Professional Documents
Culture Documents
Method Statement Form - AHU
Method Statement Form - AHU
Revision History
Rev. Date Revision Details Prepared Checked Reviewed Approved
Title : Page 2 of 16
Document No. : Effective Date : Revision :
1. PURPOSE
The purpose of this method statement is to have a systematized work procedures
that complies with the General Standards and Rules and Regulations being
implemented on project site to ensure the Quality of work that will be made and
Safeness of all persons that will be involved in doing such activities.
This method statement is prepared for the provision of Air Handling Unit
of………………….Project to be undertaken by Italthai Engineering Co. Ltd.
2. SCOPE OF WORK
This method statement defies the delivery / handling, installation and Testing of Air
Handling Unit and Fan Coil Unit for………………..Project. This ensures all the
materials that will be used are in compliance with the contract specifications and
requirements approved by the Consultant.
3. MATERIALS
Air handling unit shall conform to standard stated in the specification and material
submission for approved
4. INSTALLATION PROCEDURES
Workmanship shall conform to standard states in specification. Method of work is as
follow installation air handling unit of air conditioning work.
4.1 Lifting and rigging recommendation.
- Recommended Rigging Method 1
- Hang or mount air handling unit with rubber pads in its position. Fix bolts,
must and washers.
- Installation chiller water pipe and drainage pipe.
- Adjust air handling unit to meet drain water flow to direction of
condensate drain pipe.
- Chiller water pipes shall be protected insulation from direct UV exposure
4.4 Installation work.
- Protect the air handling unit from the damaged by the above working
with plastic sheet.
4.5 Installation work.
4.5.1 Duct Connections
All air ducts should be installed In accordance with the standards of Air
Conditioning and Ventilating System as per approved shop drawing and
discharge air duct connections to the unit should be made with a flexible
duct material as per material approved. Typically, about three inches is
needed for this connection to rigid ductwork. Avoid sharp turns and use
splitters or turning vanes when elbows are necessary. Make turns in the
same direction of rotation as the fan. Discharge Ductwork should run in a
straight line, unchanged in size or direction. Refer to Figure 5 and 6 for typical
duct work installation.
Figure 5 : Typical Discharge Ductwork Recommendations
Title : Page 7 of 16
Document No. : Effective Date : Revision :
Trap the drain line as shown in figure 7 for section with negative static
pressure. When more than one section has a drain pan, trap each section
individually. Do not connect all drains to a common drain line with only
one trap. Use the following drain connection recommendation.
4.6 Inspection and testing.
- The site engineer shall verify that all conduits equipment and
material are conformed to the specification before work
commences
- The site engineer or supervisor shall verify the construction drawing is
good for construction.
- The site engineer shall ensure that type of equipment to be
installed is in accordance with the specification.
- In function inspected of equipment visual check by site engineer; QC
engineer and MTL representative.
5. SAFETY
One of the main aspects of this procedure shall comply with the Safety, Health, and
Environment (SHE). This is to control the occurrence of injuries as well as damage
to equipment and properties during the entire construction period. To ensure a safe
working environment, the safety measures will be implements as follows.
Preparation of Job Safe Analysis (JSA) and Work Method Statement to
apply for the work permit from SEA-Consult Engineering Co., Ltd. for
approval.
An approved work permit, JSA, and Work Method Statement shall be
displayed in the working area.
Before commencing any scope of work, the supervisor will carry out the
JSA at the job site with all personnel working on the scope of work shall
be present.
Carry out Toolbox meetings with all personnel working on this
activity shall be present.
Personal Protective Equipment (PPE) must be worn at all-time in the
inclusive working zone or PPE zone.
Provide the signage/barricades and marked tape with a warning
label in the exclusive zone to indicate a boundary of the working
area.
Title : Page 9 of 16
Document No. : Effective Date : Revision :
ATTACHMENT
I. Quality Control Check list and Check Sheet
Title : Page 12 of 16
Document No. : Effective Date : Revision :
Title : Page 13 of 16
Document No. : Effective Date : Revision :
Title : Page 14 of 16
Document No. : Effective Date : Revision :
ATTACHMENT
II. Inspection and Test Plan
Title : Page 15 of 16
Document No. : Effective Date : Revision :
Title : Page 16 of 16
Document No. : Effective Date : Revision :