Name of the Project: Atal Medical University, Lucknow

PSP Projects Limited Finishing Check List

Wall Tile
Water Internal External Door Frame Door Shutter Window Window Flooring (Tile Polish & Internal External Toilet Gird Toilet CP
S.No. Name of Building No. of Proposed Floor RCC work Block work dado / Lift Kota stone Granite False Ceiling
Proofing Plaster Plaster Fixing Fixing Frame Fixing Glass Fixing /Italian) Grinding Paint Paint Ceiling Fitting
facing

Basement Floor Completed Completed NA Completed NA 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%


Gr. Floor Completed Completed Completed Completed Completed Completed Completed Completed 80% Completed Completed Completed Completed Completed Completed 70% 40% Completed Completed
1st Floor Completed Completed Completed Completed Completed Completed Completed Completed 80% Completed Completed Completed Completed Completed Completed 90% 40% Completed Completed
2nd Floor Completed Completed Completed Completed Completed Completed Completed Completed 80% Completed Completed Completed Completed Completed Completed 70% 40% Completed Completed
Administrative Building 3rd Floor Completed Completed Completed Completed Completed Completed Completed Completed 80% Completed Completed Completed Completed Completed Completed 60% 40% Completed Completed
1 4th Floor Completed Completed Completed Completed Completed Completed Completed Completed 80% Completed Completed Completed Completed Completed Completed 60% 25% Completed Completed
5th Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed 90% Completed 20% Completed Completed 60% 0% Completed Completed
6th Floor Completed Completed Completed Completed 80% Completed Completed Completed 0% Completed 20% Completed 0% Completed 85% 30% 0% 80% 80%
7th Floor Completed Completed Completed Completed 80% 0% 0% 20% 0% 30% 0% Completed 0% Completed 40% 0% 0% 10% 10%
8th Floor Completed Completed Completed 70% 40% 0% 0% 0% 0% 0% 0% 0% 0% 80% 30% 0% 0% 0% 0%
Terrace Floor/ Mumty Completed Completed 50% 0% 60% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

Gr. Floor Completed Completed NA Completed 0% 0% 0% 0% 0% 80% 0% 0% 0% 50% 0% 0% 0% 0% 0%


Auditorium 1st Floor Completed Completed 0% 90% 0% 0% 0% 0% 0% 20% 0% 0% 0% 0% 0% 0% 0% 0% 20%
2 2nd Floor Completed 60% 0% 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
3rd Floor Completed 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor/ Mumty 70% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0% 0% 0% 0% 0%

Gr. Floor Completed Completed NA Completed Completed Completed Completed Completed 0% Completed Completed Completed Completed Completed NA 50% 30% 0% Completed
Type-02 Building 1st Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed Completed Completed Completed Completed NA 50% 30% 0% Completed
3 2nd Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed Completed Completed Completed Completed NA 50% 30% 0% Completed
3rd Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed Completed Completed Completed Completed NA 50% 30% 0% Completed
Terrace Floor/ Mumty Completed Completed Completed Completed Completed Completed Completed Completed 0% NA NA Completed Completed Completed NA 50% 30% 0% Completed

Gr. Floor Completed Completed NA Completed Completed Completed Completed Completed 0% Completed 0% Completed Completed Completed NA 50% 70% 0% Completed
1st Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed 0% Completed Completed Completed NA 50% 70% 0% Completed
Type-05 Building 2nd Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed 0% Completed Completed Completed NA 50% 70% 0% Completed
4
3rd Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed 0% Completed Completed Completed NA 50% 70% 0% Completed
4th Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% 0% 0% Completed Completed Completed NA 50% 70% 0% Completed
Terrace Floor/ Mumty Completed Completed Completed Completed Completed Completed Completed Completed 0% 0% NA Completed Completed Completed NA 50% 70% 0% Completed

Gr. Floor Completed Completed NA Completed Completed Completed Completed Completed Completed Completed NA Completed Completed Completed NA 50% 80% 0% Completed
VC Residence Building
5 1st Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA Completed Completed Completed NA 50% 80% 0% Completed
Terrace Floor/ Mumty Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA Completed Completed Completed NA 50% 80% 0% Completed

file:///conversion/tmp/activity_task_scratch/727673401.xlsx,727673401.xlsx 1 of 13
Name of the Project: Establishment of NEW Medical College & Upgradation of District Hospital to 500 bedded Hospital on EPC basis at Auraiya, Uttar Pradesh, INDIA
Finishing Check List
Door Window Wall Tile Granite
S.N Water Internal External Door Frame Window Tile with Kota stone Polish & False Internal External Toilet Gird Toilet CP
Name of Building No. of Proposed Floor RCC work Block work Shutter Frame dado / Lift With
o. Proofing Plaster Plaster Fixing Glass Fixing Skirting with skirting Grinding Ceiling Paint Paint Ceiling Fitting
Fixing Fixing facing Skirting
G. Floor Completed Completed NA Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 90% 60% 0% Completed 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 90% 60% 0% Completed 0%
2nd. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 90% 60% 0% Completed 0%
3rd. Floor Completed Completed Completed Completed Completed Completed Completed Completed 90% Completed Completed Completed Completed Completed 90% 60% 0% Completed 0%
Academic Block 4th. Floor Completed Completed Completed Completed 60% 10% 40% 10% 10% Completed Completed Completed Completed Completed 0% 0% 0% 0% 0%
5th. Floor Completed Completed Completed Completed 0% 0% 0% 0% 0% Completed 60% 60% 40% 40% 0% 0% 0% 0% 0%
6th. Floor Completed Completed 0% 75% 0% 0% 0% 0% 0% 30% 0% 0% 0% 0% 0% 0% 0% 0% 0%
7th. Floor Completed 70% 0% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty Completed 70% 40% 30% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed 0% 80% 0% 0% 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%


1st. Floor Completed Completed Completed Completed 0% 80% 0% 0% 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
2nd. Floor Completed Completed Completed Completed 0% 80% 0% 0% 0% Completed 60% 90% 0% 70% 0% 0% 0% 0% 0%
UG Boys Hostel (184
Seats), Boys interns (26 3rd. Floor Completed Completed Completed Completed 0% 20% 0% 0% 0% 90% 0% 0% 0% 0% 0% 0% 0% 0% 0%
2 Seats)-Double Seater
Rooms 4th. Floor Completed Completed Completed Completed 0% 0% 0% 0% 0% 10% 0% 0% 0% 0% 0% 0% 0% 0% 0%
5th. Floor Completed Completed 50% 60% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
6th. Floor Completed 75% 0% 10% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed 0% 0% 0% 0% 0% 0% 0% Completed 0% Completed 0% 0% 0% 0% 0%


1st. Floor Completed Completed Completed Completed 0% 0% 0% 0% 0% 0% 0% 95% 0% 50% 0% 0% 0% 0% 0%
UG Girls Hostel (120 2nd. Floor Completed Completed Completed Completed 95%
Seats), Girls interns ( 26 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
3 Seats), Double Seater 3rd. Floor Completed Completed 40% 60% 0% 0% 0% 0% 0% 0% 0% 95% 0% 0% 0% 0% 0% 0% 0%
Rooms 4th. Floor Completed 70% 0% 0% 0% 0% 0% 0% 0% 0% 0% 95% 0% 0% 0% 0% 0% 0% 0%
5th. Floor Completed 30% 0% 0% 0% 0% 0% 0% 0% 0% 0% 95% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA  0% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 75% 75% 0% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 75% 75% 0% 0%
Type-II Residence
2nd. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 75% 75% 0% 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA 75% 75% NA NA

G. Floor Completed Completed NA Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 90% 75% 0% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 90% 75% 0% 0%
2nd. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 90% 75% 0% 0%
Type-III Residence
3rd. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 90% 75% 0% 0%
4th. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 90% 75% 0% 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% NA NA NA NA NA 0% 0% NA NA

G. Floor Completed Completed NA Completed 0% 0% 0% 0% 0% Completed Completed Completed Completed Completed 0% 0% 0% 0% 0%


