Drywall Work Installatin Method Statement

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 10

METHOD OF STATEMENT Page 1 of 10

(Drywall Work)
Company Doc. No. Date Revision
Contractor Ref. No.
0

METHOD STATEMENT FOR

(Drywall Work)

FOR

Project No: (…………………………………)

REVISION ISSUE
DESCRIPTION REVIEW / STATUS
HISTORY DATE

PREPARED BY: REVIEWED BY: APPROVED BY:

HSE Documents
METHOD OF STATEMENT Page 2 of 10
(Drywall Work)
Company Doc. No. Date Revision
Contractor Ref. No.
0

Table of Contents
Scope 3
Objective.................................................................................................................................................................. 3
Term & Definitions...................................................................................................................................................3
Responsibilities.........................................................................................................................................................3
Site Supervisor..................................................................................................................................................4
Site Worker.......................................................................................................................................................5
HSE Officer........................................................................................................................................................5
Submission Documents............................................................................................................................................5
Delivery, Storage and Handling................................................................................................................................5
Site Conditions.........................................................................................................................................................6
Products................................................................................................................................................................... 6
Installation Guide.....................................................................................................................................................6
Jointing..................................................................................................................................................................... 7
First Coat..........................................................................................................................................................7
Second Coat......................................................................................................................................................7
Third Coat.........................................................................................................................................................7
Quality Control & Assurance....................................................................................................................................7
Health, Safety & Environment..................................................................................................................................8
Manpower Resourcing...........................................................................................................................................10
Appendices (As Applicable)....................................................................................................................................10
1. Risk Assessment (Attached)........................................................................................................................10

HSE Documents
METHOD OF STATEMENT Page 3 of 10
(Drywall Work)
Company Doc. No. Date Revision
Contractor Ref. No.
0

Scope
The scope of the written Method of Statement for Drywall Work. Works are executed following the Contract
Specification and safety requirements, related hazards and concerns are analyzed and safety precautions are
implemented throughout the progress of the work.

Objective
 Strict adherence to this method statement is critical to the health and safety of all manpower engaged
in the work.
 Any deviation must first be authorized by the site supervisor.
 Work safely throughout the entire process.

Term & Definitions


 Follow the agreed terms and conditions to proceed with the job
 [Client/Company] and Local Authority Regulations
 Contract Requirements & Specifications .
 [Client/Company] HSE & PTW requirements

The technical terms & definitions to be carried out during the works are below:

 HSE – Health, Safety, and Environment


 PTW – Permit to Work
 Toolbox talk – Pre-Task briefings related to safety
 PPE – Personal Protective Equipment
 MOS – Method of statement
 Contractor – [XYZ]
 Performer – Contractor Engineer

Responsibilities
 Ensure strict compliance with PTW and procedure.
 Deploy competent and certified staff.
 Conduct pre-job briefings/toolbox talk/Hazard Communication.
 Ensure proper coordination with plant supervisor/operator
 Ensure usage of correct tools and equipment.
 Ensure to keep away from other equipment or wires/cables not related to the job.
 Maintain good housekeeping at all times.
 The site Engineer will be managing the activities to execute the works as detailed in MOS with safe
practice and procedure

HSE Documents
METHOD OF STATEMENT Page 4 of 10
(Drywall Work)
Company Doc. No. Date Revision
Contractor Ref. No.
0

