Time Schedule Rencana Perkuatan Jembatan Bunut
Time Schedule Rencana Perkuatan Jembatan Bunut
WEEKS
NO. JOB DESCRIPTION UNIT VOLUME BOBOT
1 2 3 4 5 6 7 8
I PREPARATION WORKS
1 Provision of keet directors, warehouse ang supporting facilities ls 1.00 0.0115 0.0115
2 Mobilitation and Demobilitation Ls 1.00 0.0131 0.0131
3 Safety Equipment Month 2.00 0.0220 0.0028 0.0028 0.0028 0.0028 0.0028 0.0028 0.0028 0.0028
4 Security Month 2.00 0.0105 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013
5 Worker shelter M2 48.00 0.0063 0.0063
6 Equipment (Mobile Crane 3T, Temporary simple pontoon) Month 2.00 0.0656 0.0082 0.0082 0.0082 0.0082 0.0082 0.0082 0.0082 0.0082
II MATERIAL
1 Piling Steel Pipe dia. 8" Thickness 6mm M 528 0.2078 0.1039 0.1039
2 H-Beam 400x400x13x21 Kg 5,676 0.0670 0.0335 0.0335
3 WF-Beam 588x300x12x20 Kg 6,378 0.0753 0.0377 0.0377
4 H-Beam 250x250x9x14 Kg 4,036 0.0477 0.0238 0.0238
5 Bracing Steel Pipe 8" thickness 5mm Kg 1,808 0.0213 0.0213
6 Steel Plate 15 mm for Stiffeners Kg 3,580 0.0423 0.0211 0.0211
7 Elastomer tebal 10 cm ukr. 40cm x 50 cm Set 16 0.0735 0.0735
8 Concrete fc'30 (include casting) m3 4.61 0.0076 0.0076
9 Rebar D25 (include instalation) Kg 160.30 0.0032 0.0016 0.0016
10 Formwork (include instalation) m2 27.46 0.0009 0.0005 0.0005
V PERMIT
1 Coordination with BBPJN V Palembang ls 1.00 0.0131 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016
2 Coordination with Department of River dan Department of Environment (BBWS dan Dinas Lingkungan Hidup) ls 1.00 0.0131 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016
3 Coordination with Department of Transportation (Dinas Perhubungan Pemkot) ls 1.00 0.0131 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016
4 Coordination with Police Region of Prabumulih City ls 1.00 0.0131 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016
Weekly Plan 0.2245 0.1956 0.1259 0.0975 0.0940 0.0770 0.1008 0.0845
Accumulation Of Weekly Plan 0.2245 0.4201 0.5461 0.6436 0.7376 0.8146 0.9155 1.0000