1st. Floor Completed Completed Completed Completed 0% 0% 0% 0% 0% Completed Completed Completed 0% 0% 0% 0% 0% 0% 0%
2nd. Floor Completed Completed Completed Completed 0% 0% 0% 0% 0% Completed Completed 0% 0% 0% 0% 0% 0% 0% 0%
3rd. Floor Completed Completed Completed Completed 0% 0% 0% 0% 0% 90% 50% 0% 0% 0% 0% 0% 0% 0% 0%
4th. Floor Completed Completed Completed Completed 0% 0% 0% 0% 0% 40% 30% 0% 0% 0% 0% 0% 0% 0% 0%
Type-IV Residence 5th. Floor
6 (20units) Completed Completed Completed 60% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
6th. Floor Completed Completed 40% 40% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
7th. Floor Completed Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
8th. Floor Completed 80% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
9th. Floor Completed 40% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

G. Floor Completed Completed NA Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA 75% 75% 0% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA 75% 75% 0% 0%
Type-V Residence
7 (8units)
Name of the Project: Establishment of NEW Medical College & Upgradation of District Hospital to 500 bedded Hospital on EPC basis at Auraiya, Uttar Pradesh, INDIA
Finishing Check List
Door Window Wall Tile Granite
S.N Water Internal External Door Frame Window Tile with Kota stone Polish & False Internal External Toilet Gird Toilet CP
Name of Building No. of Proposed Floor RCC work Block work Shutter Frame dado / Lift With
o. Proofing Plaster Plaster Fixing Glass Fixing Skirting with skirting Grinding Ceiling Paint Paint Ceiling Fitting
Fixing Fixing facing Skirting
Type-V Residence 2nd. Floor
7 (8units) Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA 75% 75% 0% 0%
3rd. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA 75% 75% 0% 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed NA NA NA NA NA NA 0% 0% 0% NA 75% 75% NA NA

Director’s Residence G. Floor Completed Completed NA Completed Completed 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% 0% 0%


(1 Units)
8 1st. Floor Completed Completed Completed Completed Completed 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% 0% 0%
Terrace Floor / Mumty 80% 80% 80% 80% 80% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA 0%

Multipurpose G. Floor Completed Completed Completed Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%


9
Terrace Floor 80% 80% 80% 60% NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA

Basement Floor Completed Completed NA Completed NA Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed 0%
Gr. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed 0%
1st Floor Completed Completed Completed Completed Completed Completed Completed 80% 30% Completed Completed Completed 50% Completed Completed Completed 0% Completed 0%
Hospital Building 2nd Floor Completed Completed Completed Completed Completed Completed Completed 80% 30% Completed Completed Completed 0% Completed Completed 20% 0% Completed 0%
1 (210 bedded) 3rd Floor Completed Completed Completed Completed Completed Completed 90% 80% 20% Completed Completed 0% 0% Completed Completed 0% 0% 60% 0%
4th Floor Completed Completed Completed Completed 90% 70% 0% 40% 0% Completed Completed 0% 0% Completed 50% 0% 0% 0% 0%
5th Floor Completed Completed Completed Completed 30% 0% 0% 0% 0% 40% 50% 0% 0% 70% 50% 0% 0% 0% 0%
6th Floor Completed Completed 0% 50% 30% 0% 0% 0% 0% 0% 0% 0% 0% 0% 10% 0% 0% 0% 0%
Terrace Floor/ Mumty Completed Completed 0% 80% 90% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

Gr. Floor Completed Completed NA Completed Completed 70% 20% 50% 0% Completed 0% Completed 0% Completed 0% 0% 0% 0% 0%
1st Floor Completed Completed Completed Completed Completed 80% 70% 80% 0% Completed 0% Completed 0% Completed 0% 0% 0% 0% 0%
2nd Floor Completed Completed Completed Completed Completed 80% 0% 80% 0% Completed 0% Completed 0% Completed 0% 0% 0% 0% 0%
Residents Hostel 3rd Floor Completed Completed Completed Completed Completed 80% 0% 0% 0% Completed 0% 0% 0% Completed 0% 0% 0% 0% 0%
2 (62 units)
4th Floor Completed Completed Completed Completed Completed 0% 0% 0% 0% 50% 0% 0% 0% 50% 0% 0% 0% 0% 0%
5th Floor Completed Completed 0% 50% Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
6th Floor Completed Completed 0% 0% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor/ Mumty 30% 10% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0% 0% 0% 0% 0%

Gr. Floor Completed Completed NA Completed Completed 80% 50% 20% 0% Completed 0% Completed 50% Completed 50% 50% 0% 0% 0%
1st Floor Completed Completed Completed Completed Completed 90% 60% 80% 0% Completed 0% Completed 50% Completed 0% 40% 0% 0% 0%
Nurses Hostel 2nd Floor Completed Completed Completed Completed Completed 90% 0% 0% 0% Completed 0% Completed 0% Completed 0% 40% 0% 0% 0%
(49 units)
3 3rd Floor Completed Completed Completed Completed Completed 0% 0% 0% 0% Completed 0% 0% 0% Completed 0% 0% 0% 0% 0%
4th Floor Completed Completed Completed Completed Completed 0% 0% 0% 0% 50% 0% 0% 0% 70% 0% 0% 0% 0% 0%
5th Floor Completed Completed 0% 0% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor/ Mumty Completed 50% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0% 0% 0% 0% 0%
Name of the Project: Establishment of New Medical College & Upgradation of District Hospital to 500 bedded Hospital on EPC basis at Kanpur Dehat, Uttar Pradesh, India
Finishing Check List
Wall Tile
Water Internal External Door Frame Door Shutter Window Window Tile with Kota stone Polish & Granite With Toilet Gird Toilet CP
S.No. Name of Building No. of Proposed Floor RCC work Block work Tile Grouting dado / Lift False Ceiling Internal Paint External Paint Light Fixture
Proofing Plaster Plaster Fixing Fixing Frame Fixing Glass Fixing Skirting with skirting Grinding Skirting Ceiling Fitting
facing
Gr. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed 0% 0%
1st Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed 0% 50%
2nd Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed 0% 0%
Academic Block College 3rd Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed 0% 0%
1 Building 4th Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% 0% 0% 0% 0%
5th Floor Completed Completed Completed Completed Completed Completed 0% 0% 0% 10% 10% 10% 0% 0% 0% 0% 0% 0% 0% 0%
6th Floor Completed Completed 0% 10% 70% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
7th Floor Completed 60% 0% 0% 70% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor/ Mumty Completed 90% 25% 20% 70% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA 0%
Gr. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA Completed 10% Completed 0% 0%
1st Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA Completed 10% Completed 0% 0%
2nd Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA Completed 10% Completed 0% 0%
Girls Hostel
2 3rd Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA Completed 10% Completed 0% 0%
4th Floor Completed Completed Completed Completed Completed Completed 80% 90% 50% Completed Completed Completed Completed Completed NA 50% 10% 0% 0% 0%
5th Floor Completed Completed Completed Completed Completed Completed 50% 70% 40% Completed Completed Completed Completed Completed NA 50% 10% 0% 0% 0%
Terrace Floor/ Mumty Completed Completed 40% 50% 80% 0% 0% NA NA NA NA NA NA NA NA 0% 10% NA NA 0%
Gr. Floor Completed Completed Completed Completed 95% Completed Completed Completed 95% Completed Completed Completed Completed Completed NA Completed 10% Completed 0% 70%
1st Floor Completed Completed Completed Completed 95% Completed Completed Completed 95% Completed Completed Completed Completed Completed NA Completed 10% Completed 0% 70%
2nd Floor Completed Completed Completed Completed 95% Completed Completed Completed 95% Completed Completed Completed Completed Completed NA Completed 10% Completed 0% 70%
Boys Hostel 3rd Floor Completed Completed Completed Completed 95% Completed Completed Completed 95% Completed Completed Completed Completed Completed NA Completed 10% Completed 0% 70%
2
4th Floor Completed Completed Completed Completed 95% Completed 90% Completed 50% Completed Completed Completed Completed Completed NA Completed 10% 0% 0% 70%
5th Floor Completed Completed Completed Completed 95% Completed 90% Completed 50% Completed Completed Completed Completed Completed NA Completed 10% 0% 0% 70%
6th Floor Completed Completed Completed Completed 95% Completed 90% 50% 50% Completed Completed Completed Completed Completed NA 50% 10% 0% 0% 70%
Terrace Floor/ Mumty Completed Completed 50% Completed 95% 0% 0% 0% 0% NA NA NA NA NA NA 0% 0% NA NA 0%
Gr. Floor Completed Completed 0% Completed 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 10% 0% 0% 0% 0%
Interns Hostel 1st Floor Completed Completed 50% Completed 20% 50% 20% 0% 0% Completed 70% 50% 0% Completed NA 10% 0% 0% 0% 0%
4
2nd Floor Completed Completed 70% Completed 20% 50% 20% 0% 0% Completed 80% 0% 0% 0% NA 10% 0% 0% 0% 0%
Terrace Floor/ Mumty Completed Completed 20% 0% 20% 0% 0% NA NA NA NA NA NA NA NA 0% 0% 0% 0% 0%
Gr. Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed Completed 0% 0% Completed NA 0% 0% 0% 0% 0%
Type-2 1st Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed Completed 0% 0% Completed NA 0% 0% 0% 0% 0%
5
2nd Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed 20% 0% 0% 0% NA 0% 0% 0% 0% 0%
Terrace Floor/ Mumty Completed Completed Completed Completed Completed 0% 0% NA NA NA NA NA NA NA NA 50% 50% NA 0% 80%
Gr. Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% 90% Completed Completed Completed Completed NA Completed 50% 0% 0% Completed
1st Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% 90% 95% Completed Completed Completed NA 70% 50% 0% Completed Completed
Type-3 2nd Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% 90% 95% Completed Completed Completed NA 70% 50% 0% Completed Completed
6
3rd Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% 90% 95% Completed Completed Completed NA 70% 50% 0% Completed Completed
4th Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% 90% 95% Completed Completed Completed NA 70% 50% 0% 0% Completed
Terrace Floor/ Mumty Completed Completed Completed Completed Completed 0% 0% NA NA NA NA NA NA NA NA 0% 50% 0% 0% 0%
Gr. Floor Completed Completed Completed Completed 0% Completed Completed 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0% 0%
1st Floor Completed Completed Completed Completed 0% Completed Completed 0% 0% Completed Completed 0% 0% Completed NA 25% 0% 0% 0% 0%
2nd Floor Completed Completed Completed Completed 0% Completed Completed 0% 0% Completed Completed 0% 0% Completed NA 25% 0% 0% 0% 0%
3rd Floor Completed Completed 0% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0% 0%
4th Floor Completed Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0% 0%
Type-4
7 5th Floor Completed 80% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0% 0%
6th Floor Completed 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0% 0%
7th Floor Completed 40% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0% 0%
8th Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0% 0%
9th Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0% 0%
Terrace Floor/ Mumty Completed 0% 0% 0% 0% 0% 0% NA NA NA NA NA NA NA NA 0% 0% 0% 0% 0%
Gr. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed NA Completed 50% 0% 0% 0%
1st Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed NA Completed 50% 0% 0% 0%
Type-5
8 2nd Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed NA Completed 50% 0% 0% 0%
3rd Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed NA Completed 50% 0% 0% 0%
Terrace Floor/ Mumty Completed Completed 50% Completed Completed 0% 0% NA NA NA NA NA NA NA NA Completed 50% 0% 0% 0%
Gr. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA Completed Completed Completed Completed Completed
Director Residense
9 1st Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA Completed Completed Completed Completed Completed
Terrace Floor/ Mumty Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA Completed Completed Completed Completed Completed

