Professional Documents
Culture Documents
Volume I
Volume I
Volume I
PROJECT MANAGER:
THE TATA POWER COMPANY LIMITED
CORPORATE CENTRE- “A” BLOCK
34, SANT TUKARAM ROAD
CARNAC BUNDER
MUMBAI - 400009
PROJECT:
1050 MW MAITHON RIGHT BANK THERMAL POWER PLANT
VOLUME – I
ITB, GCC & INFORMATION FORMS
NOVEMBER 2007
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED CONTENTS:
TITLE MAITHON POWER LIMITED
COAL HANDLING SHEET 1 OF 1
1050 MW MAITHON RIGHT BANK TPP
SYSTEMS
CONTENTS
VOLUME - I
A1 R0 INTRODUCTION 3
A2 R0 INSTRUCTION TO BIDDERS 38
A A3 R0 INFORMATION FORMS 41
1.0 Maithon Power Limited (MPL) having its registered office in New Delhi is a
joint venture company between The Tata Power Company Limited (TPC)
and Damodar Valley Corporation (DVC). TPC has a stake of 74% and DVC
has a stake of 26%. MPL proposes to set up a 1050 MW Coal based
Maithon Right Bank Thermal Power Project (MRBTPP) at the right bank of
river Barakar in Dhanbad District of Jharkhand State in the eastern region
of India. The project is a Mega Power Project under the Mega Power Policy
of the Government of India.
2.0 This specification covers on an Engineering, Procurement and Construction
(EPC) basis the design, engineering, manufacturing, shop fabrication,
assembly, testing and inspection at supplier’s works, packing, dispatch,
shipping, delivery at Indian port/unloading at Indian port/delivery from Indian
port to site in case of imported equipment and delivery/unloading at site for
indigenous equipment, unloading and storing at site, insurance upto time of
provisional take over, handling at site, complete erection, start-up,
commissioning, successful performance testing and handing over of the
following equipment and systems forming part of the Coal Handling
System (CHS) Package:
i) Wagon unloading system (Track Hoppers)
ii) Crushing and screening system
iii) Belt conveyors
iv) Stacker and reclaiming system
v) Bunker ventilation system
vi) Dust suppression system
vii) Dust extraction system
viii) In-motion wagon weighing system
ix) Auxiliaries system
x) Bulldozers
xi) Shunting Locomotives
xii) Coal yard drainage system
xiii) Instrumentation and Controls for CHS
xiv) Electrical systems for CHS
xv) Civil works for CHS
ISSUE
R0
ISSUE
R0
specification.
6.0 Current status of the Project
Land acquisition for the project is almost completed.
Following clearances have been obtained:
ISSUE
R0
CONTENTS
Cost of Bidding.............................................................................................................8
Bids to be complete....................................................................................................10
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
CONTENTS
Award .........................................................................................................................21
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
CONTENTS
Annexure 1.................................................................................................................25
Annexure 2.................................................................................................................30
Annexure 3.................................................................................................................37
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
1.5 General Information on Site Location and Ambient Conditions have been
provided in Section B of Volume II.
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
The OWNER/ PROJECT MANAGER shall not bear any liability for
foreign exchange variation after the conversion of Contract Price to
Indian Rupees as per clause above.
16.2 The Bidders shall, include all taxes, duties, cess, and levies in their
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
operating in India.
In case of International Bidders:
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
behalf of the Bidder, with his usual signature mentioning their name and
designation with a stamp(s) or seal(s) for suitable identification of the
Bidder, as the case may be in accordance with this clause 21.0. The
names of all person(s) signing should also be typed or printed below the
signature. All pages of the Bid shall have initials of the person(s) signing
the Bid with stamp(s)/seal(s) as suitable identification of the Bidder. All
drawings submitted by the Bidder shall also have initials of the authorised
signatory of the Bidder.
21.3 The Bid must also contain the place of business of the person or persons
making the Bid.
21.4 Bid by a Partnership Firm must be furnished with full names of all partners
and be signed with the partner's name, followed by the signature and
designation of one of the authorised partners or other authorised
representative(s). A certified copy of the Partnership Deed, relevant
Power of Attorney and current address of all the partners of the firm shall
also accompany the Bid.
21.5 Bid by a Corporation / Limited Company must be signed with the legal
name of the Corporation Limited Company by the President, Managing
Director or by the Secretary or any other person or persons holding Power
of Attorney for signing the Bid, in which case a certified copy of the Power
of Attorney for signing the Bid and the Board resolution authorising the
grant of such Power of Attorney shall be furnished along with the Bid.
Such Limited Company /Corporation shall also furnish satisfactory
evidence of its existence along with its Bid.
21.6 A Bid by a person, who affixed to his signature the word 'President',
'Managing Director', 'Secretary', ‘Agent' or any other designation, without
disclosing his principal and without enclosing certified copies of Power of
Attorney and Board Resolution or equivalent Authorisation will be
rejected. Satisfactory evidence of authority of the person signing on behalf
of the Bidder shall be furnished with the Bid.
21.7 No Erasures or whitening and rewriting shall be permitted. Changes, if
any, shall be effected only by cancellation of the original writing by striking
and re-writing it alongside. All such changes shall carry the initials of the
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
35.2 The successful Bidder shall provide the Contract Performance Guarantee
(CPG) in the form of a Contract Performance Bank Guarantee, issued by
a bank meeting the requirements below:
35.2.1 In case of Domestic Bidders:
From any Reserve Bank of India (RBI) approved Scheduled Bank (Public
Sector Banks, Private Banks or Foreign Banks) operating in India.
35.2.2 In case of International Bidders:
From any Reserve Bank of India (RBI) approved Scheduled Bank (Public
Sector Banks, Private Banks or Foreign Banks) operating in India.
Or
From any Indian Public Sector Scheduled Bank, operating in the country
of the Bidder.
Or
35.2.3 From any Foreign Bank but counter-guaranteed by an Indian Public
Sector Scheduled Bank.
35.3 It is the responsibility of the Bidder to verify and confirm to himself that the
Bank issuing the CPG meets the above requirements, and is counter-
guaranteed as required.
35.4 The Contract Performance Guarantee (CPG) will be in Indian Rupees.
Exchange rate to be considered for arriving at the CPG value shall be as
per Clause 16.1.
Failure of the successful Bidder to comply with the requirements of
clauses 34.0, 35.0 and if applicable clause 36.0 shall constitute a breach
of Contract, cause for annulment of the award, forfeiture of the Bid
Security and any such other remedy the OWNER may take under the
Contract, and the OWNER may resort to awarding the Contract to the next
competitive Bidder.
36.0 Corrupt/ Fraudulent Practices
36.1 OWNER/ PROJECT MANAGER requires that Bidders/ Suppliers/
Contractors observe the highest standard of ethics during the entire
process of Bidding from the purchase of Tender Documents up to the
award of Contract for CHS Package and thereafter in execution. In
pursuance of this policy,
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ANNEXURE 1
As explained in clause 22.1 of Section A2, the Bidder shall submit two envelopes
A and B as a part of his Bid with inner envelopes Aa and Ab in envelope A and
Ba, Bb & Bc in envelope B.
The contents of each of the envelopes are as follows :
Enclosure :
Relevant supporting documents in respect of projects like copies of authentic work
orders, and completion certificates to demonstrate satisfactory commercial operation
of plants. The contact details of owners or owners representatives of these projects
and their names, addresses, phone, fax numbers, email ids, etc. who could be
contacted for corroboration of details furnished and for obtaining clarifications should
also be mentioned. No claim without supporting documents shall be accepted in this
regard.
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
Enclosure
Relevant end user’s certificate as references for performance signed by the officer
not below the rank of Chief Engineer/ Plant Manager/ station Superintendent of
respective Power Station. These documents shall elaborate problems faced
during commissioning and commercial operation and enumerate failure of
components/ equipment/ systems. The details of contacts representing owners of
these projects and their names, addresses, phone, fax numbers, email ids, etc.
who could be contacted for corroboration of details furnished and for obtaining
clarifications should also be mentioned. No claim without supporting document
shall be accepted in this regard.
Financial Data-Balance Sheet
Information form 4A(i)
Financial Data-Income Statement
Information form 4A(ii)
Financial Data-Cash Flow Statement
Information form 4A(iii)
Financial Data-Status of Contracts in
Information form 4B
Progress
Financial Projections-Balance Sheet
Information form 4C(i)
Financial Projections –Income
Information form 4C(ii)
Statement
Financial Projections –Cash Flow
Information form 4C(iii)
Statement
Financial Data – Available credit
Information form 4D
Financial Data – Rating
Information form 4E
Enclosure:
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
Annual reports of the Bidder including audited Profit and Loss Statements, Balance
Sheets, Cash Flow Statement and Auditor’s Reports for the immediately five
preceding fiscal years and an authority from the Bidder to seek references from the
Bidder’s bankers and auditors shall be submitted. The Bidder should also provide
details of Contacts including their names, address, phone, fax numbers, email ids,
etc. in respect of aforesaid Bankers and Auditors. Credit Rating certificates issued by
appropriate rating agencies for each Bidder to be attached.
Financial Projections as made available to Banks or Credit Rating Agencies or the
like and where not made available to be prepared and enclosed in line with internal
processes of the Bidder. Bank Certificates to prove the availability of stated lines of
credit should be provided. Any other information that is relevant for satisfying the
qualification criteria should also be provided.
Personnel Capabilities
Information form 5A
Candidate Summary
Information form 5B
Arbitration History
Information Form 6
Enclosure:
Particulars regarding attachments, executions, show cause notices, arbitration or
restraint in respect of any assets or receivables of Bidder. Details of all statutory
liabilities having a significant bearing on the Bidder.
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ANNEXURE 2
BID EVALUATION
The Bid shall be evaluated in three stages:
1.0 Stage-I: Evaluation of Bid Security
1.1 On the date of Bid opening, the envelopes containing Qualification Bid
& Bid Security of Bidders (i.e. envelopes Aa and Ab) and Technical
and Un-priced Commercial Bid (i.e. envelopes Ba and Bb) shall be
opened. Envelope Ab will be opened first to check if the bidder has
submitted the Bid Security Bank Guarantee (BG) as specified.
Envelope Aa, Ba, and Bb will be opened next if the specified
requirements for BG submission have been complied with. Bids not
meeting the criteria for sealing and marking of Bids as specified in
clauses 22.1 to 22.4 shall be rejected by the OWNER/ PROJECT
MANAGER.
2.0 Stage-II: Evaluation of Qualification, Technical and Un-priced
Commercial Bid
2.1 Scrutiny of Qualification and Responsiveness
The contents of envelope Aa will be examined considering the
following:
a) Meets the eligibility criteria as specified.
b) Has been properly signed as specified.
c) Is substantially responsive* to the requirements of the Tender
Documents;
d) Provides any clarification and or substantiation that the
OWNER/ PROJECT MANAGER may require to determine
responsiveness and;
e) Has all the required Information Forms, Undertakings,
Guarantees, Enclosures, Schedules etc.
f) The Bidder shall confirm in the Covering Letter to the bid that
his Bid is ‘Firm and Irrevocable’, valid and open until the Date
of validity as specified. Bids without this statement will be
treated as non-responsive.”
*For purposes of this determination, a substantially responsive Bid is
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
2.2.3 In respect of the Bids not found deficient, each relevant Bidder shall
be required to submit Price Implication Bid in respect of resolved
Commercial and Technical issues in envelope Bd which together with
the Bid is in compliance with the Tender Documents except for the
listed unresolved Commercial and Technical variations/ deviations
prepared by the OWNER/PROJECT MANAGER.
3.0 Stage-III: Final Evaluation
3.1 On a date indicated by the OWNER/PROJECT MANAGER,
envelopes Bc and Bd containing the Price Bid and Price Implication
Bid respectively of those Bids not found deficient based on technical
and commercial scrutiny shall be opened.
3.2 Each responsive Price Bid will be scrutinized for compliance with
Tender Documents particularly clause 16.0 of section A2 and with
regard to price break-up in terms of various supplies, services, tax
along with detailed explanation on tax exemption. The Price Bids not
found compliant shall be rejected and such bids shall not be
considered further.
3.3 Correction of Errors
Price bids will be checked by the OWNER/ PROJECT MANAGER for
any arithmetic errors. Errors will be corrected by the OWNER/
PROJECT MANAGER. Where there is a discrepancy between the
amounts in figures and in words, the amount in words will govern. The
amount stated in the Bid will be adjusted by the OWNER/ PROJECT
MANAGER in accordance with this procedure for the correction of
errors and, shall be considered as binding upon the Bidder. If the
Bidder does not accept the corrected amount of Bid, his Bid will be
rejected, and the Bid Security will be forfeited in accordance with
clause 19.7 of this section A2.
3.4 The responsive and compliant Price Bids shall be evaluated for the
determination of the Evaluated Bid Price as detailed in clause 3.5 of
this Annexure 2, considering the following:
a) There shall be no Price adjustment on account of currency
exchange rate variation during the entire period of the Contract.
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
4.0 For every week delay beyond the specified 0.5% of total contract price
completion schedule for each sub-system forming
part of CHS Package as specified under Clause 1.4
of Section A2
ISSUE
R0
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A2
ANNEXURE 3
ISSUE
R0
SECTION-A3
INFORMATION FORMS
TCE 4891A-H-500-004 TCE CONSULTING ENGINEERS LIMITED SECTION: A3
FORM TITLE
B Statement of Bidders
2 Revenue Data
6 Arbitration History
ISSUE
R0
FORM TITLE
Contractor
ISSUE
R0
Date : ___________
Sir,
In accordance with the Tender Document, the undersigned representative of the firm /
company: ____________________________________________________________
_____________________________________________________________________
Firm :
Company :
The undersigned hereby declares to have read and understood the Tender
Documents and hereby submit the following Bid, which is in compliance with the
Tender Documents (except for the deviations listed in the respective Schedules)
comprising the following:
ISSUE
R0
The signing by the undersigned of this Bid guarantees the truth and
accuracy of all statements contained in Tender Documents and of all
answers to the questions contained herein or hereinafter made.
ISSUE
R0
• reject or accept any Bid, cancel the Bidding process, and reject all
applications, and
In all of the above cases. MPL/ PROJECT MANAGER shall not be held
liable for any claims whatsoever.
By this letter, the undersigned who acts in name and on account of the
Bidder, declares that, by virtue of the Power of Attorney (copy enclosed
herewith) along with the certified copies of Board Resolution authorizing
the issue of such power of attorney (copy enclosed herewith) in the case
of Companies, he has been granted and has the widest authority to
effect all the necessary formalities for the Bid.
ISSUE
R0
STATEMENT OF BIDDERS
________________________________
3 Legal Status
______________________________
(Day) (Month) (Year)
________________________________________________________
(Original currency)
________________________________________________________
(Equivalent in US $)
________________________________________________________
ISSUE
R0
________________________________________________________
________________________________________________________
________________________________________________________
________________________________________________________
Engineers _______________________________
Specialists _______________________________
_______________________ ___________________________
_______________________ ___________________________
_______________________ ___________________________
_______________________ ___________________________
ISSUE
R0
[Bidders should provide the following information relating to himself to demonstrate that
they meet the requirements stated in the Instructions to Bidders]
1. Name of Bidder
___________________________________________________________
2. Experience of the Bidder in EPC / CHS Package during the year 2001 to 2006 (*)
Year Name & Brief Role of the Value of the Current
Location of Description Bidder Contract (in Status &
Project USD) Year of
Commissio
ning
2001
2002
2003
2004
2005
2006
*Give details of all the EPC / CHS Packages undertaken in the respective years.
Attach separate Information Form (1B) for each power project completed between
2001 and December 2006.
Yes No
ISSUE
R0
If yes, provide details including man days lost and number of days delay,
explain the reasons and your counter plan taken. Attach as many sheets
as required.
Yes No
_____________ ______________________________________
1 Role of Bidder
Prime Contractor
_____________________
_____________________
10 Whether project completed within contracted period. If No, give reasons for
the same, also give particulars of LDs paid, payable and LDs disputed (if
any) Attach extra sheets, if necessary
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
ISSUE
R0
__________________________________________________
____________ ________________________________
REVENUE DATA
Name of Bidder:
_______________________________________________________________
[Bidder should provide the following information relating to himself to demonstrate that
they meet the requirements stated in the Instruction to Bidders]
ISSUE
R0
List of revenue from contracting of EPC/CHS Packages of the last five fiscal years
converted to Indian Rupees or U.S dollars at the rate at end of each period in
accordance with of ITB
(INR/US$)
Name of Employer Name of Revenue from contracting
Contract
Total values
Applied Exchange
rates to convert in
US$
Note : A certificate from an approved Audit firm certifying the aforesaid information
may be sought by the owner.
ISSUE
R0
ISSUE
R0
ISSUE
R0
* Capital stock
* Additional paid-in
capital
* Retained earnings
ISSUE
R0
Name of Bidder:
Net Sales
Cost of sales
Gross profit
Other Expenses
* Depreciation
* Interest paid
* Other expenses
Operating income
Other earnings
Income taxes
Net income
• Indicates sub-items
ISSUE
R0
Name of Bidder:
* Indicates sub-items
ISSUE
R0
Name of Bidder:
Give full information about all your uncompleted works on contract now in progress
whether prime or subcontracts.
Project Location Owner and his Contract Work Date of Scheduled Present
Name and Country Contact details Amount as of certified commencement Date of status*
December and completion
2006 Amount
(INR/US$) received
* Delay, before schedule, on schedule (In case of delay, the details on estimated
time and cost over run shall also be provided).
ISSUE
R0
Name of Bidder:
* Indicates sub-items
Note : (1) Indicate the applied exchange rates to convert into US Dollars.
(2) Also indicate the extent to which each asset is encumbered or charged.
ISSUE
R0
Name of Bidder:
Net Sales
Cost of sales
Gross profit
Other Expenses
* Depreciation
* Interest paid
* Other expenses
Operating income
Other earnings
Income taxes
Net income
* Indicates sub-items
ISSUE
R0
Name of Bidder:
* Indicates sub-items
ISSUE
R0
Name of Bidder:
In (INR/US$)
Name of Bank Amount of Credit * Credit required for Balance Credit
Existing Available *
Commitments *
TOTAL
ISSUE
R0
Name of Bidder:
Rating :
(As of :
Whether any downgrading / upgrading has been done in the last five years? If so,
please provide all details of such upgrades / downgrades.