 The performer must get the work permit approved before starting the work, and close the work permit
after completion of the work
 The contractor should strictly follow plant rules and regulation while doing the job.
 The performer and Plant supervisor/Operator have to discuss and understand the scope before
proceeding to the job.
 Any damage to the plant property while doing the work will be fixed by the contractor on his expenses
 The contractor should strictly follow plant rules and regulation while doing the job.
 The performer and Plant supervisor/Operator have to discuss and understand the scope before
proceeding to the job.
 Responsible for overall projects executions
 Adapt a leading role concerning contractor’s quality and safety procedures
 Always be informed of the task to the plant responsible person
 Supervise the works.
 Make sure all the labourers adhere to the HSE policies ex. Use safety restraints, safety harness...etc.
 Directly monitor the repairing activities at the site.
 Report on the spot any non-conformance to the Plant Supervisor.
 Provide all necessary tools, equipment, and material required at the site.
 Stop all unsafe work activities.
 Ensure availability of all required tools to maintain a safe working environment.
 Ensure compliance with procedures concerning equipment and related certification and permits.
 Ensure that the workers under his command fully understand the hazards and risks involved in the job
and are responsible to ensure they work in a safe environment.
 The service technician, in attendance, must sign into the plant room, where applicable and make the site
manager or site representative, aware of the works to be undertaken and the areas in which the worker
wishes to work before commencing with any works.
 The site team must aware of the worker about fire, health and safety and specific site requirements. As
the workers will be working within unfamiliar buildings, they must also be made aware of the positions
of fire alarm call points, fire evacuation assembly points, fire extinguishers or blankets and the nearest
fire escape routes.

Site Supervisor
 The carrying-out of work and the proper distribution of all the available resources in coordination with
the Site Engineer daily.
 Daily reports of the works are achieved and coordinated for future planning with the Site Engineer.
 Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
 Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
 Should acquire any necessary civil works clearances and coordination.

HSE Documents
METHOD OF STATEMENT Page 5 of 10
(Drywall Work)
Company Doc. No. Date Revision
Contractor Ref. No.
0

 The identified HSEQ aspects and TBT are briefed to the working crew before the starting of the job and
its HSE Officer/Representative shall be responsible for the safe executing of the above activities in strict
compliance with approved MOS/TRA via Control, supervise and record toolbox meetings.
 Ensure that all HSE requirements are met and implemented while executing the works.

Site Worker
 Maintenance of all materials associated with fire protection systems and in line with [Company/client]’s
SOW
 Following approved checklists for service and maintenance of the assets.
 Handling of the site materials, accessories, tools and equipment.
 Ability to perform routine maintenance on equipment and determine when and what kind of
maintenance is needed.
 Maintaining circuits and sensors, following wiring and system specifications.
 Performing other related activities as instructed by the Superior.

HSE Officer
 The implementation of all safety measures following the HSE plan and that the whole workforce is
aware of its proper implementation.
 The implementation of safety measures is adequate to maintain a safe working environment on the
maintenance activity.
 Inspection of all the site activities and training personnel in accident prevention and its proper reporting
to the Maintenance Manager.
 The site is maintained in a clean and tidy manner.
 Ensure only trained persons shall operate the power tools.
 Ensure all concerned personals shall use PPE and all other items as required.
 Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with ladders.
 Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
 Ensure safe access to site work at all times.

Submission Documents
Technical Data: technical data, test certificates, installation instructions and valid Bomba’s certificates for fire-
rated assemblies for approval before commencement of work will be provided by the manufacturer.

Delivery, Storage and Handling


Coordinate deliveries to comply with the Construction Schedule and arrange for off-the-ground storage. Do not
load any area beyond the safe design and recommended load limits.

Do not store product outside. Always try to stack gypsum/calcium silicate boards flat on a smooth, even and dry
surface.

HSE Documents
METHOD OF STATEMENT Page 6 of 10
(Drywall Work)
Company Doc. No. Date Revision
Contractor Ref. No.
0

Site Conditions
Install work only in areas closed and protected against the weather. Provide appropriate Ventilation &
Dehumidification (VD) to eradicate extreme moisture in the areas of work to ensure appropriate drying, curing
of the compounds.

Try to never install such type of work in any area unless convinced that the work accomplished has dried out and
that no more installation of damp materials is proposed.

Products
Gypsum Board of a selected thickness (12.5 millimetres, 15 millimetres, 16 millimetres or 19 millimetres) to be
used.

Stud of selected width (49 millimetres, 62 millimetres, 72 millimetres or 92 millimetres) to be used which is
determined by the architect in the specification.

