BSBPMG537 - Assessment Task 2 - Project Portfolio
BSBPMG537 - Assessment Task 2 - Project Portfolio
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 0 of 42
Qualification Details:
Training Package Code & Title: RII – Resources and Infrastructure Industry Training Package
Qualification National Code & RII50520 – Diploma of Civil Construction Design
Title:
Unit National Code & Title: BSBPMG537 - Manage Project Procurement
Assessment Title: Assessment Task 2 - Project Portfolio
Student Details:
Assessment plan
The student must be assessed as satisfactory in the following tasks to demonstrate competence in
various ways.
Evidence number / Assessment method / Type of Detail/Task Instructions/Description
Task number evidence / Task name
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 1 of 42
Purpose of Assessment:
The purpose of this assessment is to evaluate the individual's capabilities in effectively managing
project procurement. It includes
Evaluate the candidate's ability to identify and articulate procurement requirements.
Assess the development of a comprehensive procurement management plan.
Scrutinize the candidate's proficiency in executing procurement and contracting activities.
Ensure adherence to established processes in the procurement and contracting phases.
Assess the candidate's demonstration of a deep understanding of project objectives, needs,
and budget constraints.
Evaluate the candidate's capacity to monitor project activities throughout the entire life
cycle.
Assess the promptness in addressing issues that may impact project objectives.
Scrutinize the candidate's ability to maintain accurate procurement records in accordance
with organizational requirements.
You must respond to all questions. Be concise, to the point and write answers within the word
limit given to each question. Do not provide irrelevant information. Remember, quantity is not
quality.
You may handwrite or use a computer to answer the questions.
You must complete the task independently and write your responses in your own words.
Do not start answering questions without understanding what is required. Read the questions
carefully and critically analyze them for a few seconds; this will help you to identify what
information is needed in the answer.
Your answers must demonstrate an understanding and application of the relevant concepts and
critical thinking.
Use non-discriminatory language. The language used should not devalue, demean, or exclude
individuals or groups based on attributes such as gender, disability, culture, race, religion, sexual
preference or age. Gender-inclusive language should be used.
When you quote, paraphrase, summarize or copy information from other sources to write your
answers or research your work, always acknowledge the source.
Where a student’s answers are deemed not satisfactory after the first attempt, a resubmission
attempt will be allowed
No marks or grades are allocated for this assessment task. The outcome of the task will be
Satisfactory or Not Satisfactory.
As you complete this assessment task, you are predominately demonstrating your written skills
and knowledge to your trainer/assessor.
The student may speak to their trainer/assessor if they have any difficulty in completing this task
and require reasonable adjustments.
For more information, please refer to the Training Organization’s Student Handbook.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 2 of 42
Student Declaration:
I have read and understood the information in the Unit Requirements before commencing
this Student Pack.
I understand the consequences of plagiarism and that a false declaration is a form of
malpractice.
I declare that the answers I have provided are my work. Where I have accessed information
from other sources, I have provided references and/or links to my sources.
I have kept a copy of all relevant notes and reference material that I used as part of my
submission.
I have provided references for all sources where the information is not my own. I
understand how the assessment is structured. I accept that the work I submit may be
subject to verification to establish that it is my own.
I understand that if I disagree with the assessment outcome, I can appeal the assessment
process, and either re-submit additional evidence undertake gap training, or have my
submission re-assessed.
All appeal options have been explained to me.
For assessment, I give the trainer/assessor permission to:
Reproduce this assessment and provide a copy to another member of staff; and
Take steps to authenticate the assessment, including communicating a copy to a plagiarism-
checking service (which may retain a copy of the assessment on its database for future
plagiarism checking).
Student Signature:
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 3 of 42
Assessment Task 2: Project Portfolio
a suitable place to complete activities that replicates a business environment including a meeting space and
computer and internet access
Grow Information Management System with bids (if using the case study)
policies and procedures that address procurement, record keeping and probity already developed (if basing
the assessment on own business)
bids or responses from at least three potential suppliers (if basing the assessment on own business)
procurement records to review the final project procurement outcomes (if basing the assessment on own
business).
review the advice to students regarding responding to written tasks in the Business Works Student User
Guide
comply with the due date for assessment which your assessor will provide
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 4 of 42
Activities
This project requires you to determine and manage project procurement on two
separate occasions. You may manage two procurement processes across two
different projects or you may manage two procurement processes for one project.
