Professional Documents
Culture Documents
PM HandBook
PM HandBook
For many of us today, working on a project is a dual role that we perform, above and
beyond our day-to-day speciality. There is usually some compulsion and nervousness
about performing our project role. We know many projects fail. So what exactly should
we do, and how does a project really work? This book tries to answer these questions.
Beyond that, this book seeks to offer you some challenges in project management. It
also questions some practices. We address much that is new today that you may be
working on tomorrow.
In the Beginning
Long ago, projectere in Latin meant to throw or carry something forward. Later, the
meaning became to plan or carry a plan forward. Today, that is basically what we mean
by project: the act of devising and executing a plan.
You may well ask: what sort of plan? A project plan is one that will clearly achieve some
specific objective or goal. That may be a business or commercial goal, a military goal or a
personal goal, say of fitness or finance. In this book, we focus on business or commercial
goals and projects to accomplish them.
Note it is the goal that matters. Building an aqueduct with the goal to deliver water from
a remote dam to the city is a worthwhile project, provided that it does deliver water in
the quantity and quality required. It is the delivery of water that counts, not the building
of the aqueduct. The aqueduct is merely the means to the end.
Next, we examine the definition of project and project goal in more detail. Then, we
examine the processes used to achieve projects. Before that, we first look at the people
side of project management.
Who is best suited to be a project manager? Research by R. Max Wideman [1] answers
that question, and is given in Appendix 1.
In fact, few people fit the ideal characteristics to manage a project. Equally, if we
checked who is best suited to drive a motor car in our busy and chaotic streets, we
might also find few people are best suited to do that too. Be that as it may, many of us
have to drive cars and manage projects. Both skills can be learnt well.
Project Manager is a prestigious job title, both fittingly used and misused. We look at
some misuses of this title in Appendix 2.
Definitions of Project
Some organisations define a project as a set of tasks that takes over 20 days estimated
labour to complete; a work request takes under 20 days to complete.
Non-project work is routine work. That is largely the same, day in and day out. An
example is to prepare and update a TV news program, taking inputs from various
sources and centres. The same process and scope apply every day, although the news
content differs.
Specific
Measurable
Achievable
Realistic
Timely
If not SMART, the project is fuzzy and unlikely to succeed. Consider the water project
above. We need to know –
So, a nine month project to build an aqueduct to a nearby lake that will supply ample
water year round is SMART, provided the resources, budget and skills needed are on
hand and the engineering challenges are average. And there are some other sources of
water in the city.
However, if some or all of these conditions are not met, then the project is not SMART.
For example, if the lake is too small or far away or if the need for water is urgent, then
this project does not compute.
Classic Projects
Operational or Upgrade
Compliance
Strategic
Operational projects dominate by far. They give us service upgrades, rate changes,
product enhancements and new-look documentation across banking, insurance, telco
and other industries. The enhancement from 3G to 4G mobile phones was one such
project. The usual goal of operational projects is to cut costs.
Next most common are compliance projects, more properly programs. Compliance
programs are typically groups of projects to achieve or comply with the goals and
timetable set by the Tax Office, Federal Legislation, Industry Regulator or other
authority. They are ‘must do’ works.
Compliance projects also include projects that restore public health and safety e.g.
proper water supply or safe lift services.
Occasionally, we deliver a strategic project. Such a project clearly enables the business
strategy of the firm. Suppose the strategy of a bank is now to offer a mobile mortgage
service (where the mortgage officer comes to you and completes the home mortgage
contract on the spot), Then projects that enable this business - building a mortgage
lending tablet, laptop or mobile app say - are strategic.
Fuzzy projects
Fuzzy Projects
Sarah and George have bought an old house. It is run-down, if not crumbling. They plan,
rather dream, to restore it.
Building work must be replanned and budgeted once problems (unknown, unseen and
unsuspected) are discovered, be it leaning structure, rotting support beams, sinking
foundations, etc. There often are several iterations of the discovery-replan-budget-
rework cycle. Each trashes the original project plan, budget and WBS (work breakdown
structure or work plan).
Lastly, the owners/builders may change their goals as the project progresses, because of
problems, permissions, lack of funds or just change of mind.
If the restoration and rebuild project does eventually finish, it is usually way behind the
original schedule and way over the original budget. Some do not finish.
The auction date is fixed and a substantial deposit is required in order to bid.
The art work requires validation by experts in its ownership, dating and style. However,
the few experts are always busy and may not be able to work on this project at all.
Failing some or all checks indicates the painting is either in the school/following of the
artist or a fraudulent, modern copy. If so, its value is much reduced.
It is likely that the Gallery will have to decide to bid or not with only some information
on hand. Also, bidding for a genuine work usually goes way over the initial estimate. So
State and Federal government funding is urgently needed too. But there is very limited
data to support grants applications, and funding may be refused.
Lastly, the original funding may come from a bequest or will that requires money to be
used only to buy a genuine work. Going ahead risks legal challenge and wide public
embarrassment. The Gallery’s own internal risk assessment may be ignored too. To
complete the project with a winning bid is possible but risky with many limitations.
Having completed in-house and peer trials with flying colours, the drug now requires US
Federal Drug Authority approval. FDA approval is granted only if and after all three
approval testing stages (each lasting 6-12 months) are completed to its satisfaction.
However, drugs often fail a stage. The commercial question is: is it worthwhile to repeat
a stage? Some drugs are abandoned, some are sold and some are retested.
If and when US FDA approval is finally granted, local market approval is now also
required, be it Australian, French, Chinese or any other. That too has its approval testing
stages to complete.
The project to gain approval and release a wonder drug is a wonder.
The animated game Julie is a sci-fi thriller [3]. It was completed and released. However,
there was little or no project management throughout the long project. The animators,
designers and artists were exhausted by ongoing technology upgrades to games,
animation and drawing systems and unplanned rework. A finished task was never
finished. Never again was the motto. Like many other games, Julie has not been updated
to today’s game platforms.
Many projects are demanding. That is normal. You would not want it any other way. A
Mission Impossible project is not feasible, not doable.
In the 1990’s, PFI projects became popular in the UK. Now they are found worldwide.
They typically undertake very large infrastructure projects e.g. airports, highways,
hospitals, prisons, schools and waste facilities, sharing the project finance, risks and
return between parties. The $8bn East West tunnel project in Melbourne and the £4bn
Channel rail link project between England and France are two prominent examples.
Private Finance Initiatives use private money for major public sector capital projects. The
private company, a consortium of builders and investors, builds and owns the facility.
Over 20-60 years, this is leased back to the state, in exchange for regular repayments.
The attraction for the state is to stretch the public purse further, funding say 15-50% of
the project; the attraction for investors is a long stream of repayments.
Some such projects are controversial. Read the case study of the Royal Liverpool
Hospital in Appendix 7.
Research suggests that hospitals are among the most challenging of PFI works . Also,
that PFI public works projects are delivered about 3% ahead of schedule compared with
Traditional public works projects which are delivered about 24% behind schedule [4].
Choosing a Project
Most businesses have many, many projects to choose from, when it comes to approving,
funding and supporting a particular project. So how can we pick a ‘good’ project? There
are several ways.
In principle, we can use a rating scheme based on a number of criteria and their weights.
The project with the highest weighed rating wins. In practice, this is uncommon. The
data needed for the various criteria is seldom available.
Payback period
Net Present Value or NPV is the net investment return of the project (revenue generated
minus build costs), with revenues discounted from the year they occur to the present.
The discount rate is the firm’s desired rate of return, or hurdle rate. That reflects the
firm’s cost of capital and expected earning rates. When evaluated at present value,
projects of very different durations, say 1 year, 3 years and 5 years, can be compared
fairly.
Also, if a project is seen as riskier than others, it can be discounted with the hurdle rate
plus a risk premium of say 3% or more. So, riskiness of project revenues can be taken
into account. An example of the calculation is the Student Questions below.
The Payback Period is the time in years and months that the project revenues will take
to equal the build costs. Figures are undiscounted. Payback Period is of interest to small
to medium enterprises which are concerned with cash flow. When will we get our
money, i.e. build costs, back?
By the way, NPV and other calculations are done easily and quickly using Excel
spreadsheet functions.
One practical tip is this. Projects rarely continue beyond 3 years, however long their
planned duration. Projects then are usually wound up, and resources are re-allocated.
So also evaluate the project NPV at 3 years.
To complete, the Internal Rate of Return is that discount rate which give a NPV of zero.
Business Case
The business justification, scope, financial measures above, outline of project work plan
and schedule, risks, etc are included in the Business Case. This is the mandatory starting
point for most projects. Projects, operational or strategic, must compete for budget
funds. Some firms call this step Strategy into Action, and so it is.
Note it is usual to sweep in to the project some related and necessary sub-project(s). For
example, a major health insurer was rebuilding its communications networks across the
nation. It had no backup or redundancy capacity in place for its communications lines or
call centres! Backup means that if a line from A to B fails, there should be an alternate
line from A to C to B as spare. So if a bulldozer accidentally cut a cable, you guessed it …
The rebuilding project thus included backup.
In the next chapter, we discuss the first basic building block of the business case. That is
project scope.
Student Questions
1. Fuzzy
How can fuzzy projects A and B be made less fuzzy? Common sense steps will do the
trick.
2. Wortbuch
The year is 1960. The German Government has now allocated funds for researchers
to complete the German Dictionary (deutsche Wortbuch). This was started in the
1830’s by the Brothers Grimm. The Brothers built the Dictionary up to the letter G.
Question is – what type of project is this?
Today, Microsoft and Domino’s are collaborating to produce an app for Xbox gamers
to order pizzas without interruption. What type of project is that for Domino’s?
3. NPV’s
Project NPV’s are C -$50k, D +$15k. Which project(s) should you invest in? Why?
4. Missions Impossible
5. Big Bank
You are Project Manager at Big Bank with a budget of $1,400k this year and a wide
choice of projects. Decide which types of projects you have, which projects you will
invest in and how much unallocated budget you will retain, if any.
Your job as Project Manager is to choose and install the new computer system for
CTP motor insurance. The system is expected to pay for itself in five years.
For CTP, the profit margin on premiums is an enviable 15%. Estimates of premiums
are $400k in year 1, $1000k in years 2-3, $1500k in year 4 and say $700k in year 5.
The state government changes insurance laws every five years so premiums in that
year are risky. Premiums are invested conservatively, earning about 6% interest.
Today, the bank bill rate is 6% and inflation is running at 2%. A risk premium of 3%
may be added, as you see fit.
A good investment has an NPV that is zero at minimum or positive. So then, what
can you spend?
Hint: Find the expected future earnings in each year from premiums and
investments. Then find the present value of earnings in each year by discounting, as
follows. The discount factor for future earnings in year n is 1/(1+D)^n where D is the
discount rate. Use Excel to calculate.
So then, what investment would just equal the sum of present values?
Rebecca has drafted a Project Initiation document. Her project concerns data
collection and needs analysis for child care in Chelsea, London. Problem is – the
business case section of the document is vague [5].
So, draft an accompanying Business Case that justifies this project, if you can. Use
the data in Rebecca’s draft and the format for business case given here [6].
The Do Nothing option is a standard feature of all business cases, but what happens
here? Should this project be done?
8. Airports Canada
It is the year 2050. There is a boom in world travel. Problem is – the airports of
Canada have maxed out. There is little or no nearby land available at reasonable cost
to enlarge airports. Landing slots and takeoff rules limit arrivals and departures too.
Airlines are already flying their biggest aircraft. What to do?
Option A is to build a new, central airport at Ottawa with bullet train connections to
Canadian and US cities. Distances Ottawa to Montreal, Quebec, Toronto and New
York are 200 km, 440 km, 450 km and 440 km respectively. The average speed of a
bullet train is 250 km per hour.