ISSUE
R0
PERSONNEL CAPABILITIES
Name of Bidder:
1. Title of position
Name of prime candidate
Name of alternate candidate
2. Title of position
Name of prime candidate
Name of alternate candidate
3. Title of position
Name of prime candidate
Name of alternate candidate
4. Title of position
Name of prime candidate
Name of alternate candidate
5. Title of position
Name of prime candidate
Name of alternate candidate
ISSUE
R0
Position Candidate
Prime Alternate
Candidate Information Name of Candidate Date of Birth
Professional Qualifications
Present employment Name of employer
Address of employer
Telephone Contact (manager / personnel
officer)
Fax Telex
Job title of candidate Years with present employer
ISSUE
R0
ARBITRATION HISTORY
Name of Bidders:
(2) As a Bidder :
ISSUE
R0
Name of Bidder :
1.
2.
3.
4.
5.
ISSUE
R0
3. We, ------------------------- Bank further agree that the Owner shall decide as to
whether the Bidder(s) is in default of due and faithful fulfilment and
compliance with the terms and conditions contained in the said Tender
including inter alia, the failure of the said Bidder(s) to keep its Bid open during
the Bid validity period set forth in the said Tender and the decision of the
Owner that the said Bidder(s) is in default as aforesaid shall be final and
binding on us.
In the event of any dispute in this specific regard pending before any Court
Tribunal, Arbitrator or any other authority, the Bank do hereby agrees to
unconditionally place the amounts claimed by the owner under this guarantee
into a separate account in the Bank or any other back as decided by the
Owner, whose disposition shall be dealt in accordance with the judgement
delivered on the said dispute by the said Court. Tribunal, Arbitrator or any
other authority. .
5. After the submission of the said Tender, the Owner shall have the fullest
liberty without affecting in any way the liability of the Bank under this
Guarantee from time to time and only after prior agreement with the Bidder(s)
to vary any of the terms and conditions of the said Tender or to extend time of
the said Tender or the period for fulfilment and compliance with the terms and
conditions contained in the said Tender by the said Bidder(s) or to postpone
for any time and from time to time any of the powers exercisable by it against
the said Bidders and either to enforce or forbear from enforcing any of the
terms and conditions contained in the said Tender including the securities
available to the Owner and the bank shall not be released from its liability
under these presents by any exercise by the Owner of the liberty with
reference to the matters aforesaid or by reason of time being given to the said
Bidders or any other forbearance, act or omission on the part of the Owner or
any indulgence by the Owner to the said Bidder(s) or of any other matter or
ISSUE
R0
thing whatsoever which under the law relating to sureties would but for this
provision have the effect of releasing the Bank from its such liability.
8. It shall not be necessary for the Owner to proceed against the said Bidder(s)
before proceeding against the bank and the Guarantee herein contained shall
be enforceable against the bank, not withstanding any other security which
the Owner may have obtained from the said Bidder(s), shall at the time when
proceedings are taken against the bank hereunder, be outstanding or
unrealised.
10. The Bank declares that it has the power to issue this guarantee and the
undersigned have full powers to do so on behalf of the Bank.
11. The Guarantee will be governed by the terms and conditions of the said
Tender and in accordance with Indian Laws. Only the Court of competent
jurisdiction in India shall have jurisdiction over any cause of action arising
under this Guarantee.
For ________________________________Bank
ISSUE
R0
1.0 You have entered into a Contract No…………… dated ……. with M/s.
…………………………… (hereinafter referred to as “the Contractor”) for design,
engineering and execution of CHS Package for 1050 MW Coal-based
Maithon Right Bank Thermal Power Project in Dhanbad District of
Jharkhand State” for the price and on the terms and conditions contained in the
said contract.
2.0 In accordance with the terms of the said Contract, “the Contractor” has
agreed to furnish you with an irrevocable and unconditional bank guarantee in
a form and from a Bank acceptable to you as Security for the due
performance by “the Contractor” of all his contractual obligations under the
said contract in an amount equal to 15% (fifteen percent) of the total value of
the contract to be valid from the date of contract and upto 2 years from the
date of take over of the last unit of “the said equipment”
ISSUE
R0
4.0 You shall have the right to file/make your claim on us under the guarantee for
a further period of six months from the said date of expiry.
5.0 This guarantee shall not be revoked without your express consent and shall
not be affected by your granting time or any other indulgence to “the
Contractor”, which shall include but not be limited to, postponement from time
to time of the exercise of any powers vested in you or any right which may
have against “the Contractor” and to exercise the same in any manner at any
time and either to enforce or forbear to enforce any covenant contained or
implied in the said contract or any other course of remedy or security
available to you, and our Bank shall to be released from its obligations under
this guarantee by your exercising any of your rights with reference to matters
aforesaid or any of them or by reasons of any other act or forbearance or
other acts of omission or commission on your part or any other indulgence
shown by you or by any other matter or thing whatsoever which under the law
would, but for this provision. have the effect of relieving our bank from its
obligation under this guarantee.
6.0 We also agree that you shall be entitled at your option to enforce this
guarantee against our bank as a principal debtor, in the first instance,
notwithstanding any other security or guarantee that you may have in relation
to “the Contractor’s” liabilities in respect of the premises.
7.0 This guarantee shall not be affected by any change in the constitution of our
Bank or “the Contractor” or for any other reason whatsoever.
8.0 Any claim / extension under the guarantee can be lodgeable at outstation
banks or at Mumbai / New Delhi branch and claim will also be payable at
Mumbai / New Delhi Branch.
9.0 Notwithstanding anything herein contained, our liability under this guarantee
is limited to Rs………….. (Rupees …………………………. Only) and the
guarantee will remain in force upto and including ………… (Date) and shall be
extended from time to time for such period or periods as may be desired by
“the Contractor”
11.0 All payment under this Guarantee shall be made free of any withholding or
deduction whatsoever.
ISSUE
R0
13.0 This Guarantee shall not be discharged, impaired or affected by reason of:
ISSUE
R0
_______________________________________________________
1.0 You have entered into a Contract No…………… dated ……. with M/s.
…………………………… (hereinafter referred to as “the Contractor”) for design,
engineering and execution of CHS Package for 1050 MW Coal-based
Maithon Right Bank Thermal Power Project in Dhanbad District of
Jharkhand State” for the price and on the terms and conditions contained in the
said contract.
2.0 In accordance with the terms of the said contract, you have agreed to make an
advance payment of Rs…………. (Rupees ………………… only) being …….. ,%
(………….. percent) of the total value of the contract on “the Contractor”
furnishing you with an irrevocable, unconditional and acceptable bank guarantee
to be valid till the date of take over of “the CHS Package” covered by your above
mentioned contract. For this purpose you have agreed to accept our guarantee.
ISSUE
R0
sole judge for such non-fulfillment and “the Contractor” shall have no right to
question such judgement.
4.0 You shall have the right to file/make your claim on us under the guarantee for a
further period of six months from the date of expiry.
5.0 The guarantee shall not be revoked without express consent and shall not be
affected by your granting time or any other indulgence to “the Contractor”, which
shall include but not be limited to, postponement from time to time of the exercise
the same in you or any right which you may have against “the Contractor” and to
exercise the same in any covenant contained or implied in the said contract or
any other course or remedy or security available to you, and our Bank shall not
be released from its obligations under this guarantee by your exercising any of
your rights with reference to matters aforesaid or any of them or by reasons of
any other act or forbearance or other acts of omission or commission on your part
or any other indulgence shown by you or by any other matter or thing whatsoever
which under the law would, but for this provision have the effect of relieving our
bank from its obligation under this guarantee.
6.0 We also agree that you shall be entitled at your option to enforce this guarantee
against our bank as a principal debtor, in the first instance, notwithstanding any
other security or guarantee that you may have in relation to “the Contractor’s”
liabilities in respect of the premises.
7.0 This guarantee shall not be affected by any change in the constitution of our Bank
or “the Contractor” or for any other reason whatsoever.
8.0 Any claim / extension under the guarantee can be lodgeable at outstation banks
or at Mumbai / New Delhi branch and claim will also be payable at Mumbai / New
Delhi branch.
9.0 Notwithstanding anything herein contained, our liability under this guarantee is
limited to Rs………….. (Rupees …………………………. Only) and the guarantee
will remain in force upto and including ………… (Date) and shall be extended
from time to time for such period or periods as may be desired by “the Contractor”
10.0 Unless a demand or claim under this guarantee is received by us in writing within
six months from ………….. (expiry date) i.e. on or before ………….. (claim period
end date), we shall be discharged from all liabilities under this guarantee
thereafter.
11.0 All payment under this Guarantee shall be made free of any withholding or
deduction whatsoever.
this Guarantee to the effect that the Contractor has failed to complete the Work
and fulfill his contractual obligations prior to such expiry and accordingly the
period of this Guarantee is required to be extended by the Bank, failing which the
amount guaranteed under this Guarantee shall be due and payable to you
forthwith without any further notice or demand from you.
13.0 This Guarantee shall not be discharged, impaired or affected by reason of:
14.0 This Guarantee shall be governed by the laws of India and only competent courts
in India shall have jurisdiction on all matters covered by this Guarantee.”
AND
…………………………………………………………… a Company incorporated under
the laws of ………………. having its principal place of business (in case of Company
registered in India – a Company incorporated in India under the Companies Act,
1956, having its registered office) at ……………………………………………………….
(hereinafter referred to as the “Contractor”, which expression shall include its
successors and permitted assigns) of the other Part.
RECITALS
WHEREAS:
(A) The Owner has received necessary approvals for setting up of a 1050
MW Coal-fired Thermal Power Project, under the Mega-Power Policy of
the Government of India, on the right bank of river Barakar in Dhanbad
District of Jharkhand State in the eastern region of India (hereinafter
referred to as the “Project”);
(B) The Owner, through its Project Manager wishes to appoint a Contractor
for ………………………………..[specify type and nature and purpose of
stand-alone independent contracts, viz. (i) Offshore Supply Contract for
Imported Equipment (‘OFSC’); (ii) Onshore Supply Contract for
Indigenous Equipment (‘ONSC’); (iii) Onshore Services Contract – for
installation, commissioning and guarantees (‘OSC’); & (iv) Co-ordination &
Guarantee Agreement (‘CGA’) – to properly tie up and guarantee the
obligations under these independent contracts] for………………………….
(C) The Contractor has represented that it has the requisite technical know-
how and experience, expertise and capability and financial and other
resources to ensure that the contracted supplies, services and other work
are executed and completed in accordance with the terms of the Contract
in a safe and environmentally responsible manner and that the contracted
work will be capable of seamless integration with other Related Works
and be carried out on, under, over or in connection with the Project Site;
(D) Relying upon the foregoing and other representations of the Contractor,
the Owner appoints the Contractor to undertake the contracted work or
services and the Contractor agrees to carry out and complete the
contracted work, services and other work and remedy any and all defects
therein, on terms and conditions of the Contract;
(E) The Contractor acknowledges that the Owner has entered into or will
enter into other contracts with other contractors and/or parties for the
ISSUE
R0
remaining elements of the Project (and not comprised in the contract work
or services) and that the Owner will have Related Works performed and
that it is of paramount importance that the contracted work, services and
other work are fully and completely coordinated with the Related Works by
the Contractor in view of their concurrent and sequential nature;
(F) The terms and conditions of this Contract have been fully negotiated
between the Project Manager on behalf of the Owner and the Contractor
as parties of competent capacity and equal standing.
1. In this Contract Agreement (and the Recitals to it) words and expressions
shall have the meanings assigned to them herein and in the Conditions
Contract referred to below.
ISSUE
R0
4.2 The Contractor hereby declared to have full knowledge and understanding of
the contents of all the foregoing documents whether contained in or
incorporated by reference thereto and accepts all the terms and conditions
contained therein. In the event of any ambiguity or conflict between any of
the foregoing Contract Documents, the Contractor shall, prior to
commencement of the subcontract supplies, services or work , be deemed to
have clarified from the Owner all such ambiguities or conflicts. The order of
precedence of the foregoing documents shall be the same as listed herein
above.
5. Effective Date & Commencement Date
5.1 The Contract is deemed to have come into effect and full force from the date
of issue of Letter of Intent by the Owner to the Contractor,
viz……………………., which shall be the Effective Date of Contract.
5.2 The Contractor shall commence work within 7 (seven) days of the issue of
Notice to Proceed from the Owner to the Contractor under this Contract,
which shall not be earlier than 10 (ten) days and not later than 180 (one
hundred and eighty) days from the date of this Contract.
6. Notices:
6.1 Any notice to be given under the Contract shall be sent to the Owner/Project
Manager or the Contractor, as the case may be, at the address set for the
below:
Address: Address:
Attn.: Attn.:
Title: Title:
Tel. Tel.
Fax: Fax:
E-mail: E-mail:
ISSUE
R0
6.2 Any notice to be given hereunder by one Party to the other Party may be sent
by pre-paid registered post or by overnight courier or by facsimile or by e-mail to
its address given herein above or to such other address as may have been
communicated by such Party to the other Party and shall be deemed to have
been received if sent by pre-paid registered post or overnight courier on the date
of its delivery as evidenced by the postal mark or receipt, if sent by facsimile on
the date of its transmission stamped on it and if sent by e-mail on the date of its
transmission as evidenced by its properties.
7.1 This Contract shall be governed by the laws of India and only Courts of
competent jurisdiction within India shall have jurisdiction on all matters
covered by this Contract.
8. General:
8.3 General Conditions of Contract (GCC), Schedules and Appendices shall form
part of this Agreement and shall have the same effect as the provisions of this
Agreement.
IN WITNESS WHEREOF the Owner and the Contractor have caused this Agreement
to be duly executed by their duly authorized representatives as of the day, month and
year herein above written.
By___________________________ By____________________________
Name: Name:
Title: Title:
ISSUE
R0
WITNESSES:
1.______________________________ 1.______________________________
Name: Name:
Title: Title:
2.______________________________ 2.______________________________
Name: Name:
Title: Title:
ISSUE
R0
PREAMBLE
based on the GCC and other terms & conditions and provisions of the tender as
applicable thereto, the Contractor is required to price his bid accordingly and outline
the implications thereof in his bid proposal.
The Contractor is deemed to have studied and understood fully the implications of
such standalone multiple contracts and shall be responsible for any and all tax &
other liabilities arising out of such independent and standalone contracts.
ISSUE
R0
CONTENTS
1.1 Definitions 9
1.3 Interpretation 20
1.9 Communications 22
1.14 Assignment 24
3.1 General 27
3.4 Procurement 36
3.6 Permitting 43
3.7 Co-operation 44
3.17 Schedule 57
ISSUE
R0
3.31 Insurance 71
4.0 SUB-CONTRACTORS 81
5.1 Requirements 85
5.2 Rejection 88
ISSUE
R0
6.0 INSURANCE 89
7.0 TITLE 97
8.0 FOSSILS 97
13.4 Application for Interim Payment Certificates and Claim for 120
Payments
ISSUE
R0
ISSUE
R0
1.1 Definitions
1.1.1 In the Contract (as defined below), unless the context requires otherwise
the words and expressions defined below shall have the meaning
hereinafter assigned to them.
1.1.2 “Affiliate” shall mean an entity controlling, controlled by, or under the
common control with, a Party directly or indirectly through ownership of
voting securities or by Contract or otherwise.
1.1.4 "Applicable Laws” means all laws, treaties, ordinances, rules, regulations
applicable in India and amendments, re-enactments, revisions,
applications, and adaptations thereto made from time to time and in force
and effect, judgements, decrees, injunctions, writs and orders of any
court, arbitrator or governmental agency or authority, rules, regulations,
orders and interpretations of any Governmental Instrumentality, court or
statutory or other body having jurisdiction over construction of the Facility
on the Facility Site, performance of the Work or supply of Goods,
operation and maintenance of the Plant, including Applicable Permits, as
may be in effect at the time of performance of work or supply of Goods
hereunder by the Contractor, which time would include Latent Defects
Period as appropriate, provided, however, that if at any time the
Applicable Laws are less stringent than the standards set forth in the
Contract hereto, the standard set forth in the contract hereto shall be
deemed to be the standards under Applicable Laws.
1.1.5 "Applicable Permits & Clearances” means any and all Permits,
Clearances, authorizations, consents, licenses (including without limitation
any import or export licenses), lease, ruling, exemption, filing,
agreements, or approvals, required to be obtained or maintained in
connection with construction of the Plant on the Site, performance of
Work, and the operation of the Plant respectively by the Contractor and
the Owner in accordance with the Contract and their maintenance, as
may be in effect at the time of Contractor's performance of Work or supply
of Goods hereunder; which time would include Latent Defects Period as
appropriate.
1.1.6 “Bid” means the tender offer of the Contractor to the OWNER/PROJECT
MANAGER in response to the Tender Enquiry as set forth in the Final
ISSUE
R0
Proposal.
1.1.7 “BTG Package” all equipment and accessories forming part of Owner’s
procurement package for Boiler, Turbine and Generator.
1.1.8 “Business Day” means a day other than a Sunday or public holiday on
which banks are open for domestic business in New Delhi / Mumbai.
1.1.10 "Change in Law" means the occurrence of any of the following after the
Effective Date of this Agreement.
e) For purpose of this definition the “law” does not include any taxation
laws.
ISSUE
R0
1.1.12 “Change Order Notice” means a written proposal issued and signed by
OWNER/PROJECT MANAGER requesting a change, submitted to
Contractor by OWNER/PROJECT MANAGER pursuant to the terms of
clause 14.0 hereof.
1.1.15 “Contract" means the documents as set out in the form of Contract
Agreement as may be amended, supplemented or modified from time to
time by agreement in Writing between the Parties.
1.1.16 “Contract Period” means the period from the Effective date upto and
including the last day of the Latent Defect Liability Period.
1.1.17 “Contract Price" means the lump sum fixed price as stated in the Contract
or such price as may be modified pursuant to clause 14.0 and as payable
by the OWNER to the Contractor in consideration of it performing the
Work or supply of Goods including all obligations of the Contractor under
and in accordance with the provisions of the Contract.
1.1.18 “Contractor’s Works" shall mean the places which are used by the
Contractor or any of its sub-vendor / Sub-Contractor for the manufacture
of equipment for the Plant or performance of Work.
1.1.20 “Contractor" means the person whose Bid has been accepted by the
OWNER/PROJECT MANAGER and the legal successors in title to such
person who satisfies the qualification criteria set forth in the Tender
ISSUE
R0
Documents.
1.1.21 “Contractor Permits” means all Permits, required by the Contractor from
any Government Instrumentality for the performance of his obligations.
1.1.24 “Cost" means all expenditure properly incurred (or to be incurred) by the
Contractor, whether on or off the Site, including overhead and similar
charges, for the full complete and proper performance of Work or supply
of Goods including discharge of all of the Contractor’s obligations under
and in accordance with the Contract which are duly audited and
supported but does not include profit.
