTAL = 1,955.00
SAY = 2,000.00