Agile Overview

In this video we will discuss an overview of Agile. Much of what we discussed lightly here will be
covered in more detail later in the course. We will start by describing Agile. Agile is an approach to
managing and working on projects. This means that it relates to both planning and doing the
actual work. In other words, it includes aspects of project management and product
development. Agile is a simple approach to managing complexity. This is an alternative to
addressing complexity with complex project management and heavy upfront planning which often
increases the overall complexity and risk of the project. Agile approaches can be applied to any type
of project. The classic use of Agile is in software development. The use of the word Agile for this
approach was coined by some leaders in the software industry in 2001. We will discuss this more
when we discuss the Agile manifesto. Most modern software projects run using Agile approaches. If
you name any company that produces software, there's a very good chance that some or all of the
company is agile. Companies that are using old-fashioned approaches are usually at a disadvantage to
their competitors. Agile techniques can also be used to manage service tickets. These can be tickets
related to software issues or any other type of service ticket such as a restaurant order. Inside of a
company, Agile approaches can be used in any department. For example, the human resources or HR
department might use Agile techniques to manage the flow related to the new hire process. As another
example, the marketing team might use them for managing a marketing initiative. Agile approaches
do not have to be used in corporate situations. For example the tasks that need to be done at a
picnic can be managed this way. If you are writing a book, Agile techniques can help you focus and
write a better book. Agile can apply to team projects and to personal projects. Finally, even if
you are building a rocket, you can use Agile techniques.

SpaceX uses Agile approaches to continuously improve their products. You can see that Agile
projects apply to working on physical products as well as on knowledge work like managing an HR
process. In this course, we will generically use the word product to refer to both physical and less
tangible deliverables of a project. Each Agile project is unique but they usually have some common
characteristics. We will discuss them briefly now, then discuss each of these characteristics more
throughout the course. Agile products are built incrementally. This means that instead of
planning, building and releasing the product all at once, small valuable increments of the
product are planned and released in a succession. The definition of release may vary by project.
For example, an increment may actually go to the customer or the increment may be releasable
subject to a business decision. Either way, each increment should be actually usable and valuable to
the customer. Agile projects are iterative. This means that you continuously obtain feedback, learn
and improve the product and the process of building the product. Each increment provides tight
feedback from both the users and from inside the team allowing continuous improvement. Agile
projects relentlessly focus on value. The team is always working on what it currently considers to be
the highest value parts of the project. After the current work, the team again decides what is the next
highest value thing to work on. This is based on continuous feedback from the team and from users of
the product. Agile projects have an empowered team. This means that the team decides how to
organize and how to accomplish its work. This is not a command and control system. You can think
of the team as containing a distributed brain where each member continuously helps make decisions.
In many cases, the members of the team have the most current knowledge and information and are in
the best position to make a good quick decision.

An Agile approach to managing projects is often chosen because the results are better than more
traditional approaches. This is especially true when the project involves a lot of uncertainty. Let's start
by looking from the customer's perspective at the benefits of products created by Agile teams. The
customer is receiving a desirable product. This is because the customer consistently provides feedback
in the development of the product. This feedback comes directly from customers or indirectly by
evaluating the data related to product usage. The team is always focused on delivering the highest
priority features which means customers are getting the most important features earlier than they
would using traditional project management techniques. Agile teams are consistently matching what
they build to what the customer is asking for. They embrace and respond quickly to change so even
recent changes in the market can be accommodated as the product is built. Agile projects also lead to
higher quality. The assumption is that team members are knowledgeable and will build with high-
quality at all times. However, mistakes and unanticipated issues will arise. In Agile projects, feedback
loops are short and mistakes are expected to be fixed when they are discovered. Agile projects also
have benefits for the team. Agile teams often have higher job satisfaction. This is due to the culture of
empowering team members to define the best way to work together. Leveraging the decision-making
ability and creativity of all team members is not only good business, but creates a stronger sense of
purpose for the team members. It also results in the use of a variety of skills and provides continuous
learning opportunities. Agile projects lead to better innovation. The Agile approach is experimental in
nature which allows innovative ideas to be quickly built and tested with real users. Because the team
and the product are adaptable, the new ideas may or may not survive in the long term. Either way, the
Agile team embraces the learning process involved. Companies that adopt Agile approaches have an
entrepreneurial spirit to them and are much less likely to be disrupted by other companies. Agile
products have lower costs than traditional projects. This is because you are consistently receiving
feedback and focusing on value. You are not performing wasteful activities. Also any problems are
resolved when they are discovered leading to lower rework costs. Agile projects are safer in the sense
that risk is lowered because you are continuously getting feedback on what you are doing. You don't
want to work on a product for a long time only to realize much later that major parts of what you have
built have low value. Agile projects also result in predictable deliveries. Even if an Agile project has a
strict deadline, the commitment can be made because you always have a shippable product. What
varies is the number of high value features that are in the product. This reduces the overall risk of the
project.

