Construction Project Classic Schedule Layout 16-Jan-24 20:19

Activity ID Activity Name Original BL1 Start BL1 Finish 2024


Duration
Jan Feb Mar Apr May Jun Jul Aug Sep
Total 446d 15-Jan-24 14-Aug-25

Construction Project 446d 15-Jan-24 14-Aug-25

Project Milestones 446d 15-Jan-24 14-Aug-25


A1440 Project Commencement Date 0d 15-Jan-24 Project Commencement Date, 15-Jan-24
A1450 Project Completion Date 0d 14-Aug-25
Engineering/Design Phase 125d 15-Jan-24 24-Jun-24 24-Jun-24, Engineering/Design Phase
Basic Design 74d 15-Jan-24 19-Apr-24 19-Apr-24, Basic Design
Road Works 74d 15-Jan-24 19-Apr-24 19-Apr-24, Road Works
A1000 Meeting 3d 15-Jan-24 18-Jan-24 Meeting
A1010 Requirement Plan 5d 18-Jan-24 24-Jan-24 Requirement Plan
A1020 Conduct Survey 15d 24-Jan-24 13-Feb-24 Conduct Survey
A1030 Prepration of basic Design 25d 13-Feb-24 16-Mar-24 Prepration of basic Design
A1040 Submission 4d 16-Mar-24 21-Mar-24 Submission
A1050 Review 21d 21-Mar-24 18-Apr-24 Review
A1060 Approval 1d 18-Apr-24 19-Apr-24 Approval
Storm Water Drainage System 74d 15-Jan-24 19-Apr-24 19-Apr-24, Storm Water Drain age System
A1070 Meeting 3d 15-Jan-24 18-Jan-24 Meeting
A1080 Requirement Plan 5d 18-Jan-24 24-Jan-24 Requirement Plan
A1090 Conduct Survey 15d 24-Jan-24 13-Feb-24 Conduct Survey
A1100 Prepration of basic Design 25d 13-Feb-24 16-Mar-24 Prepration of basic Design
A1110 Submission 4d 16-Mar-24 21-Mar-24 Submission
A1120 Review 21d 21-Mar-24 18-Apr-24 Review
A1130 Approval 1d 18-Apr-24 19-Apr-24 Approval
WSN 74d 15-Jan-24 19-Apr-24 19-Apr-24, WSN
A1140 Meeting 3d 15-Jan-24 18-Jan-24 Meeting
A1150 Requirement Plan 5d 18-Jan-24 24-Jan-24 Requirement Plan
A1160 Conduct Survey 15d 24-Jan-24 13-Feb-24 Conduct Survey
A1170 Prepration of basic Design 25d 13-Feb-24 16-Mar-24 Prepration of basic Design
A1180 Submission 4d 16-Mar-24 21-Mar-24 Submission
A1190 Review 21d 21-Mar-24 18-Apr-24 Review
A1200 Approval 1d 18-Apr-24 19-Apr-24 Approval
Water Supply Connection Chamber 74d 15-Jan-24 19-Apr-24 19-Apr-24, Water Supply Connection Chamber
A1210 Meeting 3d 15-Jan-24 18-Jan-24 Meeting
A1220 Requirement Plan 5d 18-Jan-24 24-Jan-24 Requirement Plan
A1230 Conduct Survey 15d 24-Jan-24 13-Feb-24 Conduct Survey
A1240 Prepration of basic Design 25d 13-Feb-24 16-Mar-24 Prepration of basic Design
A1250 Submission 4d 16-Mar-24 21-Mar-24 Submission
A1260 Review 21d 21-Mar-24 18-Apr-24 Review
A1270 Approval 1d 18-Apr-24 19-Apr-24 Approval
Detail Design 51d 19-Apr-24 24-Jun-24 24-Jun-24, Detail Design
Road Works 51d 19-Apr-24 24-Jun-24 24-Jun-24, Road Works
A1280 Meeting 3d 19-Apr-24 23-Apr-24 Meeting
A1290 Prepration of Detail Design 28d 23-Apr-24 29-May-24 Prepration of Detail Design
A1300 Submission 4d 29-May-24 04-Jun-24 Submission
A1310 Review & Approval 16d 04-Jun-24 24-Jun-24 Review & Approval
Storm Water Drainage System 51d 19-Apr-24 24-Jun-24 24-Jun-24, Storm Water Drainage System
A1320 Meeting 3d 19-Apr-24 23-Apr-24 Meeting
A1330 Prepration of Detail Design 28d 23-Apr-24 29-May-24 Prepration of Detail Design
A1340 Submission 4d 29-May-24 04-Jun-24 Submission
A1350 Review & Approval 16d 04-Jun-24 24-Jun-24 Review & Approval
WSN 51d 19-Apr-24 24-Jun-24 24-Jun-24, WSN