file:///conversion/tmp/activity_task_scratch/727673401.xlsx,727673401.xlsx 4 of 13
Name of the Project: Establishment of New Medical College & Upgradation of District Hospital to 500 bedded Hospital on EPC basis at Kanpur Dehat, Uttar Pradesh, India
Finishing Check List
Wall Tile
Water Internal External Door Frame Door Shutter Window Window Tile with Kota stone Polish & Granite With Toilet Gird Toilet CP
S.No. Name of Building No. of Proposed Floor RCC work Block work Tile Grouting dado / Lift False Ceiling Internal Paint External Paint Light Fixture
Proofing Plaster Plaster Fixing Fixing Frame Fixing Glass Fixing Skirting with skirting Grinding Skirting Ceiling Fitting
facing

Multipurpose Hall
10 G Completed 85% 95% 70% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Basement Completed Completed Completed Completed NA Completed 0% NA 0% Completed Completed Completed Completed Completed 40% Completed 0% 0% 10% 0%
Gr. Floor Completed Completed Completed Completed Completed Completed 80% 40% 0% Completed Completed Completed Completed Completed 70% Completed 0% Completed 10% 0%
1st Floor Completed Completed Completed Completed Completed Completed 80% 60% 60% Completed Completed Completed Completed Completed 70% Completed 0% Completed 10% 0%
2nd Floor Completed Completed Completed Completed Completed Completed 70% 80% 75% Completed Completed Completed Completed Completed 60% Completed 0% 0% 10% 0%
3rd Floor Completed Completed Completed Completed Completed 80% 60% 80% 75% Completed Completed Completed Completed Completed 60% 0% 0% 0% 0% 0%
11 Hospital Building 4th Floor Completed Completed Completed Completed Completed 80% 50% 80% 60% Completed Completed Completed 0% Completed 80% 0% 0% 0% 0% 0%
5th Floor Completed 95% 55% 65% 70% 55% 45% 0% 0% 50% 40% 100% 0% 70% 80% 0% 0% 0% 0% 0%
6th Floor Completed 90% 55% 65% 70% 0% 0% 0% 0% 20% 30% 60% 0% 60% 80% 0% 0% 0% 0% 0%
7th Floor Completed 65% 90% 50% 50% 0% 0% 0% 0% 50% 70% 70% 0% 0% 10% 0% 0% 0% 0% 0%
8th Floor Completed 65% 0% 45% 50% 0% 0% 0% 0% 50% 70% 70% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor/ Mumty Completed 60% 40% 10% 40% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Gr. Floor Completed Completed Completed Completed 90% Completed 70% 90% 100% Completed Completed Completed Completed Completed NA 50% 10% 75% 0% 0%
1st Floor Completed Completed Completed Completed Completed Completed 80% 90% 100% Completed Completed Completed Completed Completed NA 50% 10% 75% 0% 0%
2nd Floor Completed Completed Completed Completed Completed Completed 80% 90% 100% Completed Completed Completed Completed Completed NA 50% 10% 75% 0% 0%
12 Nurses Hostel 3rd Floor Completed Completed Completed Completed Completed Completed 80% 90% 100% Completed Completed Completed Completed Completed NA 50% 10% 75% 0% 0%
4th Floor Completed Completed Completed Completed Completed Completed 80% 90% 100% Completed 95% 90% Completed Completed NA 50% 0% 75% 0% 0%
5th Floor Completed Completed Completed Completed Completed 80% 80% 90% 100% 90% 95% 0% 0% 0% NA 50% 0% 75% 0% 0%
Terrace Floor/ Mumty Completed Completed 60% 60% 80% 80% 0% 0% 0% NA NA NA NA NA NA 0% 0% 0% 0% 0%
Gr. Floor Completed Completed Completed Completed 90% Completed 80% 80% 30% Completed Completed Completed Completed Completed NA 50% 10% 10% 0% 0%
1st Floor Completed Completed Completed Completed 90% Completed 80% 80% 30% Completed Completed Completed Completed Completed NA 50% 10% 10% 0% 0%
2nd Floor Completed Completed Completed Completed 90% Completed 80% 80% 20% Completed Completed Completed Completed Completed NA 50% 10% 0% 0% 0%
3rd Floor Completed Completed Completed Completed 90% Completed 80% 80% 30% Completed 90% Completed Completed Completed NA 50% 10% 0% 0% 0%
13 Resident Hostel
4th Floor Completed Completed Completed Completed 90% Completed 60% 80% 0% Completed 90% Completed Completed Completed NA 50% 10% 0% 0% 0%
5th Floor Completed Completed Completed Completed 90% Completed 80% 60% 0% Completed 90% 80% 0% Completed NA 50% 0% 0% 0% 0%
6th Floor Completed Completed Completed 95% 90% 80% 75% 55% 0% Completed 90% 80% 0% 50% NA 50% 0% 0% 0% 0%
Terrace Floor/ Mumty Completed Completed 80% 40% 90% 0% 0% 0% 0% NA NA NA NA NA NA 0% 0% 0% 0% 0%

file:///conversion/tmp/activity_task_scratch/727673401.xlsx,727673401.xlsx 5 of 13
Name of the Project: Establishment of NEW Medical College attached with exixting, District/Referal hospital on EPC basis at Kushinagar, Uttar Pradesh, INDIA
Finishing Check List
Window Wall Tile
S.N Name of Building No. of Proposed RCC work Block work Water Internal External Door Frame Door Shutter Window Glass Tile with dado / Lift Kota stone Polish & Granite With False Ceiling Internal External Toilet Gird Toilet CP
o. Floor Proofing Plaster Plaster Fixing Fixing Frame Fixing Fixing Skirting facing with skirting Grinding Skirting Paint Paint Ceiling Fitting

