Professional Documents
Culture Documents
A Heuristic Approach For Petrochemical Plant Layout Considering Steam Pipeline Length
A Heuristic Approach For Petrochemical Plant Layout Considering Steam Pipeline Length
A Heuristic Approach For Petrochemical Plant Layout Considering Steam Pipeline Length
net/publication/301773260
CITATIONS READS
10 435
3 authors:
Xiao Feng
SEE PROFILE
All content following this page was uploaded by Yan Wu on 13 May 2021.
a r t i c l e i n f o a b s t r a c t
Article history: Plant layout design affects both investment and performance of a factory. To maximize the economic benefits of a
Received 10 June 2015 petrochemical factory, a large number of factors must be considered simultaneously, such as material flow, heat
Received in revised form 20 July 2015 flow and safety. However, conventional principles for plant layout design and optimization do not involve the
Accepted 28 November 2015
heat flow, resulting in higher construction investment. To solve this problem, a new heuristic approach is pro-
Available online 30 April 2016
posed in this paper based on the current layout design principles. Both material flow (pipelines for process
Keywords:
streams) and heat flow (pipelines for steam) are considered. Three optimization methods with different objec-
Petrochemical plant layout tive functions are used to optimize the layout. The application of proposed approach is illustrated with a case
Heuristic study. The optimal scheme and pipeline networks can be obtained, and the pipeline length is reduced
Steam system significantly.
Pipeline length © 2016 The Chemical Industry and Engineering Society of China, and Chemical Industry Press. All rights reserved.
Optimization
http://dx.doi.org/10.1016/j.cjche.2016.04.043
1004-9541/© 2016 The Chemical Industry and Engineering Society of China, and Chemical Industry Press. All rights reserved.
Y. Wu et al. / Chinese Journal of Chemical Engineering 24 (2016) 1032–1037 1033
2.1. Method 1 the length and diameter of high pressure steam pipeline, reducing
the investment, the loss of steam pressure and temperature.
This method is used to design plant layout for shorter material flow (3) On the premise of shortest high pressure steam pipeline, large
pipeline. A number of principles are developed on the basis of Chemical medium pressure steam users are near the power station as far
Engineering Design [21], Preliminary Chemical Engineering Plant De- as possible, by adjusting the locations of small users with high
sign [22], and Code for layout design of petrochemical plant (GB pressure steam consumption, to reduce the medium pressure
50984-2014) [23]. The content is as follows. pipe diameter and length.
(4) Low pressure steam pipe network do not need to be near the
(1) For safe operation and less energy consumption, the plants
power station. For less pipeline length, the plants producing low
using hydrogen at high temperature and high pressure, such
pressure steam and steam users are put together.
as gas oil hydrocracking and residue hydrotreating, are close to
(5) The last three points (5,6, and 7) in Method 1 should be considered.
the hydrogen production installment.
(2) The units include aromatic hydrocarbons, isomerization, contin-
uous reforming and naphtha hydrotreating are placed jointly be- The principles in Method 2 are also listed according to the decreasing
cause of their upstream and downstream relationship. Sulfur order of importance. When principles conflict each other, arrange the
recovery and delayed coker are close to each other. Fluid catalytic workshops to obtain the shortest high pressure steam pipeline length
cracking plant is the most close to its upstream installment resi- as far as possible.
due hydrotreating.
(3) Crude oil fractionation unit is near crude oil storage, which is its 2.3. Method 3
upstream facility. Processes for final products, such as diesel, ker-
osene and gasoline, are preferred to stay together and close to This method considers material and heat flows simultaneously, in-
the storage devices. cluding almost all the contents of Methods 1 and 2. Some other points
(4) The power station is located at the edge of the factory, near the that should be referenced are also listed according to the decreasing
railway and delayed coker. This layout not only reduces the envi- order of importance.
ronment pollution caused by coal dust, but also facilitates the
supply of fuel coal and petroleum coke. (1) Determine the location of power station. Find the large consump-
(5) The utility such as air separation unit, air compressor station, de- tion users of high pressure steam, put them close to the power
salt water station and water treatment is close to the main station, and determine their relative position preliminarily.
users, shortening pipeline and avoiding heat loss. Air separa- (2) According to material flow directions, find the plants that should
tion and air compressor plant is far away from the power sta- be combined with the large consumption users of high pressure
tion for a good air environment, which is beneficial in steam. Adjust their locations properly in the light of their lower
improving equipment operation. pressure steam consumption.