The new airport will make extensive use of underground facilities to store and
service both planes and passengers. That is a new design. Bangkok and Dubai
airports have underground trains.
Option B is more simply to build a new airport at Quebec with bullet train access to
Montreal. Distance Quebec to Montreal is 200 km. Again, the new airport will
develop and use underground facilities. Option C is the Do Nothing case.
There is an extensive rail network in place. It is 3 times slower than bullet train.
Draft a business case here. Focus only on the Benefits and Disadvantages of each
option. What do you recommend? What are sensible Next Steps?
You are going down in the lift at lunch time to the cafeteria. It is busy and bustling. There
are many people who know you as Project Manager in this project. They all want to talk.
What do you think will be the subject most asked about in the project –
Budget
Benefits
Duration
Scope
Process
People?
Usually, the most asked subject is the scope. People assume the rest will follow. And
what is Scope?
SCOPE
Scope means the agreed range, contents or inclusions of the work, with a strict and clear
boundary that separates in from out of scope. Project Scope goes hand-in-glove with
Project Goal
Assumptions Made
Constraints
A simple example may help. Suppose your project is to repaint and redecorate a room.
Imagine how different the project will be if the goal is –
How do we work out or define the scope? Some investigations, discussions and planning
are required, and some iteration as well. There are often some reference documents
that bear on and inform the result.
As well, we use a Checklist to build the scope wherever possible. For example, Telstra
uses a checklist of work usually required to bring new telco products, routers and hubs
into service. National Mutual uses a checklist of work usually required to bring new
insurance or investment products into service.
What can go wrong with scoping? Sometimes, a project manager is pressured into giving
a quick-and-dirty scope. The result is you guessed it … The next project manager must
redo the scope properly.
What happens if the scope costs over the desired budget? Here we redo the scope with
a careful prioritisation of project inclusions, their benefits and costs. Also, we often split
the project into prioritised versions or releases.
Gobeli and Larson found that planning problems were cited as the most
frequent barrier to project success. Within this category, unclear definition of
goals, objectives, scope, plans, or design was the predominant planning
problem [7].
In examining the reasons why cost and schedule overruns are experienced on
software development projects, Genest et al. identify the failure to manage
scope as a probable cause [8].
SCOPE CREEP
Is that all to project scoping? No. Scope Creep refers to uncontrolled changes in a
project's scope.
Sometimes, the scope increases by adding both new products and new features of
already approved products. As a result, the project drifts away from its original purpose.
Scope creep also results in a project overrunning its original budget and schedule, as
more is to be done at the same cost and in the same time. This is usually unrealistic.
Confusion of what products and features are properly required to bring about
the achievement of project objectives in the first place
Over-promising and being easy to please
Divergent views as project sponsors change
Unplanned but necessary work generated by planned tasks
Poor change control.
We discuss Change Control later. That process addresses proposed changes to scope
later in the project. These are investigated, prioritised and agreed or rejected on their
merits.
In the next chapter, we discuss the third basic building block of the business case. That is
the project work plan.
Student Questions
The year is 1890. The Turkish Government is considering a new project, the
Instanbul to Mecca railroad. There is much public support for the project.
The route will be very long. There will be a railway from Istanbul along the Turkish
coast to Damascus Syria, then to Port Said Egypt and along the Red Sea coast of
Saudi Arabia. Finally, the line will head inland to Mecca. The cost of construction and
upkeep will be very high, and the duration of the project will be long. Railway makers
and engineers are delighted.
2. Opera France
The French Minister of Culture has announced a new project. There will be a
thorough review of the funding and performance of opera in France, The report will
be tabled in five months time, before the new financial year. The Minister has invited
experts to join the review. Congratulations! You have been named as Chairperson.
In France, there are four competing national opera companies. Many cities host
opera/music festivals too. Opera often uses joint works. The Opera National, for
example, works with Radio France and the Chamber Orchestra of Paris. Opera is
distributed by many media. A live performance may also be televised and digitised.
There are specialist opera companies also.
All forms of opera, music and the arts are partly subsidised by the national
budget, along with various other budgets. The management and marketing of
opera is local, at company or festival level.
For whom is this good? Can more be done for less? Those are some of the
social, economic and other dimensions of your review.
Allez y! Go to it.
Iinsure wants a call centre built double-quick. It will handle all motor claims
from across South Africa, and maybe house & contents claims later. A
residential complex has been purchased in the downtown Durban area.
This will need refit and commissioning. Fire safety and other standards
must be met. About 150 managers and staff will use the new centre. All office
infrastructure needs to be provided: cabling, desktops, networks, systems,
printers, etc. Electricity, lighting, lifts, ventilation and parking may or may
not be sufficient for the new centre.
In anticipation, Iinsure has built call centre claims systems. But, these use old
model HP PCs and HP will soon to cease making them. A suite of call
centre technologies needs to be purchased, integrated and installed from
Telsa and other vendors.
Iinsure has just reorganised after losing some major contracts: so who will be
the managers, the supervisors and the call agents in the new centre is
unclear. Personnel are upset. Things are going slowly.
It may be useful to link this call centre to other Iinsure call centres in Cape
Town and Johannesburg. Iinsure has discussed the project with ISI
Corporation, but no contract has been drafted or signed. Budget likewise has
not been set. Questions from ISI to Iinsure are usually met with an
impatient now!
By the way, call centres that sell policies are profit centres. Call centres that
administer claims are cost centres.
It is time to mine right now. The drill samples, the geology and the
geochemistry results are excellent and coincide. Even the old timers agree.
Nevada Prospecting has been exploring tenements outback for the last two
summers. The nearest pub is at Malbon, 90 miles away.
The nearest major rail junction and town is at Concurry, 250 miles away.
Roads are just bush tracks, difficult enough for a jeep. There are two
rivers en route, prone to occasional flooding.
Nevada will process copper, silver, lead and zinc on site in a new mine.
Copper is the dominant metal. Ore concentrate will be transported by
road to Concurry, and by rail to depots in Gladstone, 1300 miles away.
There it will be shipped overseas.
So, heavy mining equipment must be brought in. New processing facilities,
camps and infrastructure (water, electricity, sewerage, food & supplies)
must be set up. AJ Lucus is one mining services company that may help.
Williams & Co is another. It sets up and services remote mine
accommodation. Queensland Rail and Gladstone Port Operators are
also likely major partners. Apart from some caravans, generators and
jeeps, Nevada has no equipment. You are beginning from the beginning.
By the way, no one has considered the environmental or legal issues. The
mine will need long-term waste storage, a by-product of ore processing. No
one has mentioned traditional land owners or protected fauna on site, if any.
Recruiting numbers of skilled miners will take some effort too.
Also, commodity prices are high today but volatile. Who knows what they will
be in nine months time?
5. Scope Creep
A. Decision to move 50 personnel from Cape Town to the new call centre
B. Omission to obtain Development Approval from the Durban Town Planning
council
C. Discovery of asbestos walls that must be removed and replaced
D. Decision to exclude house & contents claims
E. Late decision to link in on-the-road claims agents.
6. Opo
It is the year 2001. The world is abuzz with the opportunities of eCommerce. That is
Internet-based trade, commerce and applications. Every man and his dog have a
scheme or two.
Opo is a telco. It envisions new services and revenues when a telco underpins this
eCommerce world. Problem is – Opo has no capacity or facilities of this kind. It offers
satellite, mobile and other traditional telco services.
So, Opo plans a new project. It will build a set of Internet-based data centres
nationwide to serve this new business. In the west, south and north, there will be
regional data centres. In the centre, there will be a national data centre. All centres
are brand new except for the south; that will be a re-equipment of the existing Rose
Bay data centre.
This looks like a 5 year building plan. And capital expenditure will easily exceed $500
million. Holy Cow! That is a large chunk of Opo’s annual revenue or net assets.
The eCommerce market is changing quickly. Opo marketing people are worried. If
our eCommerce facilities and services are not in place very soon, the opportunities
will be gone!
So, what advice would you give to make this project SMARTer? What alternatives
would you suggest?
The divisional manager who is initiating, supporting and funding the project is the
Sponsor. Usually, there is a single sponsor. But, in more complex projects, you will find
two sponsors, hopefully with a common voice. The Sponsor often envisions the project
goals and outcomes in a compelling way.
Your early project discussions are with the Sponsor. But who else is needed on and
around the project team?
Are all stakeholders equal? No. Critical stakeholders may grant or block permission and
cooperation for the project, as they see fit. Harmony among stakeholders enables
success whereas conflict typically leads to failure.
In fact, shifting alliances among stakeholders may reshape the direction and content of a
conflicted project. This is commonplace. D’Herbemont and César consider the strength
of alliances for and against a project. [9]
Some of these people are assigned; others need to be identified and engaged in the
project, if available. Go for it! Every project is different. Who was appropriate and
available for the last project may not be now.
All the project and support personnel will need engagement and briefing from you, the
project manager. A number of these will be new to their role. So, a glossary of Project
Roles and Responsibilities is necessary. A large and complex project will need a
Communications Plan too.
A common addition is the Business User Co-ordinator, also known as the Buck. In the
case of joint project development, the Buck and the Project Manager work together to
prioritise and steer project work.
We assume that the Strong Matrix or Project Organisation is the usual and normal
project organisation for the enterprise. Here, everyone has both a project role and a
specialist, day-to-day role. Some alternatives forms of organisation are discussed in
Chapter.
The processes the project will follow are also usually part and parcel of the enterprise,
whether Classical (waterfall), Agile Scrum (prototyping) or Rapid (timeboxed) project
development. Some tailoring of processes is allowed, especially for smaller projects.
Does following processes mean no disagreements? No. People naturally disagree. Some
may even have a better way. As Manager, you need to listen, guide and follow-up. As
Leader, you need to show and clear the way forward.
Make it good! These check that all of us have the one-and-the same understanding and
expectations of the project, its goals, deliverables, duration and costs.
Note that in practice the Sponsor may be reviewing multiple projects, rather than a
single project, by the Project Review Board structure.
Student Questions
1. Critical Stakeholders?
Our project was to draft, review and gain acceptance of a strategic plan for the
sustainable development of an entire river catchment, in a rapidly developing
section of coastal Guangzhou, China. To do this, we planned and conducted a
process of wide community consultation.
All were involved in a process of public meetings, networking, focus groups and
workshops. Promotional work included newspaper columns and media interviews.
High level negotiations were conducted with national and provincial governments.
Who were the critical stakeholders here? Is that only government departments?
2. Camping in Zambia
Camps need to be built quickly in Zambia to shelter refugees from Rwanda. The UN
and other international bodies will help. Zambians will do most of the work. Consider
the stakeholders in this project –
The work plan or Work Breakdown Structure (WBS) answers the question – how, step
by step, will the project goal and scope be realized?
Work breakdown structure is an exhaustive, hierarchical tree structure of tasks,
milestones and deliverables that will complete the project. Thus, the WBS serves as the
basis for much of project planning.
Inspect
Apply a second coat? Paint again
MS – finished painting
MILESTONES
Above, we show some Milestones or key progress points as MS. These serve to navigate
or measure our progress through the project just like the way points through an airline
flight path. Usually, milestones are show as diamonds. A project with flag-style
milestones is -
This makes the project timeline very clear.
The WBS should generally not exceed 100 tasks, preferably less. The WBS should be of
limited depth and breadth in tasks. How many tasks are listed in the painting project
above? It is just about readable.
If many more tasks are required, use Sub-project(s). If a number of small, related tasks
are involved, sweep them into Work Package(s).
The clear naming of phases, activities and tasks is also important. What does this
name/task mean? If readers cannot tell or you cannot remember, then go back and
clarify.
Notice how in the painting WBS above we have a number of activities like Prepare the
Room, which contain a number of tasks. This Activity-Task tree structure is typical.