G. Floor Completed Completed NA Completed Completed Completed Completed 80% 50% Completed Completed Completed Completed Completed 80% 50% 0% 90% 20%
1st. Floor Completed Completed Completed Completed Completed Completed Completed 80% 50% Completed Completed Completed Completed Completed 70% 50% 0% 90% 20%
2nd. Floor Completed Completed Completed Completed Completed Completed Completed 80% 50% Completed Completed Completed Completed Completed 50% 50% 0% 0% 0%
3rd. Floor Completed Completed Completed Completed Completed Completed Completed 80% 0% Completed Completed Completed Completed Completed 30% 0% 0% 0% 0%
Academic Block(for
1 100 admissions)
4th. Floor Completed Completed Completed Completed Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
5th Floor Completed Completed 0% 70% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
6th Floor Completed 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
7th Floor Completed 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty Completed 80% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

G. Floor Completed Completed NA Completed Completed Completed Completed Completed 50% Completed Completed Completed 0% Completed 50% 80% 0% 0% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed 50% Completed Completed Completed 0% Completed 0% 80% 0% 0% 0%
2nd. Floor Completed Completed Completed Completed Completed Completed Completed Completed 50% Completed Completed Completed 0% Completed 0% 80% 0% 0% 0%
UG Boys Hostel (180 3rd. Floor Completed Completed Completed Completed Completed Completed Completed Completed 50% Completed Completed Completed 0% Completed 0% 80% 0% 0% 0%
2 Seats),
4th. Floor Completed Completed Completed Completed Completed Completed 0% 0% 0% Completed Completed Completed 0% 0% 0% 0% 0% 0% 0%
5th. Floor Completed Completed Completed Completed Completed 0% 0% 0% 0% Completed Completed Completed 0% 0% 0% 0% 0% 0% 0%
6th. Floor Completed 80% Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

G. Floor Completed Completed NA Completed Completed Completed Completed Completed 0% Completed Completed Completed 0% Completed Completed 0% 0% 0% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
2nd. Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
UG Girls Hostel (120
3 Seats), 3rd. Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
4th. Floor Completed Completed Completed Completed Completed 0% 0% 0% 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
5th Floor Completed Completed Completed Completed Completed 0% 0% 0% 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
Terrace Floor / Mumty Completed Completed Completed Completed 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Interns hostel(50 G. Floor Completed Completed NA Completed Completed Completed 50% 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
seats for both boys
& girls) 1st. Floor Completed Completed Completed Completed Completed Completed 50% 50% 0% Completed Completed Completed 0% Completed 0% 50% 0% 0% 0%
4
2nd. Floor Completed Completed Completed Completed Completed Completed 50% 50% 0% Completed Completed Completed 0% Completed 0% 50% 0% 0% 0%
Terrace Floor / Mumty Completed Completed 0% 0% Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Type-II Residence(12 G. Floor Completed Completed NA Completed Completed Completed Completed Completed 0% Completed Completed Completed Completed Completed 0% 50% 50% 70% 0%
units)
1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% 70% 50% 70% 0%
5
2nd. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% 70% 50% 70% 0%
Terrace Floor / Mumty Completed Completed 0% Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 0% 70% 50% 70% 0%

G. Floor Completed Completed NA Completed Completed Completed 0% Completed 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
2nd. Floor Completed Completed Completed Completed Completed Completed 50% Completed 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
6 Completed Completed Completed Completed Completed Completed 50% Completed 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
3rd. Floor
Completed Completed Completed Completed Completed Completed 0% Completed 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
4th. Floor Completed Completed Completed Completed Completed Completed 0% Completed 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
Type-III Residence
(20 units) Terrace Floor / Mumty Completed Completed 50% Completed Completed Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

G. Floor Completed Completed NA Completed Completed Completed 0% 20% 0% 25% 0% 80% 0% 0% 0% 0% 0% 0% 0%


1st. Floor Completed Completed Completed Completed Completed Completed 20% 70% 0% Completed Completed 80% 0% 0% 0% 0% 0% 0% 0%
2nd. Floor Completed Completed Completed Completed Completed Completed 0% 70% 0% Completed Completed 80% 0% 0% 0% 0% 0% 0% 0%
3rd. Floor Completed Completed Completed Completed Completed Completed 0% 70% 0% Completed Completed 80% 0% 0% 0% 0% 0% 0% 0%
4th. Floor Completed Completed Completed Completed 0% Completed 0% 70% 0% Completed Completed 80% 0% 0% 0% 0% 0% 0% 0%
Type-IV Residence
7 (20units)
5th Floor Completed Completed Completed Completed 0% Completed 0% 0% 0% 50% 50% 0% 0% 0% 0% 0% 0% 0% 0%
6th Floor Completed Completed Completed Completed 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0% 0% 0% 0%
7th Floor Completed Completed Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
8th Floor Completed Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
9th Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Name of the Project: Establishment of NEW Medical College attached with exixting, District/Referal hospital on EPC basis at Kushinagar, Uttar Pradesh, INDIA
Finishing Check List
Window Wall Tile
S.N Name of Building No. of Proposed RCC work Block work Water Internal External Door Frame Door Shutter Window Glass Tile with dado / Lift Kota stone Polish & Granite With False Ceiling Internal External Toilet Gird Toilet CP
o. Floor Proofing Plaster Plaster Fixing Fixing Frame Fixing Fixing Skirting facing with skirting Grinding Skirting Paint Paint Ceiling Fitting

G. Floor Completed Completed NA Completed Completed Completed Completed Completed 80% Completed Completed Completed Completed Completed 0% 80% 50% 80% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed 80% Completed Completed Completed Completed Completed 0% 80% 50% 80% 0%
8 Type-V (8 Units) 2nd. Floor Completed Completed Completed Completed Completed Completed Completed Completed 80% Completed Completed Completed Completed Completed 0% 80% 50% 80% 0%
3rd. Floor Completed Completed Completed Completed Completed Completed Completed Completed 80% Completed Completed Completed Completed Completed 0% 80% 50% 80% 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed Completed Completed Completed Completed 0% 0% 0% 0% 0%

Director’s Residence G. Floor Completed Completed NA Completed Completed Completed Completed Completed 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
(1 Units)
9 1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed Completed Completed 0% Completed 0% 0% 0% 0% 0%

Multipurpose G. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%


10
Terrace Floor 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Basement. Floor Completed Completed NA Completed 0% 0% 0% 0% 0% 0% 0% 80% 0% 0% 0% 0% 0% 0% 0%


G. Floor Completed Completed 50% Completed 0% 0% 0% 0% 0% 90% 60% 20% 0% 50% 25% 0% 0% 0% 0%
1st. Floor Completed Completed 20% 70% 0% 0% 0% 0% 0% 40% 0% 0% 0% 0% 10% 0% 0% 0% 0%
2nd. Floor Completed 80% 0% 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
3rd. Floor Completed 70% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Hospital Building
11 (500 bedded) 4th. Floor Completed 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
5th. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
6th. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
7th Floor 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
8th Floor 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed 60% NA 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%