Jointing Compound

Paper Tape

Installation Guide
 Always Install metal wall framing as per the manufacturer’s instructions.
 Complete and mark the wall position and make allotment for openings.
 Fix track channel appropriately and securely along the centre line of floor and ceiling at 600 millimetres
centres with reasonable fixings.
 Then cut the stud to an exact fit into the height of the needed and or desired wall height. Locate the first
stud into the track channel, twist into position and fix to the abutting wall at 600 millimetres centres.
Locate the next stud at 600mm centres to a friction fit within the track channel sections.
 In grafting and or splicing the studs due to height recommendations, 2- stud members are boxed with
minimum overlapping of 600 millimetres. For the designed partition, height more than the plasterboard
length, an extra track channel adjusted horizontally to strengthen and support an infill panel is
recommended and required.
 Drywall partition above ceiling shall allow for cut out opening service such as ducts, trunk and cable
trays.
 The main contractor shall confirm and coordinate with all sub-contractors on the correct location and
size of the openings. Any gaps around any pipe ducts through the partition shall be appropriately sealed
with a proprietary Fire Smoke Stop System (FSSS).
 If the full height partition had to be terminated below the ventilation duct route parallel to the
partitions, the stud of the partition shall be secured to the support frame of the duct. In such installation
services, space between the duct and reinforced concrete soffit and or rim required not to be sealed up.

HSE Documents
METHOD OF STATEMENT Page 7 of 10
(Drywall Work)
Company Doc. No. Date Revision
Contractor Ref. No.
0

Jointing
Support all internal and external corners/angles and Panel Joints (PJ’s) for wall surface with paper tape installed
in and accomplished with Jointing Compound (JC).

First Coat
 Using a trowel, apply compound to the plasterboard recessed joint formed by the recessed edge of the
board. The compound should be applied 3 millimetres -5 millimetres thick to strengthen with tape
bonding.
 Centre the paper tape along the joint
 Leave sufficient compound under the tape to achieve a good bond.
 Immediately apply a thin coat of compound over the tape. This minimizes the probability of the tape
edge curling or wrinkling which could cause cracking of the wall or installation.
 Cover all fastener heads and allow the first coat to set/dry. Leave all joint and fastener
 heads with a smooth finish and feathered edges.

Second Coat
1) When the first coat has set/dried scrape back any build-up of the compound. Affix or apply a second
coat of compound by utilizing a trowel. The second coat should be accomplished as flush as viable to the
Board Face (BF).
2) Using a trowel, cover fastener heads with a second coat approximately 25 millimetres wider than the
first coat.
3) Allow setting/dry.

Third Coat
1) When the second coat has set/dried, scrape back any build-up of compound along the joint, to give a
smooth and level surface.
2) Apply a finishing coat with a trowel to a width of approximately 275 millimetres. A wet sponge
(applicator) may be utilized on the joint edges to help gain a smooth finish.
3) Apply a finishing coat to fastener heads approximately 25mm wider than the second coat.
4) Allow setting/dry completely.

Quality Control & Assurance


[Company] shall implement a Quality Management System at the Project site covering the requirements of ISO
9001:2015 QMS.

GIG shall manage to:

 Identify the processes needed for achieving the quality service and product as per client satisfaction and
applicable standards.

HSE Documents
METHOD OF STATEMENT Page 8 of 10
(Drywall Work)
Company Doc. No. Date Revision
Contractor Ref. No.
0

 Determine the sequence and interaction of the execution processes, and determine criteria and
methods required to ensure the effective operation and control of these processes.
 Ensure the availability of information necessary to support the operation and monitoring of these
processes i.e., project specifications/method statements.
 Measure, monitor and analyze these processes by following the work and service plans.
 Implement actions necessary to achieve the planned results and continual improvement.
 Identify QHSE hazards associated with its activities and planning for risk control.
 Established to maintain quality of the works following specification and standard.
 Materials to be inspected by Plant Supervisor/Operator after delivery to site.
 Works shall be inspected by the Plant Supervisor/operators at every stage.
 To ensure that quality is maintained, we will coordinate with the on-site [Client’s] team regularly.
 The plant Supervisor/operator and the Client’s representative shall inspect the materials and
workmanship
 Approval by the supervisor or the operator in charge during the time of work will be accepted as
sufficient evidence that arrangements for manufacture and quality comply with these requirements.
 Always inspect the job by supervisor/operators on each step of the work progress.