1.1.26 “Day” means a calendar Day of 24 (twenty four) hours and “Year” means
365 (three hundred and sixty five) days.
ISSUE
R0
1.1.29 “Effective Date" or "Effective Date of Contract" means the date on which
the Contract comes into force and effect, i.e. From the date of issue by
the OWNER of the Notice to Proceed (NTP) to the Contractor.
1.1.31 "Final Take Over" or “Final Taking Over” or “Final Acceptance” shall mean
Taking-over of the CHS Package for the purpose envisaged under the
Contract or that for which the CHS Package is commercially capable, as
certified upon successful completion of Performance Test, as described
under section C5 of this specification.
1.1.32 “Final Payment Certificate” means the payment certificate issued by the
OWNER/PROJECT MANAGER or his Representative under clause 13.8
hereof to the Contractor.
1.1.33 “Final Proposal” shall mean final offer of Bidder incorporating all the
amendments and clarifications.
Debt or equity financing to the OWNER for provision of funds for the
development, design, construction and I or operation of the Plant; or
Funds for refinancing part or whole or take-out of any such financing.
1.1.35 “Financial Closing Date" means the date on which OWNER has access to
funds pursuant to Financing Documents.
1.1.37 “Force Majeure Event” shall have the meaning set forth in clause no. 20.0
of these General Conditions of the Contract.
1.1.46 “Initial Operation" shall have the meaning as defined under section C5 of
this specification.
1.1.49 “Interim Payment Certificate” means any payment certificate other than
Final Payment Certificate, issued by the OWNER or OWNER’s
Representative pursuant to clause no. 13.0 hereof.
1.1.50 “Latent Defect” shall be the defects inherently lying within the Goods
which do not manifest during normal inspections carried out by the
OWNER in accordance with O&M manual during the Warranty Period.
1.1.51 “Latent Defect Liability Period” means the liability period as set forth in
clause 12.2.2 hereof.
ISSUE
R0
1.1.53 "Manuals” means all the various instruction manuals to be provided as per
the Contract by the Contractor and shall include Manuals described in
Specifications or General Conditions of Contract.
1.1.54 "Manufacturer" means any entity or firm who is the producer and furnisher
to the Contractor of any material or designer and fabricator of any
equipment / systems which is to be incorporated in or forms part of the
Plant / work.
1.1.55 Materials” means Goods and other things of all kinds to be provided and
incorporated, to be used in the permanent Works / Plant/ Works by the
Contractor, including Goods purchased by the OWNER and supplied to
the Contractor as a free issue or the supply-only items (if any) which are
to be supplied by the Contractor under the Contract.
1.1.56 “Mechanical Completion” shall have the meaning as defined under section
C5 of this specification.
1.1.57 “Milestone Payment Schedule” means the document which sets forth the
limits of payments to be released (worked out, inter alia, on the basis of
payment terms agreed by the OWNER/PROJECT MANAGER) by linking
such payment limits (in terms of percentages) with detailed milestones
commencing from the date of Notice to Proceed. Such percentages shall
be with reference to the Contract Price, more particularly defined in clause
13.1.1 (v).
1.1.61 “Notice in Writing" or "Written Notice" shall mean a notice in writing, typed
or printed or hand written characters, sent (unless delivered personally or
otherwise proved to have been received) by registered post or by
electronic transmission to the last known private or business address or
registered office of the addressee and shall be deemed to have been
received when in the ordinary course of post or by electronic media it
would have been delivered.
ISSUE
R0
1.1.72 “Performance Guarantees” shall have the meaning set forth in this
Section and Section C6 of Vol.II.
1.1.73 "Performance Test" means, with respect to the CHS Package, the
operation of the Plant as an integrated whole by the Contractor in
coordination with Other Contractors as applicable, in accordance with the
provisions of this Section and Section C5 of Vol. II to prove and establish
the Performance Guarantees as per section C6 of Vol.II.
ISSUE
R0
1.1.76 "Preliminary Operation" shall have the meaning as defined under section
C5 of this specification.
1.1.77 “Project” and or “Plant” means the Facility and all the Works that are
necessary for 1050 MW Coal-fired Thermal Power Project, under the
Mega-Power Project Policy of the Government of India, on the right bank
of river Barakar in Dhanbad District of Jharkhand State in the eastern
region of India.
1.1.78 “Project Documents” mean collectively this Contract, the Power Purchase
Agreement, the Land Lease Agreement, Fuel Supply Agreement,
Transportation Agreement and any other contracts entered into or to be
entered into by the Owner with Other Contractors in connection with the
Project including without limitation any contacts for Related Works.
1.1.79 “PROJECT MANAGER” shall mean The Tata Power Company Ltd., or
their duly authorised representatives, who is the Project Manager for the
Project.
1.1.82 "Punch List” means the list prepared by OWNER at the time of Provisional
Acceptance and thereafter periodically revised by OWNER as necessary,
and in any case updated by OWNER within 20 (twenty) days following
Owner’s receipt of a Notice of Final Acceptance, in each case with the full
co-operation of Contractor, which list shall set forth certain items of Work
which remain to be performed by the Contractor in order to ensure that
the CHS Package fully complies with all of the standards and
requirements set forth in the Contract.
1.1.84 “Related Works” shall mean the works other than the Work under the
Contract performed or to be performed by the Owner or Owner’s Other
Contractors in connection with the Project either prior to, concurrently or
subsequently with the Works within or outside the Site with whom the
Contractor shall co-ordinate and interface his activities covered by the
Contract.
1.1.85 “Reliability Operation” or "Trial Operation" shall have the same meaning
as per clause 7.0 of Section C5 of Vol. II of specification.
1.1.86 "Schedule" shall have the meaning set forth in clause no. 3.17 hereof.
1.1.87 “Site” means all those parcels of land owned by OWNER on which the
1050 MW Maithon Right Bank TPP will be located, as more particularly
identified on the site plan and described in Drawings forming part of
Contract hereto.
ISSUE
R0
1.1.90 "Take Over Certificate" means the certificate issued as per requirements
described under Section C5 of specification.
1.1.91 "Temporary Works" means all temporary works of every kind (other than
Contractor's equipment) required for the execution and completion of the
Works and the remedying of any defects.
1.1.94 "Tests before Take Over" means the tests prescribed in the 'Specification',
and any other such tests as may be agreed between the OWNER and
Contractor or instructed as a Change Order, which has to be carried out
by the Contractor before the Taking Over of the CHS Package.
1.1.95 “Warranty Period" shall mean the period of 12 (twelve) months beginning
from the date of the CHS Package as a whole is taken over as stated in
the Provisional Acceptance (Provisional Take Over) Certificate, as
described under section C5 of this specification.
1.1.96 “Works” or “Services" means all the work and obligations of the Contractor
under the Contract including without limitation, the Work and services
briefly described in Specifications for the CHS Package including
permanent works and temporary works as appropriate under the Contract.
The section headings and marginal notes are not part of these General
Conditions of Contract, and shall not be taken into consideration in their
interpretation.
1.3 Interpretation
1.3.1 Words importing Persons or Parties shall include related firms and
corporations and any organisation having legal capacity. Words importing
the singular also include the plural and vice versa where the context
ISSUE
R0
1.3.2 Unless inconsistent with the provisions of the Contract, the meaning of
any shipping terms and the rights and obligations of the parties there
under shall be as set forth in the latest International Chambers of
Commerce (ICC) official rules for interpretation of trade terms as per
"INCOTERMS 2000".
1.3.3 The term Contractor shall include its Sub-contractor as the context
requires.
1.4.1 Applicable law to this Contract shall be the Indian Law. The respective
rights, privileges, duties and obligations of the OWNER and the
Contractor under this Contract shall be governed and determined by the
Laws of State of Jharkhand and of the Republic of India.
The costs of stamp duties and similar charges imposed by law on the
Contract or Agreement or any part thereof shall be borne by the
Contractor.
Effective Date of Contract means the date on which the Contract comes
into force and effect, i.e. From the date of issue by the OWNER of the
Notice to Proceed (NTP) to the Contractor.
ISSUE
R0
e) Tender document
f) Contractor’s Proposal
g) Schedule of Prices
The Contractor shall keep on the Site one complete set of the Contract,
the Documents, Change Orders, communications given or issued under
various clauses and sub clauses including clause 1.6 and the Documents
referred / mentioned in sub-clause 1.7 duly authenticated by the Owner’s
Representative. These Documents shall be either true copies or original
documents, the same being verified as true copies by OWNER’s
Representative. The OWNER, the Owner’s Representative and his
delegates (as referred to in sub-clause 2.4) shall have the right to use
such Documents at all reasonable times.
1.9 Communications
ISSUE
R0
1.10.2 In addition and without prejudice to the foregoing the Contractor shall
provide to the OWNER “as built” Drawings of the CHS Package
consequent to Provisional Acceptance as per requirements detailed in
Section C12 of Volume – II.
1.11.2 The Contractor shall indemnify the OWNER in case of breach of this
clause by the Contractor. If these Documents are received by a third party
from the Contractor and the third party makes use of these Documents to
cause harm or monetary loss to the OWNER or use these Documents for
ISSUE
R0
their personal gain / monetary gain, the Contractor shall compensate the
OWNER for the loss suffered as well as for the value of gain derived by
third party.
1.12.1 The Contractor shall treat the details of the Contract as private and
confidential, except to the extent necessary to carry out his obligations
hereunder. The Contractor shall not publish, permit to be published, or
disclose any particulars of the Contract in any trade or technical paper or
elsewhere without the prior consent in writing of the OWNER and at the
Owner’s sole discretion.
1.12.2 The contractor shall indemnify the OWNER in case of breach of this
clause. If the confidential details relating to this Contract or its contents
are received by a third party from the Contractor and the third party
makes use of these details to cause harm or monetary loss to the
OWNER or use these Documents for their personal gain/ monetary gain,
the Contractor shall compensate the OWNER for the loss suffered as well
as for the value of gain derived by the third party. The Contractor shall
not use the confidential details of the Contract for any other purpose
except for the strict purpose of this Contract.
1.13.1 From fiscal and execution considerations, the Owner intends to enter into
independent stand-alone contracts for the CHS Package tendered by the
Owner including (i) Offshore Supply Contract for imported equipment; (ii)
Onshore supply Contract for indigenous equipment; (iii)Onshore Services
Contract for installation, commissioning and guarantees; (iii) Coordination
and guarantee agreement.
1.13.2 The Contractor, with whom the above Contracts are entered into by the
Owner, shall be responsible for effective coordination and interfacing of all
his contracting activities and obligations under the Contract in a seamless
manner, irrespective of whether the same is specifically detailed in such
Contracts, to ensure that the Guaranteed Time Schedule and
Performance Guarantees set forth in the Contracts are properly fulfilled in
a timely manner.
1.13.3 Such Contractor shall be additionally liable to ensure that all such co-
ordination and interfacing of contracting activities under all such Contracts
are performed and guaranteed by him on a single point responsibility
basis in as much as the Owner will only be required to liaise with and look
upto only such Contractor for the timely and proper performance of all
such Contracts by the Other Contractors.
1.14 Assignment
ISSUE
R0
1.14.1 The Contractor shall not, without the prior consent of the OWNER assign
to any person any benefit of or obligation under the Contract in whole or in
part. Such assignment, if approved by OWNER, shall not relieve the
Contractor from any obligations, duty, or responsibility under the Contract.
1.14.3 The OWNER shall not, without the prior consent of the Contractor, assign
to any Person any benefit of or obligation under the Contract in whole or
in part. However, the OWNER can assign to its parent companies or
subsidiary companies without prior permission of the Contractor. Such
assignment shall not relieve the OWNER from any of its obligations,
duties or responsibilities under the Contract.
1.14.4 Any Sub-Contracts entered into by Contractor pursuant to clause no. 4.0
of these Conditions of Contract shall provide that, pursuant to terms that
are available on a commercially reasonable basis, the rights and
obligations of the Contractor under each such sub-Contract are
assignable and delegable to OWNER, its successors and assigns and the
Financing Parties and shall be deemed to have been assigned to the
OWNER, or if required by the OWNER to the Financing Parties forthwith
upon OWNER's/PROJECT MANAGER’s written request without any
further act, deed or thing and irrespective of termination or otherwise of
the Contract.
The OWNER shall grant the Contractor right of access to, and make
available the Site to the Contractor in accordance with the terms of the
Owner’s property rights within reasonable time after the Effective Date for
the performance of the Work or pursuant to and in accordance with the
Contract. Such right and use of the Site may not be exclusive to the
Contractor. In the execution of the Works, no persons other than the
Contractor or his duly appointed representative, Sub-contractor and
workmen, shall be allowed to do Work on the Site, except by the special
permission, in Writing of the OWNER’s representative.
2.2.1 The OWNER/PROJECT MANAGER shall, at the request and cost of the
Contractor assist him in applying for Contractor Permits and other
Construction Permits as defined herein. Such requests may also include
requests for the OWNER's/PROJECT MANAGER’s assistance in applying
for any necessary government consent for the export of Contractor's
equipment when it is removed from the Site.
The OWNER has appointed The Tata Power Company Limited (TPC) to
be the PROJECT MANAGER and provide project management
consultancy services for the Project. TPC shall act as an OWNER's
ISSUE
R0
Representative to exercise the rights and carry out the duties of the
OWNER under the Contract. OWNER’s representative shall also include
Consultant / Consulting Engineer or Third Party Inspection Agency as
required or deemed appropriate or authorised by the OWNER/PROJECT
MANAGER. Any act, instruction or decision of the OWNER’s
representative shall be as if this was an act, instruction or decision of the
OWNER.
2.4.5 Further, the OWNER is also free (subject to the rights the Contractor
himself has) to copy, use, reproduce all designs, Drawings, models,
plans, Specifications, design details, photographs, CAD Materials, and
any other material as supplied by the Contractor in connection with
Facility or Works for completion, repair, reconstruction, modification,
maintenance etc.
3.1 General
ISSUE
R0
3.1.1 The OWNER/ PROJECT MANAGER has engaged the Contractor relying
upon the representations, assurances and Warranties made by the
Contractor including the representation that the Contractor has the
experience, skill and resources to perform the Work or supply the Goods
and to design, engineer, supply, erect, construct, install, build and
complete in all respects the CHS Package fit for the purpose and deliver
the same to the OWNER in accordance with the Contract, and Contractor
acknowledges such reliance by the OWNER and the acceptance of the
Contractor for such engagement.
3.1.2 Without prejudice to the foregoing, except as otherwise expressly set forth
in the Contract as within the scope of OWNER’s obligations under the
Contract, the Contractor shall supply the Goods and / or perform or cause
to be performed all Work and Services required in connection with the
design, engineering, supply of equipment, procurement (including, without
limitation, all transportation services in connection therewith),
construction, erection, start-up, commissioning, testing including
conducting of Performance Tests and other works and services upto the
Final Acceptance of the CHS Package by the OWNER and in connection
therewith provide all Materials, equipment, machinery, tools, labour,
transportation, administration and other services and items required to
complete the CHS Package in all respects.
If there are any supplies, Work and Services required in connection with
the design, engineering, procurement, manufacture, supply, transportation
to site, fabrication, construction, erection, testing, commissioning and upto
Final Acceptance of the CHS Package which are not specifically
mentioned in the Contract or which are not under the Contract expressly
stated to be outside the Contractor’s Scope of Work or Supply described
in the Contract, but which are necessary to complete, commission and
efficiently operate the CHS Package as per Prudent Utility Practices, and
have the performance as guaranteed under the Contract by the
Contractor including for normal, safe and continuous operation of the CHS
Package, the Contractor shall provide or cause the same to be provided
as part of its obligations under the Contract. The Work to be performed or
Goods to be supplied by the Contractor under the Contract shall, without
prejudice to the generality of the foregoing include but not be limited to the
following:
ISSUE
R0
e) Project management.
3.2.1 Contractor shall provide all design and engineering services necessary for
design, engineering, erection, supply of equipment, installation, testing
ISSUE
R0
Contractor acknowledges the fact that the OWNER has agreements with
the fuel suppliers, other Contractors, off takers and other third parties.
Contractor shall co-operate with all these parties in the design,
engineering, procurement, fabrication, supply, delivery, construction,
Commissioning, start-up, testing, Take-over, operation, maintenance and
repair efforts, and accommodate their reasonable interface and
interconnection requirements within the limitations of Contractor's design
and scope of Work or Goods or other obligations hereunder.
ISSUE
R0
c) For each part of the CHS Package, and except to the extent that
the prior consent of the OWNER / OWNER's Representative shall
have been obtained:
f) Manuals
ISSUE
R0
The Contractor undertakes that the execution of the Contract and the
performance will be in accordance with the Applicable Laws.
3.3.1 Contractor shall develop a construction plan and shall carry out, oversee,
co-ordinate and ensure the expeditious design, engineering, procurement,
fabrication, construction, Commissioning, start-up and testing of the CHS
Package in accordance with Specification and other provisions of the
Contract consistent with the Guaranteed Time Schedules.
3.3.2 Contractor shall supply all material and construction equipment required
in the performance of the Work. All components of the CHS Package
including special tools shall be brand new equipment other than
ISSUE
R0
3.3.3 Contractor shall perform and cause its Sub-Contractors to perform all
design, engineering, procurement, fabrication, construction, erection,
Commissioning, start-up, testing, operation and maintenance upto Take-
over in accordance with Good Engineering Practices and Prudent Utility
Practices so that the CHS Package shall operate in accordance therewith
all Applicable Laws and all Applicable Permits and in a manner as not to
void or diminish any manufacturer's Warranty or any Insurance coverage
with respect to the Project. Contractor shall inspect or cause to be
inspected all equipment and shall reject those items not in compliance
with the Specification, or approved Quality Assurance Plans. Contractor
also shall carry out and oversee (a) the manner of incorporation of the
equipment into the CHS Package and the workmanship with which such
equipment is incorporated and (b) the performance of the Work.
3.3.6 The field activities of the Contractors working at site will be co-ordinated
by the OWNER’s Representative and his decision shall be final in
resolving any disputes or conflicts between the Contractor and Other
Contractors and tradesman of the OWNER regarding scheduling and co-
ordination of Work. Such decision by the OWNER’s Representative shall
not be a cause for extra compensation or extension of time for the
Contractor.
3.3.7 The OWNER’s Representative shall hold weekly meeting or daily meeting
if required of all the Contractors working at Site, at a time and place to be
designated by the OWNER’s Representative. The Contractor shall attend
such meetings and take notes of discussions during the meeting and the
ISSUE
R0
3.3.8 Time is the essence of the Contract and the Contractor shall be
responsible for performance of his Works in accordance with the specified
construction Schedule. If at any time, the Contractor is falling behind the
Schedule, he shall take necessary action to make good for such delays by
increasing his work force or by working overtime or otherwise reduce such
delays by increasing his work force or by working overtime or otherwise
accelerate the progress of the Work to comply with the Schedule and
shall communicate such actions in writing to the OWNER’s
Representative, satisfying that his action will compensate for the delay.