1st. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
2nd. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Sr. Doctor Residents 3rd. Floor 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
12 (62 units) 4th. Floor 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
5th. Floor 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
6th. Floor 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed 50% 50% 40% 0% Completed Completed 50% 50% Completed 60% 20% 50% 0% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed 85% 60% Completed Completed Completed 80% Completed NA 80% 50% Completed 0%
2nd. Floor Completed Completed Completed Completed Completed Completed Completed 85% 60% Completed Completed Completed 80% Completed NA 80% 50% Completed 0%
Nurses Hostel
13 3rd. Floor Completed Completed Completed Completed Completed Completed Completed 85% 60% Completed Completed Completed 80% Completed NA 80% 50% Completed 0%
4th. Floor Completed Completed Completed Completed Completed Completed Completed 85% 60% Completed Completed Completed 80% Completed NA 80% 50% Completed 0%
5th. Floor Completed Completed Completed Completed Completed Completed Completed 85% 60% Completed Completed Completed 80% Completed NA 80% 50% Completed 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed Completed 0% 0% 0% NA 0% 0% 0% NA 50% 50% NA NA
Name of the Project: Establishment of NEW Medical College & Upgradation of District Hospital to 500 bedded Hospital on EPC basis at Lalitpur, Uttar Pradesh, INDIA
Finishing Check List

Wall Tile
S.N Name of Building No. of Proposed Floor RCC work Block work Water Internal External Door Frame Door Shutter Window Window Tile with dado / Lift Kota stone Polish & Granite With False Ceiling Internal External Toilet Gird Toilet CP
o. Proofing Plaster Plaster Fixing Fixing Frame Fixing Glass Fixing Skirting facing with skirting Grinding Skirting Paint Paint Ceiling Fitting

G. Floor Completed Completed NA Completed Completed Completed Completed completed completed Completed Completed Completed Completed Completed 80% 30% 60% complete 10%
1st. Floor Completed Completed Completed Completed Completed Completed Completed completed completed Completed Completed Completed 50% Completed 80% 30% 60% 50% 0%
1 Academic Block 2nd. Floor Completed Completed Completed Completed Completed Completed Completed completed completed completed Completed Completed 50% Completed 75% 30% 60% 50% 0%
3rd. Floor Completed Completed Completed Completed Completed Completed Completed completed 20% completed Completed Completed 50% Completed 75% 30% 60% 50% 0%
Terrace Floor / Mumty Completed Completed 50% Completed Completed Completed Completed completed 20% Completed Completed 50% Completed 75% 30% 60% 50% NA

G. Floor Completed Completed NA Completed Completed Completed Completed completed completed Completed Completed Completed completed Completed completed completed 50% completed 0%
UG Boys Hostel 1st. Floor Completed Completed Completed Completed Completed Completed Completed completed completed Completed Completed Completed completed Completed completed completed 50% completed 0%
(211 Seats), Boys 2nd. Floor Completed Completed Completed Completed Completed Completed Completed completed completed Completed Completed Completed completed Completed completed 30% 50% completed 0%
2 interns (26 Seats)- 3rd. Floor Completed Completed Completed Completed Completed Completed Completed completed completed Completed Completed Completed completed Completed 0% 30% 50% 0% 0%
Double Seater
Rooms 4th. Floor Completed Completed Completed Completed Completed Completed Completed completed 90% Completed 80% 50% completed 50% 0% 30% 50% 0% 0%
5th. Floor Completed Completed Completed Completed Completed Completed Completed completed 90% Completed 80% 50% completed 50% 0% 30% 50% 0% 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed Completed completed 90% NA 50% completed 50% NA 30% 50% NA NA
5
G. Floor Completed Completed NA Completed Completed Completed Completed completed completed Completed Completed Completed 0% Completed completed completed 50% completed 0%
UG Girls Hostel
(151 Seats), Girls 1st. Floor Completed Completed Completed Completed Completed Completed Completed completed completed Completed Completed Completed 60% Completed completed completed 50% completed 0%
interns ( 26 Seats), 2nd. Floor Completed Completed Completed Completed Completed Completed Completed completed completed Completed Completed Completed 60% Completed completed completed 50% completed 0%
3 Double Seater
Rooms 3rd. Floor Completed Completed Completed Completed Completed Completed Completed completed completed Completed completed completed 70% completed completed 30% 50% completed 0%
Weightage In SOP 4th. Floor Completed Completed Completed completed Completed completed completed completed completed completed completed completed 70% completed completed 30% 50% completed 0%
-3% Terrace Floor / Mumty NA
Completed Completed 0% completed Completed completed completed completed completed completed completed completed 70% completed completed 30% 50% completed

G. Floor Completed Completed NA Completed Completed Completed Completed completed completed Completed 90% Completed Complete Completed 0% 30% 50% 0% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed completed completed Completed 90% Completed Complete Completed 0% 40% 50% 0% 0%
Type-II Residence
2nd. Floor Completed Completed Completed Completed Completed Completed Completed completed completed Completed 90% Completed complete Completed 0% 40% 50% 0% 0%
Terrace Floor / Mumty Completed Completed 0% Completed Completed Completed Completed completed completed Completed NA Completed complete Completed NA 40% 50% NA NA

G. Floor Completed 50% NA 0% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%


1st. Floor Completed 50% 0% 0% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
2nd. Floor 50% 20% 0% 0% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Type-III Residence
3rd. Floor 50% 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
4th. Floor 50% 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 50% 20% 0% 0% 0% 0% 0% 0% 0% NA NA 0% 0% 0% 0% 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed 0% 0% 0% 0% 60% 0% 60% 0% 0% 0% 0% 0% 0% 0%


1st. Floor Completed Completed Completed Completed Completed 50% 50% 0% 0% 60% 60% 60% 0% 60% 0% 0% 0% 0% 0%
Type-IV Residence 2nd. Floor
(20units)
Completed Completed Completed Completed Completed 40% 40% 0% 0% 50% 50% 0% 0% 40% 0% 0% 0% 0% 0%
3rd. Floor Completed Completed Completed Completed Completed 40% 0% 0% 0% 60% 0% 0% 0% 0% 0% 0% 0% 0% 0%
6 4th. Floor Completed 90% 40% 0% 70% 40% 0% 0% 0% 60% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 90% 40% 0% 0% 0% 40% 0% 0% 0% 60% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed completed 0% 0% 0% 0% completed 0% 80% 60% 60% NA 0% 0% 0% 0%


1st. Floor Completed Completed Completed Completed completed 0% 0% 0% 0% Completed 0% 80% 60% 60% NA 0% 0% 0% 0%
Type-V Residence 2nd. Floor NA
7 (8units) Completed Completed Completed Completed completed 0% 0% 0% 0% 0% 0% 90% 60% 60% 0% 0% 0% 0%
3rd. Floor Completed Completed Completed Completed 0% 0% 0% 0% 0% 0% 0% 90% 60% 60% NA 0% 0% 0% 0%
Terrace Floor / Mumty Completed 90% 0% 0% 0% 0% 0% 0% 0% 0% NA 90% 60% 60% NA 0% 0% NA NA

Director’s G. Floor NA
Residence Completed Completed NA Completed Completed Completed Completed completed completed Completed Completed Completed Completed completed completed completed completed 0%
8 (1 Units) 1st. Floor Completed Completed Completed Completed Completed Completed Completed completed completed Completed Completed Completed Completed completed NA completed completed completed 0%
Weightage In SOP Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed Completed completed completed Completed completed Completed Completed completed NA completed completed completed NA
-1%
Multipurpose (250
seated Capacity) G. Floor Completed Completed NA 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
9 Weightage In SOP
Terrace Floor Completed Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
-2%

Dinning Block G. Floor Completed Completed NA Completed Completed 0% 0% 0% 0% 70% NA 50% 50% 80% 0% 0% 0% 0% 0%
10
Terrace Floor Completed Completed Completed NA Completed NA NA NA NA NA NA NA NA NA NA NA NA NA NA

G. Floor Completed Completed NA completed completed 0% 0% 0% 0% 0% 0% completed completed completed 0% 50% 50% 0% 0%
10 Autopsy
Terrace Floor / Mumty Completed Completed completed completed completed 0% 0% 0% 0% 0% NA NA NA NA NA NA NA NA NA
Name of the Project: Establishment of NEW Medical College & Upgradation of District Hospital to 500 bedded Hospital on EPC basis at Lalitpur, Uttar Pradesh, INDIA
Finishing Check List