It is also typical to find a Phase-Activity tree structure. So we could show the above WBS
in phases –
Preparation Phase
Plan the Work
Plan the Decor
Get the Materials
Prepare the Room
Coat 1 Phase
Paint the Room coat 1
Inspect and Decide
Coat 2 Phase
Paint the Room coat 2
Inspect and Decide
Finish Up Phase
Clean Up
Hand over painted Room.
That brings us to the structure of the classic project plan. It has these phases –
Design or Requirements
Develop or Build
You will see and use this structure often. It is also known as a Waterfall plan.
Note also that project scope and requirements align closely. The requirements phase
details further the exact work needed.
Tuzcu and Esatoølu found that completed and accurate requirements at the
beginning of a project and allocation of sufficient time to determine
requirements were factors that influenced project success [10].
Is the style of project management needed in each phase one and the same? No. We
need to vary our approach –
Explorer in conceptual work
Don’t worry – project managers can and do vary their management styles as above. So
can you.
BOTTOM UP?
Our discussion implies that projects are planned and worked from the task, bottom up.
That is overwhelmingly so. But it is not the only way. Alternatives are –
Prototyping means to work iteratively through the design, build and test of the product
or service from first impression to final version. We work shoulder-to-shoulder with the
stakeholders. They can steer the path and improve the deliverables as we go. At least
four, at most six iterations are applied.
Simpler projects lend themselves to prototyping. A simple, online system, say for
housing rentals, would perhaps be a suitable project here. A multilane highway or a
patrol boat project would not.
Work activities and deliverables are prioritised to fit into, that is to be conducted within,
the fixed duration of the time box. We work shoulder-to-shoulder to achieve this. Board
approval for major purchases, if needed for the project, is not time boxed. That is the
only exception.
Woolworths and British Petroleum use time boxing for Rapid Project Delivery [13]. We
will consider time-boxing further.
Are there other approaches? Yes, for example, Critical Chain Project Management [14].
But, does Rapid Project Delivery achieve the same goals more simply and easily? Indeed.
Of course, there are challenges too. Sometimes, there is too little time available, too
great a scope and too few resources for a classic project approach. What can we do? Let
your inspiration and ingenuity loose on the cases below.
In the next chapter, we discuss the fourth basic building block of the business case. That
is the project risks.
Student Questions
Wind and tide rule sailors. Refugees bound for Italy can find themselves in Malta.
Problem is – numbers are overflowing. Malta needs two camps for 5000 refugees,
built right now. Only rural areas have the space available at reasonable cost.
Refugees stay two years or more before moving on.
You are the project manager for this work. What are –?
A. SMART goal
B. Critical scope
C. WBS
2. Remona
Remona makes beautiful ceramic tiles, wanted the world over. It needs to diversify
beyond the European and American markets. Remona will build a new plant in China
to serve the Asia Pacific region. It is your project. What are -?
A. WBS
B. Key Milestones
By the way, Remona has learned the hard way that it must register and protect its
trademarks and patents.
CXC is an empire. It has over 3500 staff, 15 divisions, and a great many products and
services. Like IBM, it is a billion pound IT company. Most British business giants
count among its clients.
Watch out! There is a five month deadline for compliance with new UK privacy
legislation! Privacy concerns the proper keeping and use of your personal
information – names addresses, medical records, PINs, telephone numbers, etc. The
legislation sets out ten principles of privacy. This is radical. Business tends to collect
data galore.
CXC does not have the time or resources to execute a privacy compliance project
across this vast scope, using the classic design-development-deploy process. No way.
Another way must be found, pronto.
Over to you, project manager. How will you structure the project?
Hint. Consider how opinion polls work. They offer two lessons.
There is a new superannuation (pension) tax levy, due in only six months! The
Australian Tax Office is supervising its collection. There are three steps: identify,
calculate and collect. The ATO often revises the rulings that determine eligible
policies and products, just as it revises other taxation rulings. The process is urgent
but volatile.
CEM is a titan of financial services; the extent of its policies and data is vast. So,
chances of complying with this new law on time seem low. CEM is justly proud of its
fine reputation. No bad news ever occurs here. If CEM failed to comply on time, that
would hit the headlines.
Over to you, project manager. How will you structure the project?
CHAPTER FIVE – RISKS OF THE PROJECT
TYPES OF RISKS
Risks are potential problems that may derail, delay or damage the project. Risks can be
of any kind –
Organisation resistance
People & skills gap
Process flaws
Technology inadequate
Funding gaps
Obsolescence
Market turmoil
Purchasing costs & delays
New laws apply, etcetera.
RISK CONTROLS
Mitigate the risk – reduce the likelihood or the impact of the risk
Transfer the risk – contract other parties to do project work for a price
Avoid the risk – use another approach, or
Accept the risk – too few resources to do otherwise.
Each risk control usually comprises several actions that fit the bill. These are devised by
common sense and experience. For example, to reduce the risk of fighting at amateur
sports matches, we may - name and shame the offenders, fine or expel the offenders,
call the police, cancel the match, fine or expel the clubs, etcetera.
In spite of its importance, risk is often unrecognised, under-stated or ignored. Risk, like
beauty, is in the eye of the beholder.
Abank Hong Kong process calls for multi-country projects over US$10 million in budget
or one year in duration to be subject to Executive Team review. However, such projects
are split up so that no Executive review is ever held.
You may ask – are billion dollar projects and their risks managed better? There is good,
bad and ugly. In the British Airport Terminal 5 project, the known critical risks were not
addressed decisively. You may be interested to read more [16-17]. Flyvbjerg et al see
risk and ambition in transportation mega-projects [18]. They talk of the ‘mega-project
paradox’ – more succeeds less.
Research now is turning to see how organisations can better develop the imagination of
risks. The better imagination of strategy or ethics poses similar challenges. Is the
problem simply solved by hiring more capable, imaginative personnel?
Present the Risk Severity Matrix. From that, focus only the highest priority risks, their
risk management responses and their contingency (fall back) plans. Let an appendix
contain all other risk discussions.
The year is 1994. There is murder and massacre in Rwanda. That is well known. But the
UN is over-stretched, too busy to respond. Except that is for Dieter. He has studied the
maps of Central Africa and the former Belgian Congo. There was/is a railway in the
Congo that runs over 500 miles to neighbouring Zambia. So, Dieter’s project is to restore
the railway, transport refugees to Zambia, and settle them in camps there. This needs to
be done most urgently, within a four month period.
The UN will obtain permission and co-operation from Rwandan and Zambian
governments
The UN will provide a minimal budget and armed force
The railway lines, locomotives, carriages and engineers are working to some
degree
Camps for 10 – 20 thousand people will be built quickly in Zambia
Resources will be found in sufficient quantity for the journeys
The coming rainy season will have minor effect on rail transport
Dieter made this project happen. He won medals from the UN and the German
government, deservedly.
Let us analyse some of these. For example, take risk I. We can say –
Likelihood – high
Impact – high, project is halted with long, difficult and violent delays
Risk response – transfer the risk to UN & Gov. Armed Forces accompanying the train
Contingency plan – escalate any long blocked train to UN Security Council and World
Press for help.
You may well want to add some other, better responses here. From this work, we then
build the Risk Severity Matrix, like so –
Event
Likelihood
High D
Mediu
m A
Low I
Event
Mediu Impac
Low m High t
RISK ONGOING
Project risk needs to be assessed at Project Initiation and Ongoing. Risk can change as
the project progresses. A project initially assessed as low risk can quickly escalate into a
high-risk project; a key person may suddenly leave for a new job, for example, taking
away scarce skills, vision and commitment.
Any emerging risk factors should be subject to the ‘Signpost of Danger’ control
mechanism. This has three simple steps – identify, escalate and apply. Any member of
the project team who identifies a risk shall escalate this risk and some options for its
management to the project manager, who then decides the best risk control. This
mechanism is both proactive and successful.
What can go wrong? Sometimes, the risk response does not match the situation. Or, the
persons expected to make the risk response disown the responsibility; it is not us. Or, it
is proposed simply to file (lose) the risks in a risk register. The risk response must be
thought out anew. Try again.
Next, we build the project network. This depicts the WBS, and leads to the project
schedule.
Student Questions
1. Holy Smoke!
PIA is an Italian business icon. It has many businesses. Fire is one major risk.
What kind of risk management controls does PIA use in each of these areas?
A. For investment services, PIA has a back-up trading centre outside Milan. New
traders are trained here on an ongoing basis. So, the back-up systems and
facilities are kept in use and are reasonably up-to-date.
B. For insurance services, PIA has contingency plans and rehearses them every
twelve months. Such plans specify how services would be recovered and
restarted, and in what priority order.
C. For data-centres, PIA has contracts with other data-centres to continue these
services in the event of fire or smoke damage. It also has anti-fire systems,
audits and rehearsals.
D. For property services, PIA also uses contingency plans. Each major property
complex or shopping mall has anti-fire systems and fire insurance cover.
Electricity failures are one source of fire. PIA seeks to have its facilities connected to
different electricity grids so that failure (and fire) affects some sites, but not all.
2. Rwanda
Work through risks B, C and K listed above. Develop their risk profiles as done for
risks A, D and I.
3. PFI projects
PFI projects are risk transfers from government to private enterprise. Read the fine
review paper now by Takim and others [19].
A. What are the three main difficulties in making PFI projects work?
B. What types of risks are being transferred?
Given the WBS, we can now build the Project Network. A picture is worth a thousand
words, so it is said. The Project Network depicts the sequence of tasks and
milestones found in the WBS. To build the Network, we need some terminology and
tools.
Tasks of the WBS are linked to one another in logical order and usually from finish of
one task to start of the next task. There may be a lag (delay) to start the next task
because other inputs like approvals or purchasing need to be completed first. Tasks
lead to completing or achieving milestones. These mark that a deliverable has been
built or a state of readiness has been reached. Tasks are linked in this way from the
start to the end of project.
This is called Activity-on Node planning, arguably the industry standard worldwide.
Tasks e.g. credit requirement are grouped into activities, activities e.g. analysis into
phases and phases e.g. design into project. Sub-projects can be linked into a master
project. Thank you, Mr Gantt.
CRITICAL PATH
Tasks on the critical path of a project have no scheduling ‘slack’. That is, any delay or
lengthening of these tasks immediately delays the project as a whole. The critical
path points to the project duration.
Thanks go to F John Reh for this example [20]. And Tim Tyler gives a fine discussion
of the critical path in cooking breakfast [21]. Check it out!
Often, projects need to be planned from the final deadline ‘backwards’; that is, we
must achieve the deadline and so schedule the start and phases to match.
The Project Network is the first step towards creating the Project Schedule. These are
NOT one and the same. The two differ in that the Project Network has simple task
durations only, while the Project Schedule has realistic task durations after personnel,
equipment and other resources have been allocated to each task and to the project.
PLANNING TOOLS
Microsoft Project and Primavera are the industry standard project planning tools.
Primavera is the tool for engineering, architecture and manufacturing projects. Both are
remarkably similar in look and feel.
MS Project in particular is very widely used; it has many features, including reporting,
resourcing and critical path. It also highlights over- and under-assignment of resources.
It does not support Apple Macintosh however. Occasionally, you will encounter PM
Workbench in place of MS Project.
There are excellent training videos on the use of MS Project. These are well worth
viewing.
GANTT CHART
MS Project gives both a Network Chart and a Gantt chart. The Gantt chart is by far the
more widely used. It is named after one of the Heroes of Project Management [22]. See
Appendix 8. Every project team expects to see a Gantt chart. This is a must, included in
every major project document.
There is strong commercial-legal use for Gantt charts, as Project Smart notes [23]. Check
out the case in point. That is well worth while.
Simple – like Painting & Decorating the Room – plan from start to end –
continuous activity
Reverse – like Meeting the Deadline – plan from end to start – continuous
activity
Event – like Annual Gala Ball in six months time – plan in phases –
discontinuous activity
Simple and reverse plans are fine to depict in one network diagram. Event plans are not.
