1ZSC029349D0080 EN, 2022-05-25

Replacing contact pin on test tap


Replacement instruction
The information contained in this document may be subject to change without prior warning and should not be considered
as binding on Hitachi Energy's behalf. Hitachi Energy accepts no liability for any errors that may appear in this document.
Hitachi Energy is not liable for any damage resulting from the incorrect interpretation of this document. This document, or
parts thereof, may not be reproduced or copied without Hitachi Energy's consent. It may not be distributed to others or used
by unauthorized parties. Any breaches to the above will be penalized with the support of applicable laws.
Contents
1 Safety 5
1.1 Levels of safety risks ................................................................................................................................................................... 5
1.2 Hazardous working situations ..................................................................................................................................................... 6
1.3 Safety precautions....................................................................................................................................................................... 6

2 Instruction 7
2.1 Replacing contact pin on test tap ................................................................................................................................................ 7
2.2 Verifying the replacement ............................................................................................................................................................ 10

Replacement instruction 3
1ZSC029349D0080 EN, 2022-05-25
4 Replacement instruction
1ZSC029349D0080 EN, 2022-05-25
1 Safety

1.1 Levels of safety risks


Throughout the manual, various types of safety risks are indicated. The most serious level on this scale
provides a warning about serious personal injury or possible death, or major damage to a product, if the
instructions are not observed.

Symbols and their meanings

The following describes the symbols that appear in the manual, along with their meaning.

DANGER!
The yellow, filled warning triangle warns that an accident will occur if the instructions are not
complied with and that it will result in serious personal injury or death and/or major damage to the
product.
It is used, for example, to warn of such dangers as: contact with high voltage, explosion or fire
risk, risk for toxic gases, risk of crushing, impacts, falls from high places, etc.

CAUTION!
The round warning symbol warns that an accident could occur if the instructions are not observed,
and that this could result in personal injury and/or damage to the product.
It is also used to warn of risks that entail burns, eye or skin injuries, impaired hearing, crushing or
slipping injuries, tripping, impacts, falls from high places, etc.
In addition, it is used to warn of functional requirements when assembling or removing equipment
where there is a risk of damage to the product or downtime.

NOTE!
The comment symbol identifies important information and conditions. Also used to indicate any
danger that could lead to property damage.

Torque
The torque symbol indicates tightening torque.

Replacement instruction 5
1ZSC029349D0080 EN, 2022-05-25
1.2 Hazardous working situations

Hazard Action

Working close to high voltage. Disconnect all plant power. Ground all objects at the workplace.
If work must be done close to live plant components, make sure that
the safety distance is in compliance with the applicable safety
regulations.
Working on ladders and platforms. Work must be done in accordance with the applicable safety
regulations.
Do not use ladders or platforms in poor weather conditions.
Working with heavy objects. Do not walk under lifted objects.
Make sure that heavy objects are stable before starting work.

1.3 Safety precautions

Precaution Action

Transformer oil Collect used transformer oil in drums.


Transformer oil is dangerous. Fumes from hot oil can cause irritation
to the respiratory organs and the eyes. Long and repeated contact
with transformer oil can cause damage to your skin.
SF6 gas SF6 gas must be recycled and never released into the atmosphere.

Waste and cleaning up Clean up liquid waste with an adsorbent. Treat waste as hazardous
to the environment.
Fire Extinguish fires with powder, foam or carbon dioxide.

6 Replacement instruction
1ZSC029349D0080 EN, 2022-05-25
2 Instruction

2.1 Replacing contact pin on test tap

General

Replacing the contact pin can be done on a bushing directly from the transport box, or on a bushing already
installed.
Please refer to the Installation and Maintenance guide 1ZSC00563-AAD for information on how to handle
the bushing e.g. lift of the bushing, disposal and environmental information.
G007958

Safety

DANGER!
Risk of electrocution!
Make sure that the transformer is de-energized and out of service before any work is performed on
the bushing .

DANGER!
Follow local regulations at all times!

NOTE!
It is recommended that the work is performed by qualified personnel.

Replacement instruction 7
1ZSC029349D0080 EN, 2022-05-25
Required equipment

Tool Note

Caliper -
Instrument to measure Capacitance and TanD -
Torque wrench 5 Nm
Socket 14mm 1/4" square drive
Thread-locking fluid, Grade 42 High strength thread locking fluid, permanent locking
Replacement kit Including 2 size contact pin and spare sealing for test
tap cover
Special socket for tightening the pin -
Lifting device If the bushing is in the transport box
Skylift If the bushing is installed on the transformer
High pressure air -

NOTE!
If not specifically stated, none of the tools are provided by Hitachi Energy.

Procedure

1. Remove the test tap cover (1).


G007959

2. Place some cloth inside the test tap to prevent


small chips or flakes from getting inside the test
tap.
G007960

8 Replacement instruction
1ZSC029349D0080 EN, 2022-05-25
3. Unthread the contact pin counter clockwise using
the special socket (3).

NOTE!
The contact pin is glued to test tap
bushing.

NOTE!
Do not use the removed contact pin as
replacement.

NOTE!

G007961
Make sure the special socket is
mounted the correct way.

4. Use high pressure air to clear the threads from old excessive locking liquide.

5. Measure the distance B.

NOTE!
If the distance is approximately 8.5 mm
use the shorter pin and if the distance
is 10.5 mm use the longer contact pin
for the replacement.
G007963

6. Apply a small amount of Loctite on the thread (2)


on the new contact pin.
G007962

2 Apply Loctite

Replacement instruction 9
1ZSC029349D0080 EN, 2022-05-25
7. Thread the new contact pin using the special
socket (3) with 5 Nm.

NOTE!
Make sure the special socket is
mounted the correct way.

G007964
8. Measure the distance A.

NOTE!
The measure should be 28,8 +/- 0,2
mm, otherwise contact Hitachi for
further evaluation.

G007968

9. Refit the test tap cover (1) with new sealing.


G007959

End of instruction

10 Replacement instruction
1ZSC029349D0080 EN, 2022-05-25
2.2 Verifying the replacement
The verification of the test tap replacement is done with measurement of capacitance and dissipation factor
over C1 and/or C2 please refer to section Measurement of capacitance and dissipation factor in the
installation guide 1zsc000563-AAD.
For bushings not installed on a transformer the measurements can be verified against nameplate, for bushings
already installed on a transformer the measurements should be compared to values recorded during
commissioning.
This can be done directly during replacement or during transformer test.

NOTE!
The transport container must be removed before measuringthe capitance and dissipation factor
(tan 8)

NOTE!
The bushing needs to be lifted out of the transport box. See installation and maintenance guide
1ZSC00563-AAD.

Replacement instruction 11
1ZSC029349D0080 EN, 2022-05-25
Hitachi Energy Sweden AB
Components
SE-771 80 Ludvika
Sweden

Customer Connect Center


1ZSC029349D0080 EN, 2022-05-25

www.hitachienergy.com/contact-us
E-mail: contact-us@hitachienergy.com

www.hitachienergy.com/offering/product-and-system/transformer-insulation-and-components

ABB is a registered trademark of ABB Asea Brown Boveri Ltd.


Manufactured by/for a Hitachi Energy company.

©Hitachi Energy 2022. All rights reserved.


Specifications subject to change without notice.

You might also like