The Contractor shall not be allowed any extra compensation for such
action.
3.4 Procurement
3.4.1 Sourcing
As part of the Work, Contractor shall procure and pay for, in Contractor's
name as an independent Contractor, all Contractor and sub-contractors
labour, Materials, equipment, supplies, soil, cement, sand, gravel, paints
and similar Materials and manufacturing, fabrication and related services
(whether on or off the Site) for construction of and incorporation in the
CHS Package or which are otherwise required for completion of the Work
in accordance with the Specification and the Contract and are not
explicitly specified to be furnished by OWNER pursuant to the terms and
provisions of the Contract including Specification. This would also include
provision of:
(ii) For the three (3) year period subsequent to such Take-Over
period (Essential spares as per Section C14 of the Contract),
each in accordance with applicable laws and governmental
approvals,
c) Contractor shall arrange and ensure the security of all the foregoing
items while in handling, transport or storage, and the safe delivery of
the same to the plant Site and the incorporation of the same into the
CHS Package. In the event any such materials, equipment, supplies
or other items are damaged, lost, stolen, destroyed or otherwise
impaired, Onshore Service Contractor shall at its own cost and
expense restore or replace such items.
3.5.1 The Contractor shall make his own arrangements for the engagement of
all staff and labour, local or otherwise, and for their payment, housing,
feeding and transport. Contractor shall provide all labour and personnel
required in connection with Work, including:
Contract;
The Contractor shall employ (or cause to be employed) only persons who
are careful and appropriately qualified, skilled and experienced in their
respective trades or occupations. The Contractor shall give preference for
appointment of local labourers in unskilled, semi-skilled and skilled
categories if such suitable labourers are available.
ISSUE
R0
The Contractor shall ensure that he pays all his personnel and shall also
ensure that his Sub-contractors pay to their personnel regularly their
wages, overtime and other compensations. The attendance register and
the wage register shall be submitted to the OWNER/ PROJECT
MANAGER for verification at regular intervals. The Contractor shall also
furnish the OWNER/ PROJECT MANAGER at regular intervals as
governed by Applicable Laws including local statutes but not less than
Monthly intervals, certificates that he has paid to his Sub-contractors and
workmen and caused his sub-contractors to pay all the dues to his Sub-
contractor workmen. In case such payment is not made regularly by the
Contractor or his Sub-contractors, the OWNER will be in his right to make
such payments and deduct the same from the Contractor's progress
ISSUE
R0
payments. In case the OWNER becomes liable to pay any wages or dues
to the labour commissioner or to any Government agency under any of
the provisions of the Minimum Wages Act, Workmen's Compensation Act
or any other Applicable Law due to act or omission of the Contractor, the
OWNER may make such payments and shall recover the same from the
Contractor's bills.
The Contractor shall comply with and shall ensure that he/his Sub-
contractors comply with all the relevant labour laws applicable to his/ his
Sub-contractors employees, and shall duly pay and afford and cause his
Sub-contractors to pay and afford to them all their legal rights. The
Contractor shall require all such employees to obey all Applicable Laws
and regulations concerning safety at Work.
No work shall be carried out on the Site outside the normal working hours
or on the locally recognised Days of rest or local festivals / holidays,
unless:
a) Contract so provides,
ISSUE
R0
3.6 Permitting
3.6.1 Contractor shall obtain and maintain in effect all Applicable Contractor
Permits including other permits as per sub clause 2.2 of this Section
required in connection with Contractor's performance of its obligations
hereunder, including supply of Goods or performance of the Work
including (a) licenses to permit Contractor to do business in the
jurisdictions where the Work is to be performed, (b) design, engineering,
procurement, fabrication; construction; erection, testing and
ISSUE
R0
The Contractor shall indemnify and hold harmless OWNER and all
OWNER indemnified parties from any damages arising from and out of
the securing of, or failure to secure, such permits.
3.7 Co-operation
ISSUE
R0
3.7.2 Contractor shall not hinder the work of other contractors and sub-
contractors of OWNER, if any employed by or on behalf of OWNER at the
Plant Site or the Project Site, to introduce and store Materials in those
areas of the Plant Site and the Project Site under OWNER’s direct control
and shall cooperate to help them perform their respective services without
hindrance or disruption. The Contractor shall also acknowledge that he
works in congruence with requirements of lenders, other contractors,
Project off takers and other related parties, and provide them appropriate
information as and when required by them and not act as to harm the
interests of any of them.
3.8.1 Promptly and within fifteen (15) days after issuance of the Notice to
Proceed, Contractor shall submit to OWNER for approval the detailed list
of equipment and materials to be shipped, and, a reasonable time after
the Notice to Proceed, an overall shipping and forwarding plan for all
equipment and other items to be shipped from abroad to India in
connection with the supply of Goods or performance of the Work.
Contractor agrees that any material variation there from shall require the
written consent of OWNER. Contractor shall select the reputed shipping
companies for the transportation and delivery of the equipment. The
Contractor shall ship the Goods in classed vessels which are not more
than 15 (fifteen) years old and which is unconditionally seaworthy and as
declared by a reputed maritime agency as on the date of travel and for the
travel to its destination. Contractor shall give preference to Indian Flag
Vessels. OWNER will be the named importer of goods forming part of the
Plant and its spares and the rights and title therein shall pass to OWNER
outside India in accordance with clause no. 7.0 hereof.
3.8.2 At least three (3) days prior to the delivery of Goods to the transporters or
embarkation for India of each shipment of equipment or maintenance
tools / tackles or spares (other than Contractor’s Equipment) where
OWNER is to be named Importer, Contractor shall send a fax to OWNER
setting forth the following information concerning each such shipment:
ISSUE
R0
j) The name, flag and owner of the vessel if shipment is by sea or the
designation of aircraft if shipment is by air and
3.8.3 Within three (3) days after embarkation for India of each shipment or
before the Goods are received at the site in case of onshore Goods, as in
sub-clause 3.8.2 above, Contractor shall send to OWNER by courier (or
by certified airmail if OWNER so agrees) for information, the following
documents:
3.8.4 The Contractor shall be responsible for the timely clearance through
ISSUE
R0
customs of any part of the CHS Package or Works for all necessary
documentation and procedural matters associated therewith. The
Contractor shall be responsible for meeting the agreed contractual time
not withstanding any customs delays and will not be entitled to extend the
time for completion, it being the Contractor’s responsibility to allow
sufficient time for clearance through customs and the like.
3.8.5 The Contractor’s Scope of Work shall include obtaining all customs
clearance, completing all clearance formalities and handling at all ports of
all equipment and material of non–Indian origin including those where
OWNER is named importer, transportation to Site and transit insurance in
India from the respective Indian ports of disembarkation and / or the
respective Manufacturer’s Works upto the Project Site, receipt, handling,
and storage of all equipment and Material at Project Site and other items
necessary or desirable for the Project or the performance of the Work.
3.8.6 Contractor shall be responsible for examining all the shipment and notify
the OWNER’s Representative immediately of any damage, shortage,
discrepancy, etc. for the purpose of OWNER’s Representative’s
information only. The Contractor shall submit to the OWNER’s
Representative every week a report detailing all the receipts during the
week. However, the Contractor shall be solely responsible for any
shortages or damage in transit, handling and/or in storage and erection /
Commissioning of the equipment at Site till the CHS Package is finally
accepted by the OWNER.
3.8.7 All demurrage, wharfage and other expenses incurred due to delayed
clearance of the material or any other reason shall be to the account of
the Contractor.
3.8.9 All equipment / systems, maintenance tools and tackles and spares which
are stored at a location other than on the plant site shall be
b) Properly tagged and identified for the plant and segregated from
other Goods (to the extent reasonably possible).
ISSUE
R0
3.11.1 During the Contract Period, the Contractor shall arrange and pay for
construction water and power necessary for the performance of the Work.
Contractor has to make its own arrangement to tap sub surface water by
drilling bore wells. Installation of bore-wells, water pumping, storage and
its distribution to required places shall be arranged by Contractor.
However, the location of the bore-well shall be approved by the OWNER
before starting of bore well activity.
Cost of all connected Works such as, but not limited to, pumps, pipeline,
tanks, etc., are to be borne by the Contractor.
ISSUE
R0
Adequate sanitary facilities inside the Plant boundary for the use of
persons employed by the Contractor at the construction Site shall be
provided and maintained by the Contractor to the extent and in such
manner and at such places as shall be acceptable to the OWNER.
Separate Toilet facilities for both gents and ladies shall be provided.
The Contractor shall arrange for catering services for their staff and
workers deployed on the project Site.
3.12.2 Contractor shall provide a copy of Training Manual and other written
material to each of Owner’s personnel participating in the programme, all
of which shall be in the English language. Training provided by Contractor
to OWNER’s personnel pursuant to the Contract shall not be a condition
for any Warranty.
ISSUE
R0
3.14.1 The Contractor shall be responsible for keeping the entire area allocated
to him clean and free from accumulation of waste Materials,
rubbish/debris/etc. at all times during the period of Contract.
The Contractor shall cause all Sub-contractors, at all times to keep the
Site reasonably clean and otherwise free from accumulation of waste
materials, rubbish, other debris resulting from performance of the Work.
ISSUE
R0
3.14.3 The OWNER and the Contractor also recognize that the creation of dust
is inevitable in construction of a Project of this nature. The Contractor
shall take reasonable steps to ensure, by watering and such other
temporary means as are necessary, that dust caused by the Works is
minimised.
The Contractor shall confine all his field operations to those Works which
can be performed without subjecting the equipment and Materials to
adverse effects during inclement weather conditions, like monsoon,
storms, etc., and during other unfavourable construction conditions.
ISSUE
R0
After the completion of the Works, the Contractor shall remove from the
Site under the direction of the OWNER’s Representative the Materials
such as construction equipment, erection tools and tackles, scaffolding,
etc., not forming part of such Works, with the written permission of the
OWNER’s Representative. If the Contractor fails to remove such
Materials, within 7 (seven) days of issue of notice by the OWNER’s
Representative to do so then the OWNER’s Representative shall have the
liberty to dispose of such Materials and credit the proceeds thereof to the
account of the Contractor.
ISSUE
R0
ISSUE
R0
3.16.4 The Contractor shall also submit to the OWNER’s Representative on the
Seventh Day of every Month a manpower report of the previous Month
detailing the number of persons scheduled to have been employed and
actually employed skill wise and areas of employment of such labour.
ISSUE
R0
3.16.5 A brief weekly report shall also be prepared by the Contractor and
distributed as per Distribution Schedule in Section C12 of Volume-II of
Specifications, applicable for Monthly reports. This report shall be
submitted on every Monday. The following shall be clearly reflected in the
report.
• Anticipated delays in the schedule for the month and action plan to
overcome them.
3.17 Schedule
3.17.1 The Contractor shall provide to the OWNER/ PROJECT MANAGER for
approval within the time stated in clause 3.16.1 the programme for the
execution of the contract, showing (a) the sequence and timing of
activities by which the contractor proposes to carry out the work and (b)
the times by which the Contractor requires the OWNER to furnish any
OWNER’s inputs as set forth in the specifications, which as and when
approved shall form the Schedule.
3.17.2 Without prejudice and in addition to the foregoing the Contractor shall
prepare and furnish to OWNER updated monthly schedules of the Work
to be performed or Goods to be supplied, including a critical path
schedule.
3.17.3 Contractor shall be responsible for ensuring and performing the Work and
supplying the Goods in conformity with the Schedule as updated from
time to time. The Schedule shall be updated on a fortnightly basis as the
Work and supply of Goods progresses and shall include delay and
acceleration analyses where appropriate together with steps being taken
as per sub clause 9.5 of this section.
ISSUE
R0
3.17.5 The Schedule that is updated on a Monthly basis shall be done from the
basic schedules which together with the updated monthly Schedule shall
be available in a computer system to which the OWNER/OWNER’s
Representative will have access to facilitate the OWNER to drill down to
the various levels to independently analyse the relevant information. This,
however, does not take away the responsibility of the Contractor to fulfil
all his obligations under the Contract, including informing the
OWNER/OWNER’s Representative about the delays as also the expected
delays and the actual plans to overcome such delays.
Contractor shall note that the Project is conceived under Mega Power
Policy of Government of India. Contractor may consider all the tax
exemptions/benefits as applicable. Contractor shall be completely
responsible to obtain all such exemptions/benefits.
ISSUE
R0
(iii) The OWNER shall recover from the Contractor and / or adjust
from the Contract Price all taxes, duties, levies, charges, interest
and penalties and the like leviable and / or assessable on the
Contractor, its Sub-contractors or their employees but levied and /
or assessed on the OWNER as a representative assessee / agent
of the Contractor, its Sub-contractors or their employees, by all
municipal, local, state or national government authorities or any
other Government Instrumentality in connection with the Work and
supply of Goods in and outside of the Country.
(iv) Further the OWNER shall recover from the Contractor and / or
adjust from the Contract Price, simple interest at the rate of Short
term Prime lending Rate of State Bank of India from the date of
payment of all taxes, duties, levies, charges, interest and penalties
and the like leviable and / or assessable on the Contractor, its
Sub-contractors or their employees but levied and / or assessable
on the OWNER as a representative assessee / agent of the
Contractor, its Sub-contractors or their employees, by all
municipal, local, state or national government authorities or any
other Government Instrumentality in connection with the Work and
supply of Goods in and Outside of the Country where the Site is
located till the date of recovery and / or adjustment by the
OWNER.
ISSUE
R0
(iv) The Contract Price and other prices given in the Schedule F1 of
Volume II “Schedule of Prices” are based on the applicable tariff
as indicated by the Contractor in the Schedule of Prices. In case
this information subsequently proves wrong, incorrect or
misleading, the OWNER shall have no liability to reimburse/pay to
the Contractor the excess taxes, fees etc; if any finally
levied/imposed under the statutes except as provided in this
clause. However, if the taxes/fee levied/imposed are lower than
the amount indicated in the Schedule of Prices, the OWNER shall
be entitled to recover the difference from the Contractor.
ISSUE
R0
All custom duties and other levies, if any payable in India including any
state thereof or outside India, in respect of Contractor’s equipment which
may be imported by the Contractor for performing any portion of the
scope of Work, to be done in India and which are not envisaged to
become the property of the OWNER as per the terms of the Contract,
shall be to the Contractor’s account and the OWNER shall not be liable
for the same in any manner whatsoever.
ISSUE
R0
The OWNER shall pay, out of the Contract Price, any withholding tax
charged by any Government Instrumentality including the Government of
India or any Indian State Government on the Contract or the performance
of the Work or supply of Goods pursuant to or under the Contract. The
OWNER shall furnish to the Contractor appropriate documentation /
certificates/ challans evidencing payment of any such withholding tax.
3.19.2 Contractor shall be responsible for the security of the CHS Package and
the Site at all times and the Goods therein while the Work is being
performed or Goods are being supplied up to the earliest of:
3.19.3 Contractor shall do all things necessary or expedient to protect any and all
parallel, converging and intersecting electric lines and poles, highways,
access or other roads, bridges, waterways, railroads, sewer lines, natural
gas pipelines, drainage ditches, culverts, fences, walls, and water lines,
power or communication cables or lines and any and all physical property
of others, from damage resulting directly or indirectly from performance of
the Work or in supply and transport of Goods. Without limiting the
generality of the foregoing, Contractor shall maintain the access roads to
the Site and all access roads within the Site, in good repair and passable
at all times as well as proper drainage system. In the event that any such
physical property is damaged or destroyed in the course of the
performance of the Work or in supply and transport of Goods, Contractor
at his cost shall rebuild, restore or replace such damaged or destroyed
physical property to full satisfaction of OWNER.
3.19.4 Contractor shall provide, and shall ensure that its Sub-contractors
provide, proper and ample protection from damage or loss to the CHS
Package, the Site, equipment and construction equipment during its
performance of the Work.
ISSUE
R0
3.19.5 In the event that any equipment / system / materials supplied by the
Contractor are damaged or destroyed for any reason prior to acceptance
of such equipment / system / materials, Contractor shall rebuild, restore or
replace the equipment / system / materials, subject to and in accordance
with the Contract including Specifications. All costs irrespective of
reimbursement of claims from Insurance shall be to Contractor’s account.
3.20.1 Contractor shall pay all required royalties and license fees with respect to
proprietary rights, intellectual property licenses and agreements, and shall
procure, as required, the appropriate proprietary rights, intellectual
property licenses and agreements, for Materials, methods, processes,
systems and Services incorporated into the CHS Package or the Project
or otherwise relating to the performance of the Work and thereafter for the
purpose of operation & maintenance of the Plant.
3.20.2 In performing the Work, Contractor shall not incorporate into the CHS
Package, or use in connection with the CHS Package or the performance
of the Work, any Materials, methods, processes, systems or service that
involve the use of any confidential information, intellectual property or
proprietary rights that OWNER does not have the right to use or
incorporate or which may result in claims or suits against OWNER,
Contractor or any subcontractor arising out of claims of infringement of
any third party domestic or foreign patent rights, copyrights, other
proprietary rights, or intellectual property rights, licenses or agreements,
or applications for any thereof, or rights of use of confidential information.
3.22.1 At the time of each Scheduled Payment or portion thereof as per the
payment terms of Contract subject to Milestone Payment Schedule under
the Contract, the Contractor shall:
ISSUE
R0
ISSUE
R0
Any item not specifically described in the contract shall be provided by the
Contractor if the providing of such additional item is necessary in order for
Contractor to satisfy Performance Guarantees and the Warranties and to
make the plant complete in all respects and to make the Plant safely and
reliably operable and capable of performing efficiently and smoothly as
specified in the Contract. Work undertaken and additional items provided
pursuant to this sub-clause shall not give rise to any adjustment in the
Contract Price.
ISSUE
R0
3.24.2 Contractor shall arrange and ensure that all design, engineering,
fabrication, manufacture, construction, installation, commissioning, start-
up and testing work requiring certification from any Government
Instrumentality are properly certified.
3.26.1 The Work procedures that have to be used during the erection shall be
those, which minimize fire hazards to the extent practicable. Combustion
materials, combustible waste and rubbish shall be collected and removed
from the Site at least once each Day. Fuels, oils and volatile of flammable
Materials shall be stored away from the construction and equipment and
material storage areas in safe containers. Untreated canvas, paper,
plastic or other flammable flexible Materials shall not at all be used at Site
for any other purpose unless otherwise specified. If any such Materials
are received with the equipment at Site, the same shall be removed and
replaced with acceptable material before moving into the construction or
storage area.
