Al Tasnim Handrails Fabrication & Painting Progress

Start Date: 3/28/2023 Status on : 4-Apr-23


JO No 2277 SCOPE FABRICATION Blasting & Painting Activity %
Completion Dispatch Remarks
No of No of Running Weight Fit Up Welidng & Visual Painting
S.No Priority ATM WO No
Dwgs Handrails Meter (MT) 30% 40% 30% 100%

1 P1 DWO-878 9 10 53.065 0.855 10.0 10.0 0.0 70% 0.00 Paint Delivery balance

2 P2 DWO-879 24 42 210.084 3.373 42.0 42.0 0.0 70% 0.00 Paint Delivery balance

3 P3 DWO-880 7 11 61.105 0.977 11.0 0.0 0.0 30% 0.00


Balance materils required
4 P4 DWO-881 43 52 263.192 4.252 25.0 0.0 0.0 0.00
Plate10mm - 6.77 Sqm

Grand Total 83 115 587.446 9.457


Inspection Stages :
1 After Welding - RFI
2 After Painting - RFI (Final Inspection)
NDT : Not in BG Scope

Snap of Fitup with 100% Safety Snap of Welding with 100% Safety Snap of QC Inspection with 100% Safety

Snap of Painting with 100% Safety Other Snap with 100% Safety