You can do this for real project(s) at your workplace, for project(s) associated with
a start-up business you are working on yourself or you can use the Simulation Pack
provided.
Vocational education and training is all about gaining and developing practical
skills that are industry relevant and that can help you to succeed in your chosen
career. For this reason, basing your project on real relationships with classmates
or work colleagues will mean that you are applying your knowledge and skills in a
relevant, practical and meaningful way!
If you use your own business or workplace, you will complete this assessment in a
role that assumes responsibility for managing and leading projects. Make sure the
business has policies and procedures that address procurement, record keeping
and probity already developed. As part of the project, you will interact with
internal stakeholders (senior managers) and a supplier who must be willing to
participate in interactions viewed in person by the assessor or on video-
recordings. Furthermore, you will be required to obtain actual bids or responses
from at least three potential suppliers. As you monitor and assess the
procurement processes, your procurements should have at least one challenge
impacting the progress of the procurement that requires a change to the timeline
and terms and condition of supply. You should also have procurement records
(e.g. invoices) available to review the final project procurement outcomes. Finally,
you must obtain feedback from internal stakeholders and suppliers on the
procurement process. Speak to your assessor to get approval if you want to base
this on your own business.
If you are basing this assessment on the case study business, read through the
Simulation Pack in preparation for this assessment. All the information needed to
complete this assessment is contained in the Simulation Pack.
You will be collecting evidence for this unit in a Project Portfolio. The steps you
need to take are outlined below. Before you begin, complete page 4 of your
Project Portfolio. You must describe the organisation you are basing this
assessment on and provide a short description of your chosen project(s) and two
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 5 of 42
procurement processes.
i Start working on Section 1 of your project portfolio. Steps 2 and 3 form part of
Section 1.
If you are basing this assessment on Grow Management Consultants, further
information to complete the next steps is available in the Simulation Pack.
If you are using your own business, make sure you have the policies and
procedures for procurement and record keeping ready.
2. For each procurement you are managing, identify project procurement requirements.
First make sure you are familiar with any policies, procedures, protocols and
templates that address project procurement, record keeping and probity.
Finally, identify the project objectives, budget and any other specific procurement
requirements (such as timeframes, contracting activities and legal requirements).
3. For each procurement you are managing, agree on the procurement requirements with relevant
stakeholder(s) to establish a Procurement Management Plan.
Before you begin, create a draft Procurement Management Plan to discuss with
the stakeholder(s).
i You may use any procurement plan template relevant to your own business or
may use the Procurement Management Plan Template (in the Simulation Pack) to
help guide your discussions with the stakeholders.
processes to deal with suppliers and vendors (including selection criteria and
selection processes).
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 6 of 42
Meet with at least one relevant stakeholder to agree on the details in your draft
Procurement Management Plan. The stakeholders you meet with will be those
you’ve previously identified that participate in decision-making.
i Meet separately for each procurement process you are managing. You may meet
face-to-face, via video-conferencing or on a telephone call. The meetings may take
place one after the other, or you may meet at two separate times. This will
depend on the nature of your project(s) and further instruction from your
assessor.
Each meeting should take 15 minutes. This will either be attended in person by
your assessor or they will attend online. If you are in the workplace, you may like
to video record the session for your assessor to watch later (attach proof to
Section 1 of your Project Portfolio). Your assessor can provide you with more
details at this step. Make sure you follow the instructions above and meet the
timeframes allocated.
You must provide proof of how you’ve done this (e.g. screen shots).
If you are using the case study, an Information Management folder structure has
been provided. Use this to save the documents.
i Assume that your organisation requires you to request approval in writing via
email to an approved decision-maker.
Your email should introduce and summarise the contents of the Procurement
Management Plan and request approval to move forward with the procurement
(as outlined in the plan).
i Separate emails are required for each procurement you are managing.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 7 of 42
You may assume that the Procurement Management Plan is attached to the email.
You are required to attach certain documents as part of your evidence – review
the documents you need to attach as outlined in Section 1 of the Project Portfolio.
i Start working on Section 2 of your project portfolio. Steps 4 and 5 form part of
Section 2.
If you are basing this assessment on the case study, further information to
complete the next steps is available in the Simulation Pack.