3.26.2 Similarly corrugated paper fabricated cartons, etc. will not be permitted in
the construction area either for storage or for handling of Materials. All
such Materials used shall be of waterproof and flame resistant type.
All other Materials such as working Drawings, plans, etc. which are
combustible but are essential for the Works to be executed shall be
protected against combustion resulting from welding sparks, cutting
flames and other similar fire sources.
ISSUE
R0
3.26.4 The Contractor shall provide enough fire protection equipment of the
types and in enough numbers for the ware-houses, office, temporary
appropriate structures, labour colony area, etc. Access to such fire
protection equipment, shall be easy and be kept open at all times.
3.27.2 The OWNER shall have lien on such goods for any sum or sums, which
may at any time be due or owing to him by the Contractor, under, in
respect of or by reasons of the Contract. After giving a fifteen (15) Days
Notice in Writing of his intention to do so, the OWNER shall be at liberty to
sell and dispose of any such goods, in such manner as he shall think fit
including public auction or private treaty and to apply the proceeds in or
towards the satisfaction of such sum or sums due as aforesaid.
The OWNER will not be responsible for any claims which may arise from
the use or otherwise of any access route. The OWNER does not
guarantee the suitability or availability of any particular access route, and
will not entertain any claim and shall not be liable for any non-suitability or
non-availability for continuous use during construction of any such route.
ISSUE
R0
3.29.1 The Contractor shall bear all costs and charges for special or temporary
rights-of-way required by him for access to the Site. The Contractor shall
also provide, at his own cost, any additional facilities outside the Site
required by him for the purposes of the Works or Services. Contractor
shall carry out a detailed route survey for assessment of transportation of
heavy and large equipment to Site.
Should the Contractor consider that the moving of one or more loads of
CHS Package or Contractor’s Equipment is likely to damage any highway
or bridge unless special protection or strengthening is carried out, then
the Contractor shall before moving the load submit to the relevant
competent authority its proposals as to moving the load, including details
of the weight and other particulars of the load to be moved and execute its
proposal for protecting or strengthening and shall obtain permission from
such authorities for such movement.
ISSUE
R0
3.31 Insurance
3.32.1 Milestones
ISSUE
R0
ISSUE
R0
3.33.1 The Contractor shall ensure proper safety of all the workmen, Materials
and equipments belonging to him or to OWNER or to others, working at
the Site. The Contractor shall also be responsible for provision of all
safety notices and safety equipment required both by the relevant
legislations and the OWNER’s Representative, as he may deem
necessary.
The OWNER’s Representative shall have the right at his sole discretion to
inspect any such container or such construction plant/equipment for which
Material in the Container is required to be used and if in his opinion, its
use is not safe, he may forbid its use. No claim due to such prohibition
shall be entertained by the OWNER and the OWNER shall not entertain
any claim of the Contractor towards additional safety provisions /
conditions to be provided for / constructed as per OWNER’s
Representative’s Instructions.
3.33.4 All equipment used in construction and erection by Contractor or his Sub
contractors shall meet Indian and International Standards of safety and
where such standards do not exist, the Contractor shall ensure these to
be absolutely safe. All equipment shall be strictly operated and
maintained by the Contractor or his Sub contractors in accordance with
Manufacturer’s operation manual and safety instructions and as per
Guidelines and Rules of the OWNER in this regard.
ISSUE
R0
3.33.5 Periodical Examinations and all Test for all lifting/hoisting equipment and
tackles shall be carried out in accordance with the relevant provisions of
Factories Act 1948, Indian Electricity Act 2003 and all relevant Law/Rules
in force from time to time. A register of such examinations and Test shall
be properly maintained by the Contractor and will be promptly produced
as and when desired by OWNER’s Representative or by the Person
authorised by him.
3.33.6 The Contractor shall be fully responsible for the safe storage of his and
his Sub-contractor’s radioactive sources in accordance with Bhabha
Atomic Research Center/ Department of Atomic Energy Rules and other
applicable provisions. All precautionary measures stipulated by
BARC/DAE in connection with use, storage and handling of such material
will be taken by Contractor.
3.33.8 Where explosives are to be used, the same shall be used under the direct
control and supervision of an expert, experienced, qualified and
competent Person strictly in accordance with the Code of Practices/Rules
framed under relevant laws, rules and regulations not restricted to Indian
Explosives Act pertaining to handling, storage and use of explosives.
3.33.9 The Contractor shall provide safe working conditions to all workmen and
employees at the Site including safe means of access, railings, stairs,
ladders, scaffoldings, etc. The scaffoldings shall be erected under the
control and supervision of and experienced and competent Person. For
erection, good and standard quality of material only shall be used by the
Contractor.
3.33.10 The Contractor or his Sub contractors shall not interfere or disturb electric
fuses, wiring and other electrical equipment belonging to the OWNER or
other Contractors under any circumstance, whatsoever, unless expressly
permitted in Writing by the OWNER to handle such fuses, wiring or
electrical equipment.
3.33.11 Before the Contractor or his Sub contractors connects any electrical
appliances to any plug or socket belonging to the other Contractor or
OWNER, he shall:
ISSUE
R0
3.33.12 The OWNER’s Representative will not grant permission to connect until
he is satisfied that:
3.33.14 No repair work shall be carried out on any live equipment. The equipment
shall/must be declared safe by OWNER’s Representative and a permit to
Work shall be issued by OWNER’s Representative before any repair work
is carried out by the Contractor or his Sub contractors. While working on
electric lines/equipments whether live or dead, suitable type and sufficient
quantity of tools will have to be provided by Contractor or his
Subcontractors to electricians/workmen/officers.
3.33.15 The Contractor shall employ necessary number of qualified, full time
Electricians/Electrical Supervisors to maintain his temporary electrical
installations.
3.33.16 The Contractor employing more workmen than specified under Factories
Act 1948 whether temporary, casual, probationer, regular or permanent or
on Contract, shall employ at least required numbers of full time officers
exclusively as Safety Officer to supervise the safety aspects of the
equipment and workmen who will coordinate with the Project Safety
Officer and OWNER’s Representative. In case of Work being carried out
through Sub-contractors, the Sub-contractor’s workmen/employees will
also be considered as the Contractor’s workmen/employees for above
purpose.
ISSUE
R0
3.33.17 In case any accident occurs during the construction/ erection or other
associated activities undertaken by the Contractor thereby causing any
minor, major or fatal injuries to his employees due to any reason,
whatsoever, it shall be the responsibility of the Contractor to promptly
inform the same to the OWNER’s Representative in prescribed form and
also to all the authorities envisaged under the Applicable Laws.
3.33.18 The OWNER’s Representative shall have the right at his sole discretion to
stop the Work or supply of Goods, if in his opinion the Work or supply of
Goods is being carried out in such a way that it may cause accidents and
endanger the safety of the persons and/or property, and/or equipment. In
such cases, the Contractor shall be informed in Writing about the nature
of hazards and possible injury/accident and he shall comply with the
instructions of the OWNER’s Representative including removal of
shortcomings promptly. The Contractor after stopping the specific Work
or supply of Goods, can, if felt necessary, appeal against the order of
stoppage of Work within 3 (three) Days of such stoppage of Work and
OWNER’s decision in this respect shall be conclusive and binding on the
Contractor.
3.33.19 The Contractor shall not be entitled for any damages/compensation for
stoppage of Work or supply of Goods due to safety reasons as provided
in clause 3.33.18 above and the period of such stoppage of Work will not
be taken as an extension of time for completion of Work or supply of
Goods and will not be the ground for waiver of levy of Liquidated
Damages,
3.33.20 The Contractor and his Sub contractors shall follow and comply with all
Safety Rules, relevant provisions of Applicable Laws pertaining to safety
of workmen, employees, CHS Package and equipment as may be
prescribed from time to time without any demur, protest or contest or
reservation.
Contractor shall, and shall cause all Sub-contractors to, implement and
administer a safety program for the CHS Package, subject to the
approval of the OWNER (which shall not be unreasonably withheld),
which shall include:
(i) All persons employed by the OWNER, Contractor and its Sub-
contractors and OWNER’s other Contractors and their Sub-
contractors in connection with the Work or supply of Goods or
OWNER and its Contractors and Sub-contractors (whether in
the performance of their obligations under the Contract or
otherwise) and all other persons who may be affected by the
performance of the Work or supply of Goods or any of such
persons.
(ii) All supplies used in connection with the CHS Package and all
equipments to be incorporated into the CHS Package,
whether in storage on or off the Site under the care, custody
or control of OWNER, Contractor, any Sub-contractor or
OWNER’s other Contractors and their Sub-contractors.
All Goods supplied under the Contract shall have their origin in the eligible
countries and territories.
ISSUE
R0
For purposes of this Clause, “origin” means the place where the Goods
where mined, grown, produced or manufactured and from where services
are supplied. Goods are produced when, through manufacturing,
processing, or substantial and major assembly of components, a
commercially recognised new product results that is substantially different
in basic characteristics or in purpose or utility from its components.
3.34.2 Packing
The Contractor wherever applicable shall, after proper painting, pack and
create all equipment for sea shipment in a manner suitable for export to a
tropical, humid climate region in accordance with internationally accepted
export practices and in such manner so as to protect it from damage and
deterioration in transit by road, rail and or sea and during storage at the
Site till the time of erection. The Contractor shall be held responsible for
all damages due to improper packing.
3.34.3 Spares
(i) All the spares for the equipment under the Contract provided by
the Supply Contractor will strictly conform to the Specifications.
(ii) All the mandatory (essential) spares covered under the Contract
shall be delivered by the target date for completion of delivery of
the mandatory spares at Project Site as per agreed despatch
schedule but in no case earlier than 2 (two) Months prior to
scheduled Date of completion of CHS Package.
ISSUE
R0
(iv) The quality plan and the inspection requirement finalised for the
main equipment will also be applicable to the corresponding
spares.
(v) The Supply Contractor will provide the OWNER with the
manufacturing Drawings, catalogues, assembly Drawings and any
other information Document required by the OWNER so as to
enable the OWNER to identify the recommended spares and
identify the quality thereof. Such details will be furnished to the
OWNER as soon as they are prepared but in any case not later
than 6 (six) Months prior to commencement of manufacture of the
corresponding main equipment and within 30 (thirty) Days from
the date of request by the OWNER. The OWNER will have
access to manufacturing drawings to determine the need and
quality of spares.
(vi) The offer for recommended spares shall be valid upto 12 (twelve)
Months after receipt of above information/Documents.
(viii) The Supply Contractor will provide the OWNER with all the
addresses and particulars of his Sub-suppliers while placing the
order on vendors for items/components/equipment covered under
the Contract and will further ensure with his vendors that the
OWNER, if so desires, will have the right to place order for spares
directly on them on mutually agreed terms based on offers of such
vendors.
ISSUE
R0
ISSUE
R0
(x) The Supply Contractor will indicate the delivery period of the
spares, which the OWNER may procure in accordance with this
clause.
4.0 SUB-CONTRACTORS
ISSUE
R0
4.1.2 The Contractor shall be solely liable for the performance of the
subcontract work by his Subcontractors, for any and all liabilities arising
there from and shall hold the Owner/Project Manager indemnified and
harmless there against. None of the subcontractors of the Contractor
shall have any contractual relationship with the Owner, nor shall they be
entitled to raise any claims against the Owner/Project Manager. All the
subcontracts of the Contractor shall be subject to assignment to the
Owner upon his written request.
4.1.3 Contractor shall provide to OWNER un-priced copy of all Sub Contracts
and other such information concerning the Subcontractors as OWNER
may from time to time reasonably request and shall ensure that each
Subcontract contains provisions in all material respects not less stringent
than the provisions of the Contract and shall include terms and provisions
required to be included pursuant to the Contract. In the event of
termination of the Contract under clause no. 15.2 or clause no. 16.2,
Contractor shall forthwith deliver to OWNER a copy of each Subcontract.
4.1.4 Each Subcontract shall contain a price list (which shall be binding to the
extent reasonably feasible for a period of three years from the date of
Take-over) covering all recommended spare parts and replacement parts
pertaining to the subject matter of such Subcontract. Each Subcontract
shall contain a certification by the Subcontractor analogous to
Contractor's specific indemnification and patent and copyright
indemnification as per clause no. 17.2 and 17.3.
4.1.5 Contractor shall supervise and direct the Work of all Subcontractors and
shall be responsible for all supply of Goods, design; engineering;
procurement; manufacturing; transportation; delivery; fabrication;
construction; erection; installation; commissioning; start-up, Initial
Operation, Reliability (trial) Operation and Tests before Taking over
including Performance Tests; maintenance, repair; methods; techniques;
sequences and procedures of and for co-ordinating the work of
Subcontractors.
ISSUE
R0
4.1.8 Contractor shall be solely responsible for paying each Subcontractor and
any other Person to whom any amount is due from Contractor for
Services, equipment, construction, equipment, Materials or supplies
otherwise related to or in connection with the CHS Package or the Work
or supply of Goods. Contractor shall take all reasonable steps and actions
to ensure that such Services, equipment, construction equipment,
Materials and supplies and the like have been or will be received,
inspected and approved and that such Services have been or will be
properly performed.
4.2.1 Contractor shall, for the protection of OWNER, obtain from all
Subcontractors, including all vendors, and Manufacturers of equipment,
all the required Warranties on all Goods and other items used in
connection with the performance of the Work or incorporated in or forming
part of the CHS Package (other than minor items), and such Warranties
shall not be amended, modified or otherwise discharged without the prior
written consent of OWNER. Warranties shall be in the joint names of
OWNER and Contractor. Such Warranties shall nevertheless and at all
times meet the minimum requirements stipulated in the Contract. Also the
liability on account of Latent Defects, which are applicable to the
Contractor, shall be similarly applicable to all the Sub-contractors of
Contractor.
ISSUE
R0
4.2.2 Contractor shall obtain from each of approved Subcontractor and each
Subcontractor that is a party to, a Subcontract pursuant to which
engineered equipment is to be provided, Warranties, which cover a period
of not less than 24 (twenty four) Months from the date of Take-over of the
CHS Package. Contractor shall obtain additional Warranties if required
by the Contract including Specifications.
4.2.4 OWNER shall be entitled to receive all benefits and proceeds (including
damages and rebates) paid by or on behalf of any subcontractor pursuant
to any Warranty. Neither Contractor nor its Subcontractors, nor any
person under the control of either thereof, shall take any action which
could release, void, impair or waive any Warranty on equipment,
Materials, items, Goods or Services relating to the CHS Package or the
Work.
4.2.5 Nothing in this clause shall derogate from the obligations of Contractor to
provide the Guarantees and Warranties described in, and to comply with
the provisions of clause no. 11.0 and 12.0 of these General Conditions of
Contract.
4.2.6 Contractor shall, on its part based on, professional judgement enforce all
Warranties provided by the Subcontractors to the fullest extent thereof till
such time they are transferred to the OWNER pursuant to sub-clause
4.2.7 below.
ISSUE
R0
4.2.9 Contractor shall require all Subcontractors to release and waive any and
all rights of recovery against OWNER, the Financing Parties and each of
their promoters (including the directors, officers and shareholders of each
such promoter), affiliates, subsidiaries, employees, successors, permitted
assigns, insurers and underwriters, and against Contractor and all other
Subcontractors which the releasing Subcontractor may otherwise have or
acquire, in or from or in any way connected with any loss covered by
policies of insurance maintained or required to be maintained pursuant to
this the Contract (other than third party liability insurance policies) or
because of deductible clauses in or inadequacy of limits of any such
policies of insurance. Contractor shall further require all Subcontractors
to include in all policies of insurance maintained by the Subcontractors
clauses providing that each underwriter shall release and waive all of its
rights of recovery, under subrogation or otherwise, against OWNER, the
Financing Parties and each of their promoters, affiliates, subsidiaries,
employees, successors, permitted assigns, insurers and underwriters,
and against Contractor and all other Subcontractors.
4.2.10 OWNER shall not be deemed by virtue of the Contract to have any
contractual obligation to or relationship with any Subcontractor.
5.1 Requirements
ISSUE
R0
5.1.1 Contractor shall perform all inspection, expediting and quality surveillance
as may be required for performance of the Services. Contractor’s
responsibilities under this sub-clause shall include, without limitation,
inspecting all supplies, Materials and equipment that comprise or will
comprise the CHS Package or that are to be used in performance of the
work.
5.1.2 The Contractor shall carry out the inspection and quality control aspects
as set out in Schedule F10 and Section C3 of the Technical Specification.
In the event the OWNER establishes that the Contractor is not carrying
out all such inspection and quality control aspects, the OWNER has the
right to appoint at Contractor’s cost third party inspection agencies (such
as Lloyds Register of Shipping / Bureau Veritas).
5.1.3 Contractor / Contractor’s third party inspection agency shall perform such
detailed inspection of all work in progress at intervals appropriate to the
stage of design, engineering, procurement, fabrication, construction,
erection, testing, Commissioning, start-up or Tests before Provisional
Acceptance as is necessary to ensure that such work is proceeding in
accordance with the Contract, the Documents, Applicable Laws,
Applicable Permits, Good Engineering Practices and Prudent Electricity
Industry Practice and to protect OWNER against defects and deficiencies
in such work (including any which would diminish or void the ability of
OWNER or Contractor to realise upon any manufacturer’s or supplier’s
warranty or under any applicable insurance coverage). On the basis of
such inspections, Contractor shall keep OWNER/PROJECT MANAGER
continuously informed of the progress and quality of all work, whether
performed by Contractor or any Sub-contractor, and shall provide
OWNER/PROJECT MANAGER with Written reports which shall contain
notwithstanding anything to the contrary contained herein defects and
deficiencies revealed through such inspections and of measures
proposed by Contractor to remedy such defects and deficiencies.
OWNER or OWNER’s Representative shall have the option, at OWNER’s
expense, of being present at all such inspections, and the Contractor shall
give notice of all such inspections agreed.
5.1.4 In the event that the progress and quality of the work is not proceeding in
accordance with the Contract, OWNER or OWNER’s Representative shall
be entitled to make recommendations to Contractor or any Sub-contactor
for the purpose of remedying such failure and any such defects and
deficiencies or variances. Any inspection performed or not performed by
OWNER/PROJECT MANAGER hereunder shall not be a waiver of any of
Contractor’s obligations under the Contract or be construed as an
approval or acceptance of any of the work or Services hereunder or
absolve the Contractor in any manner of its liabilities, responsibilities and
obligations under the Contract.