Wall Tile
S.N Name of Building No. of Proposed Floor RCC work Block work Water Internal External Door Frame Door Shutter Window Window Tile with dado / Lift Kota stone Polish & Granite With False Ceiling Internal External Toilet Gird Toilet CP
o. Proofing Plaster Plaster Fixing Fixing Frame Fixing Glass Fixing Skirting facing with skirting Grinding Skirting Paint Paint Ceiling Fitting

Basement. Floor Completed 0% 75% 0% 0% 0% 0% 0% 0% Completed 0% 0% 70% 0% 0% 30% 40% 0% 0%


G. Floor Completed Completed Completed Completed 50% 80% 0% 0% 0% Completed Completed Completed 60% Completed 40% 30% 40% 0% 0%
1st. Floor Completed Completed Completed Completed 45% 70% 0% 0% 0% Completed Completed Completed 60% Completed 0% 30% 40% 0% 0%
2nd. Floor Completed Completed Completed Completed 40% 70% 0% 0% 0% Completed Completed Completed 60% Completed 0% 30% 40% 0% 0%
3rd. Floor Completed Completed Completed Completed 35% 60% 0% 0% 0% Completed Completed Completed 50% Completed 0% 30% 40% 0% 0%
Hospital Building
12 (210 bedded) 4th. Floor Completed Completed Completed Completed 35% 40% 0% 0% 0% Completed Completed Completed 0% Completed 0% 30% 40% 0% 0%
5th. Floor Completed Completed Completed Completed 35% 0% 0% 0% 0% completed 40% completed 0% 40% 0% 30% 40% 0% 0%
6th. Floor Completed Completed Completed Completed 35% 0% 0% 0% 0% completed 0% completed 0% 0% 0% 30% 40% 0% 0%
7th. Floor Completed Completed Completed 0% 35% 0% 0% 0% 0% completed 0% completed 0% 0% 0% 30% 40% 0% 0%
8th. Floor Completed completed 0% 0% 0% 0% 0% 0% 0% completed 0% completed 0% 0% 0% 30% 40% 0% 0%
Terrace Floor / Mumty completed completed 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 30% 40% NA NA

G. Floor Completed Completed NA Completed 0% 35% 0% 0% 0% 45% 20% 40% 0% 0% 0% 10% 20% 0% 0%
1st. Floor Completed Completed completed Completed 0% 25% 0% 0% 0% 35% 20% 40% 0% 0% 0% 10% 20% 0% 0%
2nd. Floor Completed Completed completed Completed 0% 0% 0% 0% 0% 0% 20% 40% 0% 0% 0% 10% 20% 0% 0%
3rd. Floor Completed Completed completed Completed 0% 0% 0% 0% 0% 0% 0% 40% 0% 0% 0% 0% 20% 0% 0%
Sr. Residents 4th. Floor
13 (32 units) Completed Completed completed Completed 0% 0% 0% 0% 0% 0% 0% 40% 0% 0% 0% 0% 20% 0% 0%
5th. Floor Completed Completed 0% 50% 0% 0% 0% 0% 0% 0% 0% 40% 0% 0% 0% 0% 20% 0% 0%
6th. Floor Completed Completed 0% 50% 0% 0% 0% 0% 0% 0% 0% 40% 0% 0% 0% 0% 20% 0% 0%
7th. Floor Completed 80% 0% 0% 0% 0% 0% 0% 0% 0% 0% 40% 0% 0% 0% 0% 20% 0% 0%
Terrace Floor / Mumty Completed Completed 0% 0% 0% 0% 0% 0% 0% 0% NA 40% 0% 0% NA 0% 20% NA NA

G. Floor Completed completed NA 0% 0% 0% 0% 0% 0% 0% 0% 30% 20% 0% 0% 0% 0% 0% 0%


14 1st. Floor Completed 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 30% 20% 0% 0% 0% 0% 0% 0%
Jr, Residents 2nd. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 30% 20% 0% 0% 0% 0% 0% 0%
(32 units) 3rd. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 30% 20% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 30% 20% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed 0% 35% 0% 0% 0% 45% 0% 50% 0% 0% 0% 10% 20% 0% 0%


1st. Floor Completed Completed Completed Completed 0% 25% 0% 0% 0% 35% 0% 50% 0% 0% 0% 10% 20% 0% 0%
2nd. Floor Completed Completed Completed Completed 0% 0% 0% 0% 0% 0% 0% 50% 0% 0% 0% 10% 20% 0% 0%
3rd. Floor Completed Completed Completed Completed 0% 0% 0% 0% 0% 0% 0% 50% 0% 0% 0% 10% 20% 0% 0%
Nurses Hostel 4th. Floor
15 (48 units) Completed Completed Completed Completed 0% 0% 0% 0% 0% 0% 0% 50% 0% 0% 0% 10% 20% 0% 0%
5th. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 50% 0% 0% 0% 10% 20% 0% 0%
6th. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 50% 0% 0% 0% 5% 20% 0% 0%
7th. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 50% 0% 0% 0% 0% 10% 0% 0%
Terrace Floor / Mumty Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 50% 0% 0% NA 0% 10% NA NA
Name of the Project: Establishment of NEW Medical College & Upgradation of District Hospital to 500 bedded Hospital on EPC basis at Sonbhadra, Uttar Pradesh, INDIA
Finishing Ceck List

S.No Water Internal External Door Frame Door Shutter Window Window Tile with Wall Tile Kota stone Polish & Granite With Toilet Gird Toilet CP
. Name of Building No. of Proposed Floor RCC work Block work Proofing Plaster Plaster Fixing Fixing Frame Fixing Glass Fixing Skirting dado / Lift with skirting Grinding Skirting False Ceiling Internal Paint External Paint Ceiling Fitting
facing
G. Floor Completed Completed NA Completed Completed Completed Completed Completed 80% Completed Completed Completed Completed Completed 90% 90% 0% 70% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed 60% Completed Completed Completed Completed Completed 80% 90% 0% 0% 0%
2nd. Floor Completed Completed Completed Completed Completed 95% 90% 95% 20% Completed Completed Completed Completed Completed 70% 60% 0% 0% 0%
1 Academic Block
3rd. Floor Completed Completed 60% Completed Completed 60% 50% 10% 0% 70% 50% 50% 0% 60% 60% 10% 0% 0% 0%
4th. Floor Completed 70% 0% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 50% 70% 0% 30% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed Completed Completed 80% 70% Completed 90% Completed Completed 90% 50% 90% 0% 0% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed 80% 70% Completed 90% Completed Completed Completed 50% 90% 0% 0% 0%
2nd. Floor Completed Completed Completed Completed Completed Completed 85% 80% 0% Completed 90% 10% 0% Completed 0% 80% 0% 0% 0%
3rd. Floor Completed Completed Completed Completed Completed 80% 80% 80% 0% 80% 90% 0% 0% 80% 0% 70% 0% 0% 0%
2 UG Boys Hostel
4th. Floor Completed Completed Completed Completed 80% 0% 0% 0% 0% 40% 0% 0% 0% 0% 0% 50% 0% 0% 0%
5th. Floor Completed Completed Completed 50% 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
6th. Floor 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 0% 50% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed Completed 80% 80% 50% Completed 95% Completed Completed Completed 50% 75% 0% 0% 0%
1st. Floor Completed Completed Completed Completed Completed Completed 80% 80% 50% Completed 95% 90% Completed Completed 50% 75% 0% 0% 0%
2nd. Floor Completed Completed Completed Completed 90% Completed 80% 80% 0% Completed 95% 70% 0% Completed 0% 50% 0% 0% 0%
3 UG Girls Hostel
3rd. Floor Completed Completed Completed Completed 80% 0% 0% 0% 0% 90% 90% 0% 0% 0% 0% 25% 0% 0% 0%
4th. Floor Completed Completed Completed 90% 80% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 25% 0% 0% 0%
Terrace Floor / Mumty 50% 50% 0% 50% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed Completed Completed Completed Completed 90% 90% Completed Completed Completed NA 90% 85% 0% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed 90% 90% Completed Completed Completed NA 90% 85% 0% 0%
4 Type-II Residence
2nd. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed 90% 60% Completed Completed Completed NA 90% 85% 0% 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed 0% 0% NA NA NA NA Completed Completed Completed NA 90% 85% NA NA

