1. BACKGROUND INFORMATION OF THE ASSET BEING VALUED
During the visit observed that Building was functional running office.
During the visit observed that Building Exteriors and some of Interiors were
damaged.
As per client and physical observation on all the floors including Basement and
Terrace floor.
Estimation of building is subject to the repair of the same class of the material.
We had not sought a full list of information and back-up data like Building acquisition
cost, building construction contract agreement, land survey maps, layout sketch
copy, etc., However, client furnished all the layout approved plans.
For this estimation exercise, the dimensions were adopted as per Building Sanction
represented by Mr. Chetan H S, (herein after called ‘Consultant’) have registered office
situated at Bangalore and owned by Mr. Rajesh Kumar, senior Architect having experience
of more than 25 yrs. in the field of Architecture, Interiors, Landscape, execution of projects
Mr. Chetan H S, CE, MIE, B’ ARCH is a registered Valuer and an practicing Architect, with an
experience of more than 20 years in the field of Designing, Construction, Architecture and
Corporate Interiors, is Member and registered Chartered Engineer in The Institute of Engineering
( India ) incorporated by Royal Charter in 1935, Kolkata, and representing “MINOAN
CONSULTANTS”, Bangalore.
4. BASES OF ESTIMATION
The area subject to building adopted as per the Layout Plans by Architect.
The guideline used for report is based on NBC 2016, (National Building Code of India
2016) by Bureau of Indian Standards. The unit rate adopted as per the Karnataka
schedule of rates for Buildings published Public Work Department, Karnataka and also
by the professional experience.
We assume the photocopies of any/all documents received by the client to be a copy of the
original without any alterations/ modifications and genuine.
In the course of this exercise we have relied upon the hardcopy, softcopy, email,
documentary and verbal information provided by the client without further verification. We
have assumed that the information provided to us is reliable, accurate and complete in all
respects. We reserve our right to alter our conclusions at a later date, if it is found that the
data provided to us by the client was not - reliable, accurate or complete.
No soil analysis or geological or other technical studies were made in conjunction with the
report, nor was any water, oil, gas or other subsurface mineral and use rights or conditions
investigated.
We have relied on data from external sources also to conclude the estimation. These
sources are believed to be reliable and therefore, we assume no liability for the truth or
accuracy of any data, opinions or estimates furnished by others that have been used in this
analysis. Where we have relied on data, opinions or estimates from external sources,
reasonable care has been taken to ensure that such data has been correctly extracted from
those sources and /or reproduced in its proper form and context.
We are independent of the client and have no current or expected interest in assets. The fee
paid for our services in no way influenced the results of our analysis.
7. LAND DETAILS
ITEM No.1. All the piece and parcel of the property bearing sub-division
No.T.S.No.4/11B1D,T.S.No.4/11B1E and T.S.No.4/10B situated at Ward E, Block 1,
Pallapatti Village, Salem Taluk measuring 6320 Sft, ITEM No 2, 4480 Sft & ITEM No3, 3120
Sft, having 3 Survey nos. as mentioned above and Bounded as follows:
West by : Meyannur main road,
East by : House belonging to Angarbhasha and Selvaraj,
North by : Land belonging to P. Komalgovind,
South by : Land belonging to P. Komalgovind
Satellite Image of Subject Property
https://www.google.com/maps/@11.6651103,78.1316501,21z
8. BUILDING STRUCTURE DETAILS
9. CONCLUSION
Based on the physical inspection & observation, and verbal information provided by Client
representative’s estimation of repair of the building is summarized as below:
The above estimation of repair of the building arrived on the basis of Karnataka schedule of
rates for Buildings published Public Work Department, Karnataka by the and professional
experience.
The estimation have been carried out based on physical inspection, observation, and
Building Sanction plan.
CHETAN H S
Bangalore
ESTIMATION CERTIFICATE
Date: Sept 30, 2023
To,
Mr. Shankar
No.27, J V Ganesh Complex, Meyannur main road,
Salem, Tamilnadu: 636005
Dear Sir,
In accordance with our engagement via verbal communication we enclose Stability Report on
the Estimation of Repair of the building Belongs to Mr. G GOVINDA KUMARA RAJA & MRS.
KOMAL GOVIND, Situated at Site No.27, J V Ganesh Complex, Meyannur road, Salem,
Tamilnadu as on Apr 25, 2023
Mr. Shankar (“Client”) has requested Minoan Consultants represented by Mr. Chetan H S
(“We”) to carry out the Stability Report & Estimation of Repair of the building as on April 29,
2023.