An event plan is best structured and depicted in separate phases, e.g. the planning and
preparation before the event, the big event itself and the follow-up after the event.
Each of these phases usually has very different time scales, say six months, 8 hours and
two days.
As noted earlier, plans may be created by task, by time box or even by prototype.
We will revisit these ideas and address resourcing in the next chapter. Stay tuned.
Student Questions
1. Fast Builders
Review the diagram of the house build project above. What is the project duration?
The Emperor has commanded General Strong to retake the Northern Province. You
as project manager will assist. General Strong is thinking –
I will need at least two armies and the navy in place in order to succeed. Our armies
must be moved accordingly. But no army can move in the northern winter. Our
attack must start and finish in the summer. That is from May to July. Our enemies in
the west are powerful. We must take care.
My commanders advise the following times to bring their forces into position –
What kind of links are there between tasks – start to start, start to finish or finish to
finish?
3. Ho
Trials of the new wonder drug Ho have almost finished. Results are very positive. We
should prepare to release the drug. When will the drug finally be available? Draw up
a ‘best case’ plan. Use the following data –
Activity Duration
Finish clinical trials 2 months
Peer group review 3 months
Australian regulatory Ok 6 months
US regulatory Ok 18 months
Auction patent rights to drug 4 months
Production ready 4 months
Media launch 2 weeks
Medical marketing campaign 3 months
Tasks are not in any particular order. Use your business sense.
US Federal Drug Authority approval is very important. It has three stages. Often, a
drug is required to continue clinical trials over a year, and then resubmit for approval
of that stage. If required to resubmit a second time, the drug that is usually
withdrawn.
So, as a warm-up exercise, tackle Student Question 1 now. That concerns Captain Cook’s
famous voyage to Brasil, the tasks to get there and the resources needed. Soccer,
Surfing, Samba …
SCHEDULING RESOURCES
Project task network times are not a schedule or plan until resources (personnel,
facilities, etc) are assigned or allocated. It is common to find that project duration
increases once resources are assigned. Check out Appendix 7 now. That shows how a
simple project changes duration as more resources are made available.
Some resources may also be constrained. For example, some personnel may only work 3
days a week; some laboratory facilities may be available after hours on a shared basis
only.
What is the normal way of allocating resources to tasks? MS Project uses the Parallel
Resource Scheduling algorithm. Its rules are given on Appendix 9 along with an example.
RESOURCE LEVELLING
In reality, most organizations have barely sufficient project resources. These are
dedicated to separate, isolated teams. Also, process, technology and business skills are
usually barriers between teams, as are ownership and budget. So, resource levelling
seldom occurs.
SPLITTING
‘Divide and conquer’ has been a guide for managers since ancient times. It remains just
as relevant and practical today. The project manager is always looking to see how each
project and each task can be split up to better meet the requirements of scope,
resources, budget and timeframe.
BOTTLENECK
Sooner or later, most projects require specialist input, review and guidance. However,
most organizations employ as few specialists as possible. So, there is a queue or bottle
neck until such time as the specialist your project needs becomes available.
HAMMOCKING
A hammock is a canvas sheet stretched between two poles. In the project world,
hamocking means to stretch the labour of the project manager between the start and
the end of the project. That is, the project manager works and is allocated across the
whole project.
Often, we also hammock executive management across the project, but count say 1-3%
of management time on each project. This way, management time is also counted in our
project time and costs.
Student Questions
1. Voyage to Brasil
For the voyage from Plymouth UK to Rio Brasil in 1770, which resources are needed for
each task?
Task
a Sponsor voyage
b Fund voyage
c Assign Captain & Ship
d Stock ship
e Crew Ship
Sail from Plymouth thru English Channel to
f the Atlantic
x Fight off pirates
g Sail across Atlantic to Rio
h Dock in Rio
j Repair & refit Ship
Resourc
es
2. Posh Tosh
Lucinda is project manager for her family firm Posh. That owns and rents top class
houses, apartments and studios in central London. When a rental lease ends, the
property is cleaned and refurbished. That takes from 2 to 5 days, depending on size and
condition. Posh has a small maintenance project team to do this.
Today, Lucinda bought a run-down block of four apartments in Chelsea. These need a
complete refit, taking an estimated 30 days intensive work. Also, legal permissions and
documents must be signed and exchanged before work can begin. That can take 30-40
days too.
Just now, the maintenance team is finishing the refit of 7 Lenster Street, with an
estimated 2 days to go. Bad News! The water heater burst and flooded the studio at
45B Baker Street, and overnight vandals trashed the house at 3 Cliveden Lane. After
police and insurance inspections over 1-2 days, each will need least 5-10 days work to
repair.
Oh, a fax has come in! The resident at 12 Half Moon Crescent has terminated his lease
today.
So, when can Lucinda put her block on the market? Draw up a schedule. What are your
project assumptions?
Hint. Work out the expected maintenance work load per week, given the data above.
That is the weighed average of the best case, normal and worst case maintenance loads,
as follows – Expected = (best*1 + normal*4 + worst*1)/6. What then is the available
capacity for refit work and so Lucinda’s best plan?
3. SteelO
Allocate a one month time box to gather and define the requirements for
each core business, namely manufacturing, logistics and finance
Allocate a six months time box to build, issue and accept tenders for new
systems
Allocate a twelve months time box to install and train in new systems across
the group
Allocate a six months time box to collect and review performance data
Allocate a one month time box to audit the project.
Before each time box, allow one week for selection, training, tooling and administration.
Assume Board approval for capital expenditure (on new systems) takes four months to
win. That is the best case.
When will the new SteelO emerge? What are your project assumptions? When should
the Chairperson issue a glowing media release about this business change to the New
York Stock Exchange?
4. Ooki
Ooki is a boat building firm in Finland. The good news is that Ooki has won two
contracts.
The first contract calls for 15 patrol boats for the Gulf States. That is on the same
standard model of keel and engine as the most recent build, but is 5 boats more. The
second calls for 10 standard patrol boats for the Italian coast guard.
The keel building yard can only fit three keels at a time. The assembly line can fit only six
boats at a time. There is a warehouse that can hold ten boats and ten engines. On the
nearby lake, there is a testing and trials facility for two boats at a time.
Once trials are passed, boats are stored in a hangar ready for delivery; that holds 10
boats. Keel, assembly and trials are expected to take 3, 2 and 3 weeks respectively.
When can the contracts be finished? The Gulf order is done first.
Ooki decides to outsource the second contract to Raiko, a firm with capacity
available right now. It takes 3 weeks to devise, negotiate and agree the outsourcing
deal. Now, when the contracts be finished?
A new contract has been opened for 4 patrol boats for Papua New Guinea. Boats
must be ready to deliver in 20 weeks or less. Should Ooki bid for this contract?
4. Tiffin
Batman Butter is a listed firm on the stock exchange. It has missed the accounts
reporting deadline twice. So, either it tables a complete set of audited accounts to the
exchange by September 1, or it is delisted. Today is January 1.
To present the accounts in the format required will take 1-2 weeks. An audit of accounts
usually takes 2-3 months. Tiffin, an accounting firm in Chennai, will consolidate and
prepare the accounts, given paper or electronic records. That will take 6-8 weeks per
company set. A reconciliation of the accounts, once consolidated, will be essential. That
needs 2-3 months.
Batman has four ultra-modern factories and two antiquated factories, A and B say.
Records are held on the SAP accounting system in the former, but not in the latter.
Mercy! To find all the relevant records could take 2-6 weeks per site.
B. Draw up a plan to make sure Batman Butter meets its deadline. Allocate task
times as necessary, not as desired or as usual. Do as you think best.
Now that we have assigned resources (and costs) to all tasks in the Gantt chart / Project
Network, we have finally got the Project Schedule. So, we see now the Project Duration
and the Critical Path. Everybody on the project wants to know this key data. Let us
understand more. But first, let us take a Baseline.
PROJECT BASELINE
Project Baseline is an (initial) cut of project schedule, budget, scope and yardstick for the
rest of the project. Progress and variance is measured against the baseline. If later a
change request for say added scope is approved, the project is re-baselined.
Often, non-critical tasks are far off the critical path so that they are unlikely to reach the
critical path, if delayed. Sometimes however, some non-critical tasks are close enough to
reach the critical path, if delayed. In such a case, a second or third path through the
project network may become critical instead. This type of project network is called
sensitive. Don’t be caught unaware of this on your project.
Take the Project Duration. The usual reaction is Oh! That’s too long! How can we
address this?
A must is to rethink and replan the remaining work, hand-in-hand with the project
sponsor.
Cost crashing seeks to find the least cost route through the project network to reduce
project duration [24]. In principle, that is a fine idea. In practice, we do not know project
costs accurately or finely enough to use this approach. Also, crashing larger networks
soon becomes unwieldy.
How can we keep the schedule up-to-date each week as the project progresses? We
need to do four things –
Enter the actual times spent on our tasks over the week past,
Estimate the time yet to spend on our tasks over the next week,
Update and review the Gantt Chart accordingly, and
Use MS Project to report any missed milestones and other exceptions.
APPROACHES to ESTIMATING
By Industry Data and Benchmarks – less rare, but costly or little comparable
data
By Function Point Analysis – rare, demands technical expertise and debated
By Time Boxing – less rare but successful; used in rapid development projects
Some project tools, including Primavera, include task estimates. That helps civil
engineering and building construction greatly, provided new projects are truly similar to
old ones.
UNCOMMON ESTIMATING
Statistical Analysis/PERT – In reality, projects tend not to fit into neat statistical profiles.
There is significant variation from project to project in the length of each phase. This
dates from the 1950s and now is all but unknown [25].
Time Box – As we know, this uses a fixed duration or time box for each major phase of a
project. The end date of the time box never moves. Tasks are managed to fit in the box.
Time boxes offer convenient Top-Down estimating. They are also easy to understand
[26].
PRACTICAL ESTIMATING
To Go or Rolling Estimate – Simply the estimated work period that is still required to be
completed as of now, no matter what the project schedule says or what the project
manager would like. Re-estimate each week. The estimate becomes more accurate as
time passes. It is 100% accurate at task completion!
Team Review or Bottom-Up Estimate – Those doing the project work are asked to
review and revise work estimates or any other part of the project plan or definition.
Informed consent is essential to work the plan.
In Fixed Price contracts, estimates of the project work required are most telling. Under-
estimates mean unprofitable contracts. Over-estimates mean failure to win contracts.
By the way, estimates for the very same project differ dramatically with the estimating
environment or organisation. A small software house will estimate the work as a fraction
of the time that a large bank or insurer requires. Both parties are amazed at each other’s
estimates.
Student Questions
1. CAD!
Toai is a small New Zealand firm specializing in Computer Assisted Drawings (CAD) for
property developments. Toai has decided to expand into Hong Kong.
With amazing luck, it wins a contract to supply drawings for housing estate projects on
Lantau. Great Fortune Properties is the owner of the estates. Today is February 1st.
Drawings for the Discovery Bay estate project must be ready on June 1st, and for the
Silvermine Bay estate on October 1st.
Progress is fine. Toai has one partner and one draftsman in Hong Kong hard at work;
double those numbers at home.
Great Fortune decides to bring forward the opening date of both estates by two months.
After all, rumour has it that competitor Noble House is planning to open its estates on
the same dates too. All the building subcontractors are impacted including Toai.
B. How can Toai adjust? To quit will ruin its reputation. To recruit new staff will
usually take one month.
2. Ball Park
Make a rough profile estimate for the Iinsure call centre project. It has the following
sub-projects –
Supplier ISI performs the technology and desktop projects. Its slow, review-based
process adds one week to every four weeks work.
If all these sub-projects were done in order, when would the call centre open?
When must Board approval for technology purchases be done, in order not to delay
the project? Assume purchases are ordered as soon as approved with a three week
wait for delivery.