ISSUE
R0
5.1.5 The Contractor shall, where required give due notice to the
OWNER/OWNER’s Representative whenever such work is ready before
covering up or putting out of view. The OWNER’s Representative shall
then either carry out the inspection, examination, measurement or testing
or notify the Contractor that it is considered unnecessary.
5.1.6 The OWNER’s Representative shall have the right to re-inspect any work
though previously inspected and approved by him at the Site, before and
after the same are erected. If by the above inspection the OWNER’s
Representative rejects any work, the Contractor shall make good for such
rejections either by replacement or modifications/ repairs as may be
necessary to the satisfaction of the OWNER’s Representative.
5.1.7 The OWNER and the OWNER’s Representative shall be entitled, during
design, engineering, manufacture, fabrication and preparation at any
places where work is being carried out, to inspect, examine and test the
materials and workmanship, and to check the progress in the
performance of the work at no extra cost to the OWNER. The Contractor
shall give all reasonable facilities and assistance, including access to
Documents to carry out such inspection, examination, measurement and
testing. All inspection and tests shall be in line with approved Inspection &
Test Plans and OWNER / OWNER’s Representative shall carry out
necessary inspection as per the Contract. Should any inspected work or
service fail to conform to the Contract, the OWNER/PROJECT
MANAGER may reject such work or service and the Contractor shall
either replace or make alterations necessary to meet Contract
requirements free of cost to the OWNER. The OWNER’s right to inspect,
test, and where necessary, reject the work or service shall in no way be
limited or waived by reason of any part of the work having previously been
inspected, tested and passed by the OWNER or OWNER’s
Representative.
5.1.8 The Contractor shall agree, with the OWNER / OWNER’s Representative
about the time and place for the testing of any equipment / Materials and
other parts of the work as specified in the Contract. The OWNER /
OWNER’s Representative shall give the Contractor not less than 24
(twenty four) hours’ notice of his intention to attend the Tests. The
Contractor shall provide sufficient suitably qualified and experienced staff
to carry out the Tests specified in the Contract. The Contractor shall
present to the OWNER/OWNER’s Representative the calibration
certificates of all the testing and measuring instruments proposed to be
used for carrying out the Tests. In case the OWNER/OWNER’s
Representative is not satisfied with the calibration certificates, the
Contractor shall arrange to get the concerned instrument(s) recalibrated
to the satisfaction of the OWNER/OWNER’s Representative.
ISSUE
R0
5.1.9 If the OWNER’s Representative does not attend at the time and place
agreed, or if the Contractor and the OWNER’s Representative agree that
the OWNER’s Representative shall not attend, the Contractor may
proceed with the Tests, unless the OWNER’s Representative instructs the
Contractor otherwise. Participation by OWNER or OWNER’s
Representative in or their absence from or failure to participate in any
Tests (other than the Performance Tests) shall not relieve or absolve the
Contractor from any Guarantee or Warranty or obligations of Services
under or in pursuance of the Contract.
5.2 Rejection
ISSUE
R0
6.0 INSURANCE
Offshore Supply Contractor shall, at its sole cost, on behalf of and in the
name of OWNER, take Insurance cover for 110 (one hundred and ten) %
of the full replacement value (including all taxes, duties, levies and all
other costs) against Marine and all other risks (including terrorists act,
water and mine, SRCC) from Free on Board at the port of despatch upto
unloading at the port of destination in India in respect of all Offshore
supplies.
ISSUE
R0
(ii) The Onshore Service Contractor shall also arrange for Insurance
against transit and all risks (including terrorists act, war and mine,
SRCC) in the name of OWNER in respect of off-shore Materials
including Goods and equipment from unloading at port of
destination in India until delivery and receipt at site including off-site
storage of the Materials on OWNER’s behalf for 110 (one hundred
and ten) % of the replacement value (including all taxes, duties,
levies and all other costs).
(iii) The Onshore Service Contractor shall also arrange for Insurance
against transit and all risks (including terrorists act, war and mine,
SRCC) in the name of OWNER in respect of 110 (one hundred and
ten)% of the value of onshore supplies from Ex-works until delivery
and receipt to site.
All construction equipment shall be brought to and kept at the Site at the
sole cost, risk and expense of Contractor, and OWNER shall not be liable
for any loss or damage thereto, except to the extent any such loss or
damage is caused solely by the OWNER. Contractor, at his sole
discretion, may maintain adequate, appropriate and prudent insurance
with respect to such construction equipment.
Contractor shall maintain with respect to the Work to be done under the
Contract, in each applicable jurisdiction, all statutory insurance benefits
and other insurance required by law including, without limitation,
unemployment Insurance.
Contractor shall at its sole expense, in the joint names of OWNER and
Contractor prior to the commencement of any Work on the Site, pursuant
to the Contract, obtain adequate insurance, against liability for damage or
death of or personal injury occurring before Final Performance
Acceptance to any Person (including any employee of the insured parties)
or to any property (other than property forming part of the CHS Package)
due to or arising out of the performance or non performance of the Work
by Contractor or any Sub-contractors and other third party liabilities on
account of obstruction, loss of amenity, trespass, nuisance or advertising
pursuant to the Contract.
Contractor shall, at its sole expense and in the joint names of OWNER
and Contractor, shall maintain automobile liability insurance covering all
owned non-owned and hired automobiles, trucks and other vehicles used
by Contractor or its Subcontractors in connection with the Work.
Contractor shall, at its sole expense, insure and shall maintain Insurance
as required by Indian and all other Applicable Laws for all actions, suits,
claims, demands, costs, charges and expenses arising in connection with
the death of or injury to any person employed by Contractor or its
Subcontractors for the purpose of the performance of the Work or supply
of Goods.
ISSUE
R0
If Contractor shall fail to effect and keep in force the Insurance for which it
is responsible under the Contract including clause no. 6.0 hereof,
OWNER may effect and keep in force any such Insurance, and pay such
premiums as may be necessary for that purpose, and from time to time,
after issuance of a reimbursement request therefor accompanied by
relevant supporting documentation, deduct the amount so paid by
OWNER from any amounts due or which may become due to the
Contractor under the Contract.
ISSUE
R0
The Insurance coverage referred to in this clause no. 6.0 shall be set forth
in full in the respective policy forms, and the foregoing descriptions of
such policies are not intended to be complete, nor to alter or amend any
provision of the actual policies and in matters, if any, in which the said
description may be conflicting with such instruments, the provisions of the
policies of the Insurance mutually agreed by the Parties shall govern;
provided, however, that neither the content of any Insurance policy or
certificate nor OWNER’s approval thereof shall relieve the Contractor of
any of its obligations under the Contract.
ISSUE
R0
a) Between the date hereof and the earlier of (i) the Final Performance
Acceptance and (ii) the Date of Termination of this Agreement,
Contractor shall bear the complete risk of loss, destruction or
damage (including deterioration in quality) of or to the equipment or
CHS Package, and all equipment and components thereof
(including all temporary equipment, Materials and other items and
including equipment, construction equipment and other items that
are purchased for permanent installation in or for use during
construction of the CHS Package or equipment regardless of
whether OWNER has title thereto or otherwise in connection with
the performance of the Work or supply of Material), arising from any
cause whatsoever.
b) At all times after the Provisional Take Over, the OWNER shall bear
the complete risk of loss, destruction or damage (including
deterioration in quality) of or to the CHS Package, and all
components thereof, arising from any cause whatsoever save and
except where covered by any Guarantee and Warranty and Latent
Defects and clause (a) above.
ISSUE
R0
Contractor further releases, assigns and waives any and all rights or
recovery against OWNER, the Financing Parties and their respective
assigns, subsidiaries, affiliates, parent companies, employees, insurers
and underwriters, and against other contractors of OWNER and their
subcontractors which Contractor may otherwise have or acquire in or from
or in any way connected with any loss covered by the policies of
Insurance maintained or required to be maintained by Contractor pursuant
to this Contract (other than third party liability insurance policies) or
because of deductible clauses in, or inadequacy of limits of, any such
policies of Insurance.
ISSUE
R0
Except to the extent prohibited by law and except for Insurance coverage
described in clause no. 6.2.2 above, all Insurance coverages referred to in
this clause no. 6.0 shall name OWNER, the Financing parties and their
respective assignees, subsidiaries, affiliates and parent companies as
additional named insured and sole loss payees, as their respective
interests may appear.
The required coverage referred to and set forth in this clause no. 6.0 shall
in no way affect or limit Contractor's liability with respect to performance of
the Work or any obligation under the Contract.
6.3.9 Contractor shall bear the risk of loss pursuant to clause 6.3.4 hereof.
However all the Insurance policy mentioned in this clause shall be
administered and managed by the Contractor and shall be effected from
the Commencement Date of contract and thereafter shall operate from the
time the relevant property leaves the premises of the manufacturers in the
country of origin, and shall continue during the ordinary course of transit
and during storage on or off the Plant Site, if any, erection and
Commissioning until the date on which OWNER takes over the care,
custody and control of the CHS Package, to the exclusion of Contractor.
The OWNER retains the right to take any or all the above Insurance
covers at his own cost. In case the OWNER exercises this option of
taking the above Insurance covers in his own name, the cost of
Insurance, and all other consequential costs incurred by Owner shall be
deducted from the Contract Price.
6.3.12 The amount of claim shall be paid to the OWNER. The OWNER at his
discretion may authorise the underwriters to pay the same directly to the
Contractors from time to time for settlement of claims related to repairs /
replacement.
6.3.13 The Contractor shall include the names of Financing Parties as indicated
and required by OWNER in the respective Insurance coverage mentioned
above.
7.0 TITLE
7.2 Ownership of the Goods procured in the country where the Site is located
shall be transferred to the OWNER when the Goods are despatched by
the Supply Contractor thereof after the necessary inspection and
verification and quality clearances subject to the following:
8.0 FOSSILS
ISSUE
R0
All fossils, coins, articles of value or antiquity, and structures and other
remains or things of geological or archaeological interest discovered on
the Site shall (as between the parties) be the property of the OWNER.
The Contractor shall take reasonable precautions to prevent his staff,
labour or other persons from removing or damaging any such article or
thing. The Contractor shall, immediately upon discovery of such article or
thing, advise the OWNER or OWNER's Representative.
The CHS Package shall be completed and shall have successfully passed
the Tests before Provisional Take Over within the time for completion as
set forth in the specification. Failing which the Contractor shall pay to the
OWNER for such delay in Completion (the “Delay Liquidated Damages”).
Payment of any Delay Liquidated Damages shall not affect or prejudice in
any way or manner OWNER’s right to terminate the Contract nor shall any
termination of Contract prejudicially affect the OWNER’s right to recover
any accrued Delay Liquidated Damages or release the Contractor from
any obligation for payment thereof.
9.4.1 The Contractor may apply for an extension of the time for completion if he
is or will be delayed before the time for completion by any of the following
causes:
9.4.2 As per the requirement of sub-clause 3.16.2 (or such other period as may
be agreed by the OWNER / OWNER's Representative), the Contractor
shall submit an application with full supporting details together with any
other notice required by the Contract and relevant to such cause. Except
that, if the Contractor cannot submit all relevant details within such period
because the cause of delay continued for a period exceeding 5 (five)
Days, the Contractor shall submit interim details at intervals of not more
than 5 (five) Days (from the first Day of such delay) and full and final
supporting details in support of his application within 7 (seven) Days of
the date of ceasure of such delay.
ISSUE
R0
9.5.1 If, at any time, the Contractor's actual progress falls behind the Schedule
in any manner or it becomes apparent that it will so fall behind, the
Contractor shall submit to the OWNER / OWNER's Representative a
revised programme taking into account the prevailing circumstances. The
Contractor shall, at the same time, notify the OWNER / OWNER's
Representative of the steps being taken to expedite progress, so as to
achieve completion within the time for completion stipulated under the
Contract, including in particular the Schedule and the Guaranteed
Completion Dates. The Contractor may also be asked to modify the plan,
as a result of the changed circumstances due to delay, in order to
complete the Work in time.
9.5.2 If any steps taken by the Contractor in meeting his obligations under this
sub clause no. 9.5 cause the OWNER to incur any additional costs, such
costs shall be recoverable from the Contractor by the OWNER, and may
be deducted by the OWNER from any monies due, or that may become
due, to the Contractor under the Contract or otherwise.
9.6.1 The OWNER may at any time instruct the Contractor to suspend progress
of part or all of the Work or supply of Goods. During suspension, the
Contractor shall protect, store and secure such part or all of the Work or
Goods against any deterioration, loss or damage or other losses.
9.6.2 If the Contractor suffers delay and / or incurs Cost in following the
OWNER I OWNER's Representative's instructions under clause no. 9.6
hereto and in resumption of the Work or supply of Goods, the Contractor
shall give notice to the OWNER's Representative, with a copy to the
OWNER. After receipt of such notice the OWNER I OWNER's
Representative shall proceed to agree or determine:
9.6.3 The Contractor shall not be entitled to extension of time for, or payment of
the costs incurred in, making good any deterioration, defect or loss
caused by faulty design, workmanship or Materials, or by the Contractor's
failure to take the measures specified in clause no. 9.6.1 of these General
Conditions of Contract.
ISSUE
R0
11.1.2 The Liquidated Damages payable by Contractor to the OWNER for delay
in achieving Provisional Acceptance by the Guaranteed Completion Date
of each sub-system of the CHS Package which is 0.5% of the Contract
Price for every week or part thereof (the “Liquidated Damages for Delay”).
ISSUE
R0
ISSUE
R0
11.4 In view of the foregoing, the Contractor accepts and agrees to such
Liquidated Damages as liquidated damages and shall not dispute such
Liquidated Damages in any proceedings under the Contract.
ISSUE
R0
12.0 WARRANTIES
ISSUE
R0
d) All information, averments and data submitted, starting from the Bid
and upto end of Contract Period, to the OWNER/PROJECT
MANAGER is correct and true. If at any later date, any of the
aforesaid information, averment and data submitted is found to be
false or incorrect, in part or in whole, the Contractor would be
treated as a Contractor in Default as per Clause 15.0 and all
consequences shall apply accordingly. The OWNER would also be
entitled to recover any cost or damages from Contractor including
through encashment/forfeiture of Contract Performance Bank
Guarantee and deductions from amounts payable to the Contractor.
12.2.1 The Warranty Period shall be Twelve (12) Months from date of Provisional
Take Over of the CHS Package.
ISSUE
R0
The above Warranties are however subject to the provision that should
any scheduled inspection of a particular item of CHS Package fall due
within the above Warranty Periods and any part or component thereof is
scheduled to be refurbished or replaced in accordance with the Operation
and Maintenance Manual, then such parts are warranted only up to the
date of such scheduled replacement or refurbishment. The refurbished or
newly replaced parts shall thereafter be covered for under the terms and
conditions agreed by the Parties with respect to such replaced or
refurbished parts.
The Latent Defects Liability Period for the CHS Package shall be thirty-six
(36) months from the expiry of the Warranty Period for the CHS Package.
Any such Latent Defects identified during the appropriate Latent Defect
Liability Period shall be corrected and made good by the Contractor at his
sole Cost.
12.2.3 OWNER shall give notice of observed defects promptly following such
observation. Such notice must be given at the latest within thirty (30) Days
from the end of the appropriate Warranty Period or Latent Defect Liability
Period as applicable.
Warrantees and Latent Defect Liability under the contract shall survive
any termination of the Contract in respect of any part of the work for which
OWNER has paid Contractor.
ISSUE
R0
In case of defective parts which are not repairable at Site but are essential
for commercial operation of the equipment, Contractor and the OWNER’s
Representative shall mutually agree to a program of replacement or
renewal which will minimise interruptions to the maximum extent, in the
operation of the equipment and the CHS Package and the Contractor
shall expeditiously provide necessary parts for replacement before shut
down planned.
If the remedying of any defect or damage is such that it shall affect the
performance of the CHS Package, the OWNER may require that Tests
before Final Take Over to be repeated to the extent necessary. The
requirement shall be made by notice within 30 (thirty) Days after the
defect or damage is remedied. Such Tests shall be carried out in
accordance with procedures set forth in Section C5 of the General
Conditions of Contract.
The Contractor shall have the right of access to all parts of the CHS
Package and to records of the working and performance of the CHS
Package, except as may be inconsistent with any reasonable security
restrictions imposed by the OWNER.
The Contractor shall, search for the cause of any defect, under the
direction of the OWNER / OWNER's Representative at Contractor’s cost.
13.1.1 The Contract Price for the entire scope of Work and supplies in line with
the Tender Documents shall be fixed, on lump sum basis and will remain
firm throughout the Contract Period.
ISSUE
R0
(i) Contract Price for the Offshore Supply Contractor shall be the CIF
Price of supplies from outside the OWNER's Country and shall be
inclusive of, inter alia, design and detailed engineering which are
integral to these items and their performance, essential
(Mandatory) spares, maintenance tools and tackles, marine
Insurance, freight, packing and forwarding and all taxes, duties
and other statutory levies in respect thereof as detailed in the
Tender Documents.
(ii) Contract Price for the Onshore Supply Contract shall include the
Ex-Works price of supplies including essential spares,
maintenance tools and tackles from the OWNER's Country and
shall be inclusive of, inter-alia, transportation, packing and
forwarding and all taxes duties and other statutory levies and the
like payable in respect thereof as detailed in the Tender
Documents.
(iii) Contract Price for the Onshore Services Contract shall be inclusive
of clearing unloading/loading, transportation, transit Insurance and
custom clearance of offshore supplies, receiving at Site of all
Goods, unloading, storage, preservation, Insurance in respect of
onshore supplies from Ex Works to Site and for Works up to Final
Take Over of the CHS Package, training, erection, testing,
installation, Commissioning, Reliability Operation and satisfactory
completion of the Tests before and upto the date of Final Take
Over within OWNER's Country and all taxes, duties and other
statutory levies and the like payable in respect thereof as detailed
in the Tender Documents.
(iv) The Contract Price for each Contract shall be as per "Schedule of
Prices" Schedule F1 of Volume - II. The rates of taxes and duties
as applicable as on 15 (fifteen) Days prior to closing date for
submission of Price Bid shall be considered for the purpose and
shall be indicated in the Schedule F1 of Volume-II.
(v) The total price is the sum of all the prices of aforementioned
Contracts and this total price shall be in respect of supplies, work
forming part of Works, and all other obligations including
Warranties, Guarantees, Performance Guarantees, Insurance
covered in the Specifications subject to other terms and conditions
in the Contract and particularly clause no. 3.18
ISSUE
R0
13.1.3 The Contract Price is not subject to any escalation and variation in price
except as otherwise provided, it being a fixed price Contract. Any
variation in Foreign Exchange during the Contract Period will be to
Contractor’s account.