If you are using your own business, you will be required to obtain bids or
responses from suppliers to complete step 5.
4. For each procurement you are managing, communicate with potential suppliers to obtain bids.
Identify at least three potential suppliers who are capable of fulfilling the
procurement requirements. Obtain information (e.g. on their website) about each
of the suppliers/vendors and summarise the information.
i Whether you are using your own business or the case study business, identify and
research three real potential suppliers (e.g. using an internet search).
i Separate emails are required for each procurement you are managing.
5. For each procurement you are managing, select a preferred supplier and negotiate the terms of supply.
i If you are using the case study, assume that the suppliers you identified are those
in the Simulation Pack and use the bid information provided in the provided
Information Management System.
If you are basing this assessment on your own business, you must have obtained
at least three responses/bids from potential suppliers.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 8 of 42
First evaluate each supplier’s bid (or response) against the selection criteria (in
your Procurement Management Plan) and any legal requirements (identified in
Section 1 of your Project Portfolio).
Select the supplier who will best meet the project requirements and then
establish a draft Terms and Conditions of Supply document.
i You may use the Terms and Conditions of Supply template provided in the
Simulation Pack or any other supply contract relevant to your organisation.
Meet with the preferred supplier to negotiate and agree on the terms and
conditions of supply. During your discussion, also arrange for regular meetings
with the supplier to track progress.
i Meet separately for each procurement process you are managing. You may meet
face-to-face, via video-conferencing or telephone call. The meetings may take
place one after the other, or you may meet at two separate times. This will
depend on the nature of your project(s) and further instruction from your
assessor.
Have your draft Terms and Condition of Supply document ready to use at the
meeting (and make sure the supplier has a copy too). Each meeting should take 15
minutes. This will either be attended in person by your assessor or they will attend
online. If you are in the workplace, you may like to video record the session for
your assessor to watch later (attach proof to Section 2 of your Project Portfolio).
Your assessor can provide you with more details at this step. Make sure you follow
the instructions above and meet the timeframes allocated.
https://www.skillsyouneed.com/ips/negotiation.html
https://blog.blackswanltd.com/the-edge/how-are-negotiation-and-interpersonal-
communication-related
Make any amendments to the Terms and condition of supply to reflect the
negotiation outcomes and obtain the relevant signatures on the contract.
Follow your organisation’s policies and procedures to save the agreed and signed
terms and conditions.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 9 of 42
i If you are using the case study business, ask your assessor to sign the contract in
the role of both CFO and Supplier.
Draft an email to one unsuccessful supplier to inform them that their bid has not
been successful. In your email, include the reasons for their unsuccessful bid.
You are required to attach certain documents as part of your evidence – review
the documents you need to attach as outlined in Section 2 of the Project Portfolio.
Start working on Section 3 of your project portfolio. Steps 6,7 and 8 form part of
Section 3.
If you are basing this assessment on the case study, further information to
complete the next steps is available in the Simulation Pack. Assume that IT Biz
Solutions has been contracted to provide the services for both projects.
If you are basing this assessment on your own business or workplace, your
procurements should have at least one challenge impacting the progress of the
procurement that requires a change to the timeline and terms and condition of
supply (step 6).
You should also have procurement records (e.g. invoices) available to review the
final project procurement outcomes (step 7).
6. For both procurements you are managing, monitor procurement progress and manage any variations.
Assume that a period of time has passed and the procurement process has started
but not yet been completed.
i Follow your organisation’s record keeping policy and procedures to maintain the
document (e.g. change the version number).
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 10 of 42
Draft an email to request approval for the new terms and Conditions of Supply
from a relevant internal stakeholder (e.g. senior manager). In your email, describe
the challenges and explain the changes you’ve made to the initial Terms and
Condition of Supply document. Request that they acknowledge their agreement
with the changes.
i Assume that you have obtained approval from the internal stakeholders and
agreement from the supplier.
i For the case study, you are required to document the work role and
responsibilities for the administration assistants for one procurement process and
create a spreadsheet of consultant’s details for the other procurement process.
Assume that a further period of time has passed, and that the procurement
process is now complete.
First, use procurement records to review the procurement outcomes and confirm
that the deliverables have met the Terms and Conditions of Supply agreement.