BUDGET BASICS
Sadly, those who authorise project budgets often allow no reserves whatsoever. Instead,
a business case must be made, presented and approved for any extra project funds. That
means delay. Is the project delay worth the extra control of spending?
Extra costs may arise innocently from changes of licence versions and costs, exchange
rate changes, new work or licences now realised necessary, etc.
Capital expenditure
Operating expenditure
Suppose our project is to build, equip and commission a new data centre on land
purchased for that purpose.
However, the definitions of Capex and Opex vary from organisation to organisation. It is
common to find that labour costs in the first three (build) years of a project are
capitalised, while labour costs in the later (maintenance) years are not. Check with your
CFO. Find and follow the convention here.
The simple budget, the capex budget and the opex budget all will show the spread of
project spending over time. As well, it is desirable, no make that necessary, to show the
spread of project spending by asset in a pie graph chart.
ACCRUALS
Funds for planned expenses must often be accrued until the expenses are in fact
recognized (invoiced), whether paid or not. How does this work?
For example, employers know that they have to pay employees at the end of the month
before they actually credit salary payment accounts. This expense is entered into an
accrued expenses account as a liability; when the company later makes the salary
credits, this accrued expense is zeroed and cash assets are debited.
Check out the mechanics of accrual in your organisation. There are end of period rules to
consider too.
And any funds unspent at end of financial year are often withdrawn. You wouldn’t want
it to be easy, would you?
Many in the organisation are uncomfortable with project finance and budgeting. They
are specialists in other disciplines. You may have to help them.
Student Questions
1. Montebano Sono
The Italian Students Association (ISA) is planning a Dance to raise money for refugees
from North Africa. The theme will be Salvo Montebano, the famous detective chief.
Angela is capo or chief; she is planning the project.
The ISA has about 400 members. Assume 50% will buy a ticket, and 25% of attendees
will buy a ticket for a friend or partner.
A. Harbour Cruise
A harbour ferry has capacity for 300 guests and costs $2000 to hire for the evening from
8pm to 8 am. Cleaning must be done by professionals, ready for the next cruise. That
costs $500. Use of big screen video and karaoke is free. DJ and bar can be arranged.
The Foyer has capacity for 250 guests and costs $1500 to hire for the evening. Cleaning
must be arranged by the hirer, ready for the next day. The Gallery is cool and
interesting. It has many facilities. Hire of big screen video costs $250 for the evening.
C. Princessa Dance Hall
The Princessa has capacity for 500 guests and costs $1000 to hire for the evening.
Cleaning must be arranged by the hirer, ready for the next day. It is not so cool. Use of
big screen video is free.
Angela assumes that the Master of Ceremonies, Medical Aides and Cleaners will be
volunteers. It will be fun also to have a karaoke contest and prizes –
Another option is to invite the African and Drama Students Associations to join in. These
have about 100 members each.
So, how should Angela decide the best option and what are the –
Va bene.
2. Rotterdam
The Dutch government plans a new highway between Rotterdam and Amsterdam. That
will be a dual two-lane highway. The distance point to point is about 80 km. The cost of
highway construction is $30-40 million per kilometre.
About 50% of traffic will be heavy trucks: that requires two reinforced lanes each way.
PFI Partners have won the contract; that runs for 15 years. PFI earns an annual toll fee,
adjusted every five years for inflation at 4%. It expects to operate and maintain the
highway at 7% of costs, with costs rising slowly by 1% every 10 years.
The Dutch government sets down service performance standards. It may deduct
penalties from the toll fee if performance is below standard, or even award the contract
to another party.
If traffic usage changes significantly, the government may also invoke a contractual
adjustment clause requiring PFI Partners to bring the highway up to new standards. PFI
will be paid for any contract variation.
B. PFI want the Payback Period to be 10 years. What is the Toll Fee?
3. Mercury
Rocky is a new PM at Mercury, which uses accruals accounting. His project has a number
of scheduled payment milestones to Hermes, Diana and other suppliers. Some delivery
milestones are met right on schedule; some are not.
All these firms are giants; it takes one-two weeks to raise an invoice or make a payment
through the right channels. Invoices and payments initiated in the second half of the
month usually fall into the next month.
Nervous, Rocky makes the following payments and accruals for project expenses –
B. What should happen if the November payment to Aries falls into December?
CHAPTER TEN – UNDERSTANDING AND TRACKING THE BUDGET
Meet EVA, Earned Value Analysis. EVA is typically used in mega-projects, especially
where there is a high political profile and a need to be seen convincingly on track. Lesser
projects typically do not yet use EVA.
Read now the Case Study EVA at Monica Park by Valle and Pereira Soares [27]. This is an
instructive example. See Appendix 7. We reproduce the Basics below.
EVA originated in the US Department of Defence. The EVA technique is widely used to
get better cost and schedule control.
Bhosekar and Vyas also give an instructive case of EVA [28]. Their graph is reproduced
below.
Standard Earned Value Analysis Graph
As well as the Basic indicators above, we also need Percentage Completion Indicators
too –
A – Actual
C – Cost
E – Earned
P – Planned or progress
S – Schedule
V – Value
Student Questions
1. Seattle Terminal 91 Build
This $70 million project built a large, two storey cruise terminal [29]. It was complex
with-
The project manager felt that it was insufficient to monitor the critical path alone.
So, this project used –
EVA
A data model of every level, floor, facility and room, and their fittings
Inspections to check and confirm some EVA / data model results.
The data model is large and complex. The inspections are selective and do not cover
every facet. What problems if any do you see here? What do you recommend?
Le Bin is bidding for the concession to build and operate 4 supermarkets with Carrefour
in Vietnam. Supermarkets are his family business. An average supermarket should yield
about 6% of costs in the first year, 12% in the next three years and 8% in the fifth year.
At the end of 5 years, Carrefour will buy out the concession; it will pay $250k per
supermarket.
What maximum bid should Le Bin make per supermarket to make this a good
investment project? Today, the bank benchmark interest rate is 3% and inflation is
running at 5%.
3. Blyth Street
The Gas & Fuel Corporation has decided to modernise its services. It will replace gas pipe
connections street by street and has hired BIC to do this. BIC will update 10 connections
each day, each worth $250. Such is the plan.
There are 1000 houses, units or businesses in Blyth Street. So this is a 100 days pilot
project.
Finding and changing the connections proves difficult, however. After ten days, BIC has
updated 73 connections only. The cost per connection with extra labour is $350.
A change request
A budget cut-back.
CHANGE REQUEST
Three months into the new project, the Sponsor notices that four requirements have
been omitted. As PM, what will you do–?
A. Ignore the items. Fifty of more requirements are now under development.
B. Include the items. They’ll have to be addressed, right?
C. Schedule the items for the next version. That tidies matters up.
D. Convene a Change Management forum. Another meeting, alas.
E. Investigate why the omission occurred.
Note that the time boxing approach is designed to cope with and include some chosen
change, because work is prioritised to fit into the timebox. It is flexible.
What does the Change Management Forum do? First, it prioritises the changes from
must-have through to nice-to-have. Next, it assesses the costs and the benefits of the
changes, and their impacts on the project schedule. So then, it decides to accept or
reject the proposed changes on merit.
A must-have change may be accepted and included in the project, delaying the
schedule. In this event, a new project baseline is made straight away.
Note that in the weeks of the Change Management Forum, the project is usually on
hold/frozen.
What can go wrong with this process? It can be difficult to find new funds for the
accepted changes. Can this slow process be streamlined too?
BUDGET CUT-BACK
Executive Management has announced a budget reduction of 20% across all projects, to
be applied by the PMO without fear or favour. That may mean your project.
Which projects are cut? They include –
Student Questions
Texas Bell is a large telco. Now, the economy is in recession. Azziz orders a $15 million
cut in project budgets with immediate effect. Some projects are listed below.
Background is as follows –
A. Julie and Bai are updating engineering networks for the release for 4G mobile and
high speed broadband services. The benefits are convincing. The remaining project tasks
are largely testing for operational readiness. Ideally, Bai needs six more engineers for 3
months. Contract rate is about $600 per day.
B. The mobiles area has many minor projects like the ones above. The benefits are hard
to discern. Updates of mobile security will come, but are 12 months or more away.
C. There is an unending stream of services to assure from all over the business.
Assurance is a must, but is slow and costly across projects, technologies and suppliers.
Could this area be outsourced for a better result?
D. Kevin has been unable to progress this project beyond the planning stage, despite
much help.
E. Like the mobiles area, the traffic area offers little convincing benefit. What happens
with or without traffic analysis?
F. This project was justified by Sam. His quick-and-dirty estimate was just that. The
scope was insufficient to deliver the goods. Now fully scoped, the costs are too high.
G. These reporting enhancements were promised to Mega, our VIP client. Projects are
stuck again. The reporting tools cannot deliver.
PROJECT AUDIT
AUDIT AIMS & AGENDA
Let us perform a Project Audit of the Home Care case below. A Project Audit aims to
discover and define what are the –
Benefits planned and realized
Costs planned and realized
Lessons learned
Follow-up actions required?
Let’s go.
Home Care is part of the social fabric of Ontario. It has over 1,000 offices large and small.
Every town or suburb has one.
Home Care serves a wide clientele: the abandoned elderly, First Nation people, children
in care, the disabled, HIV patients, nursing mothers, patients newly released from
hospital, refugees and many others. Dedicated specialists, nurses, social workers,
paramedical staff and volunteers provide the care. Behind the scenes, bookkeepers
schedule and reschedule appointments, and record the fees for services incurred.
Reporting and accounting are centralized in the Toronto office. Home Care falls under
the responsibilities of the Minister of Health.
At the heart is the reporting of service performance, for each interest group has vocal
demands. Interest group politics is played hard. A biting expose will be in the press
tomorrow if demands are not met today. Rottweilers are gentler.
Phillipa, the new CEO, proposes a radical scheme. She will cut costs by dispensing with
all the bookkeepers and combine the two carer-bookkeeper jobs into one. She will
require each staffer to schedule appointments and to book fees incurred. With the funds
saved, she will automate performance reporting and accounting across the state. The
result should be a more flexible, need-focussed and timely service for all.
To achieve this, new systems and infrastructure are required. Costs are expected to be
$3-4 million. Tenders are called. The automation of Home Care begins.
Armano, a blue-chip management consulting firm, wins the tender. It plans to use
software called Flexi to provide the new flexible scheduling. That is the key component.
Armano outsources the evaluation of infrastructure to contractors.
Things begin to go wrong. Soon, Armano finds that Flexi cannot do or be modified to do
what is required. Very few people are notified of this. Work continues. The tender is not
recalled. Armano decides to use its staff to program the new scheduling, raising costs.
Worse, the programmers cannot obtain any guidance on these complex scheduling
requirements, and so program the new exactly as the old. There is no review and
improvement, and no added flexibility. The old is concreted in.
The evaluation of infrastructure passes quickly, almost unnoticed. The contractors
depart. The data for current capacity, expected growth of services and future capacity of
infrastructure barely fills one page. The evaluation is almost as brief.
The bookkeepers are dismissed. The new role is announced. Staffers are dismayed and
upset; most are career-long carers, and cannot or will not become clerks and
bookkeepers as well. A change management team is set up, but is promptly axed.
Meantime, systems work has fallen way behind schedule. It is much more complex and
costly than imagined. Early plans called for numbers of staff to assemble in Toronto to
perform testing in August. They start to arrive. This is premature. Project Manager Joe
calls a halt to this. He is promptly dismissed.
Eventually, Home Care is automated. The results are not pretty. Costs were $12 million,
excluding outstanding long service and termination payments to bookkeepers (say $10
million). Reporting is much slower, more frustrating and incomplete. The infrastructure
is already overloaded. Another $5 million is needed to fix this. And say another $7
million on top to obtain flexible scheduling.