G. Floor Completed 50% NA 0% 60% 0% 0% 0% 0% 0% 0% 0% 0% NA 50% 0% 0% 0%


1st. Floor Completed Completed Completed Completed 60% 0% 0% 0% 0% 75% 75% 60% 0% 80% NA 50% 0% 0% 0%
2nd. Floor Completed Completed Completed Completed 60% 0% 0% 0% 0% 60% 60% 60% 0% 30% NA 50% 0% 0% 0%
5 Type-III Residence
3rd. Floor Completed 64% 0% 25% 60% 0% 0% 0% 0% 25% 25% 0% 0% 0% NA 0% 0% 0% 0%
4th. Floor 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0%
Terrace Floor / Mumty 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed 90% 0% 0% 0% 0% 50% 0% 50% 50% Completed 0% 90% 70% 0% 0%
1st. Floor Completed Completed Completed Completed 90% 80% 50% 60% 0% Completed Completed Completed Completed Completed 0% 90% 70% 0% 0%
2nd. Floor Completed Completed 70% Completed 90% 0% 0% 60% 0% 75% Completed 80% 80% Completed 0% 90% 70% 0% 0%
6 Type-IV Residence
3rd. Floor Completed Completed Completed Completed 90% 0% 0% 60% 0% Completed 0% 0% 0% 0% 0% 50% 70% 0% 0%
4th. Floor Completed Completed Completed Completed 90% 0% 0% 60% 0% 50% 0% 0% 0% 0% 0% 0% 70% 0% 0%
Terrace Floor / Mumty Completed Completed 0% Completed 90% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 70% NA NA

G. Floor Completed Completed NA 90% 50% 0% 0% 0% 0% 0% 0% 50% 0% 0% NA 0% 0% 0% 0%


1st. Floor Completed Completed 80% Completed 50% 0% 0% 30% 0% Completed 0% 50% 0% 70% NA 80% 0% 0% 0%
7 Type-V Residence 2nd. Floor Completed Completed 80% Completed 50% 0% 0% 30% 0% 90% 0% 50% 0% 0% NA 40% 0% 0% 0%
3rd. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0%
Terrace Floor / Mumty 10% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed Completed Completed Completed Completed Completed NA Completed Completed Completed NA 90% 90% 60% 50%
8 Director’s Residence 1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA Completed Completed Completed NA 90% 90% 60% 50%
Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA Completed Completed NA NA 90% 90% NA NA

G. Floor Completed 90% NA 50% 30% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%


9 Multipurpose
Terrace Floor Completed Completed Completed Completed 30% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

G. Floor Completed Completed NA Completed 80% 80% 80% 0% 0% 80% NA Completed Completed 80% 0% 0% 0% 0% 0%
10 Dinning Block
Terrace Floor Completed Completed Completed NA 80% NA NA NA NA NA NA NA NA NA NA NA NA NA NA

Basement. Floor NA 0% NA 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
G. Floor Completed 40% û 10% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
1st. Floor Completed 65% 0% 70% 0% 0% 0% 0% 0% 60% 60% 0% 0% 0% 0% 0% 0% 0% 0%
2nd. Floor 80% 60% 0% 30% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
11 Hospital Building 3rd. Floor 80% 30% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
4th. Floor 30% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
5th. Floor 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
6th. Floor 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

Page 10
Name of the Project: Establishment of NEW Medical College & Upgradation of District Hospital to 500 bedded Hospital on EPC basis at Sonbhadra, Uttar Pradesh, INDIA
Finishing Ceck List

S.No Water Internal External Door Frame Door Shutter Window Window Tile with Wall Tile Kota stone Polish & Granite With Toilet Gird Toilet CP
. Name of Building No. of Proposed Floor RCC work Block work Proofing Plaster Plaster Fixing Fixing Frame Fixing Glass Fixing Skirting dado / Lift with skirting Grinding Skirting False Ceiling Internal Paint External Paint Ceiling Fitting
facing
G. Floor Completed Completed NA Completed Completed 70% 0% 30% 0% 80% Completed Completed Completed Completed 0% 60% 0% 0% 0%
12 Lecture Theatre 1st. Floor Completed Completed Completed Completed Completed 30% 0% 0% 0% NA NA 90% 90% û 0% 60% 0% 0% 0%
Terrace Floor / Mumty Completed 90% Completed 90% Completed 0% 0% 0% 0% NA NA 90% 90% û NA 0% 0% NA NA

Page 11
Name of the Project: Establishment of NEW Medical College & Upgradation of District Hospital to 500 bedded Hospital on EPC basis at Sultanpur, Uttar Pradesh, INDIA

Finishing Ceck List

S.No Water Internal External Door Frame Door Shutter Window Window Tile with Wall Tile Kota stone Polish & Granite With Toilet Gird Toilet CP
. Name of Building No. of Proposed Floor RCC work Block work Proofing Plaster Plaster Fixing Fixing Frame Fixing Glass Fixing Skirting dado / Lift with skirting Grinding Skirting False Ceiling Internal Paint External Paint Ceiling Fitting
facing
G. Floor Completed Completed NA Completed Completed Completed Completed Completed 70% Completed Completed Completed Completed Completed Completed 70% 25% Completed 25%
Academic Block 1st. Floor Completed Completed Completed Completed Completed Completed 95% Completed 80% Completed Completed Completed Completed Completed Completed 70% 25% Completed 0%
1
(college Building) 2nd. Floor Completed Completed Completed Completed Completed Completed 95% Completed 85% Completed Completed Completed Completed Completed Completed 70% 25% Completed 0%
(For 100 3rd. Floor Completed Completed Completed Completed Completed Completed 95% Completed 70% Completed Completed Completed Completed Completed Completed 50% 25% Completed 0%
Admissions) 4th. Floor Completed Completed Completed Completed Completed Completed 95% Completed 75% Completed Completed Completed Completed Completed 80% 50% 0% 80% 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed 0% Completed NA Completed NA Completed Completed NA NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed Completed Completed Completed 95% Completed Completed Completed Completed Completed NA 70% 25% Completed 25%
UG Boys Hostel 1st. Floor Completed Completed Completed Completed Completed Completed 98% Completed 95% Completed Completed Completed Completed Completed NA 70% 25% Completed 25%
(184 Seats), Boys 2nd. Floor Completed Completed Completed Completed Completed Completed 98% Completed 95% Completed Completed Completed Completed Completed NA 70% 25% Completed 0%
2
interns (26 Seats)- 3rd. Floor Completed Completed Completed Completed Completed Completed 98% Completed 95% Completed Completed Completed Completed Completed NA 70% 25% Completed 0%
Double Seater 4th. Floor Completed Completed Completed Completed Completed Completed 98% Completed 95% Completed Completed Completed Completed Completed NA 70% 25% Completed 0%
Rooms 5th. Floor Completed Completed Completed Completed Completed Completed 98% Completed 95% Completed Completed Completed Completed Completed NA 70% 25% Completed 0%
6th. Floor Completed Completed Completed Completed Completed Completed 98% Completed 95% Completed Completed Completed Completed Completed NA 70% 25% Completed 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed 98% NA NA Completed NA Completed Completed Completed NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed 98% 98% Completed 98% Completed Completed Completed Completed Completed NA 75% 25% Completed 50%
UG Girls Hostel (120 1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA 75% 25% Completed 50%
Seats), Girls interns 2nd. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA 50% 25% Completed 50%
3 ( 26 Seats), Double 3rd. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA 50% 25% Completed 50%
Seater Rooms
4th. Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed NA 50% 0% Completed 50%
Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed 95% NA NA Completed NA Completed Completed Completed NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed 95% 95% 70% 0% Completed Completed Completed Completed Completed NA 50% 25% 98% 0%
Type-II Residence 1st. Floor Completed Completed Completed Completed Completed 95% 95% 70% 0% Completed Completed Completed Completed Completed NA 50% 25% 98% 0%
4 (12 units) 2nd. Floor Completed Completed Completed Completed Completed 95% 95% 70% 0% Completed Completed Completed Completed Completed NA 50% 25% 98% 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed 0% 0% 0% 0% Completed NA Completed Completed Completed NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed Completed Completed 70% 0% Completed Completed Completed Completed Completed NA 50% 25% 0% 0%
1st. Floor Completed Completed Completed Completed Completed Completed Completed 70% 0% Completed Completed Completed Completed Completed NA 50% 25% 0% 0%
Type-III Residence 2nd. Floor Completed Completed Completed Completed Completed Completed Completed 70% 0% Completed Completed Completed Completed Completed NA 50% 25% 0% 0%
5 (20 units) 3rd. Floor Completed Completed Completed Completed Completed Completed 95% 70% 0% Completed Completed Completed Completed Completed NA 50% 25% 0% 0%
4th. Floor Completed Completed Completed Completed Completed Completed 95% 70% 0% Completed Completed Completed Completed Completed NA 50% 0% 0% 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed 0% 0% 0% 0% Completed NA Completed Completed Completed NA 0% 0% NA NA