Then, seek feedback from the internal and external stakeholder’s you’ve dealt
with during the procurement process (i.e. senior management and the suppliers)
on their experience of the procurement processes and procedures. Do this by
creating a survey to send to all stakeholders (either using an online tool, or paper-
based).
Do you think that variations and changes to the procurement process were
handled professionally and efficiently?
Reflect on the procurement process to identify any lesson learned during the
process.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 11 of 42
Document lessons learned and recommended improvements for future projects.
i If you are basing this assessment on our own business, and are unable to receive
the actual feedback from the stakeholders via your survey, you may use the
feedback provided in the Simulation Pack to do this step.
Write a procurement closure report that includes the stakeholder feedback and
your own personal reflection on the procurement processes. Include:
i You may use any template relevant to your organisation or you may use the
Procurement Closure Report Template provided in the Simulation Pack.
Make sure you have completed all sections of your Project Portfolio, answered all
questions, provided enough detail as indicated and proofread for spelling and
grammar as necessary.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 12 of 42
Section 1: Determine and Agree on Procurement Requirements
Review any relevant Project management policy and procedures: In this policy and
organisational policies, procedures, the procurement process is discussed. A procurement
procedures, protocols and management plan is developed and shared with the shareholder
templates that address: when procurement issue is raised. Every project is to be recorded
and stored with a pre-set name and a project folder is to be
procurement
established for each project.
processes
record keeping
probity.
Highlight any appropriate Code of Ethics: In the code of ethics, it is shows that the company
information and make notes put an importance in probity in procurement. Upholding the highest
on the policies and standards of probity and integrity enables organisations to
procedures as you process safeguard procurement activities to ensure those activities and
and summarise the processes are robust and can withstand scrutiny
requirements.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 13 of 42
Role and responsibilities My role in this procurement process is the operations manager of
Grow Management Consultant company.
What role are you assuming
for this procurement process?
What are your responsibilities My responsibility for this procurement process is to oversee all
for this procurement process? procurement activities as the Project Manager. I have to approach
the suppliers and contract the supplier to help improve the website
and the electronic communication process.
Stakeholders.
Identify the stakeholders The stakeholders associated with the procurement process are the
associated with this senior managers, CEO, finance manager, legal manager, suppliers
procurement process. and administrative assistants.
Which stakeholders will The CEO, senior manager, finance manager and the legal manager
participate in procurement will participate in the procurement decision-making processes.
decision-making processes?
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 14 of 42
Specific procurement
requirements
What are the cost parameters The cost parameters for this procurement process are $12000 for
for this procurement process? the upgrade of the website
The contracting activities for the upgraded website that are required
Which contracting activities are:
are required?
• at least nine pages
• a data base library for clients
• the ability to ask for a quote for services
Are there any specific legal • the ability to book in to seminars
requirements? • a shopping carts
Are there any other specific There are no specific legal requirements for this procurement
requirements for this process. The specific requirements for this procurement are:
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 15 of 42
Procurement Management
Plan
Procurement approval Thank you for your involvement in the Web-design project. It’s an
important part of our strategy and we’d like the website to be user-
Include your draft email to
friendly, comprehensive and suitable for access via multiple devices
this section of the portfolio.
and operating systems. It should include:
• a shopping cart.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 16 of 42
selected based on the following three factors:
The CFO has approved a budget of $12000 for the upgrade. As you
plan, consider the two Administration Assistants who will need to be
trained to maintain the website once it has been set up.
Kind regards
CEO.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 17 of 42
PROCUREMENT PROCESS 2: Include procurement description
Role and responsibilities My role in this procurement process is the operations manager of
Grow Management Consultant company.
What role are you assuming
for this procurement process?
What are your responsibilities My responsibility for this procurement process is to oversee all
for this procurement process? procurement activities as the Project Manager. I have to approach
the suppliers and contract the supplier to help improve the website
and the electronic communication process.
Stakeholders. The stakeholders associated with the procurement process are the
senior managers, CEO, finance manager, legal manager, suppliers
Identify the stakeholders
and administrative assistants.
associated with this
procurement process.
Which stakeholders will The CEO, senior manager, finance manager and the legal manager
participate in procurement will participate in the procurement decision-making processes.
decision-making processes?
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 18 of 42
Project objectives Improve electronic communication processes to increase the
Identify the project objectives, efficiency of the company's electronic communication and increase
needs and budget (at least the business relationship with clients.
one).