(6) Sewage treatment is in low-lying areas of the refinery, (3) Medium pressure steam pipeline network, throughout almost the
preventing sewage from flow backward and helping environ- whole factory, has the most users. Changing the locations of plants
mental protection. To reduce the pipeline investment, sulfur has small effect on the length of pipeline. Therefore, small users of
recovery unit, which produces a great deal of waste-water, medium pressure steam do not have to be near the power station.
should be close to sewage farm. By contrast, shorter material pipeline should be in higher priority.
(7) Comprehensive administrative zone locates in the higher
ground for safety and is close to downtown and highway to
When these factors conflict, the plants with large consumption for
avoid potential safety hazards for commuting of employees.
three levels of steam may not be close to the power station. They can
be near the plants producing a large amount of steam for steam usage.
These principles are listed according to the decreasing order of im-
When a plant does not need any level of steam and has few material
portance. They may give some contradictions. In the design process
flows, it can stay at the end of steam pipeline. This extends the material
the designer should meet the principles in the front of the list and
flow pipeline slightly, while greatly shortens the length of steam pipe
meet the requirements of production process and environmental pro-
network.
tection simultaneously as far as possible.
3. Case Study
2.2. Method 2
(GOH), residue hydrotreating (RH), fluid catalytic cracking (FCC), from plant to the pipe rack is neglected. Draw the material and steam
kerosene hydrotreating (KH), hydrogen production (HP), crude oil flows in the general arrangement of plants using arrows representing
fractionation (COF), air compression and air separation (ACAS), water the direction, and the total pipeline length is the sum of arrow lengths,
treatment works (WTW), storage (STO), central control room (CCR), which are the distance between plants, an integer times 100 m.
and laboratory centre (LC).
The material flow direction among plants is shown in Table 1. They 3.3. Results
are used to guide the design of process stream pipelines.
CASE 1 is designed by simplifying and adjusting an existing plant
Table 1
layout of petrochemical refinery according to Method 1. Fig. 2 shows
Material flow directions among plants the optimal plant layout for material flow pipeline. The numbers on
the line represent the material flows in Table 1. The total length for
Material flow Flow direction
the material flow pipe is 5500 m. Fig. 3 shows the steam pipelines,
1. Atmospheric-vacuum distillates From COF to RH, GOH, DH, NH, KH, with a total length of 3700 m. The pipeline length for different levels
CR and DC
of steam is 1300 m (3.5 MPa), 1400 m (1.0 MPa) and 1000 m (0.4 MPa).
2. New hydrogen From HP to KH, RH, GOH, NH, CR,
DH, CGH and IU CASE 2 is designed using Method 2. The specific layout steps are as
3. Sour water From COF, KH, FCC, RH, GOH, NH, follows.
DH, CGH and DC to SR According to the situation of railway, RTD is in the west of the refinery.
4. Rich amine solution From COF, FCC and RH to SR
PS is at the edge of the factory, connected to RTD to facilitate the fuel
5. Desulfurized and dealcoholized LPG From FCC and DC to GS
6. Low pressure separator From RH, GOH, DH and CR to HP
transportation and reduce the dust pollution. To be close to more work-
7. LPG From FCC to HP shops simultaneously, it locates in the northwest, without linking with
8. Fractionator bottom oil From NH to CR; from RH to FCC the large tank farm of steam consumption. COF, FCC, RH, GOH, SR, AC