Next we will discuss one of the foundations of Agile, the scientific method. We've seen that managing
and working on Agile projects includes many small iterative learning loops. This resembles the
scientific method and in fact the scientific method can be thought of as the foundation of Agile
projects. Since most of us are at least somewhat familiar with the scientific method, we can use that
knowledge to help understand Agile projects. The basic idea of the scientific method is to start with
an idea or hypothesis then build an experiment to test the idea, then observe the results of the
experiment and learn from it. You can then repeat the process using what you have learned to improve
in the next iteration. It is a series of continuously learning and improving iteration's which also could
be called loops or cycles. This is called an empirical approach to problem solving where you are
learning from the results of experiments. In Agile projects, we shift our thinking a little bit so that
instead of using the scientific method only for discovery, we also use it to accomplish the work of a
project. In addition to creating a hypothesis, we plan some work. We then do the work. We then learn
from the feedback on both our work and the process that was used to do the work. We repeat the cycle
in order to do more work leveraging the knowledge that we have gained in the previous iterations.
The scientific method can be thought of as a formalized description of what the brain is doing when it
is problem solving. Accomplishing the work of projects involves a lot of problem-solving. So, it's not
surprising that agile approaches are based on the scientific method.

The iterative learning loop of the scientific method is the foundation of many processes. These loops
are used in many contexts, including for general business and for software development. They are
used by individuals and by teams. The specific number and names of the parts of the loop may vary,
but they all follow the same basic idea. The main idea is to continuously learn and improve using
iterations. Let's go through some examples of concepts that are basically derivatives of the scientific
method. Plan, do, check, act or plan, do, check, adjust is a concept used to improve business
processes. These steps are basically the same steps as the scientific method. Plan, build, release can be
thought of the steps involved in software development. Spotify has an approach with think, build,
ship, and tweak as the steps. If you realize that the scientific method is the parent of all of these
approaches, you can see that there are many seemingly different explanations of basically the same
ideas.
Next, we will compare agile projects to the traditional waterfall approach. The traditional way to
manage projects is also known as the waterfall approach. The simplified explanation of waterfall is
that instead of continuously planning and releasing increments of the product, you develop the entire
product in distinct phases. A typical first phase is the analyze phase, where customer requirements are
defined. The output of this phase is usually a requirements document. The project then moves on to
the design phase, where the features related to the requirements are designed. The output of this phase
is usually a design document. The features are then built. Once the product is built, it is passed to the
quality assurance department for testing. When the product passes quality assurance, it is passed to
manufacturing or operations for release. Each of these phases usually is owned by separate teams. So
one team is passing their output to the next team in succession. You can see that this simplified view
of the waterfall approach contains effectively only one pass through the scientific method. There is no
looping. This approach to projects is somewhat similar to traditional mass production in
manufacturing. The batch size of each phase is large, effectively the size of the entire product. This is
partially because of the perceived cost benefit of economies at scale. It also may be a practical
approach if certain steps take a lot of setup and time to execute. The waterfall approach still has value
for some projects, but for many projects, it is an outdated approach that leaves you susceptible to
being disrupted by your competitors. Even when a waterfall approach is necessary, elements of agile
processes can be included in the project.