13.1.4 The Contractor shall pay all taxes, duties and levies in consequence of his
obligations under the Contract, and the Contract Price shall not be
adjusted for such Costs, taxes, duties and levies except as may otherwise
be expressly stated in clause no. 3.18 of the General Conditions of
Contract;
13.2.1 Contractor shall furnish to OWNER within 14 (fourteen) Days from the
date of execution of Contract Agreement, a Contract Performance Bank
Guarantee (the “Performance Security”) as a Performance Security for
due and faithful performance of its obligations under Contract, as
mentioned in Instructions to Bidders in format of Information Form CP (in
Section A3), for an amount equivalent to 15 (fifteen) % of the Contract
Price. The validity of the Performance Security shall be up to end of
Warranty Period plus claim period of six Months. The charges for counter
guaranteeing of Performance Security, if any, shall be borne by and be to
Contractor’s account. The CPG shall be in the form of an irrevocable bank
guarantee and issued by a bank meeting the following requirements:
Or
Or
13.2.2 In case Contractor fails to fulfil its obligations under Contract, the
proceeds of Performance Security may be appropriated by OWNER as
part compensation for any loss resulting from Contractor's failure to
perform and fulfil the various obligations concerning supply of Goods and
Work under Contract without prejudice to any of the rights or remedies to
which the OWNER may be entitled under the Contract or otherwise in law.
13.2.4 Contractor shall extend the validity of the Performance Security suitably, if
it is required, due to delay in Acceptance of CHS Package for reasons
attributable to Contractor, at its own cost well in time and in any case at
least 60 (sixty) days before the expiry of the period of validity thereof.
ISSUE
R0
13.3.2 Documentation and Bank Guarantee for Advance Payment shall include:
Or
Or
13.3.3 All further payments under the Contract shall be made as stipulated in the
Contract.
For supply of Goods, the payments shall be linked with the despatch of
Materials and shall only be made after production of all despatch
Documents in case of supplies of non Indian origin as per the relevant
Contract conditions which will, inter alia, include 3 original Bills of Lading
for CIF supplies and the equipment Material Despatch Clearance
certificate issued by the OWNER/OWNER’s Representative after
inspection if applicable.
For supply of Goods, the payment shall be linked with the despatch of
Materials and shall only be made after production of all despatch
Documents and Material Despatch Clearance Certificate issued by the
OWNER/OWNER’s Representative after inspection if applicable.
ISSUE
R0
ISSUE
R0
ISSUE
R0
13.3.7 Essential spare, and maintenance tools and tackles price as per items
of schedule- F14,F8,F9 of Volume-II
ISSUE
R0
Based on the terms of payment as per clause 13.3 and agreed Work and
supply schedule prepared in line with detailed network schedule, payment of
Contract Price shall be subject to limits of Milestone Payment Schedule and
the following in respect thereof.
b) Later of (i) accomplishment of a milestone and (ii) the date fixed for
accomplishment of such a milestone as set out in the Milestone
Payment Schedule.
13.4 Application for Interim Payment Certificates and Claim for Payments
13.4.1 The Contractor shall submit a statement, "the Interim Payment Certificate", in
six copies to the OWNER / OWNER's Representative after the end of each
month before the tenth day of the next month, in a form approved by the
OWNER / OWNER's Representative, showing the amounts to which the
Contractor considers himself to be entitled, together with supporting
Documents which shall include the detailed report on the progress during the
month in accordance with clause no. 3.17 above. The statement shall include
the following items, as applicable, which shall be expressed in the currencies
in which the Contract Price is payable, in the sequence listed:
ISSUE
R0
13.4.2 Contractor shall raise its consolidated invoices / bills only once a month.
13.5.1 The mode of payment by OWNER to the Contractor shall be mutually agreed
to after approval of financing plan by the Lenders.
13.5.2 The OWNER shall pay the amount certified in each Interim Payment
Certificate within 30 days from the date on which the OWNER / OWNER's
Representative received the Contractor's statement and supporting
Documents and the OWNER shall pay the amount certified in the Final
Payment certificate within 120 days from the date of issue of the Take-over
certificate.
ISSUE
R0
13.5.3 Pursuant to this clause no. 13.0, if the commercial banks are closed due to a
public holiday, period as above shall be extended to the first business day
after the end of the period concerned. In addition, unless the parties
otherwise agree, OWNER shall not be obligated to pay, in respect of any
request for payment, any amount in excess of amount anticipated to be paid
for Work or supply of Goods completed in such date, as set forth in the
mentioned payment schedule as per item 4.0 of Schedule F1 of Volume - II,
“Schedule of Prices”. If any request for payment does not comply in all
Material respects with this clause no. 13.0, OWNER shall inform Contractor
about the same within 15 days following the receipt of such request for
payment, and Contractor shall re-submit such request for payment. If less
than the full amount is paid, OWNER shall state in writing the reasons for
paying such lesser sum. Any dispute shall be dealt with under clause no.
22.0 below and shall not be a basis for withholding payment of any
undisputed amount. Any dispute regarding OWNER's payment of a lesser
sum than that set forth in a request for payment must be raised by Contractor
within 30 days of receipt of such payment, or Contractor's right to dispute
such payment is waived. During the pendency of any such Dispute and the
resolution thereof, Contractor shall continue to perform the Work in
accordance with the provisions set forth herein.
13.7.1 All costs, damages or expenses, which the OWNER may have paid, for
which under the Contract the Contractor is liable, will be claimed by the
OWNER. All such claims shall be billed by the OWNER to the Contractor
regularly as and when they fall due. Such bills shall be supported by
appropriate and certified vouchers or explanations, to enable the Contractor
properly identify such claims. Such claims shall be paid by the Contractor
within 15 (fifteen) Days of the receipt of the corresponding bills and if not paid
by the Contractor within the said period, the OWNER may the deduct the
amount, from any monies due or becoming due by him to the Contractor
under the Contract or may be recovered by actions of Law or otherwise, if the
Contractor fails to satisfy the OWNER of such claims.
ISSUE
R0
13.7.2 OWNER shall have the right to withhold from any payment due to Contractor,
including the final payment, such amounts as OWNER reasonably deems
necessary or appropriate to protect it because of any one or more of the
following reasons:
13.7.3 In addition to the provisions of this clause no. 13.7 which relates to the
recovery by the OWNER of any amounts that the OWNER may have paid, for
which the Contractor is liable under the Contract, the OWNER shall also be
entitled to recover all the dues in terms of the Contract including Liquidated
Damages for delay, Liquidated Damages for the shortfall in the guaranteed
performance parameters, etc., by way of deductions from the payments due
to the Contractor or that may become due to the Contractor in future or from
any securities / guarantees under the Contract and / or otherwise.
ISSUE
R0
13.7.4 Notwithstanding any dispute that Contractor may have, and regardless of the
basis thereof or grounds therefor, Contractor agrees that it will, for so long as
the Contract has not been terminated diligently prosecute the Work up to
Final Performance Acceptance and Take-over of CHS Package, all in
accordance with the terms of the Contract.
13.7.5 Any payment due to OWNER by the Contractor and remaining unpaid
beyond the stipulated date shall be liable to interest payment at the rate of
1(one) percentage point above the short term Prime Lending Rate of State
Bank of India from the date of due to OWNER to the date of receipt of dues
from Contractor by OWNER.
ISSUE
R0
Any final request for payment which does not satisfy all of the conditions set
forth above does not constitute a valid and proper final request for payment
and OWNER shall not have any obligation to make any payment there under.
13.8.2 Within 120 (One hundred and twenty) Days following the Final Performance
Acceptance of CHS Package and issue of Final Acceptance certificate, and
OWNER’s receipt of a valid final request for Payment, OWNER shall pay to
Contractor, the Contract Price then unpaid plus all other net amounts then
owed by OWNER to Contractor hereunder in connection with such CHS
Package, less
The Claims Reserve shall be held by the OWNER until Contractor provides
OWNER with:
ISSUE
R0
13.8.3 All payments made during the Contract including the Final payments shall be
on account payments only till release of the Contract Performance
Guarantee, which shall be construed to be the Final Payment. The Final
Payment will be made on completion of all the Works and of fulfilment of all
obligations under the Contract by the Contractor.
13.8.5 All payments to be made by the OWNER under the Contract shall be subject
to compliance by the Contractor of all statutory requirements as may be
applicable.
Contractor shall perform all Work required or appropriate for all Punch List
Items within a Schedule to be mutually determined by Contractor and
OWNER/PROJECT MANAGER after submission of the Final Request for
Payment in accordance with clause no. 13.8 above. Such Schedule shall
provide for completion of all Punch List Items as soon as practicable following
determination of the completion schedule. Upon completion of the Punch List
Items, Contractor may submit to OWNER and the OWNER's Representative
a request for release of the Punch List Reserve and shall furnish with such a
request a certificate that all Punch List Items have been completed. Unless
OWNER/PROJECT MANAGER disputes a charge or statement in such
request or certificate, OWNER shall release the Punch List Reserve to
Contractor within 30 (thirty) Days after receipt of Contractor's request
therefore given in accordance with the foregoing sentence of this clause no.
13.9.
ISSUE
R0
13.10.2 The Final Payment shall be deemed to release Contractor from all obligations
hereunder except those in respect of OWNER acceptance of such CHS
Package, Contractor's Guarantees and Warranties regarding the CHS
Package, the indemnification and any other obligations under the Contract,
which by their terms can be deemed to survive beyond the Final Payment.
13.11 Release
ISSUE
R0
14.2.2 The Contractor shall not make any alteration and/or modification of the
Services unless and until the OWNER/OWNER’s Representative instructs or
approves a Change Order in Writing.
14.2.3 Change Orders may be requested by the Contractor (the “Change Order
Request”) (i) in case its performance of Services is affected by any Change in
Laws or any act or omission of the OWNER, OWNER’s Representative or
OWNER’s Other contractors, or (ii) to propose any change which in the
Contractor’s opinion will reduce the cost of constructing, maintaining or
operating the CHS Package or otherwise be of benefit to the OWNER.
14.3.2 If the Contractor issues a Change Order Request, the Contractor shall submit
a proposal addressing the following:
ISSUE
R0
14.3.5 Contractor shall not suspend performance of this Contract during review and
negotiation of any Change Order, except as may be directed by OWNER or
required by Applicable Law
14.3.6 Payment in respect of the approved Change Orders shall be released by the
Owner to the Contractor on satisfactory completion of such Change Order
and its certification by the Owner’s Representative in the same manner as
applicable to corresponding milestone payments under the Contract.
(i) cease all further work, except for such work as may be necessary and
instructed by the OWNER/OWNER’s Representative for the purpose of
making safe or protecting those parts of the Services already
executed, and any work required for leaving the Site in a clean and safe
condition;
ISSUE
R0
(iv) handover those parts of the CHS Package executed by the Contractor
up to the date of termination; and
(v) remove all Contractor’s Equipment, which is on Site and repatriate all
his staff and labour from the Site.
If the Contractor fails to carry out any of his obligations, or if the Contractor
does not execute the Services in accordance to the Contract, the
OWNER/OWNER’s Representative may give notice to the Contractor
requiring him to make good such failure. The Contractor shall remedy the
same or take reasonable action to remedy the same within fifteen (15) Days
from date of such notice.
If the Contractor:
ISSUE
R0
then the OWNER may, without prejudice to any other right or remedy
OWNER may have under the Contract after having given thirty (30) Days’
notice to the Contractor, terminate the Contractor’s employment under the
Contract, should Contractor fail to rectify within such notice period or
commence to rectify the defaults within fifteen (15) Days of receipt of such
notice from OWNER; provided always that in the case of paragraph (d)
above, the termination shall become effective on OWNER issuing the notice
of termination.
OWNER may take possession of any and all materials, documents, purchase
orders, correspondence and schedules that OWNER deems necessary to
complete the CHS Package. The OWNER is also free to take possession of
and use Contractor’s Equipment at Site free of any cost. The rights and
authorities conferred on the OWNER and the OWNER’s Representative by
the Contract shall not be affected by such termination.
The Contractor shall not be released from any of his obligations or liabilities
accrued under the Contract. For the avoidance of doubt, the termination of
the Contract in accordance with this clause shall neither relieve the
Contractor of his accrued obligations for Warranty or Latent Defects or his
accrued liability to pay Liquidated Damages for Delay and/or Performance
nor shall entitle him to reduce the value of Contract Performance Security.
15.2.2 The OWNER may upon such termination complete the CHS Package
himself and/or by employing any other contractor. The OWNER or such
other contractor may use for such completion such of the Documents made
by or on behalf of the Contractor, Contractor’s Equipment, Temporary Works,
plant and materials as he or they may think proper. Upon completion of the
Services, or at such earlier date as the OWNER/OWNER’s Representative
thinks appropriate, the OWNER/OWNER’s Representative shall give notice
that the Contractor’s Equipment and Temporary Works will be released to the
Contractor at or near the Site. The Contractor shall remove or arrange
removal of the same from such place without delay and at his cost.
ISSUE
R0
15.2.3 Upon termination, if OWNER is of the opinion that he is not able to complete
the CHS Package himself or with the help of other Contractors, then he may
reject the incomplete Works. In such an event the OWNER shall recover all
money paid by the OWNER to the Contractor for the incomplete /rejected
CHS Package. The Contractor shall also dismantle and dispose off the
rejected/incomplete Works and also clear the Site at his cost. If he fails to do
so, the OWNER will dismantle and dispose off the rejected incomplete CHS
Package and clear the Site at Contractor’s Cost and risk and recover all
expenses incurred in this regard from the Contractor.
15.3.1 After termination under clause no. 15.2 above, the Contractor shall not be
entitled to any further payment under the Contract, except that, if OWNER
completes the CHS Package and the costs of completion are less than the
Contract Price, the OWNER shall pay Contractor an amount properly
allocable to Services fully performed by Contractor prior to termination for
which payment was not made to Contractor or a Sub-contractor, upon
completion of the CHS Package by OWNER.
15.3.2 The OWNER shall be entitled to recover from the Contractor the extra costs,
if any, of completing the Works. In addition, OWNER shall be entitled to
exercise any rights or remedies available to OWNER hereunder or at law or
in equity.
15.4 Bribes
then the OWNER may, after having given 15 (fifteen) Days' Notice to the
Contractor, terminate the Contractor's employment under this Contract and
also expel him from the Site. The effects of termination contained in clause
15.2 above shall apply mutatis mutandis to the termination under this clause.
In addition he will also be subjected to any criminal liability, which it may
incur, and payment of loss or damage to the OWNER resulting from any
cancellations.
ISSUE
R0
16.1.1 If the OWNER fails to certify a payment or pay the Contractor the amount due
and fails to explain why the Contractor is not entitled to such amount, within
120(One hundred and twenty) Days after the expiry of the time stated in
clause no. 13.0 above within which payment is to be made, except for any
deduction that the OWNER is entitled to make under the Contract, the
Contractor may suspend Work or supply of Goods or reduce the rate of Work
after giving not less than 60 (sixty) Days' prior Notice to the OWNER. Such
action shall not prejudice the Contractor's entitlements to payment under
clause no. 13.0 above and to terminate under clause no. 16.2 below.
16.1.2 If the Contractor suspends Work or supply of Goods or reduces the rate of
Work, and the OWNER subsequently pays the amount due, the Contractor's
entitlement under clause no. 16.2below shall lapse in respect of such delayed
payment, unless Notice of termination has already been given, and Notice
period of 60 (sixty) Days has expired and the Contractor shall resume Work.
16.2 Termination
If the OWNER:
a) Fails to pay the Contractor the amount due within 180(One Hundred
and Eighty) Days after the expiry of the time stated in clause no. 13.0
above within which payment is to be made (except for any deduction
that the OWNER is entitled to make under the Contract or any disputed
amount), or
16.3.1 Notwithstanding anything to the contrary in this Contract, Contractor shall not
be entitled to terminate this Contract unless:
ISSUE
R0
b) Curing themselves
16.4.1 After termination under clause 16.2 above, the Contractor shall:
a) Cease all further Work, except for such Work as may be necessary and
instructed by the OWNER / OWNER's Representative for the purpose
of making safe or protecting those parts of the Works already executed,
and any Work required to leave the Site in a clean and safe condition,
c) Hand over those other parts of the Works executed by the Contractor
upto the date of termination, and
16.4.2 Any such termination shall be without prejudice to any other right of the
Contractor under the Contract.
16.5.1 After termination under clause no. 15.1 or clause 16.2 above, the OWNER
shall return the initial Advance Bank Guarantee and Contract Performance
Security, (except to the extent required for the surviving obligations of the
Contractor) and shall pay the Contractor an amount calculated and certified
in accordance with clause no. 20.6 and sub contractor cancellation charges.
ISSUE
R0
17.0 INDEMNIFICATION
17.1.1 Contractor shall fully indemnify, save harmless and defend OWNER,
OWNER’s shareholders, the OWNER’s Representative, and the directors,
agents and employees of the OWNER (the “OWNER Indemnified Parties”)
from and against any and all claims, including reasonable legal costs,
(collectively the “Damages”) by third parties in respect of death or bodily
injury or in respect to loss or damage to any property (other than the Plant or
part thereof not yet taken over) which arises out of or in consequence of the
Services whilst the Contractor has responsibility for the care of the works to
the extent resulting from Contractor’s or any Sub-Contractor’s or their agents
or employees intentional act, negligence, or strict liability or omission in the
performance of the Services hereunder; provided that the foregoing
obligation shall not apply to the extent the OWNER Indemnified Parties are
contributory negligent or strictly liable or to the extent such damages are
caused by the intentional acts or omissions of the OWNER Indemnified
Parties.
ISSUE
R0
17.1.2 OWNER shall fully indemnify, save harmless and defend Contractor and its
shareholders and the directors, agents and employees of the Contractor (the
“Contractor Indemnified Parties”), from and against any and all claims,
including reasonable legal costs, (collectively the “Damages”) by third parties
in respect of death or bodily injury or in respect to loss or damage to any
property which arises out of or in consequence of the execution of the Project
to the extent caused by OWNER’s or OWNER’s other contractor’s strict
liability, intentional act or omissions or negligence; provided that the
foregoing obligation shall not apply to the extent the Contractor Indemnified
Parties are contributory negligent or strictly liable or to the extent such
damages are caused by the intentional acts or omissions of the Contractor
Indemnified Parties.