9. Tail oil From GOH to FCC and CR are large users of 3.5 MPa and 1.0 MPa steams, so they are near
10. FCC gasoline From FCC to CGH
the power plant according to the usage of steam level. Among them,
11. Heavy naphtha From GOH to CR
12. Light naphtha From NH to IU FCC is the largest gas producer, so it may be moved eastward appropriate-
13. Non-aromatics From AC to IU ly for providing steam to other plants, as well as reducing the pressure
14. Reforming hydrogen From AC to CR drop loss. AC and CR use the most 3.5 MPa steam and are close to FCC.
15. Depentanizer bottom oil From CR to AC COF needs a lot of three levels of steam, so it is also near PS. In addition,
16. Sewage From SR to STA
RH and GOH are near PS as far as possible because they also need lots
of high pressure steam. Other high pressure steam users, DC and DH,
The steam system balance for the petroleum refinery is illustrated in are in the vicinity of FCC to make the high pressure steam pipe shortest.
Fig. 1. It is used to guide the design of steam pipelines. For medium pressure steam users IU and CGH, they are near AC and CR.
For 0.3 MPa steam users, HP is near CR. IU and HP are near AC and CR,
CGH is near DC. This layout can give the shortest length of medium pres-
3.2. Calculation for pipeline length sure steam and low pressure steam network. Storage covers a large area
and uses medium pressure steam, so it is in the broad south of refinery.
We simplify the calculation of the length of pipe network. Each plant STA should be on the edge of refinery with low-lying area, so it is in the
is a point, ignoring its size. Some joint units such as crude oil fractionation, southwest. CCR and LC are on the east of the factory, near the roads. GS
fluid catalytic cracking and sulfur recovery, occupy the position of two and NH should be far away from dust, so they are near CCR and LC.
plants. The distance between two plants is set to be 100 m and the length Other plants, KH, ACAS, and WTW, are in the rest of positions.
CR&
HP FCC SR
AC
99t·h-1 273t·h-1 75t·h-1 107t·h-1
52t·h-1
3. 5MPa
165t·h-1 203 t·h-1 94t·h-1
42t·h-1 4t·h-1 3t·h-1 5t·h-1 47t·h-1 20t·h-1 23t·h-1
FCC RH
GOH
DC CR&AC
CR&AC
CR& DH CR&
COF GOH DC 94t·h-1 COF RH DC DH SR lo ss
AC AC
203t·h-1
10t·h-1 19t·h-1 7t·h-1 12t·h-1
63 t·h-1
1. 0MPa
24t·h-1
20t·h-1 13t·h-1 30t·h-1 16t·h-1 3t·h-1 21t·h-1 75t·h-1 4t·h-1 35t·h-1 30t·h-1 59t·h-1 8t·h-1
CR&
COF RH SR 165tt·h-1
AC CR& oth
IU COF STO CGH RH GOH FCC DC SR lo ss
AC ers
24t·h-1 56t·h-1 38t·h-1 17t·h-1 24t·h-1
0. 4MPa
HP COF RH IU SR lo ss
15
14
AC CR GOH KH ACAS
13
9
11
STA
IU NH RH HP WTW
6
2
3
1
16
5
4
8
7
GS DH CCR
SR FCC COF
DC CGH LC
RTD
PS STORAGE
AC CR GOH KH ACAS
STA
IU NH RH HP WTW
0.4MPa
3.5MPa
GS DH CCR
1.0MPa
SR FCC COF
DC CGH LC
RTD
PS STORAGE
10
DC CGH ACAS
PS COF FCC
DH KH WTW
7
8
RTD 4
2
RH AC IU GS CCR
12
15
14
SR 13
9
GOH CR HP NH LC
11 8
16
STA STORAGE
DC CGH ACAS
PS COF FCC
DH KH WTW
0.4MPa
3.5MPa
RTD 1.0MPa
RH AC IU GS CCR
SR
GOH CR HP NH LC
STA STORAGE
The optimized plant arrangement scheme of CASE 2 is shown in Figs. 4 3.4. Discussion
and 5. Fig. 4 shows the material flow pipeline network. Compared with
CASE 1, the material flow pipeline network of CASE 2 is more complicated, Table 2 summarizes the results. When only the material flow pipe-
with a total length of 6900 m. The total length of steam pipe is much line network is optimized in CASE 1, steam pipeline stretches a lot,
shorter, as shown in Fig. 5. It is 2900 m. These results are in accordance which is 3700 m. In CASE 2, the length of material flow pipeline is larger,