G. Floor Completed Completed NA 95% 60% 95% 0% 0% 0% Completed Completed Completed Completed Completed NA 0% 0% 0% 0%
1st. Floor Completed Completed Completed 95% 60% 90% 0% 0% 0% Completed Completed Completed Completed Completed NA 0% 0% 0% 0%
Type-IV Residence 2nd. Floor Completed Completed Completed 95% 60% 90% 0% 0% 0% Completed Completed Completed 70% Completed NA 0% 0% 0% 0%
6 (20units) 3rd. Floor Completed Completed Completed 95% 50% 85% 0% 0% 0% Completed Completed 90% 70% Completed NA 0% 0% 0% 0%
4th. Floor Completed Completed 75% 95% 30% 80% 0% 0% 0% 90% 40% 75% 65% 90% NA 0% 0% 0% 0%
Terrace Floor / Mumty Completed Completed 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed Completed Completed 0% 0% Completed Completed Completed Completed Completed NA 50% 50% Completed 0%
Type-V Residence 1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed 95% Completed Completed Completed Completed Completed NA 50% 50% Completed 0%
7 (8units) 2nd. Floor Completed Completed Completed Completed Completed Completed Completed Completed 95% Completed Completed Completed Completed Completed NA 50% 30% Completed 0%
3rd. Floor Completed Completed Completed Completed Completed Completed Completed Completed 95% Completed Completed Completed Completed 90% NA 50% 30% Completed 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed 0% 0% 0% Completed NA Completed Completed 90% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed Completed Completed Completed 0% Completed NA Completed Completed Completed NA 70% 50% Completed 25%
8
Director’s Residence 1st. Floor Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed NA Completed Completed Completed NA 70% 50% Completed 25%
(1 Units)
Terrace Floor / Mumty Completed Completed Completed Completed Completed Completed Completed Completed 0% Completed NA Completed Completed NA NA 70% 50% NA NA

9
Multipurpose G. Floor Completed Completed NA Completed Completed 0% 0% 0% 0% Completed Completed Completed Completed 95% NA 0% 25% 0% 0%
Terrace Floor Completed Completed Completed Completed Completed NA NA 0% 0% NA NA NA NA NA NA NA NA NA NA

10
Dinning Block G. Floor Completed Completed NA Completed Completed 40% 0% 0% 0% 70% Completed Completed Completed Completed NA 0% 0% 0% 0%
Terrace Floor Completed Completed Completed NA Completed NA NA NA NA NA NA NA NA NA NA NA NA NA NA

Autopsy G. Floor Completed Completed NA Completed Completed 0% 0% 0% 0% Completed Completed Completed Completed Completed NA 50% 25% 0% 0%
11
Terrace Floor / Mumty Completed Completed Completed Completed Completed 0% 0% 0% 0% Completed NA Completed Completed Completed NA 50% 25% 0% 0%

Basement. Floor Completed Completed NA Completed 0% 0% 0% 0% 0% Completed 90% 95% 0% 90% 0% 0% 0% 0% 0%


G. Floor Completed 90% 0% 85% 0% 0% 0% 0% 0% Completed 80% 95% 0% 80% 0% 0% 0% 0% 0%
1st. Floor Completed 75% 0% 70% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Hospital Building
12 (210 bedded) Page 12
Name of the Project: Establishment of NEW Medical College & Upgradation of District Hospital to 500 bedded Hospital on EPC basis at Sultanpur, Uttar Pradesh, INDIA

Finishing Ceck List

S.No Water Internal External Door Frame Door Shutter Window Window Tile with Wall Tile Kota stone Polish & Granite With Toilet Gird Toilet CP
. Name of Building No. of Proposed Floor RCC work Block work Proofing Plaster Plaster Fixing Fixing Frame Fixing Glass Fixing Skirting dado / Lift with skirting Grinding Skirting False Ceiling Internal Paint External Paint Ceiling Fitting
facing
Hospital Building 2nd. Floor Completed 60% 0% 40% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
12 (210 bedded) 3rd. Floor 70% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
4th. Floor 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
5th. Floor 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
6th. Floor 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Terrace Floor / Mumty 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed 95% NA Completed 0% 0% 0% 0% 0% Completed Completed 75% 0% Completed NA 0% 0% 0% 0%


1st. Floor Completed 98% Completed Completed 0% 0% 0% 0% 0% Completed Completed 75% 0% Completed NA 0% 0% 0% 0%
2nd. Floor Completed 98% Completed Completed 0% 0% 0% 0% 0% Completed Completed 75% 0% Completed NA 0% 0% 0% 0%

Sr. Residents 3rd. Floor Completed 98% Completed Completed 0% 0% 0% 0% 0% Completed Completed 0% 0% Completed NA 0% 0% 0% 0%
13 (32 units) 4th. Floor Completed 98% 0% Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0%
5th. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0%
6th. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0%
7th. Floor Completed 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% 0%
Terrace Floor / Mumty 25% 0% 0% 0% 0% 0% 0% 0% 0% 0% NA 0% 0% 0% NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed 0% 0% 0% 0% Completed Completed Completed Completed Completed NA 0% 0% 98% 0%

Jr, Residents 1st. Floor Completed Completed Completed Completed Completed 0% 0% 0% 0% Completed Completed Completed Completed Completed NA 0% 0% 98% 0%
14 (32 units) 2nd. Floor Completed Completed Completed Completed Completed 0% 0% 0% 0% Completed Completed Completed Completed Completed NA 0% 0% 98% 0%
3rd. Floor Completed Completed Completed Completed Completed 0% 0% 0% 0% Completed Completed Completed Completed Completed NA 0% 0% 98% 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed 0% 0% 0% 0% Completed NA Completed Completed Completed NA 0% 0% NA NA

G. Floor Completed Completed NA Completed Completed Completed 95% 0% 0% Completed Completed Completed Completed Completed NA 75% 30% Completed 0%
1st. Floor Completed Completed Completed Completed Completed Completed 95% 0% 0% Completed Completed Completed Completed Completed NA 75% 30% Completed 0%

Nurses Hostel 2nd. Floor Completed Completed Completed Completed Completed Completed 95% 0% 0% Completed Completed Completed Completed Completed NA 75% 30% Completed 0%
15 (48 units) 3rd. Floor Completed Completed Completed Completed Completed Completed 95% 0% 0% Completed Completed Completed Completed Completed NA 75% 30% Completed 0%
4th. Floor Completed Completed Completed Completed Completed Completed 95% 0% 0% Completed Completed Completed Completed Completed NA 75% 30% Completed 0%
5th. Floor Completed Completed Completed Completed Completed 95% 90% 0% 0% Completed Completed Completed Completed Completed NA 75% 30% Completed 0%
Terrace Floor / Mumty Completed Completed Completed Completed Completed 0% 0% 0% 0% Completed NA Completed Completed Completed NA 0% 30% NA NA

Page 13