STA HONDA

STA. CRUZ MINDORO


Third Ace Construction
ID WORK DESCRIPTION Duration Start 27Finish
Feb '22 06 Mar '22 13 Mar '22
T W T F S S M T W T F S S M T W T F S
1
2 GENERAL REQUIREMENTS 14 days? Tue 01/03/22 Fri 18/03/22
3 Purchasing of Materials 8 days? Tue 01/03/22 Thu 10/03/22
4 Off- Site Fabrication 5 days? Mon 07/03/22 Fri 11/03/22
5 On-Site Fabrication 3 days? Mon 14/03/22 Wed 16/03/22
6 Mobilization and Demobilization 2 days? Mon 14/03/22 Tue 15/03/22
7 Installation and Setup 4 days Tue 15/03/22 Fri 18/03/22

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks
Milestone Manual Task External Milestone
Project: - GUANZON MASINLOC- GA
Date: Mon 21/02/22 Summary Duration-only Progress
Project Summary Manual Summary Rollup Deadline
External Tasks Manual Summary
External Milestone Start-only

Page 1