The Minister wants to see you, Jack is told. The Minister and his staff are angry; they
know what could have been achieved, and what has been achieved elsewhere. Like
sandcastles, hopes of a better service are swept away.
Yet, the project audit requires sign-off from Phillipa, Amano and others. There is a limit
to what people will admit, when it reflects badly on them and threatens their future. The
audit is fair but qualified or compromised. A Ministerial Inquiry or Royal Commission
would audit more freely.
The Ontario Treasury wants to see you too, Jack hears. Officers of Treasury cannot
understand what could have gone wrong with the tender and the infrastructure
evaluation. We have a clear, well-established framework for such work, they say. Jack
explains that is an administrative framework only. The officers do not see.
At last, Bright Hope is paid for the audit. Interest groups are on the attack. Watch out!
So, what were signs that things were going wrong? These include –
The Minister of Health is involved (early) in the project. The Minister’s budget
responsibility is billions of dollars; this project is millions of dollar.
People started to arrive on schedule for testing but were turned away
People are fired early / often e.g. PM Joe and the Change Management team
The key change of job is unacceptable to almost all carers, but that is ignored.
Changes are made anyway.
No personnel are on hand to define better, streamlined workflow. The old workflow
is reused without any improvement or flexibility.
1. Nobody from Home Care, the Ministry or Treasury is actually managing the
tender, the infrastructure assessment or the project
2. Nobody is aware of changes / events that made the project much more
expensive than planned. These are not tabled and discussed, but passed
over.
4. The key system Flexi is chosen without testing its ability to schedule work like
Home Care
5. The tender should have been halted and restarted when the key system
failed at the very beginning
6. No expertise is made available to build better workflow or better services,
guaranteeing wasted effort.
We leave the Costs and Benefits as a Student Question for you. What then are lessons
learned and follow-up steps needed? These include –
OTHER FACTORS?
What about a brake on rash and unworkable changes? Would a mandatory feasibility
study, at least in big projects, help? Yes, but that omits smaller projects like this.
The carers triggered the Minister’s early involvement in this project. But ultimately, that
led nowhere. Would matters have been different in a strongly unionized country like
France or Spain? Perhaps
PROJECT CLOSURE
Project Audit and Project Closure are similar processes. Project Audit is more focused on
commercial outcomes, and is best conducted by independent auditors from outside the
company. Project Closure is more focused on completeness and lessons learned.
A large corporation may choose only ‘troubled’ projects where project directors want
participants to reflect and learn. A blue chip consultancy may choose every project in
order to build up a database of experience.
Project closure reports are usually done, if at all, within 3 months of end of project.
As before, we first ask ourselves – signs, problems and causes?
Student Questions
1. Home Care
2. Julie Bravo
Make a Project Closure Report for the ‘Julie Bravo’ game project in Appendix 10.
We have left broad organisational matters as one of the later chapters of the book,
simply because as employees we have to accept, fit in with and use the organisational
structure, its project processes and peculiarities. Like the marriage contract.
TYPES of PROJECT ORGANISATION
The usual form is the so-called Strong Matrix Organisation (also known as Matrix
Organisation and Project Organisation), where we all have at least two reporting lines
and responsibilities. The advantage is to spread scarce expertise across many projects.
The disadvantage is sometimes conflict of responsibilities and demands.
Alternatives are –
Some examples will help. Sentry Insurance Hong Kong realized that in fact insuring high-
value motor cars would be much more profitable than insuring any and all motor cars,
especially if theft could be reduced. So, it started a project to bring on new high-value
motors onto the books and to shift other motors off the books. The project required
deep expertise in a traditional functional area, motor insurance.
The areas of the business all took part without any change. The project worked well. In
the first year, the gross profitability of the new book was the reverse of the usual loss.
This was a functional project team at its best.
For its top priority transformation project, Telstra set up dedicated project teams. These
remained in place for about two years. The advantage was to allocate the most able
resources to the work. The disadvantages were several.
BUREAUCRACY!
Air France, Amazon, Boeing, Cisco, Citibank, DHL, Ebay, iTunes, Orange… all support
millions of products. So, project delivery in these businesses must be ultra-reliable. New
projects must not disrupt existing products and services. New products and services
must perform superbly and long term.
How is that achieved? Holding reviews throughout the project lifecycle from
requirements to deployment. That means a lot of reviews and documents to review. So,
the process here is naturally bureaucratic. For new hires, this often spells culture shock.
OMG!
Other businesses, say a Woolworths, focus on rapid project delivery to capture the
moving consumer market. For these, such bureaucratic process would be inappropriate.
GOVERNANCE
How are projects best governed or controlled? One of the simplest and best ways is to
use PRINCE2. That stands for Projects in a Controlled Environment version 2 [30].
Here, controls are applied at stages or gates. The first stage is called say Initial
Investigation. To enter this stage requires an approved business case. During the initial
investigation, costs and benefits estimated in the initial business case are refined. If the
new figures are within a tolerance limit of the old, then the project is allowed to enter
the next stage, development say. The business case is updated. And so on. If the
tolerance limit is exceeded, the project ends at this point.
Within each stage, the project may be worked by whatever process is deemed fit, be it
classical project development, time boxing or prototyping.
Government agencies and Universities with limited public funds that must be
spent to best effect
To govern a work program of 50-60 projects, we use program governance. That herds
projects in priority order through Prince2 stages and/or development phases to
completion.
TRAINING
In this author’s view, PMBOK (Project Management Book ok Knowledge) [31] is a fine
qualification for those who want to know about projects e.g. sales and support staff. It is
arguably not the qualification for those who want to deliver projects i.e. project
managers.
Alas, training in industry standard applications is often a matter of luck. Your firm has
chosen SAP, say, so now you will be trained at company expense in its use. Lucky are
you!
By the way, some common training courses need restructure. HR chooses candidates
only with the highest qualification e.g. PRINCE2 Practitioner, as a matter of policy. That is
whether the highest qualification is necessary or not. So then, other suitable
qualifications e.g. PRINCE2 Foundation are ignored, null and void.
Student Questions
Why is it important to assess the culture of the organization before deciding what
project team structure to use?
The Managing Director has another project in mind. That is, to transform Sentry as a
customer service-driven insurer, and so to capture new market share. This project
will need work, change and co-ordination across every area of the business. Is the
Functional Project Organisation right for this project? What do you recommend?
CHAPTER FOURTEEN – PROJECT AND PEOPLE
Characteristics of Teams
Think of a good soccer team like Arsenal or Barcelona. Consider how it plays. A team in
sport, business or the armed services has –
Shared leadership and responsibility – little gap between captain and crew
Shared success or failure – we won.
A group of people is not a team, unless first they have stormed, normed and formed a
team. If so, then they will perform as a team. A group cannot be arbitrarily called, or told
to be, a team.
A virtual team is one that is spread around the globe and that is in contact only by
conference call, email and fax. This is more and more common, bringing together say
outsourcing from India, technology from the USA, resources from Africa and local
interests.
Typically, the so-called project team is simply a group working under the direction of the
Project Manager. It is not a team. But, you will have to accept being called a team many
times. That is part of the price of employment.
Limited communications
Limited discussion and debate
Limited sharing of goals and responsibility
Goal dissonance or dissent.
To solve these problems, force is usually applied. The team and its tasks are micro-
managed (and unempowered). This often completes some tasks, but suppresses
communication and makes team work even more unlikely. Where can this lead,
especially when combined with a lack of honesty?
Dysfunctional Teams
To say that ‘All we need is a good tool. That will solve all our problems’ is common. This
shuts the mind to real needs e.g. proper management, processes, prioritisation,
openness, etc. Our heads are stuck in the sand like emus.
Technical people want the job, the world and the project to be technical.
Non-technical, organisational issues are inconvenient and not the right stuff.
To say that ‘We are on schedule’ is common too until suddenly we announce failure at
the very last moment. This ignores the fact that failure set in much earlier, but was not
admitted or addressed. Sponsors and stakeholders are angry, embarrassed. The team
excuses itself and is fired.
Project teams, airline pilots and others have a strong achievement drive.
They are also persistent, used to difficulties and used to macho effort. They
are from the technical professions, where communication and openness are
traditionally weak.
In the circumstances of the project or flight, there is often ‘must do’ pressure
and expectation to perform. The above people do not expect to fail – ever.
So…
These days, major corporations are training their personnel in Ethics. That is the study of
good, moral conduct So, are any of these actions Ok –
There are many lists of criteria for an effective or good project manager. Rather than
revisit these, we accent the positive. There is a fine case study, the Pennsylvania State
Water Plan; note the care taken to get the people skills and the processes right across
this large and complex project. Bravo!
Student Questions
1. Ethics
Why are the actions A, B and C above unethical?
A. Find and compare three or more lists of criteria for an Effective or Good
project manager. Is there a core of common criteria/which?
B. Is the ace technical guru the best candidate for project manager?
D. How should the criteria differ with the project organisation, be it large or
small?
Based in the UK, Regal is a major general insurance house. It has subsidiaries and joint-
venture companies scattered throughout the globe. Insurance processes and, to a lesser
degree, products are more or less uniform globally. Regal sees that the key difference is
size of business or population.
This approach is popular and effective. Most businesses are happy to follow central
policy in systems. As a result, the Regal Group achieves economies of scale and skill.
From time to time, Regal will replace or renew systems within each size category. That
generates projects of international scale. Project teams report both to the UK and
locally, but funding is local.
On occasion, mismatch of central and local goals can spark conflict. But that is
uncommon.
Chemonix Saone Basle (CSB) has major banking interests in the UK, North America and
Japan. It also has subsidiaries and joint-venture companies scattered throughout the
globe.
CSB tends to run systems projects on a global scale often. Examples include year 2000,
desktop refresh and BASEL compliance programs, among others.
Central policy best reflects the interests of the largest and most sophisticated businesses
within the group, namely the UK and US operations. However, policy is a
recommendation only.
Projects are funded locally, with both local and global reporting lines. On the ground, the
local project manager has great responsibility but little authority.
Mismatch between global and local goals is common and difficult to resolve. The norm is
naturally that projects exist to achieve local business goals, operations and products. So,
support for any global project is often debated, disputed and tardy.
Siam Insurance Thailand (SIT) decided to renew its systems with the Sherwood general
insurance system, originating from the UK. At SIT, systems were managed by an Indian
subsidiary Kali. The firm itself is part Thai-, part Indian-owned.
However, Kali rejected this approach, wishing to retain its role as principal and sole
manager of the project. In the end, the project was completed in the traditional way.
Other factors
Just Do It!
Finances
Coffee Break!
Tact
Perfection
There is a tendency to leave all our project management experience at home and just
buckle down to get it done. That usually fails. The basics of project management, like
Scope, SMART, WBS, Budget and the rest are basics for very good reasons.
What may be an average salary for a US, UK or Canadian project manager may equal or
exceed the salary of an Indian Managing Director. What is normal rental and cost of
living expenses in Hong Kong and Japan are unsupportable on a US, UK or Australian
salary. Without appropriate change, such personnel arrangements and projects will not
begin or work.
Normal office behaviour to take a coffee break at home may appear erratic and
undisciplined abroad. Check first.
No doubt, practices differ. But everybody believes they are just as capable and advanced
as anyone else. Comparisons are tactless and counter-productive.
Are you working in a tolerant or perfectionist milieu? New Zealanders might reject a
project that delivers only 85% of outcomes planned, saying this does not work.
Australians might accept the delivery, imperfect though it is, and prioritise defects for
later releases.
Culture Matters
‘The strangers came across the shores to teach us their ways. And they blamed us
too for bein’ what we are …’
Phillip was working for a large American company that supplies auto parts around the
world. His area was purchasing. Managers were expected to obtain orders, sign-offs and
payments from clients on time, or else. Like clockwork. After several years in Malaysia
and Singapore, Phillip was sent to Thailand. His project was to train and lead Thais to
follow US practices. As we know, Thailand is an important auto and motorbike
manufacturer.