17.2.1 Contractor shall fully indemnify, save harmless OWNER Indemnified Parties
from and against any claim, demand, liability, action, proceedings, cost or
expense in favour of any third party with respect to:
17.2.2 OWNER shall fully indemnify, save harmless and Contractor Indemnified
Parties from and against Damages in favour of any third party with respect to:
ISSUE
R0
17.3.1 In performing the Services, Contractor shall not incorporate into the CHS
Package, or use in connection with the CHS Package or the performance of
the work, any materials, methods, processes, systems or service that involve
the use of any confidential information, intellectual property or proprietary
rights that Contractor does not have the right to use or incorporate or which
may result in claims or suits against OWNER, Contractor or any Sub-
contractor arising out of claims of infringement of any third party, domestic or
foreign patent rights, copyrights, other proprietary rights, or intellectual
property rights, licenses or agreements, or applications for any thereof, or
rights of use of confidential information.
17.3.2 Contractor shall provide OWNER with royalty free license for the sole
purpose to operate and maintain the CHS Package.
17.3.3 Contractor shall fully indemnify and save harmless and defend the OWNER
Indemnified Parties from and against any and all Damages that the OWNER
Indemnified Parties may suffer, incur or pay by reason of any claims or suits
arising out of claims of infringement of any patent rights, copyrights or other
intellectual property, proprietary or confidentiality rights with respect to
equipment, designs, techniques, processes and information designed or used
by Contractor or any sub-Contractor in performing the Work or supply of
Goods hereunder or under the Sub-Contracts in any way incorporated in or
related to the Project other than any such equipment, designs, techniques,
processes and information provided by the OWNER Indemnified Parties.
17.3.4 If, in any suit or claim relating to the foregoing, a temporary restraining order
or preliminary injection is granted, Contractor shall make every effort to
secure the suspension of the injunction or restraining order. If, in any such
suit or claim or any part, combination or process thereof, is finally held to
constitute an infringement and its use is permanently enjoined, Contractor
shall promptly make every reasonable effort to secure for OWNER a license,
at no Cost to OWNER, authorising continued use of the infringing Goods or
Work. If Contractor is unable to secure such license within a reasonable time,
Contractor shall, at its own expense and without impairing performance
requirements, either replace the affected Goods or Work, or part,
combination or process thereof with non-infringing components or parts or
modify the same so that they become non-infringing.
17.3.5 Final payment to the Contractor by the OWNER will not be made while any
such suit or claim remains unsettled.
ISSUE
R0
17.4.1 Promptly after receipt by a party of any claim or Notice of the commencement
of any action, administrative or legal proceeding, or investigation as to which
the indemnities provided may apply, such Party shall notify the other Party in
Writing of such fact provided that the failure of a Party to give any such
Notice promptly shall not excuse the indemnifying party from its
indemnification obligations hereunder except to the extent any such failure
actually prejudices the indemnifying Party in the defence of such matters.
17.4.2 The indemnifying Party shall assume on behalf of the indemnified Party and
conduct with due diligence and in good faith the defence thereof with counsel
reasonably satisfactory to the indemnified Party; provided that the
indemnified Party shall have the right to be represented therein by advisory
counsel of its own selection and at its own expense; and provided, further,
that if the defendants in any such action include both the indemnifying Party
and the indemnified Party and the indemnified Party shall have reasonably
concluded that there may be legal defences available to it which are different
from or additional to, or inconsistent with, those available to the indemnifying
Party, the indemnified Party shall have the right to select separate counsel to
participate in the defence of such action on its own behalf at the indemnifying
Party's expense.
17.4.3 The indemnified Party shall, at the request of the indemnifying Party, provide
all reasonably available assistance in the defence or settlement of any such
claim, action, proceeding or investigation, and all reasonable costs and
expenses incurred by the indemnified Party in connection with the defence or
settlement of any such claim, action, proceeding or investigation shall be
reimbursed by the indemnifying Party promptly upon demand thereof. The
indemnified Party shall not settle or compromise any claim, action or
proceeding without the prior Written consent of the indemnifying Party such
consent not to be unreasonably with held.
ISSUE
R0
The provision of this Clause 17.0 shall survive final acceptance or the
termination of this Contract; provided that neither Party shall have any
indemnity obligations pursuant to this Clause 17.0 for any claim arising out of
or resulting from events or circumstances occurring after the termination of
this Contract or after the expiration of the Latent Defect Liability Period; and
provided further that neither Party shall have any indemnity obligation
pursuant to this Clause 17.0 unless notice of any such claim for indemnity by
either Party is received by the indemnifying Party prior to the date that is
three (3) years after the expiration of the Latent Defect Liability Period.
18.1 The Contractor shall take full responsibility for the care of the Works from the
commencement date indicated in the Notice to Proceed until the date of issue
of the Certificate of Provisional Take Over for the CHS Package, when
responsibility shall pass to the OWNER.
18.2 The Contractor shall take responsibility for the care of any outstanding Work
or obligations which is required to be completed/ fulfilled prior to the expiry of
the Contract Period, until the OWNER's Representative confirms in Writing
that such outstanding Work or obligation has been completed / fulfilled.
18.3 If any loss or damage happens to the CHS Package, during the period for
which the Contractor is responsible, the Contractor shall rectify such loss or
damage, at his cost, so that the Works conform to the Contract. The
Contractor shall also be liable for any loss or damage to the Works caused by
operations carried out by the Contractor after the date of issue of the
Certificate of Provisional Take Over until the expiry of the Contract Period in
so far as such loss or damage is not covered under Insurance to be taken by
the OWNER for operation of Plant.
ISSUE
R0
Except for any specific liability which may be identified in the Contract and
which may be payable hereunder, Contractor shall not be liable for any
special, incidental, indirect, or consequential Damages or any loss of
business Contracts, revenues or other financial loss (or equivalents thereof
no matter how claimed, computed or characterised) arising out of or in
connection with the Performance of the Work or supply of Goods unless
caused by Contractor’s negligence or wilful misconduct. In addition, OWNER
shall have no liability or any special, incidental, indirect or consequential
Damages or any loss of business Contracts, revenues or other financial loss
arising out of this Contract.
(iii) the overall cap on Liquidated Damages (for Delay, and Performance)
in the aggregate shall be twenty per cent (20%) of the Contract Price;
19.2.2 Other than those specific remedies stated in this Contract, Liquidated
Damages shall be OWNER’s sole remedy for (i) Contractor’s delay or (ii)
shortfall in Performance Guarantees.
19.2.3 Payment of the above Delay Liquidated Damages shall not affect or prejudice
in any way or manner OWNER’s right to terminate the Contract nor shall any
termination of Contract prejudicially affect the OWNER’s right to recover any
accrued Delay Liquidated Damages or release the Contractor from any
obligation for payment thereof.
ISSUE
R0
The OWNER’s and Contractor’s remedies and liabilities that are identified in
this Contract shall be the sole and exclusive remedies available to the Parties
in respect of matters to which they are said to relate in this Contract
irrespective of any rights and remedies which might be available at common
law, in tort (including negligence), by statute or otherwise.
a) Act of God;
ISSUE
R0
a) The affected Party gives the other Party Written Notice of the
occurrence of the Force Majeure Event as soon as practicable after the
occurrence of the Force Majeure Event and also gives the other Party
Written Notice describing in reasonable detail the particulars of such
occurrence, including an estimation of its expected duration and
probable impact on the performance of such Party's obligations
hereunder, and thereafter continues to furnish thereto timely regular
reports with respect to continuation of the Force Majeure Event;
e) The affected Party shall use its best efforts to continue to perform its
obligations hereunder and to correct or cure the event or condition
excusing performance;
20.3 Limitations
b) The affected Party shall not be relieved from obligations under this
Contract to the extent that the negligence or wilful misconduct of the
affected Party (or in the case of Contractor or any Sub-Contractor
thereof) contributes to or aggravates the Force Majeure Event.
ISSUE
R0
b) The effect of such event of Force Majeure could not have been
prevented or avoided or removed despite exercise of reasonable due
diligence whether before, after or during the event of Force Majeure.
If, in consequence of Force Majeure, the Plant or any part thereof shall suffer
loss or damage, the Contractor shall be entitled to claim and receive payment
for the cost of Work or supply of Goods executed in accordance with the
Contract, prior to the event of Force Majeure.
Irrespective of any extension of time, if a Force Majeure event occurs and its
effect continues for a continuous period of 270 (two hundred and seventy)
Days or have been delayed for a cumulative period in excess of 365 (Three
hundred and sixty five) Days, either the OWNER or the Contractor may give
to the other a Notice of termination, which shall take effect 30 (thirty) Days
after the giving of the Notice. If, at the end of the 30 (thirty) Day period, the
effect of the Force Majeure continues, the Contract shall terminate. If the
Contract is terminated under this clause no. 20.6 or clause no. 15.1 or 16.2
the OWNER shall determine the work done and pay to the Contractor.
a) The amounts payable for any Work or supply of Goods carried out for
which a Price is stated in the Contract;
b) The cost of CHS Package and Materials ordered for the Works which
have been delivered to the Contractor, or of which the Contractor is
liable to accept delivery: such Plant and Materials shall become the
property of (and be at the risk of) the OWNER against payment
therefore by the OWNER, and the Contractor shall place the same at
the OWNER's disposal promptly upon receipt of request in respect
thereof from the OWNER.
21.0 FINANCING
21.2 The Contractor acknowledge that the OWNER will seek financing from a
variety of sources. The Contractor
21.3 The Contractor shall seek performance solely from the Owner to satisfy the
Owner’s obligations under this Contract.
21.4 The Contractor agrees, upon Lenders’ request, to enter into a Direct
Agreement with the Lenders in the form reasonably required by the Lenders.
22.1.1 If the Contractor or OWNER intends to claim any additional payment under
any clause of these conditions, the Party claiming shall give Notice to the
other Party or as soon as possible and in any event within 30 (thirty) Days of
the start of the event giving rise to the claim.
22.1.2 Within 30 (thirty) Days of such Notice, or such other time as may be agreed,
the Party claiming shall send to the other Party an account, giving detailed
particulars of the amount and basis of the claim along with the necessary
supporting documentation. Where the event giving rise to the claim has a
continuing effect, such account shall be considered as interim. The Party
claiming shall then, at such intervals as the other Party may reasonably
require, send further interim accounts giving the accumulated amount of the
claim and any further particulars. Where interim accounts are sent to the
other Party, the Party claiming shall send a final account within 15 Days of
the end of the effects resulting from the event.
ISSUE
R0
22.1.3 If the Party claiming fails to comply with this clause no. 22.1.2, he shall not be
entitled to any additional claim and shall be deemed to have waived the
same.
22.2.1 Any disputes or differences arising out of or in connection with the Contract
shall, to the extent possible, be settled amicably between the Parties.
22.2.2 If any dispute or difference of any kind whatsoever shall arise between
OWNER and Contractor, arising out of the Contract for the performance of
the Works whether during the progress of Works or after its completion or
whether before or after termination, abandonment or breach of Contract, it
shall, in the first place be referred to and settled by OWNER’s
Representative, who within a period of 30 (thirty) Days on request by either
Party to do so, shall give Written Notice of his decision to the OWNER and
the Contractor.
22.2.3 All disputes or differences in respect of which the decision, if any, of the
OWNER’s Representative has not become final or binding as aforesaid, shall
be referred within the next thirty (30) days, for resolution by the intervention
of the Managing Director's or CEO's of the respective Parties within the next
thirty (30) days.
22.3 Arbitration
ISSUE
R0
22.3.1 If the disputes or differences under Clause 22.2.3 herein above are still not
resolved, the same shall be referred for arbitration in accordance with the
Indian Arbitration & Conciliation Act, 1996, or any statutory modification or
enactment thereof for the time being in force.
22.3.2 The Contractor and the OWNER will continue to perform their respective
obligations under the Contract during the Arbitration proceedings unless such
performance itself relates to the dispute referred to Arbitration pursuant to
this sub-clause.
22.3.4 Arbitration shall be sole and exclusive remedy between the Parties regarding
the dispute referred to Arbitration and any claims, counterclaims issues or
accountings presented or plead to the arbitrators in connection with such
dispute.
22.3.5 The award rendered in any Arbitration commenced hereunder shall be final
and conclusive. The award should be implemented and promptly paid.
22.3.6 The Arbitrators shall have full powers to review or revise the decisions,
opinions, certifications or valuations of the OWNER’s Representative. The
OWNER and the Contractor hereby undertake to carry out the award without
delay. The expenses of Arbitration shall be paid as may be determined by
the arbitrators. They may from time to time, with the consent of the Parties,
enlarge the time for making the award. In case of aforesaid arbitrators dying,
neglecting, resigning or being unable to act for any reason, it will be lawful for
the Parties to nominate another arbitrator with mutual consent of both the
parties.
22.3.8 This clause no. 22.2 shall remain in full force and effect notwithstanding any
lawful termination of the Contract where either Arbitration has already
commenced or the liabilities between the OWNER and the Contractor have
not been fully determined.
ISSUE
R0
23.1 The failure of either Party to enforce at any time any of the provisions of this
Contract or any rights in respect thereto or to exercise any option therein
provided, shall in no way be construed to be a waiver of such provisions,
rights or options or in any way to effect the validity of the Contract.
23.2 The exercise by either Party of any of its rights herein shall not preclude or
prejudice either Party from exercising the same or any right it may have
hereunder.
Each Party hereby represents and warrants to the other Party that:
It is duly organized and validly existing under the laws of its jurisdiction of
incorporation and is qualified to do business in India/…….. (specify any other
country), and in all other jurisdictions in which the nature of the business
conducted by it makes such qualification necessary, and has all requisite
legal power and authority to carry on its business and to execute this
Contract and to perform the terms, conditions and provisions hereof.
24.2 Authorization.
The execution, delivery and performance by such Party of this Contract have
been duly authorized by all requisite corporate action.
24.3 Enforceability.
This Contract constitutes the legal, valid and binding obligation of such Party,
enforceable in accordance with the terms hereof.
24.4 No Conflict.
Neither the execution nor delivery nor performance by such Party of this
Contract, nor the consummation of the transactions contemplated hereby, will
result in a violation of, or a conflict with, any provision of the organizational
documents of such Party; a contravention or breach of, or a default under,
any term or provision of any indenture, contract, agreement or instrument to
which such Party is a party or by which such Party or its property may be
bound, or a violation by such Party of any Law.
ISSUE
R0
24.6 Litigation.
There is no action, suit or proceeding now pending or (to its best knowledge)
threatened against it (or any Subcontractor, in the case of the Contractor)
before any court or administrative body or arbitral tribunal that could
reasonably be expected to adversely affect the ability of such Party (or any
Subcontractor, in the case of the Contractor) to perform its obligations
hereunder (or under any Subcontract) other than those notified to the Project
Company in writing by the Contractor.
24.7.1 It has or will be the holder of all Permits required to allow it to operate or
conduct its business as contemplated hereby;
24.7.2 It has thoroughly examined this Contract, the Technical Specification and all
applicable Laws and has become familiar with their terms;
24.7.3 It has, and its Subcontractors have, full experience and proper qualifications
to manufacture Equipment and perform the Work and to construct the CHS
Package under the Contract .
It has ascertained the nature and location of all Work to be performed at the
Site, the character and accessibility of the Site and its surrounding areas,
availability of lay-down areas for Equipment and tools, the existence of
obstacles to construction (including any reasonably identifiable underground
obstacles, if any, referred to in this Contract), the availability of facilities and
utilities, the location and character of existing or adjacent work or structures,
the conditions of roads, waterways and railroads in the vicinity of the Site and
in the State of Jharkhand in India, including the conditions affecting shipping
and transportation (such as the limitations of bridges and tunnels), access,
disposal, handling and storage of materials, the surface conditions and other
general and local conditions, including labour, safety, weather, environmental
conditions, geological conditions, if any, noted in this Contract, water supply,
water quality, waste water capacity of existing municipal systems and all
other matters that might affect its performance of the Work or its costs or the
construction of the CHS Package
ISSUE
R0
24.7.4 All services provided and procedures followed by the Contractor hereunder to
engineer, design, procure, construct, commission, start-up and test all the
Equipment and other items in the CHS Package shall be done in a
workmanlike manner and in accordance with:
24.7.5 It is familiar with all necessary facilities for delivering, handling and storing all
Equipment and other parts of the Work
24.7.6 It is familiar with all labour conditions and agreements relating to the
performance of the Work;
24.7.7 It will design the Equipment and Work for CHS Package so that the useful
life thereof may reasonably be expected to thirty (30) years;
24.7.8 The Contractor has no reason to believe that any Contractor Permits will not
be readily obtainable by the Contractor in the ordinary course of business
upon due application therefore;
24.7.9 It has satisfied itself as to the means of communication with and access to
and through the Site and accommodations it may require and the precautions
and times and methods of working necessary to prevent any Contractor
Person from creating any nuisance or interference, whether public or private,
which might give rise to any law and order problems within or outside the
Site.
25.0 MISCELLANEOUS
25.1 Non-Waiver.
Neither Party shall be deemed to have waived any right under this Contract
unless such Party shall have delivered to the other Party a written waiver
signed by such waiving Party. No failure or successive failure by either Party
to enforce any covenant or agreement, and no waiver or successive waivers
by either party of any condition of this Contract, shall operate as a discharge
of such covenant, agreement or condition, or render the same invalid, or
impair such Party's right to enforce the same in the event of any subsequent
breach thereof by the other Party.
ISSUE
R0
25.2 Severability.
In order that the Parties may fully exercise their rights and perform their
obligations hereunder arising from the performance of the Work, such
provisions of this Contract that are required to insure such exercise or
performance shall survive the termination of this Contract for any cause
whatsoever.
This Contract constitutes the entire agreement and contains all of the
understandings and agreements of whatsoever kind and nature existing
between the Parties, and supersedes, to the extent permitted by Indian law,
all prior written or oral agreements, commitments, representations,
communications and understandings between the Parties.
25.5 Amendment.
All of the terms and provisions of this Contract shall be binding upon and
inure to the benefit of the Parties and their respective successors and
permitted assigns. This Contract is for the sole benefit of the Parties, and to
the extent provided herein, the Indemnities, and is not for the benefit of any
other Person.
25.7 Counterparts.
ISSUE
R0
For the avoidance of doubt, this Contract is not intended to confer any legally
enforceable rights on any Person other than the Parties, their successors in
title and their permitted assignees, whether pursuant to the Contracts (Rights
of Third Parties) Act 1999 or otherwise.
ISSUE
R0
TABLE – 1
1.4 No objection certificate for plant Chief Electrical Engineer of CHS Contractor
layout with regard to electrical Jharkhand
equipment, operational safety
1.6 Consent under the Factories Directorate of Town and CHS Contractor
Act, 1948 relating to fire fighting Planning of Government of
capacities of the Power Plant Jharkhand
ISSUE
R0
ISSUE
R0