The waterfall approach to managing and building projects has many downsides. The biggest issue is
that your big, upfront plan will be wrong. This is because you can't predict the future, especially for
complex, one-off projects. High value features aren't correctly identified. Until the customer actually
tries a feature, they don't really know if they will use it. As a result, you build many unnecessary
features. For example, it may turn out that the customer really only uses two of the 10 features that
you built. There's waste, not only in building those features, but also in making the customer wait for
those two useful features while you build all 10. Things are harder, more problematic, and take longer
to build than you think. In general, people who build things are optimistic about how long it will take
to build it. As a result, most complex waterfall projects fall behind schedule, sometimes by quite a lot.
The market and/or your team will change while you build the product. In the waterfall approach,
you'd create a detailed plan for one big release in the future. During that time, the market may change
in ways that you should be adapting to, but you don't, because you continue to follow the original
plan. Also, if you lose key team members during the development of the project, it will delay the
entire project because the original plan assumed that you would have the original team for the entire
time.

In a waterfall approach, change is hard and expensive. This is because you've created a big upfront
plan and any changes can have major ripple effects for the rest of the project. A change later in the
project life is especially difficult and expensive to make because a lot of work has already been put
into the original design and the product isn't designed to handle changes like that. This is why in any
waterfall projects, there's often a separate change management process for dealing with changes to the
original plan. In a waterfall project, you tend to create a lot of obsolete documents. Because the
waterfall approach assumes that the project will go through distinct phases while the product is being
built, the output of one phase tends to include a document or documents that the next phase picks up
and works with. This is problematic in many ways. The document may not be written in a way that
the people in the next phase truly understand, resulting in waste. Also, as the next phase discovers
things that need to change, they often don't update the documents from the previous phase causing the
documents of the project to become out of sync and eventually obsolete. Also towards the end of
waterfall projects, changes are often made because of discovery of last minute problems. These
changes are often made without being properly documented causing the documents from previous
phases to become further obsolete. In waterfall projects, the feedback on what you are doing often is
drastically delayed. For example, let's say that you identified a high value feature during the analyze
phase. That feature eventually is released when the product is released. This can be months or years
after the high value feature was identified. That is a long time to wait to learn that your high valued
feature is actually of low value. As another example, let's say there the software feature is built in the
build phase. If testing is a separate phase, that test may be months after the feature was built. If the
testing fails, the engineer who built it will barely remember building it or may no longer be available
to help fix it. Delayed feedback like this is a source of waste in the project.

A question that you may have is when is waterfall used? Well, if the setup cost for a phase is high,
you tend to plan very carefully and work in big batches. In other words, if it takes a lot of time or
expense to setup what is needed to send a single feature through a single phase, you tend to batch the
features in order to achieve economies of scale. Let's look at software development as an example. In
the not-too-distant past, companies had to buy computers used for every phase in the process. They
would have to predict how many they would need, order them, wait for them to arrive and set them
up. They would then have to install the software on the computers depending on how they used it. It
made sense to batch all of the testing in this way because all that is needed simply to set up and run a
single test. There were separate people whose job it was only to setup computers and others who only
set up and ran tests. As a result, the developers and testers were different people doing work at
different phases of the project. The team members didn't necessarily want the steps to be so difficult
and would have preferred a more agile approach, but the state of the art at the time, made that very
difficult to achieve in reality. Another reason to use waterfall is when the work is relatively
predictable. You can do the work in separate steps with large batch sizes. However, this is often not
the case with one-off projects. Another question that you may have is, why is waterfall outdated in
many cases? Well, the setup costs of some phases is trending to zero or at least no longer a major
factor. This is true in terms of both time and expense and means that the batch size can be reduced to
much smaller numbers. You no longer have to think in terms of a project going through each phase
successively and instead can think of each feature or part of a feature going through each phase very
quickly. As the setup cost of the phases of the project become negligible, the entire justification for
managing projects using the waterfall approach begins to fall apart. Agile approaches become
superior.
Now hopefully, you are beginning to see the clear difference between agile and waterfall approaches.
In waterfall, you are effectively performing one giant iteration of the scientific method with the entire
product being built phase by phase. In an agile approach, there are many small iterations where small
batch sizes go through each of the phases relatively quickly. The end of each iteration results in a
product increment that is usable by the customer. The agile approach provides the benefits of rapid
feedback and because planning is continuously happening, the product can adapt quickly. All projects
are unique and many projects will contain elements from both agile and waterfall approaches. Even if
you need to use waterfall techniques for some projects, it is a good idea to have a solid understanding
of agile principles and practices and use them where they make sense. If you are using waterfall
techniques on a project that doesn't really require them, there's a good chance that your competitors
using an agile approach will be at a strong advantage.
We have seen that a waterfall process is more sequential than an agile process. Agile processes are
more concurrent with each feature going through phases quite quickly. If you have multiple
developers on an agile project, each of them may be working on different phases at any one time.
Because of the fundamental differences between waterfall and agile processes, project management
for the two approaches is different. Waterfall is more of a predictive, command and control process
with big upfront planning, and agile is more of an adaptive, distributed process with just enough and
continuous planning. In some ways, agile processes mean that everyone on the team is somewhat
involved in planning and project management work. We will discuss this more as we move through
the course.
Here
is a review of what we discussed in this video. Agile is an approach to managing and working on
projects. Agile uses many small increments and iterations. The waterfall approach uses one
giant iteration and provides little continuous feedback. Agile project management is
fundamentally different than traditional project management.

