PROJECT PLANNING - CPM ORIGINAL DATA

Title: critical path Method


Activity Symbol Duration

1-2 A 3.00
1-3 B 4.00
1-4 C 6.00
3-4 D 3.00
2-5 E 9.00
2-6 F 1.00
3-6 G 4.00
4-6 H 5.00
4-7 I 4.00
5-8 J 3.00
6-8 K 6.00
6-9 L 3.00
7-9 M 6.00
8-9 N 9.00
PROJECT PLANNING - CPM SCHEDULE

Title: critical path Method


Activity Symbol Duration Earliest Start Latest Finish Total Float Free Float

1-2 A 3.00 0.00 6.00 3.00 0.00


c 1-3 B 4.00 0.00 4.00 0.00 0.00
1-4 C 6.00 0.00 7.00 1.00 1.00
c 3-4 D 3.00 4.00 7.00 0.00 0.00
2-5 E 9.00 3.00 15.00 3.00 0.00
2-6 F 1.00 3.00 12.00 8.00 8.00
3-6 G 4.00 4.00 12.00 4.00 4.00
c 4-6 H 5.00 7.00 12.00 0.00 0.00
4-7 I 4.00 7.00 21.00 10.00 0.00
5-8 J 3.00 12.00 18.00 3.00 3.00
c 6-8 K 6.00 12.00 18.00 0.00 0.00
6-9 L 3.00 12.00 27.00 12.00 12.00
7-9 M 6.00 11.00 27.00 10.00 10.00
c 8-9 N 9.00 18.00 27.00 0.00 0.00