What are the cost parameters The cost parameters for this procurement process are $5000 for the
for this procurement process? upgrade of the website.
The contracting activities for the upgraded website that are required
Which contracting activities are:
are required?
Ensure that all communication is carried out in a consistent,
professional manner.
Be user friendly.
Are there any specific legal There are no specific legal requirements for this procurement
requirements? process.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 19 of 42
Procurement Management
Plan
Procurement approval
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 20 of 42
ensure that all communication is carried out in a consistent,
professional manner
be user friendly.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 21 of 42
Section 2: Initiate Procurement
Identify at least three 1. ICT World: ICT world specialise in website. They can create and
potential suppliers. host websites that are both beautiful and functional. ICT World
would train selected staff in website maintenance. Some of this
would be carried out prior to roll-out, and the rest in their
workplace when the new website is up and running.
Summarise information about 2. IT Biz Solutions: Website development is an area in which IT Bis
each supplier. Solutions excels. IT Biz Solutions are able to show clients how to
collaboratively transform information technology into business
advantages. IT Biz Solutions provide clients with a range of
professional services.
3. Online Business Partners: Online Business Partners develops
websites that become entities. Online Business Partners have
successfully created websites for hundreds of bids.
Bids Email:
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 22 of 42
Preferred supplier ICT World: The approximate cost for upgrading the website is
$10,000 and staff training $1,600 per 20 hours. The website
How do the suppliers development will take approximately three months.
compare using the selection
IT Biz Solutions: The approximate cost for upgrading the website is
criteria?
$10,000 and staff training $1,500 per 20 hours. The website
development will take approximately three months.
Does each bid meet legal Each bid meets the legal requirements.
requirements?
Terms and condition of The supplier meeting is viewed in person by the assessor.
supply
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 23 of 42
Unsuccessful suppliers
Dear suppliers,
Good morning, I want to inform you that your bid for the procurement
has not been chosen by the company. I am sorry and hope that we can
work together in the future.
Thank you,
Best regard,
Operations Manager.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 24 of 42
PROCUREMENT PROCESS 2: Include procurement description
Identify at least three 1. ICT World: ICT world specialise in website. They can create and
potential suppliers. host websites that are both beautiful and functional. ICT World
would train selected staff in website maintenance. Some of this
would be carried out prior to roll-out, and the rest in their workplace
when the new website is up and running.
Summarise information about 2. IT Biz Solutions: Website development is an area in which IT Bis
each supplier. Solutions excels. IT Biz Solutions are able to show clients how to
collaboratively transform information technology into business
advantages. IT Biz Solutions provide clients with a range of
professional services.
Bids
Includes the specifications of Good morning, I want to inform you that Grow Management
the procurement and a Consultant is looking for a company to help upgrade and developed
description of the selection the electronic communication process. The requirements for the
criteria and selection process electronic communication process are: ensure that all
communication is carried out in a consistent, professional manner
requests that the supplier
and be user friendly. The budget available is $5,000.
submits a bid within a specific
timeframe Best regard,
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 25 of 42
confirms that they Operations Manager.
understand the project
objectives?
Preferred supplier ICT World: The approximate cost for improving electronic
communication process is $1,500 for set up and managing email
How do the suppliers
service is $2,500 for 1 year. The email service will be managed for six
compare using the selection
weeks.
criteria?
IT Biz Solutions: The approximate cost for improving electronic
communication process is $1,600 for set up and managing email
service is $2,400 for 1 year. The email service will be managed for six
weeks.
Does each bid meet legal Each bid meets the legal requirements.
requirements?
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 26 of 42
Terms and condition of The supplier meeting is viewed in person by the assessor.
supply
Dear suppliers,
Good morning, I want to inform you that your bid for the
procurement has not been chosen by the company. I am sorry and
hope that we can work together in the future.
Best Regards,
Operations Manager.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 27 of 42
Agreed and signed Terms and Condition of Supply
☐
document (procurement 2)
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 28 of 42
Section 3: Monitor and Review procurement
Assume that a period of time has passed and the procurement process has started but not yet been
completed.
Monitor procurement
Provide a status update for The procurement is progressing as plan in the Terms and Conditions of
the procurement’s progress. Supply agreement. The website is progressing well. The home page has
received approval, and the current focus is on collating the information
Arrange regular meetings
and images that are needed for the rest of the website.
with supplier to track
progress
How is the procurement The company management appointed several Administration Assistants
progressing in comparison to to assist in collecting the information that we need, and they have done
the Terms and Conditions of this very well. They are a busy team, but well organised.
Supply agreement?
Review procurement The challenge for the project is that there are too many duties and
progress unclear roles and responsibilities for the administrative assistant. They
requested that their roles and responsibilities be formally and clearly
Identify at least one
documented to include only work-related duties.
challenge.
Provide extra rewards for the extra work (increase their salary or
give them a bonus if they finished the training perfectly).
Yes, there are some changes in the variations required to the Terms and
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 29 of 42
Are any variations required to Conditions and Supply agreement.
the Terms and Conditions and
Supply agreement (identify at
least one change to the
The senior management team met and agreed that training may be
timeline requirements)?
deferred to be completed within two months after the website has been
Include the updated Terms delivered, with IT Biz Solutions maintaining the website in those two
and Conditions of Supply. months (free of charge).
Assume that a further period of time has passed, and that the procurement process is now complete.
Procurement outcomes
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 30 of 42
Which procurement records The procurement records that I have used to review procurement
have you used to review outcomes is invoice.
procurement outcomes?
Grow Management Consultants' new website has been online for three
months, and it has been a great success. The same design has been
applied to the company’s emails, and the new email and
Summarise the available
communication system is functioning very well. All staff are using the
information and determine
new system without assistance.
effectiveness of procurement
processes and procedures
Include the records to review Records to review outcomes to this section of the portfolio (Invoice)
outcomes to this section of
the portfolio (e.g. invoices,
project schedules).
Seek feedback
Page 31 of 42
related to communication responses to my thanks
procurement emails
sufficient and
clear?
Respond to feedback
Reflection
What lessons did you learn in Lessons learned in the procurement process:
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 32 of 42
the procurement process (at 1/ Analysing key performance indicator.
least two)?
2/ Transparency is important.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 33 of 42
(procurement 1)
Survey (procurement 1) ☐
Assume that a period of time has passed and the procurement process has started but not yet been
completed.
Monitor procurement The procurement is progressing as plan in the Terms and Conditions of
Supply agreement. The website is progressing well. The home page has
Provide a status update for
received approval, and the current focus is on collating the information
the procurement’s progress.
and images that are needed for the rest of the website.
Arrange regular meetings
with supplier to track
progress
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 34 of 42
vendor requesting a status
update to this section of the
portfolio.
Review procurement The challenge for the project is that there are too many duties and
progress unclear roles and responsibilities for the administrative assistant. They
requested that their roles and responsibilities be formally and clearly
Identify at least one
documented to include only work-related duties.
challenge.
Provide extra rewards for the extra work (increase their salary or
give them a bonus if they finished the training perfectly).
The senior management team met and agreed that training may be
deferred to be completed within two months after the website has been
delivered, with IT Biz Solutions maintaining the website in those two
Include the updated Terms months (free of charge).
and Conditions of Supply.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 35 of 42
changes.
Assume that a further period of time has passed, and that the procurement process is now complete.
Procurement outcomes
Which procurement records The same design has been applied to the company’s emails, and the
new email and communication system is functioning very well. All staff
have you used to review
are using the new system without assistance.
procurement outcomes?
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 36 of 42
Include the records to review
outcomes to this section of
the portfolio (e.g. invoices,
project schedules).
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 37 of 42
procurement hardware
process were update.
handled
professionally
and efficiently?
Respond to feedback
Reflection
What lessons did you learn in There are a lot of steps in making a procurement to happen legally
the procurement process (at in the company.
least two)? Lack of detail in procurement plan can result in confusion of how
the processes should be done.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 38 of 42
What would you do Preparing procurement templates and steps that to be taken in
differently next time (at least advance.
two improvement Learn and discuss more regarding the related procurement to get
suggestions)? more information.
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 39 of 42
Survey (procurement 2) ☐
BSBPMG537 - Manage Project Procurement – Assessment Task 2 - Project Portfolio | V 2.0 | 2023
Page 40 of 42
Assessment Result:
Trainer/Assessor Name:
Assessment Decision:
Satisfactory Not Yet Satisfactory
Trainer/Assessor Signature
Date