Health, Safety & Environment


Before commencing any work, the team shall strictly follow as per the [Client’s] Health & Safety
recommendations for handling and use of the materials. Ensure all involved personnel shall be aware of the
same. The general safety guidelines are given below:

1. Ensure the work area is safe & clean.


2. All employees shall adopt safe working practices.
3. Safety equipment PPE (Safety helmet, safety shoes, coveralls, gloves, goggles, face mask as applicable)
to be worn at all times.
4. When working at a high level, the appropriate safety harness shall be used and secured whilst working-
extra care shall be taken whilst using tools at a high level to prevent dropping.
5. Ensure sufficient lighting is available during testing.
6. Report all accidents no matter how small to the Safety Officer on duty.
7. Proper access for the labour and equipment shall be provided for the works.
8. All machinery shall be checked for maintenance records.
9. The site shall be cleaned from all debris, steel waste, nails, etc.
10. Toolbox talks to be conducted before the commencement of testing works.
11. Close supervision on safety requirement shall be provided.
12. All necessary barriers, signage lighting etc., to be provided and maintained.
13. All employees working on the site shall be trained in [Client’s] PTW.
14. Awareness in plant Emergency evacuation procedures.

HSE Documents
METHOD OF STATEMENT Page 9 of 10
(Drywall Work)
Company Doc. No. Date Revision
Contractor Ref. No.
0

15. Inspect tools and ensure that they are free of defects.
16. Ensure that appropriate tools are used for each activity.
17. Ensure only Trained and Competent Workers allowed to use power tools.
18. Ensure strict compliance with PTW procedure.
19. Deploy competent and certified staff.
20. The work area shall be barricaded using safety Cones and Warning Tapes.
21. Conduct pre-job briefings/toolbox talk/Hazard communication.
22. Display warning signs ‘Entry Restricted to Authorized Persons Only.
23. Do not touch any plant existing equipment’s and ensure that the plant properties are safe during and
after the work completion.
24. Ensure proper coordination and communications with plant authorities.
25. Ensure the availability of First aid medicines and fire extinguishers nearby.
26. [Client’s] HSE Standard Policies & Procedure to be Followed
27. All personnel involved will use necessary PPE as required such as safety helmet, safety shoes, visible
jackets, rubber gloves, glasses, earplugs etc.
28. Ensure All personnel wear Surgical Masks and Hand gloves all the time as a precautionary measure to
COVID-19
29. All employees shall attend a safety induction Training Course to identify all hazards associated with this
work.
30. The workers will be made aware of safety requirements related to this activity through daily toolbox and
safety talks.
31. All required work permits will be acquired and kept available at respective work sites hanged clearly in
plastic folders.
32. Access and good housekeeping should be maintained in all working areas.
33. Waste management should be strictly enforced by site supervision.
34. All workers shall be provided with proper tools & equipment’s to execute the work safely.

Below are some COVID-19 Safety precautionary measures to be followed:


 Numbers of the technician visiting the site.
 The vehicle used (3 person in one car) is mandatory as per Covid-19 transportation regulation.
 Covid-19 PPE: FACE SHEILD, Face mask, Hand gloves is mandatory.
 The contractor should provide their own, Hand sanitizers and hand wash liquid.
 A health certificate is optional
 Social distance must be observed.
 Prevents shaking hands.
 Maintain Proper Hygiene.
 Sanitize the area after the job completion.
 Covid-19 toolbox talk must be followed.

HSE Documents
METHOD OF STATEMENT Page 10 of 10
(Drywall Work)
Company Doc. No. Date Revision
Contractor Ref. No.
0

Manpower Resourcing
Number of
S. N. Position
Employees
1 Project Engineer
2 Site Supervisor
3 Site worker
Total

Appendices (As Applicable)


1. Risk Assessment (Attached)

HSE Documents

You might also like