with the expectation. Besides, the pipeline length for different levels of 6900 m. Thus optimizing only one type of pipeline is not comprehen-
steam is 1000 m (3.5 MPa), 1300 m (1.0 MPa) and 600 m (0.4 MPa). sive. The total length of pipeline in CASE 3 (8500 m) is smaller than
CASE 3 is designed using Method 3. The specific layout steps are as that in CASE 1 (9200 m), so the optimization of both material and
follows. steam pipelines do reduce the overall pipeline cost. In particular, for
Adjust the layout of Figs. 4 and 5. Keep the positions for RTD, STA, STO, 3.5 MPa steam pipeline, whose investment is large, the length in CASE
CCR, LC, ACAS and WTW, which have less material and steam flows. The 3 (1000 m) is equal to that in CASE 2 and less than that in CASE 1
location of PS is the optimal and does not need adjustment. Then combine (1300 m). The layout plan of CASE 3 achieves the best result, which is
the related plants according to upstream and downstream relationship of 8500 m, although the total length of steam pipeline (3000 m) is a little
material flow and safety factor in Method 1. GOH and RH should be near longer than that of CASE 2 (2900 m). Besides the reduction in pipeline
HP; AC, IU, CR and NH are close to each other; SR and DC, FCC and RH are investment, the loss of steam pressure and temperature can be also re-
as close as possible; DH, KH and CGH are also adjacent to each other and duced due to the reduction in pipeline length. Therefore, Method 3 has
better near HP. In this way, the length of material pipeline is reduced. Con- more application prospects.
sidering the steam usage, adjust the positions of binding plants according
to Figs. 4 and 5 for appropriate steam pipeline length. Following the above 4. Conclusions
methods, several layouts are obtained by comparing a variety of schemes.
The final layout plan of CASE 3 is shown in Figs. 6 and 7. Fig. 6 displays This paper develops a complete set of principles to consider the
the material flow pipeline network. The total length is 5500 m, which is length of both process stream pipeline and steam pipeline in the design
smaller than 6900 m in CASE 2. The same value in CASE 1 and CASE 3 of plant layout. Method 1 and Method 2 are proposed to determine the
shows very good optimized result. Fig. 7 displays that steam pipelines of layout with the shortest process stream pipeline and steam pipeline, re-
different levels are as simple as that in CASE 2. The total length of steam spectively. Method 3 shortens the total pipe length for material and
pipelines in CASE 3 is 3000 m. The pipeline length for different levels of steam flows. For three cases, the total length of material and steam pipe-
steam is 1000 m (3.5 MPa), 1200 m (1.0 MPa) and 800 m (0.4 MPa). line is 9200, 9800 and 8500 m. In CASE 3, the length of material pipeline
13
AC IU ACAS
14
PS COF FCC
12
CR NH WTW
8
7
3
10
RTD
8
6
2
GOH HP DH KH CCR
SR 9
DC RH CGH GS LC
16
STA STORAGE
AC IU ACAS
PS COF FCC
CR NH WTW
0.4MPa
3.5MPa
RTD 1.0MPa
GOH HP DH KH CCR
SR
DC RH CGH GS LC
STA STORAGE
[6] R. Kern, How to get the best process-plant layouts for pumps and compressors,
Table 2 Chem. Eng. 84 (26) (1977) 131–140.
Summary for pipeline lengths [7] R. Kern, How to find the optimum layout for heat exchangers, Chem. Eng. 84 (19)
(1977) 169–177.
Types of pipeline CASE 1/m CASE 2/m CASE 3/m [8] R. Kern, Space requirements and layout for process furnaces, Chem. Eng. 85 (5)
(1978) 117–122.