Jira Overview
0:01
In this video, we will discuss an overview of Jira.
Play video starting at ::7 and follow transcript0:07
We will start by discussing Jira and its hierarchy. In this course, we will use Atlassian Jira as a tool to
help work with Agile processes. We will use hands-on Jira labs to reinforce the Agile principles and
practices that you will learn. Jira is software used to help manage, develop, and communicate about
projects. The projects can be team projects or individual projects. They can be quite complex or rather
simple. The product that is developed for the project can be just about anything. Jira is very easy to
get started with, it's very flexible and can be used in a way that matches your Agile processes. Jira can
even be used if you mainly follow a waterfall approach to project management. Jira is organized
around a hierarchy. The highest level is what we call the application level. A single Jira
application can contain any number of projects. In the hands-on lab associated with this video, you
will sign up for a free Jira site that you can use to create projects. The next level of the Jira
hierarchy is the project level. A project contains one or more issues. An issue is any work item
related to the project. The next level is a level of a specific issue. At this level you can see and
change the details of the issue. An issue can represent any work that needs to be done in the
project.

When you log into Jira using your browser, you can view
the projects on your site by clicking the Projects drop down in the navigation bar at the top. You will
then see a list of projects that you recently worked on and can click "View all projects" to see the list
of projects on your site as shown here. You can also click on your work to see recent projects as well
as recent issues that you've worked on. Once you have navigated to a specific project, you will see a
project sidebar. All of the links in the sidebar only apply to the current project. If you click on the
issues link in the project sidebar, you will see a list of issues in the project. You can also view the
details of an issue on the right. Here you can see three sample issues listed and they are used to help
build some of the features of the project. We've now seen the two main ways to navigate in Jira. The
navigation bar at the top of the screen is always visible and usually the options there apply to all
projects on your site. For example, you can search for issues across your entire site using the search
box in the upper right. Once you've selected a project, you can use the Projects sidebar to work inside
of the project. In the top navigation bar, the icon to the left of the "Your work" link is the Jira icon.
This icon may look different depending on which Jira products you're using on your site. You can
click this icon to view a list of the projects in your site. The icon that we see here is for Jira software,
which is the product that you will be using for the hands-on portion of this course. The term software
in Jira software is a nod to the fact that there are integrations and other features related to software
development. However, Jira software is used to manage the work of many other types of products too.
In addition to Jira software, other Jira products include Jira Core and Jira Service Desk. Jira Core is
included with Jira software. Also, if you use both Jira software and Jira Service Desk, your icon will
look like this, indicating that both products are available on the site. The icon in the upper left of the
top navigation bar opens the "Switch to" menu. This allows you to switch to any other Atlassian
products or sites that you may be using. This course focuses on Jira software, but you are free to try
any of the other products. Most of these products have free plans that you can use indefinitely. Notice
that there's also an administration link that is to access site administration, which we will discuss later.
Next, we will discuss creating a project and issues. To create a project, click on the Projects drop
down in the top navigation, then click on " Create project". While viewing a list of projects, you can
also click the "Create project" button in the upper right. You will create your first project in the first
reading for this course. When you click on create project, you're given a choice of creating a classic
project or a next-gen project, along with the list of the differences between the two types of projects.
Classic Projects are traditional Jira projects. In general, they are more mature and have more
functionality than next-gen projects. They have more configuration capabilities and configurations
can be shared among multiple projects. They are created by Jira administrators. Next-gen projects are