Actual Level of Effort Remaining Work Milestone Page 1 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
Construction Project Classic Schedule Layout 16-Jan-24 20:19
Activity ID Activity Name Original BL1 Start BL1 Finish 2024
Duration
Jan Feb Mar Apr May Jun Jul Aug Sep
A1360 Meeting 3d 19-Apr-24 23-Apr-24 Meeting
A1370 Prepration of Detail Design 28d 23-Apr-24 29-May-24 Prepration of Detail Design
A1380 Submission 4d 29-May-24 04-Jun-24 Submission
A1390 Review & Approval 16d 04-Jun-24 24-Jun-24 Review & Approval
Water Supply Connection Chamber 51d 19-Apr-24 24-Jun-24 24-Jun-24, Water Supply Connection Chamber
A1400 Meeting 3d 19-Apr-24 23-Apr-24 Meeting
A1410 Prepration of Detail Design 28d 23-Apr-24 29-May-24 Prepration of Detail Design
A1420 Submission 4d 29-May-24 04-Jun-24 Submission
A1430 Review & Approval 16d 04-Jun-24 24-Jun-24 Review & Approval
Procurement Phase 81d 24-Jun-24 07-Oct-24
Bulk Items 28d 24-Jun-24 30-Jul-24 30-Jul-24, Bulk Items
Crush 24d 24-Jun-24 25-Jul-24 25-Jul-24, Crush
A1460 RFQ 4d 24-Jun-24 29-Jun-24 RFQ
A1470 Recieve Bids 4d 29-Jun-24 04-Jul-24 Recieve Bids
A1480 TBT 4d 04-Jul-24 10-Jul-24 TBT
A1490 Inspection & Commitment 4d 10-Jul-24 15-Jul-24 Inspection & Commitment
A1500 PO Issue 4d 15-Jul-24 20-Jul-24 PO Issue
A1510 Material arrival at site 4d 20-Jul-24 25-Jul-24 Material arrival at site
Steel 27d 24-Jun-24 29-Jul-24 29-Jul-24, Steel
A2020 RFQ 1d 24-Jun-24 25-Jun-24 RFQ
A2030 Recieve Bids 7d 26-Jun-24 04-Jul-24 Recieve Bids
A2040 TBT 3d 04-Jul-24 09-Jul-24 TBT
A2050 Inspection & Commitment 2d 09-Jul-24 11-Jul-24 Inspection & Commitment
A2060 PO Issue 1d 11-Jul-24 12-Jul-24 PO Issue
A2070 Material arrival at site 13d 12-Jul-24 29-Jul-24 Material arrival at site
Cement 27d 24-Jun-24 29-Jul-24 29-Jul-24, Cement
A2080 RFQ 1d 24-Jun-24 25-Jun-24 RFQ
A2090 Recieve Bids 7d 26-Jun-24 04-Jul-24 Recieve Bids
A2100 TBT 3d 04-Jul-24 09-Jul-24 TBT
A2110 Inspection & Commitment 2d 09-Jul-24 11-Jul-24 Inspection & Commitment
A2120 PO Issue 1d 11-Jul-24 12-Jul-24 PO Issue
A2130 Material arrival at site 13d 12-Jul-24 29-Jul-24 Material arrival at site
Tiles 27d 26-Jun-24 30-Jul-24 30-Jul-24, Tiles
A2140 RFQ 1d 26-Jun-24 27-Jun-24 RFQ
A2150 Recieve Bids 7d 27-Jun-24 05-Jul-24 Recieve Bids
A2160 TBT 3d 05-Jul-24 10-Jul-24 TBT
A2170 Inspection & Commitment 2d 10-Jul-24 12-Jul-24 Inspection & Commitment
A2180 PO Issue 1d 12-Jul-24 13-Jul-24 PO Issue
A2190 Material arrival at site 13d 13-Jul-24 30-Jul-24 Material arrival at site
Long Lead Items 81d 24-Jun-24 07-Oct-24
Electric Panels 81d 24-Jun-24 07-Oct-24
A1740 RFQ 1d 24-Jun-24 25-Jun-24 RFQ
A1750 Recieve Bids 12d 26-Jun-24 11-Jul-24 Recieve Bids
A1760 TBT 3d 11-Jul-24 15-Jul-24 TBT
A1770 Inspection & Commitment 4d 15-Jul-24 20-Jul-24 Inspection & Commitment
A1780 PO Issue 1d 20-Jul-24 22-Jul-24 PO Issue
A1890 Arrival at Site 60d 22-Jul-24 07-Oct-24
ITS 81d 24-Jun-24 07-Oct-24
A1900 RFQ 1d 24-Jun-24 25-Jun-24 RFQ
A1910 Recieve Bids 12d 26-Jun-24 11-Jul-24 Recieve Bids
A1920 TBT 3d 11-Jul-24 15-Jul-24 TBT
A1930 Inspection & Commitment 4d 15-Jul-24 20-Jul-24 Inspection & Commitment