Material flow 5500 6900 5500
[9] R. Kern, Instrument arrangements for ease of maintenance and convenient opera-
3.5 MPa steam 1300 1000 1000
tion, Chem. Eng. 85 (9) (1978) 127–134.
1.0 MPa steam 1400 1300 1200
[10] M.C. Georgiadis, S. Macchietto, Layout of process plants: A novel approach, Comput.
0.4 MPa steam 1000 600 800 Chem. Eng. Suppl. 21 (1997) S337–S342.
All steams 3700 2900 3000 [11] H. Tarkesh, A. Atighehchian, A.S. Nookabadi, Facility layout design using virtual
Total length 9200 9800 8500 multi-agent system, J. Intell. Manuf. 20 (4) (2009) 347–357.
[12] A.R. Mckendall, J. Shang, S. Kuppusamy, Simulated annealing heuristic for the dy-
namic facility layout problem, Comput. Oper. Res. 33 (8) (2006) 2431–2444.
is 5500 m, which is equal to that in CASE 1, and the length of steam pipe- [13] F.S. Hillier, Quantitative tools for plant layout analysis, J. Ind. Eng. 14 (1) (1963)
33–40.
line is 3000 m, only a little longer than that in CASE 2 (2900 m). There-
[14] J. Skorin-Kapov, Tabu search applied to the quadratic assignment problem, ORSA J.
fore, CASE 3 is considered to be the optimized scheme, which can Comput. 2 (1) (1990) 33–45.
significantly increase the economic benefit. The results of three cases [15] K.V. Chandratre, K.N. Nandurkar, Applying genetic algorithm to dynamic layout
show that the steam pipe network optimization in process plant layout problem, Int. J. Appl. Oper. Res. 1 (3) (2011) 1–9.
[16] Q.L. Lin, H.C. Liu, D.J. Wang, L. Liu, Integrating systematic layout planning with fuzzy
is very meaningful. The methodologies proposed can help to put for- constraint theory to design and optimize the facility layout for operating theatre in
ward optimized plant layout plan. Further work is needed to optimize hospitals, J. Intell. Manuf. 26 (1) (2015) 87–95.
the layout of petrochemical plants with steam system using mathemat- [17] X. Luo, Y.M. Yang, Z.X. Ge, X.S. Wen, Maintainability-based facility layout optimum
design of ship cabin, Int. J. Prod. Res. 5 (3) (2015) 677–694.
ical programming method. [18] A.S. Tubaileh, Layout of flexible manufacturing systems based on kinematic con-
straints of the autonomous material handling system, Int. J. Adv. Manuf. Technol.
References 74 (9—12) (2014) 1521–1537.
[19] F.D. Penteado, A.R. Ciric, An MINLP approach for safe process plant layout, Ind. Eng.
[1] F.F. House, An engineer's guide to process-plant layout, Chem. Eng. 76 (16) (1969) Chem. Res. 35 (4) (1996) 1354–1361.
120–128. [20] Y.F. Wang, W. Wang, X. Feng, Heat integration across plants considering distance
[2] R. Kern, How to manage plant design to obtain minimum cost, Chem. Eng. 84 (11) factor, Chem. Eng. 35 (2013) 25–30.
(1977) 130–136. [21] R.K. Sinnott, X.F. Song, Chemical engineering design, fourth ed. China Petrochemical
[3] M.L. Kaura, Plot plans must include safety, Hydrocarb. Process. 59 (7) (1980) Press, Beijing, 2009 657–668 (in Chinese).
183–194. [22] W.D. Bassel, Preliminary chemical engineering plant design, Elsevier North Holland,
[4] R. Kern, Layout arrangements for distillation columns, Chem. Eng. 84 (17) (1977) New York, 1980 141–158.
153–160. [23] GB50984–2014, Code for layout design of petrochemical plant, China Planning
[5] R. Kern, Arrangements of process and storage vessels, Chem. Eng. 84 (24) (1977) Press, 2014 (in Chinese).
93–99.