Types of Scheduling:
1. Forward: It consider network start date
a. First forward then backward Pre-requisites for automatic scheduling:
2. Backward: It considers network end date
a. First backward then forward • Network Start date
3. Current Date: Same as forward scheduling with Start date as today's date • Network Finish
a. First forward then backward • Duration (Internal activity)
• Planned Delivery time (External activity)
• Relationships
Calculated Dates:
1. Earliest dates: Forward Scheduling
a. Earliest Start
b. Earliest Finish
2. Latest dates: Backward Scheduling
a. Latest Start
b. Latest Finish
A1
Earliest 01.06.2023 30.06.2023 Lead
On time
Latest 15.06.2023 15.07.2023
Lag
Float = 15 days
09 06 2023 Page 1
Functional Specification
09 June 2023 22:17
Logic:
Pass Start date from input to PROJ-PLFAZ.
Pass End date from input to PROJ-PLSEZ.
Fetch PROJ-PSPNR. // Proj Def
How to get Testimonials on Trustpilot?
Fetch PROJ-POST1. // Description
Step 1: Click on
https://www.trustpilot.com/review/henryharvin.com?
Pass PROJ-PSPNR to PRPS-PSPHI.
sort=recency
Fetch PRPS-PSPNR. //WBS ID
Step 2: Click on Write a Review
Fetch PRPS-POST1. // WBS Description
Step 3: Write a Review
Step 4: Send a Screenshot to the Trainer
Fetch PRPS-OBJNR.
https://docs.google.com/forms/d/e/1FAIpQLScEjKs6xK_t
Pass PRPS-OBJNR to JEST-OBJNR.
Wr-
Fetch JEST-STAT where JEST-INACT not equal to X.
GgwowwQPHa6jRBLnhzfkcYo4zuf78r30SOA/viewform?
Pass JEST-STAT to TJ02-ISTAT.
usp=sf_link
Fetch TJ02-TXT04. //WBS Status
Output
Project Def Description WBS Description Status Budget
09 06 2023 Page 2
Configurations
12 May 2023 20:56
1. Budget Profile
2. Tolerance Limit
3. Project Profile
4. WBS User Status
5. Validation
6. Substitution
7. Define coding Mask
8. Create Project Types for WBS Elements
9. Assign Project Types to Project Profile
10. Specify Applicants for WBS elements
11. Specify Persons Responsible for WBS Elements
12. Define Priorities for WBS Elements
13. Define user fields
14. User Interface settings
15. Define control key
16. Define Field Selection for Networks
17. User Fields for NW
18. Define Confirmation Parameters
19. Maintain network types
20. Specify Parameters for Network Type
21. Maintain network profiles
22. Planning Profile
23. Costing Variant
24. General Version Definition (OKEV)
25. Settlement Profile
26. Settlement Strategy for WBS
27. Settlement Strategy for Network
28. Define Parameters for Network Scheduling
29. Define Parameters for WBS Scheduling
30. Define Reduction Strategies
09 06 2023 Page 3