Energetically, Phillip explained and insisted on the new purchasing procedures. And he
hired Thai account managers with great connections to swing things too. But to no avail.
It was clear that procedures were not being followed. Even head office in Hong Kong
noticed. Thais listened to but politely ignored Phillip. Orders and payments rolled in
anyway, sooner or later.
Sanuk is the Thai word for fun. Phillip did not have time or patience for that. After
another year, he was fired.
Student Questions
1. Thailand
Congratulations! You are to replace Phillip. Before you take up the job, do some
research. Can you -?
Find a case study of successful Foreign-Thai project. Why did this succeed?
2. Turkey
Turkey is booming, so they say. It is building perhaps the world’s largest airline hub, and
is rebuilding hospitals throughout the Middle East. There are property development
projects and oil & gas pipeline projects too. Can you -?
Find a case study of successful Foreign-Turkish project. Why did this succeed?
Title confusion
Title inflation
Title deflation.
The title Technical Project Manager is confusing. Where do the responsibilities of the
Project Manager and the Technical Project Manager begin and end? Who exactly is
responsible when things go wrong? Forget it. This title should be Technical Consultant.
The title Project Manager is sometimes given to Assistants in the Public Service or
Education industries. This is purely nominal; no Project Management duties are
performed. High status title is given perhaps in lieu of salary. The title should be
Executive Assistant.
The title Project Leader is sometimes given instead of Project Manager, the title Project
Manager instead of Program Manager and so on. This is a ploy by employers to save on
salary.
APPENDIX 3 – ROYAL LIVERPOOL HOSPITAL, A PFI CASE STUDY
Denis Campbell
The Guardian, Friday 6 July 2012
It sounds like the sort of hospital every patient wants to stay in. All inpatients have their
own room, all 643 of which are en-suite, and there is a large, tree-filled green area
outside to admire from the window. This is what the Royal Liverpool hospital will look
like under plans for a £455m development – with £242m of that coming from a PFI deal
– which has almost been finalised. Work is due to start in 2013.
No one doubts that the existing hospital – due for demolition and once likened to "a
little bit of eastern Europe" – needs to go. One member of staff says: "This building isn't
fit for purpose. Its systems – heating, water, ventilation and electricity – are failing.
Everything is failing. The systems are expensive to maintain and are very disruptive
when they do fail."
The current hospital was only built in 1974, much more recently than a lot of other
National Health Service (NHS) stock. But a wrangle over health and safety meant it was
not fully occupied until four years later.
Its replacement is taking time to move from concept to reality. In March 2010, just
before the last election, the Labour health secretary Andy Burnham approved the plan.
Two months later, the newly elected coalition called a halt to all pending PFI deals, while
ministers examined the state of the public finances they had inherited. Weeks later, the
new health secretary Andrew Lansley gave the scheme his blessing.
The team behind the planned new Royal Liverpool hospital had learned lessons from
other PFI projects, and their plan would deliver value for money, he said.
The use of PFI is back in the headlines after last week's announcement that South
London Healthcare NHS Trust became overwhelmed by debt. It has to pay £61m a year
in PFI repayments, a massive 14.4% of its income.
It is usually 6% to 10% elsewhere, said Prof John Appleby, chief economist at the King's
Fund health think tank. "To focus on PFI as a cost which could break a hospital seems to
me not right, when you consider that pay is a far bigger cost – usually 70%," he says.
APPENDIX 4 – MONICA PARK, AN EVA CASE STUDY
THE USE OF EARNED VALUE ANALYSIS (EVA) IN THE COST
MANAGEMENT OF CONSTRUCTION PROJECTS
Jose Angelo Valle, Carlos Alberto Pereira Soares
ABSTRACT
The objective of this article is to present and discuss the main factors involved in the use
Earned Value Analysis (EVA) in the cost management of civil construction projects. These
factors include advantages and disadvantages, difficulties and benefits, problems and
solutions and criteria and results based on the experience of a real case study in Brazil.
EVA was applied in the civil construction of an indoors amusement park, named Monica
Park. It is inside the Citta America Shopping Centre, in Rio de Janeiro, Brazil. The park has
30
attractions, covers an area of 10,000 square meters and was built in 10 months from
January to October 2000 for US$ 5 million.
The Monica Park is an indoor amusement park based on the concept of a Family
Entertainment Centre located at the Citta America Shopping Centre, in Rio de Janeiro
City, Brazil. The park has 30 attractions with an instantaneous capacity for 1,300 people, a
daily capacity of 4,000 people and an annual capacity of 300,000 people.
The park has an area of 10,000 square meters, including areas for fast food, special partie
and a shop related to the theme of Monica, a child book character famous in Brazil.
The construction work took 10 months and was completed in 2000.
Thematization is the complex services related to provide the park with thematic elements
related to the theme of the park: Monica Park. One of the main suppliers was the compan
which provided the thematization of the park. The operation of the park was largely
implemented through contracts for fast food operators, thematic shops, cleaning services
APPENDIX 5 – JULIE BRAVO, A PROJECT CLOSURE CASE STUDY
Post mortem: Julie Bravo
By Scott Alden
December 2000
(edited version)
Background
The decision to create a game started back in the summer of 1997. Ritual Entertainment
was in full-blown production of SIN at the time. Kevin Eastman was looking to make a
videogame based on a new animated movie called Heavy Metal: JULIE BRAVO
Kevin told us that the name of the movie was based on the name of the lead character
in the movie and that character was based on the image of his wife, Julie. The name of
the movie was later changed to Heavy Metal 2000, but we decided to keep the
name.
Kevin is the owner of the Heavy Metal magazine and co-creator of the Teenage Mutant
Ninja Turtles. When we discussed the possibilities of the game, we came up with idea of
the game being a sequel to the movie instead of doing the standard movie-to-game
conversion. Kevin was thrilled to hear this, and fully supported our decision to make the
game a sequel to the movie.
Very early in the production, we received a crate full of Heavy Metal magazines. We
spent days poring over the issues to see what kinds of styles Heavy Metal is known for,
and to get inspiration for designing the characters.
Kevin also gave us complete control over the story and provided us with some
inspirational concept sketches, which influenced the design of the game. Working with
Kevin has been a blast and he's supported us completely with our decisions on what to
put in the game.
APPENDIX 6 – PENNSYLVANIA STATE WATER PLAN, A PM CASE STUDY
Work though the Project Network from start to end. Examine each group of tasks.
Resource the task of the group with the least slack first. Resource the task with the
least duration second. Use least task id as tie breaker to decide between two equal
ranking tasks. Resources are not idle if possible.
We can allocate two or more resources to the tasks of this network. Let us begin
with two resources A and B.
First, task 2 is allocated one free resource A as planned. We leave task 1 for the
moment because only one resource B is free. Rather than do nothing, task 3 is
resourced next and allocated one free resource B. Once two resources A and B are
free, task 1 is then allocated its resources. That is after 4 days. Thus, its earliest
start date is shifted 4 days later, and the schedule slack becomes -3. A task with
zero or negative slack lies on the critical path. So, that includes tasks 1 and 2. We
can continue in this manner. With two resources, the duration is 21 days.
In summary, the shift in Earliest Start date, after waiting for resources, changes the
Network slack to the Schedule slack.
For the fine aqueducts, amphitheatres, canals, lighthouses, roads, temples… we salute
you.
Gustav Eiffel
He gave France and the world the Eiffel Tower. He also invented new methods of
construction and safety. Everybody said that he could not do it, it would be a disgrace
and it would be a waste of money. He proved his critics wrong.
Henry Gantt
He gave us the Gantt Chart for project planning and scheduling. This is used everyday
around the world. He was an engineer and consultant working about 1910.
He led the Marshall Plan for rebuilding the bombed-out cities and infrastructure of
Europe after 1945. That took some compassion, leadership and political ability.
He led and delivered the Snowy Mountains Hydroelectricity scheme in 1949. His
workforce was largely migrants.
Vice-Admiral Grace Hooper
The war years proved an opportunity for women to move into the information and data
processing world. Grace rose to the rank of Vice-Admiral in the US Navy IT&T Service.
That pioneered PERT and other innovations in project management in the 1950s.
Steve McConnell
He led the invention of Rapid Project Delivery and Agile methods in the 1990s, in
response to the failure of many projects.
You
Chapter 1
1. Fuzzy
Answer – Use checklists of likely work and costs for project A, house restoration. Set
down policy guidelines for project B, art purchase.
2. Wortbuch
Answer – These are evidently not strategy or compliance projects. So they are
operational or upgrade projects.
3. NPV’s
Answer – Invest in project D with positive NPV. Positive NPV means project revenue
exceeds projects costs; negative NPV means the reverse.
4. Missions Impossible
Hypo is a titan of investment, banking and property services. Three years ago, it
outsourced all information, technology and telecommunications to Mina. The
performance of Mina is disappointing and costly. Relations are sour.
Roberta of Hypo complains that the length of phone calls is assumed not measured,
and so Hypo may be overcharged. Mina technicians investigate, concluding that call
lengths cannot be measured accurately. Gary, head of operations at Mina, offers a
commercial discount. That seems to settle the matter.
Roberta is not satisfied. She contacts Brent, head of consulting at Mina, who
authorises a project with the latest technology to measure call lengths.
This project is impossible because experts have already confirmed it cannot be done.
It rests on a politically correct promise and no more. The PM soon quit, frustrated.
5. Big Bank
6. CTP Motors
So, what happens if it is not done at all or done only in part? No comment.
So, there no need to draft an accompanying business case because the heart of the
case, the business justification, is lacking or obscure. Save your effort.
8. Airports Canada
Option C, Do Nothing
Benefits –
Costs nothing
Disadvantages –
Benefits –
Disadvantages –
Disadvantages –
Next steps –
Recommendations –
Chapter 2
Can railroad also serve general transport needs in Turkey, over part of route?
Better investment if so. Check best route.
PS. The project went ahead, but bankrupted the Turkish Government.
2. Opera France
This is a project in search of both its goal and its scope. You need to –
1. Shape and agree with the Minister what will be a useful and doable goal
2. Start a large data collection/mining exercise for opera sales, costs and subsidies –
what are the facts?
3. Check what previous reports, research and criticism addressed here – what are
the gaps and future directions?
European opera takes a long break between mid-year and new-year. The
economics of opera must improve if performances are held year round.
Are there opportunities for Opera France abroad, say in Beijing and Sydney,
which have not been tapped?
Let us look at the SMART test; that is most vulnerable at T, timely. This project looks
like a busy 12-month work. So, we will –
Iinsure is adding a call centre to serve claims only; that cost centre generates no
revenue. It would be better to absorb the claims work in other Iinsure call centres, or
to change the function of the new call centre to serve both new business and claims,
if indeed there is a market justification for another call centre. The
strategic/commercial view is lacking but necessary.
What is the project goal? Is it S.M.A.R.T.? Assume the default goal of operational
projects applies.
How can the scope be split up? Think critical, desirable and nice to have.
Critical scope is –
Sweep in’s
Building Refit
Infrastructure Refit
Desktop Fit Out
Call Centre Technology Purchase & Installation
Motor claims capacity
Operator Training
Desirable scope is –
Nice-to-have scope is –
Link with other call centres (useful in an emergency to share work load)
Road access clearly needs to be swept into the project. Assume a simple level dirt
road wide enough for two large container trucks to pass safely.
