SUPPLIMENTARY WORK

CONSTRUCTION OF TYPE-II COMMUNAL LATRINE

Unit
NO DESCRIPTION Unit Qty. Price T/price

A. Latrine Construction

A. sub-structure

1. Excavation and Earth Work

1.1 Site clearance to depth not exceeding 200mm m2 40

Trench excavation in ordinary and soft rock formation to a depth of


1.2 150cm for retaining wall from RGL m3 20

Bulk excavation in ordinary and soft rock formation up to an


1.3 average depth of 350cm from NGL m3 20

Backfilling around retaining wall masonry with selected granular


borrowed materials 80% from outside and 20% from site well ram
1.4 in layers not exceeding 20 cm thick m3 10

Load and cart away surplus excavated material and deposit at an


1.5 appropriate place outside the site at least 5km m3 38

Subtotal carried to summary -

2. Concrete Work

7cm thick lean concrete class C-5, 150kg/m3 concrete, under


2.1 masonry retaining wall foundation m2 16

Subtotal carried to summary -

3. Masonry Work

Supply and build trachytic or equivalent stone retaining wall


masonry bedded with cement mortar 1:3 ratio. Price includes any
3.1 works to complete the job m3 26

Subtotal carried to summary

Total

6XTotal

15% VAT

Grand Total with VAT