Gantt Chart BPM
Gantt Chart BPM
Gantt Chart BPM
Project Start Date 8/1/2023 (Tuesday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Project Lead 31 Jul 2023 7 Aug 2023 14 Aug 2023 21 Aug 2023 28 Aug 2023 4 Sep 2023 11 Sep 2023 18 Sep 2023
31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
% WORK
WBS TASK START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE DAYS
1 Vedor Selection & System Installation - -
1.1 Evaluating the System Tue 8/01/23 Tue 8/08/23 8 100% 6
1.2 Selecting the best System Wed 8/09/23 Sun 8/13/23 5 100% 3
1.3 Installing the System Mon 8/14/23 Mon 8/14/23 1 100% 1
1.4 Allign the workflows Tue 8/15/23 Thu 8/17/23 3 100% 3
2 User Training - -
2.1 Conduct Training Session Fri 8/18/23 Tue 8/22/23 5 100% 3
2.2 Educating about the system Wed 8/23/23 Fri 8/25/23 3 100% 3
6 Problem Resolution
6.1 Resolving the issues Sat 9/30/23 Wed 10/04/23 5 100% 3
6.2 Collaboration to solve problem Thu 10/05/23 Sat 10/14/23 10 100% 7
9 Continuous Improvement
9.1 Regular reviews Sat 11/18/23 Wed 11/22/23 5 100% 3
9.2 Using the feedback for Enhancement Thu 11/23/23 Sat 12/02/23 10 95% 7