The timetable of 9 months is depends on building the road access into the mine. If
say that takes 3 months to survey, clear and grade, then only 6 months remains for
the rest of the project with much to do. That seems too short a time.
physical design and build of the mine, its infrastructure and treatment plant
contracts with Queensland Rail for transportation of ore
contracts with Gladstone Ports for storage of ore
leasing of plant and equipment
In the Iinsure case above, what would constitute Scope Creep? All except d –
11. Opo
The SMART test fails at A achievable, R realistic and T timely. It is unlikely that the
high capital demands for the project can be met. Some advice is as follows –
If the eCommerce market blooms, then Opo will have some capacity and a
springboard for further expansion in the updated Rose Bay site. If the eCommerce
market fades, then no further capital is wasted. Meantime, learn the market
together with new partners.
Chapter 3
1. Critical Stakeholders?
All these parties could and would use their influence (guanxi) with Government to
change or block the project if they perceived that it ran against their best interests.
2. Camping in Zambia
A list of stakeholders might include –
E – The project team – Zambian Army, UN, Red Cross, M.S.F., suppliers
D – The opponents – some Zambian publics, media
C – The informed – Presidents, UN, media
B – The impacted – Refugees, Zambian government and services
A – The champions – UN High Commission for Refugees, media, churches
Chapter 4
Build two large camps with accommodation, facilities, infrastructure and access
to provide a healthy, safe and normal life for refugees in transit. Each camp will
flexibly accommodate 5000-7000 people, be built within 9 months or less, and
cost 5m euros or less.
Accommodation will be flexible dormitory style, separate for men and for
women and children. Camps will include simple communal facilities for
education, food, health and recreation. Camps will have the normal
Infrastructure of water, power, sewerage and gas services. Access means a
layout of streets and connections with transport links. Fire, hygiene and
safety standards will be met.
Community services say banking, education, health, police and religion, will
stretch to serve and support the camps. Entrepreneurs will step in offer other
services in demand e.g. Internet access. Refugees will be employed to
provide some services e.g. cleaning, waste, security. Each camp will in time
elect a major.
Survey Grounds
Engage Architects
Design Camps
Alert Community Services
MS Ready to tender
Connect Infrastructure
Test Infrastructure
Update per Test
Liaise with Community Services
MS Infrastructure Ok
Complete Access
Engage Suppliers
Store Supplies
Engage Community Services
MS Ready to Open.
2. Remona
Opinion polls use small samples of the population to gauge the general view; they
also focus in on the important question or the swinging voter.
With this in mind, the project can be structured by sample of clients/data and by
‘radar’ view of the ten privacy principles. Then, we can assess which sources clash
with which privacy principles, if any. We will advise the project outcomes to the
Chief Legal Officer, the project sponsor, to address as required.
The CXC Privacy project was indeed completed on time and budget in this way.
A better approach is to calculate the tax and pay it early to the ATO, with an
agreement that data to identify taxable policies will follow in good time.
Next, we use common and plentiful desktop technology to download policy data
from a range of platforms to calculate and upload the tax payable. If the tax rules
change, we repeat the process.
Of course, we convince our Executive Sponsors to adopt this approach, to find the
extra $1-2 millions in tax and to agree matters with the ATO.
Chapter 5
1. Holy Smoke!
PIA is an Italian business icon. It has many businesses. Fire is one major risk.
What kind of risk management controls does PIA use in each of these areas?
2. Rwanda
Take risk B, railway breaks down in use but there is no backup train or route
Likelihood – medium
Impact – high, project is halted or stopped
Risk response – avoid - maintain and repair railway stock in good order before
starting off, seek engineers and artisans, retrace route to start if necessary
Contingency plan – escalate case to UN Security Council and World Press for help.
Take risk C, Panic and disorder in boarding refugees overturns carriages and derails
the train
Likelihood – medium
Impact –high, confidence and railway stock are destroyed. project is halted or
stopped
Risk response – transfer and mitigate – use UN Force to maintain order while
boarding, and use series of barriers to limit numbers boarding
Contingency plan – allow only limited number with tickets to queue for boarding,
keep the nature of tickets secret, and vary ticket with each trip. Also use UN Force to
supervise boarding.
Take risk K, Zambian government grants one year visas, but strife long continues
You may have alternative answers here. An updated Risk Severity Matrix follows.
Event
Likelihood
High B, C D
Medium A
Low I
Lo Mediu Event
w m High Impact
3. PFI projects
Operation Risk – e.g. unforeseen costs in operating the facility, penalties for
non-performance, obsolescence of the facility in the long term
Demand Risk – demand for services may vary greatly over the long PFI lease
Chapter 6
1. Fast Builders
Add the times of the tasks on the critical path. Tasks 1-4 require 68 hours, and tasks 10-
13 require 32 hours. So the project duration is 100 hours, about 13 days. Such fast
builders! Have you got their number?
Plan is first to –
These moves are on the critical path. Any delay of one move delays the others and
makes our readiness milestone later. We are ready to attack on day 50.
Plan is second to –
This preserves our strength in the West and adds an extra force, 60 days after the battle
has begun, as reserve or occupation force. If all goes well, we may reverse these moves.
Risk lies in our South.
The Centre, North, Navy and Special Forces moves are linked finish-to-finish. The North
and Navy moves are also linked start-to-start. The South and West moves are linked
finish-to-start.
Day 50 should coincide with May 1, the beginning of our summer. Moves of our forces in
spring are feasible; we should announce routine manoeuvres in spring. Day 1 is March
10-11. Our campaign starts then.
3. Ho
The best case is for Ho to complete all regulatory trials without fail or repeat. So, the
best timeline is 27 months. Here, the media and marketing tasks are done in parallel
with the production ready task.
There is no auction of a successful drug patent; it is too valuable. An auction may apply
in some other circumstances e.g. to fund development of an even more effective drug.
The worst case is for Ho to require three extended 12-months trials for US approval, and
then fail or be withdrawn at the end of the last trial. So, this worst timeline is 41 months.
There is no auction of a failed drug patent; it has little or no value.
Chapter 7
1. Voyage to Brasil
For a sponsor voyage, use resources – 1 King George III, 2 Sir Joseph Banks
For h dock in Rio, use – 7 Harbour Master, 8 Pilot, 13 Crew, 16 Ship, 17 Shipyard and 18
Captain
2. Posh Tosh
Lucinda has at least 60-70 days before going to market, allowing for legal then refit
work. Does the volume of maintenance work affect that timing?
Then, the expected maintenance load is (2 + 4*5 + 14)/6 or 6 days. That is a fulltime load
for the small maintenance team, and leaves 0-1 day per week spare.
So, if Lucinda uses only the Posh maintenance team, the 30 day refit will span 30 weeks
or more! That is unacceptable.
Thus, assume –
Lucinda hires a refit team for her block of apartments. Then the timeline is
70 days, about 10 weeks.
3. SteelO
Note that the use of time boxes to shape, prioritise and schedule has given this project a
very precise, certain timeline that otherwise it would not have.
The Chairman may advise the NYSE of changes at SteelO after Installation & Training are
complete, in month 23.
4. Ooki
In week 18, Ooki ships ten boats to the Gulf. In week 19 or later, Ooki ships
the remaining 5 boats.
There should be no bid for the PNG boats, since there is no capacity to build in 20
weeks.
5. Tiffin
Data in scope is that needed to report balance sheet, profit & loss, sources of
funds and notes on accounts. It should be found in the General Ledger or
equivalents.
Time is tight. One high impact risk is that some discrepancy or defect in the data
threatens the deadline. Batman can request an extension of time if necessary.
Chapter 8
1. CAD!
Projects are brought forward by two months, an extra load of 4 months work.
Options may be –
Either way, one or both projects may run late. That will mean penalty payments and loss
of reputation for Toai.
2. Ballpark
Call Centre Technology is ready to build, starting at week 15.6 say week 16.
Chapter 9
1. Montebano Sono
Angela finds that the Harbour Cruise and National Galley Foyer are too costly given the
expected number of ISA tickets and revenue. If other Student Associations join in,
matters may be different. But that is uncertain. She decides to focus on the Princessa
Dance Hall option.
Costs will be $3950, with 5 prizes of $50 and 1 DJ. Assume volunteers clean up after the
dance.
So, the fund for refugees is $1050. Better still to invite other Student Associations along.
The Hall has ample capacity.
2. Rotterdam
Capex Opex
Construction Cost Toll Fee
Contractual Variation Cost, if any Operations & Maintenance Cost
Penalties, if any
After 10 years, Net Revenue is 5*(F - 0.07C) + 5*(1.04F - 0.075C) or 10.4F – 0.725C. At
Payback, Investment equals Revenue, that is C = 10.4F – 0.725C. So, F = 1.725C / 10.4 or
F = 398k.
A good investment has zero or positive NPV. So, we find F < 1.64147C/8.81908 or 449k.
3. Mercury
Chapter 10
A large, complex data model may be innocently and misleadingly in error, but
errors may be very hard to detect.
Inspections raise costs, may not address key works and may not be
statistically significant or useful.
Some advice is –
In Year 1, Years 2-4 and Year 5, expected revenue is 0.06S, 0.12S, and 0.08S + 250.
Discount factors in years 1-5 are then 0.9259, 0.8573, 0.7938, 0.7350 and 0.6806. These
bring future revenues to present values.
Good investment criterion is that the NPV is zero at minimum or positive. That is, the
present value of revenue should be equal to or greater than the investment.
3. Blyth Street
The project is over budget and behind schedule. Work is underperforming, giving
71-73 cents per dollar only.
C. Action
Can BIC change the process, use new tools and offer incentives to speed up the
work?
D. We find –
You may apply cuts more or less generously as you see fit. Expect disagreements and
lobbying aplenty!
Chapter 12
1. Home Care
Estimates are –
2. Julie Bravo
A planned WBS is also a must. Here that spans storyline, features, effects and
tasks.
Games engines/tools need to be wisely chosen, and any new versions need
to be introduced carefully to avoid disruption of schedule and relearning of
use.
Marketing goals and actions to achieve them need to be planned from the
start; Julie Bravo needed a multi-user version of the game and early
availability to gamers.
Chapter Thirteen
Why is it important to assess the culture of the organization before deciding what
project team structure to use?
This is because the project structure needs to match the organisation culture. If not,
there will be conflict, lack of approval, lack of participation, delay and more problems.
No, the Functional Project Organisation is not right for this cross-business project.
Instead, we recommend a Strong Matrix (Project) Organisation. We do not recommend
a Dedicated Project Organisation because we want the whole Sentry organisation to
own and participate in the project.
Chapter Fourteen
1. Ethics
C. Giving a friend details of a job opportunity – this has not been made public
yet.
The information belongs to the company and is not yours to give. This
behaviour is also unfair and favouritism. Wait until the job is released to
notify your friend.
A. Find and compare three or more lists of criteria for an Effective or Good
project manager. Is there a core of common criteria/which?
Yes, there are some common criteria. Check this out yourself.
B. Is the ace technical guru the best candidate for project manager?
No, technical prowess is rarely listed among criteria for good or effective
project manager. Yet, this continues to be an important criterion for
recruiting project managers!
D. How should the criteria differ with the project organisation, be it large or
small?
1. Thailand
Find a case study of successful Foreign-Thai project. Why did this succeed?
See the NED Project [33], a solar energy project with Thai and Hong Kong
participants under the sponsorship of the Asian Development Bank. Support of the
nearby communities was the key to success.
One is – remember that, when working in Thailand, relationships are often more
valuable than extra profit [34].
2. Turkey
Find a case study of successful Foreign-Turkish project. Why did this succeed?
See the Pipeline project [35], an engineering project with Turkish and German
participants. Close working relations between the parties was the key to success.
7. Gobeli, D.H., and Larson, E.W. The Barriers Affecting Project Success
Proceedings of the 1986 Seminar Symposium Drexel Hill, PA: The Project
Management Institute, 1986, p25.
8. Genest, B.A., Nguyen, T.H., Paradis, J., and Smith, J. Measuring Success in
Software Development Projects. Proceedings of the 1986
Seminar/Symposium Drexel Hill, PA: The Project Management Institute, 19
p 177.