Question 1

Correct

Mark 1.00 out of 1.00

Arrange the cost of the following components from highest to lowest for a distributed grid-connected solar PV system, with 1 being
the highest and 4 being the lowest

Grid-connected Inverters 2 

PV Modules 1 

Transportation and Insurance 4 

Mounting structure 3 

Your answer is correct.


The correct answer is: Grid-connected Inverters → 2, PV Modules → 1, Transportation and Insurance → 4, Mounting structure → 3

Question 2

Correct

Mark 1.00 out of 1.00

Interest during construction (IDC) shall be calculated based on

Project construction period


Schedule of disbursement of loan
Debt and equity ratio
None of the above

Your answer is correct.

The correct answers are: Project construction period, Schedule of disbursement of loan

https://isatraining.gses.in/mod/quiz/review.php?attempt=5304&cmid=120 1/3
12/5/22, 11:00 Attempt Quiz for Session 5: Attempt review

Question 3

Correct

Mark 1.00 out of 1.00

The viability gap funding (VGF) is a quantum of financial support provided by the government or donor agency to project developer
in the form of

Short term loan


Capital Grant
Working capital
Interest free loan

Your answer is correct.

The correct answer is: Capital Grant

Question 4

Correct

Mark 1.00 out of 1.00

If the Salvage value of a solar asset is considered as 10% what will be the maximum depreciation allowed for taxation purpose

It will depend upon the method of calculation of depreciation


It depends upon the asset’s performance
100%
90%

Your answer is correct.


The correct answer is: 90%

https://isatraining.gses.in/mod/quiz/review.php?attempt=5304&cmid=120 2/3
12/5/22, 11:00 Attempt Quiz for Session 5: Attempt review

Question 5

Correct

Mark 1.00 out of 1.00

Arrange the following development phases for a grid-connected solar PV system, from starting phase to the end phase.

Operation and Maintenance phase 4 

End-of-the-life project management 5 

Engineering procurement and construction phase 3 

Development phase 2 

Preparation phase 1 

Your answer is correct.

The correct answer is:


Operation and Maintenance phase → 4,
End-of-the-life project management → 5,

Engineering procurement and construction phase → 3,


Development phase → 2,
Preparation phase → 1