Based on the physical inspection & observation, and verbal information provided by Client
representative’s estimation of Repair of the building is summarized as below:
The above estimation of repair of the building arrived on the basis of Karnataka schedule of
rates for Buildings published Public Work Department, Karnataka by the and professional
experience.
The estimation have been carried out based on physical inspection, observation, and Building
Sanction plan.
For Minoan Consultants
Chetan H S
Bangalore
INSPECTION & STABILITY REPORT
(ASSESEMENT OF CIVIL, INTERIORS, ELECTRICAL & AIR CONDITION AS PER
THE NATIONAL BUILDING CODE OF INDIA 2016, BUREAU OF INDIAN STANDARDS )
Procedure: By physically checking all the areas in respect to Interiors, Civil, Electrical, DG set, AC’s so that we can benefit to the
national economy in a number of ways – ensuring provision of safe reliable quality goods; minimizing health hazards to consumers;
promoting exports and imports substitute; control over proliferation of varieties, etc. through standardization, certification and testing.
Also mainly contains administrative regulations, development control rules and general building requirements; fire safety
requirements; stipulations regarding materials, structural design and construction (including safety in construction); building and
plumbing services; landscaping and outdoor display structures; approach to sustainability; and asset and facility management.
1. STRUCTURAL DESIGN:
The Building comes under the Business Building which houses Offices, Banks, and Commercial
Establishments. It is located on Main 80 feet road. Constructed in 2012, the Building is of
Column and Beam Structure, having standard height of 11’5” feet floor to floor level, using
standard materials. The Load, forces and effects have been calculated with soil testing for
foundations etc. All slabs are concrete plain and reinforced. The building consists of Basement
floor + Ground Floor + Three Upper Floors with Two Lifts for access and standard staircase.
There is a Lift Room constructed at the Terrace with proper planning and accessibility. The
External Front Façade is designed with Structural Glazing using 5mm thick glass with Aluminum
Box sections at regular intervals and covering the gaps with silicon sealant. The side walls are
with standard Sliding Aluminum windows with small balcony at regular intervals. Cafeteria is
constructed on terrace floor using Gol volume sheets having slope of for water drain. It is
assumed that all necessary Permissions from local Authority has been taken and by-laws are
followed with no/minimum violations.
Observations & Suggestions: There are Broken Glasses in 1st, 2nd & 3rd Floor. Need to be
replaced Immediately, All the rubber sealant to be replaced periodically in front as well as in
side Facade. There are dampness in the wall in 1st floor, need to change the existing Aluminum
window to UPVC Window. Regular cracks in wall observed in 2nd floor & 3rd floor, simple
sealant with wall putty is needed.
2. INTERIOR DESIGN:
A. Gypsum Partition: All the interiors were erected/ installed in 2012. Existing partition are
gypsum partition of 4inch thick, with aluminum channels, and fixing of gypsum boards on either
sides. The Door are standard Flush door laminated on both sides using door closer and 4inch
Solid Brass Ball-Bearing Door Hinge with privacy glass panel in between.
Suggestions: Crakes developed over the period of 12 years in the jambs on either sides. Need
to use solid wooden partition of 12 inches on either side of door to avoid crakes in partition.
Although there are solid partitions made on many doors with laminate, it is recommended that
the height of the wooden partition and glass opening remains same as to not have uneven
sizes. Refer pics below. This is observed throughout the in all floors. Also use 5-6 inch Solid
Brass Ball-Bearing Door Hinge.
B. False Ceiling: All the Grid ceiling with mineral fiber sheets are cracked, even the grid
channels are bent with gypsum boards cracked in most of the ceilings.
Suggested to go for Open Ceiling without any false ceiling materials in combinations of Open
cell ceiling and Rafter Ceiling. But all the internal wires, cables, has to be re-drawn in particular
way so that the ceiling looks good. Also the existing structure is column and Bean, the design
has to be within the columns.
C. Flooring: Existing vitrified tiles have exposed to lot of wear and tear, some of them have
cracked and broken. Recommend to go for combination of Granite, Marble, Vinyl, Carpet and
Wooden floor.
D. Training Room: All round 3 inch height aluminum skirting is required removing the existing
wooden skirting. Partition need to be used with wooden panels at chair height so that chair
movement does make the wall scratch resistant.
E. Vertical Blinds: Blind in 1st, 2nd & 3rd floor on the rear side is totally broken and not
functioning, need to replace it with Roller blinds.
Existing blinds not working.
F. Carpentry Checks: Visual check of exposed surfaces to detect and correct dents, uneven
surfaces, bubbles and chippings in panels.
Cabinets are tested to tolerate every weather condition and high levels of humidity.
All wooden board edges go through trimming, pasting and rounding of corners to ensure a
flawless finish.
Visual checks also ensure the panel finishes are free from defects, scratches, cracks etc.
We check the panel finishes for color and pattern/grain as per the design intent.
We also check the shutters for opening, grain orientation, profile, finish and shade variation.
This is to ensure that the design intent is as per the customer requirement.
We also test our hardware, right from the advanced connectors to soft-closing hinges, for
durability.
Additionally, visual checks to ensure that glass/mirror surfaces are free from scratches, patches
and corner chipping
Checking Membrane finishes by interior design team to ensure they are free from wrinkles, air
pockets and dust. For this we use our anti-bubble technology
Checks are done to make sure there is no shade variation, color dripping and pinholes
Furniture check for buff marks and paint peel-offs
We also make sure that edge sharpness and uniform edge radius is maintained in all shutters.
3. Air Conditioning, Heating & Mechanical Ventilation:
For this report we have considered Planning, selection, design considerations, installation,
testing and commissioning of air conditioning, heating and mechanical ventilation systems for
buildings. Planning includes equipment room for central AC plant, air handling units and
package units, pipe shafts, supply/return air ducts and cooling tower.
All the below mentioned items were checked:-
Refrigeration for cold stores, Testing, commissioning and performance validation.
Specialized application, Building automation system for HVAC control, monitoring and
verification. Symbols, units, color code and identification of services.
Mechanical ventilation. Installation of HVAC system. Heating. Design of air conditioning.
Planning. Outdoor and indoor design conditions. Refrigerants.
A. Fire Prevention
Classification of buildings based on occupancy, from fire safety point of view • Demarcation of
fire zone • Types of building construction • Openings in fire resistant walls and floors • Electrical
installations • Escape lighting and exit signage • Air conditioning, ventilation and smoke control •
Heating • Glazing • Surface interior finishes • Fire Command Centre (FCC)
B. Lifestyle Safety
General exit requirements
• Occupant load
• Egress components – Exit access – Exit – Exit discharge
• Compartmentation
• Smoke control
• Gas supply
• Hazardous areas, gaseous, oil storage yard, etc.
• Fire Officer • Fire drills and fire orders
C. Fire Protection
Requirements for firefighting installations (refer Table 7) • Maintenance of firefighting installation
and systems.
On inspection of this Office Building premises, the following Fire prevention, firefighting and
evacuation measures recommended and are considered absolutely essential from fire safety
point of view:
Sl. Description Existing observation Recommended
No
01 Accessibility Separate entrance on East side with 9 mtrs Adequate
wide road
02 Number of Entrance Two entrance/exit, One for employers, one Adequate
for visitors
03 Diesel Generator Two nos. of 50KVA & 40 KVA capacity Adequate
04 No of Staircase Two nos. on either side of building Adequate
05 No of Lifts Two nos. on either side of building Adequate
06 Portable Extinguisher Co2 type 6Kgs kept at all areas Adequate
07 First Aid hose reel Not provided recommended
08 Over Head Tank for Not provided recommended
Exclusive Fire Hose
09 Escape Route Plan Provided at each floor level Adequate
10 Safety Measures Board Provided in all electrical rooms & Main room Adequate
11 No Smoking Board Provided Adequate
12 Fire Siren Not Provided Recommended
13 Smoke Detectors Provided in Server, Electrical & Conference Adequate
14 Firefighting Training Trained staff Adequate
1. Explosives and flammable materials should not be kept in store room, UPS room,
Electrical Panel room, near electrical panel premises.
2. Accumulation of combustible waste in and around premises be avoided.
3. The exit ways shall always be kept clear without any obstruction.
4. Liquefied petroleum Gas should not be kept in store.
5. The doors shall not be locked / latched during working hours.
6. As per Honorable Supreme Court Order, the staff have to be trained to handle safety
equipment, initiate emergency evacuation in the event of Fire. Fire safety drills had to be
conducted periodically with Fire Service Department.
The Stability report / Valuation of the above property is arrived basing on Land and Building
Method. The land value is arrived basing on prevailing market rate, Registration rate, recent sale
transactions and other points that will affect the land value. The building value is arrived basing
on specifications of the building, prevailing market rate of different materials and labour charges
and age of the building and depreciation factor.
The information furnished above is true and correct to the best of my Knowledge
I have no direct or indirect interest in the property valued
Authorized Signatory
Chetan H S
Chartered Engineer
CE, MIE, B' Arch
Bangalore