Awal impounding 22-Sep-21

DATA OPERASI BENDUNGAN GONGSENG


PENGISIAN AWAL
1 Hari ke - 79 Kamis 09 Desember 2021 17:00:00 WIB BOBOT
3
2 Volume Total EL.+ 93.00 22,346,000.00 m
Volume Efektif 14,413,000.00 m3
3 MAW EL. + 82.60 m
4 Volume saat ini 3,661,555.20 m3 16.39 %
Luas Genangan 90.42 Ha 31.50 %
Sebelumnya hari ke- 79 Kamis 09 Desember 2021 12:00:00 wib
5 MAW EL. + 82.57 m
Volume 3,634,844.80 m3
Kenaikan Elevasi 0.03 m

6 Q-Outflow
Drop Inlet Elv +86.05 0.00 m3/det

7 Penguapan 0.00 mm/hari 0.00 m3/det


8 Q-Inflow 1.484 m3/det 5

Dam Instruments
9 Rembesan di waduk (mm)
V-notch 1 (kanan) 0.12 liter/det
V-notch 2 (kiri) 0.65 liter/det
V-notch 3 (pondasi) 1.22 liter/det
TOTAL 1.99 liter/det
14 Curah Hujan Sta. Gongseng 0.00 mm

15 Temperature max 38.00 °C


16 Temperature min 33.00 °C
17 Wind Run 3.16 m/s
18 Barrometer 200.00 mb

Keterangan: v-notch dilaporkan pada jam 17:00 wib

C:\Bendungan Gongseng\monitoring pengisian awal\[Monitoring impounding rev-3 Gongseng - Copy (version 1).xlsx]WLharian