ANJIKHAD PROJECT

2021 2022 2023 2024


Item Description Total

M10

M11

M12

M13

M14

M15

M16

M17

M18

M19

M20

M21

M22

M23

M24

M25

M26

M27
M1

M2

M3

M4

M5

M6

M7

M8

M9
Aug-22

Aug-23
Nov-21

May-22

Nov-22

May-23

Nov-23
Dec-21

Jun-22

Sep-22

Dec-22

Jun-23

Sep-23

Dec-23
Feb-22

Mar-22

Apr-22

Feb-23

Mar-23

Apr-23

Feb-24

Mar-24
Oct-21

Jan-22

Oct-22

Jan-23

Oct-23

Jan-24
Jul-22

Jul-23
Span Construction
Segments ID Saty No Start Date End Date Item Description
LHS/RHS Phases

Stay Strand Supply 240 240 240

Stay Materials Supply 2nd Lot 3rd Lot 4th Lot

Stay Installation 0 0 0 8 4 12 8 8 8 0 4 8 12 8 8 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 96

Stay Cable Fine Tuning 24 24 24 24 96

C1 L1 1 7th 24-Jan-22 26-Jan-22 Stay Installation - C1+L1 (LHS & RHS) 4Nos 1

C2 L2 2 7th 27-Jan-22 29-Jan-22 Stay Installation - C2+L2 (LHS & RHS) 4Nos 2

Seg-25 Seg-25 25 - 31-Jan-22 14-Feb-22 -

C3 L3 3 8th 15-Feb-22 17-Feb-22 Stay Installation - C3+L3 (LHS & RHS) 4Nos 3

Seg-24 Seg-24 24 - 18-Feb-22 3-Mar-22 -

C4 L4 4 8th 4-Mar-22 7-Mar-22 Stay Installation - C4+L4 (LHS & RHS) 4Nos 4

Seg-23 Seg-23 23 - 8-Mar-22 15-Mar-22 -

C5 L5 5 8th 16-Mar-22 18-Mar-22 Stay Installation - C5+L5 (LHS & RHS) 4Nos 5

Seg-22 Seg-22 22 - 19-Mar-22 26-Mar-22 -

C6 L6 6 8th 28-Mar-22 30-Mar-22 Stay Installation - C6+L6 (LHS & RHS) 4Nos 6

Seg-21 Seg-21 21 - 31-Mar-22 13-Apr-22 -

C7 L7 7 8th 14-Apr-22 16-Apr-22 Stay Installation - C7+L7 (LHS & RHS) 4Nos 7

Seg-20 Seg-20 20 - 18-Apr-22 25-Apr-22 -

C8 L8 8 8th 26-Apr-22 28-Apr-22 Stay Installation - C8+L8 (LHS & RHS) 4Nos 8

Seg-19 Seg-19 19 - 29-Apr-22 6-May-22 -

C9 L9 9 8th 7-May-22 10-May-22 Stay Installation - C9+L9 (LHS & RHS) 4Nos 9

Seg-18 Seg-18 18 - 11-May-22 24-May-22 -

C10 L10 10 8th 25-May-22 27-May-22 Stay Installation - C10+L10 (LHS & RHS) 4Nos 10

Seg-17 Seg-17 17 - 28-May-22 3-Jun-22 -

C11 L11 11 8th 4-Jun-22 7-Jun-22 Stay Installation - C11+L11 (LHS & RHS) 4Nos 11

Seg-16 Seg-16 16 - 8-Jun-22 14-Jun-22 -

C12 L12 12 8th 15-Jun-22 17-Jun-22 Stay Installation - C12+L12 (LHS & RHS) 4Nos 12

N2 N2 - 9th 18-Jun-22 29-Jul-22 -

C3-12 L3-12 - 10th 30-Jul-22 5-Aug-22 2nd Stage Stressing -

Seg-15 Seg-15 15 - 6-Aug-22 19-Aug-22 -

C13 L13 13 11th 20-Aug-22 24-Aug-22 Stay Installation - C13+L13 (LHS & RHS) 4Nos 13

Seg-14 Seg-14 14 - 25-Aug-22 31-Aug-22 -

C14 L14 14 11th 1-Sep-22 5-Sep-22 Stay Installation - C14+L14 (LHS & RHS) 4Nos 14

Seg-13 Seg-13 13 - 6-Sep-22 12-Sep-22 -

C15 L15 15 11th 13-Sep-22 16-Sep-22 Stay Installation - C15+L15 (LHS & RHS) 4Nos 15

Seg-12 Seg-12 12 - 17-Sep-22 30-Sep-22 -

C16 L16 16 11th 1-Oct-22 5-Oct-22 Stay Installation - C16+L16 (LHS & RHS) 4Nos 16
Seg-11 Seg-11 11 - 6-Oct-22 12-Oct-22 -
C17 L17 17 11th 13-Oct-22 17-Oct-22 Stay Installation - C17+L17 (LHS & RHS) 4Nos 17
Seg-10 Seg-10 10 - 18-Oct-22 24-Oct-22 -
C18 L18 18 11th 25-Oct-22 28-Oct-22 Stay Installation - C18+L18 (LHS & RHS) 4Nos 18
Seg-9 Seg-9 9 - 29-Oct-22 11-Nov-22 -
C19 L19 19 11th 12-Nov-22 16-Nov-22 Stay Installation - C19+L19 (LHS & RHS) 4Nos 19
Seg-8 Seg-8 8 - 17-Nov-22 24-Nov-22 -
C20 L20 20 11th 25-Nov-22 29-Nov-22 Stay Installation - C20+L20 (LHS & RHS) 4Nos 20
Seg-7 Seg-7 7 - 30-Nov-22 7-Dec-22 -
C21 L21 21 11th 8-Dec-22 12-Dec-22 Stay Installation - C21+L21 (LHS & RHS) 4Nos 21
Seg-6 Seg-6 6 - 13-Dec-22 26-Dec-22 -
C22 L22 22 11th 27-Dec-22 30-Dec-22 Stay Installation - C22+22 (LHS & RHS) 4Nos 22
Seg-5 Seg-5 5 - 31-Dec-22 6-Jan-23 -
C23 L23 23 11th 7-Jan-23 11-Jan-23 Stay Installation - C23+L23 (LHS & RHS) 4Nos 23
Seg-4 Seg-4 4 - 12-Jan-23 18-Jan-23 -
C24 L24 24 11th 19-Jan-23 23-Jan-23 Stay Installation - C24+L24 (LHS & RHS) 4Nos 24
Seg-3 Seg-3 3 - 24-Jan-23 1-Feb-23 -
Seg-2 Seg-2 2 - 2-Feb-23 10-Feb-23 -
Seg-1 Seg-1 1 - 11-Feb-23 20-Feb-23

B-F B-F 13th 21-Feb-23 21-Mar-23 Ballast filling 0


C1-24 L1-24 13th 22-Mar-23 30-Mar-23 3rd Stage Stressing 0
N3 N3 14th 31-Mar-23 11-May-23 N3-120 Meters Deck Casting 0
C1-24 L1-24 15th 12-May-23 18-May-23 Stay Lift Off Test 0
C-B C-B 15th 19-May-23 17-Jun-23 Crash barrier casting 0

T-1 T-96 15th 19-Jun-23 18-Jul-23 Track Laying 0

CW-1 CW-96 15th 19-Jul-23 16-Sep-23 Other Civil Work 0

FT-1 FT-96 96 15th 18-Sep-23 1-Nov-23 Stay Lift Off & Fine Tuning 96
SG-1 SG-96 96 15th 2-Nov-23 25-Dec-23 Stay Greasing 96
D-1 D-48 48 15th 26-Dec-23 21-Jan-24 Damper Fixing 48
D-49 D-96 48 16th 22-Jan-24 16-Feb-24 Damper Fixing 48

HCC Activity

VSL Activity

Total Stay Installation - 96 No's


Total Segment erected/mth - - - 8 4 12 8 8 8 - 4 8 12 8 8 8 - - - - - - - - - - - - - - 96

Cum. Segments erected/mth - - - 8 12 24 32 40 48 48 52 60 72 80 88 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96