Actual Level of Effort Remaining Work Milestone Page 2 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
Construction Project Classic Schedule Layout 16-Jan-24 20:19
Activity ID Activity Name Original BL1 Start BL1 Finish 2024
Duration
Jan Feb Mar Apr May Jun Jul Aug Sep
A1940 PO Issue 1d 20-Jul-24 22-Jul-24 PO Issue
A1950 Arrival at Site 60d 22-Jul-24 07-Oct-24
Asphalt 81d 24-Jun-24 07-Oct-24
A1960 RFQ 1d 24-Jun-24 25-Jun-24 RFQ
A1970 Recieve Bids 12d 26-Jun-24 11-Jul-24 Recieve Bids
A1980 TBT 3d 11-Jul-24 15-Jul-24 TBT
A1990 Inspection & Commitment 4d 15-Jul-24 20-Jul-24 Inspection & Commitment
A2000 PO Issue 1d 20-Jul-24 22-Jul-24 PO Issue
A2010 Arrival at Site 60d 22-Jul-24 07-Oct-24
Construction Phase 321d 24-Jun-24 14-Aug-25
Road Works 321d 24-Jun-24 14-Aug-25
Earth Works 164d 24-Jun-24 23-Jan-25
A2200 Natural Ground Compaction 29d 24-Jun-24 01-Aug-24 Natural Ground Compaction
A2210 Excavation (Open Area) 10d 01-Aug-24 14-Aug-24 Excavation (Open Area)
A2220 Excavation (Pits) 43d 14-Aug-24 08-Oct-24
A2230 Embankments 36d 09-Oct-24 23-Nov-24
A2240 Sub Grade 46d 25-Nov-24 23-Jan-25
Base & Course Works 41d 23-Jan-25 17-Mar-25
A2250 Sub Base 19d 23-Jan-25 17-Feb-25
A2260 Aggregate Base work 22d 17-Feb-25 17-Mar-25
Asphalt Works 52d 17-Mar-25 23-May-25
A2270 Prime Coat 7d 17-Mar-25 26-Mar-25
A2280 Asphalted Concrete Base Coat 26d 26-Mar-25 29-Apr-25
A2290 Tack Coat 8d 29-Apr-25 09-May-25
A2300 ACWC 7d 09-May-25 17-May-25
A2310 TST 4d 19-May-25 23-May-25
Road Saftey & Furniture Works 20d 23-May-25 18-Jun-25
A2320 Traffic Sign Post Installment 4d 23-May-25 28-May-25
A2330 Traffic Signal Installment 4d 28-May-25 03-Jun-25
A2340 Lane Marking 4d 03-Jun-25 07-Jun-25
A2350 Pavement Stud - Single 4d 07-Jun-25 13-Jun-25
A2360 Pavement Stud - Double 4d 13-Jun-25 18-Jun-25
Pipe Sleeve 44d 18-Jun-25 14-Aug-25
A2370 Excavation 4d 18-Jun-25 24-Jun-25
A2380 Concrete 4d 24-Jun-25 28-Jun-25
A2390 Back fill 4d 28-Jun-25 03-Jul-25
A2400 Precast Concrete 4d 04-Jul-25 09-Jul-25
A2410 Precast Kerb Block-14"x12"x6" 4d 09-Jul-25 14-Jul-25
A2420 Precast Kerb Block-8"x12"x6" 4d 14-Jul-25 19-Jul-25
A2430 Pipe lay down 200mm 4d 19-Jul-25 24-Jul-25
A2440 Pipe lay down 250mm 4d 24-Jul-25 30-Jul-25
A2450 Surface Prepration & Paint 4d 30-Jul-25 04-Aug-25
A2460 Sand Cushion 2" Layer 4d 04-Aug-25 09-Aug-25
A2470 Chenab Sand laying and Compaction 4d 09-Aug-25 14-Aug-25
Storm Water Drainage system 0d
WSN 0d
Water Supply Connection Chamber 0d
Water Supply RCC Valves Chamber 0d
Sewerage Collection 0d
Electrification and Street Lightening 0d

Actual Level of Effort Remaining Work Milestone Page 3 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation