Follow Up PCD New Style - Unit 1a

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

NEW STYLE

Update:
FOLLOW UP

STYLE ALLOCATION
PATTERN MAKER

REVIEW TRIAL&

SAMPEL ROOM

COMMENT PPS
SEWING TRIAL
LOADINGDAN

POLA ACTUAL
MODARIS &
POLA TRIAL
SAMPLE &

EMAIL KE
Prioritas

BUYER

PPM
LINE

PCD
STYLE STATUS REMARK

H-21 H-16 H-13 H-11 H-10 H-9 H-7


PLAN 22-Jan 27-Jan 31-Jan 02-Feb 03-Feb 05-Feb 07-Feb
1 27,28 THST RESILIENCE
ACT

PLAN 24-Jan 30-Jan 02-Feb 05-Feb 06-Feb 07-Feb 09-Feb


2 14 WACOAL PCC234
JEPANG ACT

PLAN 25-Jan 31-Jan 03-Feb 06-Feb 07-Feb 08-Feb 10-Feb


3 12 WACOAL BCC234
JEPANG ACT

PLAN 26-Jan 01-Feb 05-Feb 07-Feb 08-Feb 09-Feb 12-Feb


4 23,27,28,29,31 TRIUMPH AMST517
,33 ACT

PLAN 27-Jan 02-Feb 06-Feb 08-Feb 09-Feb 10-Feb 13-Feb


5 1,3,4,9,21 TRIUMPH AMST516
ACT

PLAN 01-Mar 07-Mar 11-Mar 13-Mar 14-Mar 15-Mar 18-Mar


6 8 WACOAL SBRD443
KOREA ACT

PLAN 01-Mar 07-Mar 11-Mar 13-Mar 14-Mar 15-Mar 18-Mar


7 12 WACOAL VBRG617
KOREA ACT

PLAN 04-Mar 09-Mar 13-Mar 15-Mar 16-Mar 18-Mar 20-Mar


8 22,23,33,34 TRIUMPH AMST1479
ACT

PLAN 08-Mar 14-Mar 18-Mar 20-Mar 21-Mar 22-Mar 25-Mar


9 3,4,33,34 TRIUMPH AMST1482
ACT

PLAN 04-Apr 10-Apr 13-Apr 16-Apr 17-Apr 18-Apr 20-Apr


10 1,18,21,22,26, TRIUMPH AMST518
31 ACT

PLAN 18-Apr 24-Apr 27-Apr 30-Apr 01-May 02-May 04-May


11 27,28,29,30 TRIUMPH AMST1484
ACT