newer to Jira and capabilities are being added by the Atlassian engineers in an agile way. While there
are many similarities, Next-gen projects have a different perspective on managing the projects.
Instead of Jira administrators mainly creating and configuring projects. Next-gen projects can be
easily created and configured by the members of the project team. The configuration applies only to
that project, so team members don't have to worry that they are changing the configuration of other
projects. The type of project that you create is up to you and your organization. Some organizations
may choose to only use classic projects and keep better control over the project configuration. Some
organizations may prefer the ease and flexibility of Next-gen projects and some organizations may
allow the project teams to choose. In this course, you will mainly work with classic projects because
they currently have more capabilities. In certain circumstances, you'll be given the option of using
Next-gen projects. The hands-on labs will identify the type of project that you should create. Either
way, what you learn in this course is foundational to any type of project that you choose. In the create
project window for a classic project, you can enter a project name. Here we are naming our project
''Project A.'' Jira will automatically suggest a project key, which is an additional shorter name for your
project. We will discuss project keys later. Notice that there's a template associated with our project.
A template defines the projects initial configuration. Each template provides different default behavior
and tools. Here we can see that the template is set to Kanban. Among other things, this means that a
Kanban board will be included with the project. We will discuss Kanban projects later in the course.
If you click on ''Change Template," you
can view the available templates. When you click on ''Change Template," Jira provides you a choice
of templates. We can see here that software is selected from the drop down. This means that you are
being shown the project templates for Jira software. These are the three Jira software templates that
you can choose from, Kanban, Scrum, and Bug-tracking. If you select ''Business'' from the drop-
down, you are shown the Jira Core Project Templates. These are templates that apply generally to any
business, such as managing the new hire process with the recruitment template. Jira Core Templates
are included with Jira software, which is why these templates are available on your site. In this course,
we will focus on Jira software templates, especially the Kanban and Scrum templates. When you are
happy with the project name, project key and template, click ''Create'' to create the project. After
creating the project, you can view some of its details and tools in the sidebar. We will discuss these
throughout the course. To create an issue for the project, click on the ''Create'' button in the top
navigation bar. In the Create Issue window, you can see and change the details of the issue. The
details are called fields. We can see that this issue belongs to the project A, project. The issue also has
a type, which in this case is story. The fields can change depending on the type of issue that is
selected. We will discuss issue types in more detail later in the course. In the summary field, you enter
a brief overview of the issue. This basically becomes the title or name of the issue. In this case, our
issue name is ''add item 1." We are using this issue to help build a feature of our product. You can add
more details in the description. You can add them now or add them at any time during the lifetime of
the issue. You click ''Create'' to add the issue to your project. You can click on the ''Issues'' tab in your
projects sidebar to see the issues of the project. Here we can see the issue we just created. Notice that
Jira has automatically assigned a unique issue key to this issue. The letters before the dash represents
a unique identifier for the project. This is called the project key and it was created when you created
the project. The issue number in the project follows the dash. Issue key values are unique in your Jira
application. To ensure this, you cannot have two projects with the same project key. Next, we will
discuss the administration hierarchy. When you work with Jira, you may need to perform some
administration tasks. This usually involves changing some configuration settings, because you are the
owner of your Jira site, you will need to be at least somewhat familiar with administering Jira. We
will see as we go through the course that there's a hierarchy associated with Jira administration. A site
administrator has responsibility for the entire site. They can do things like add users to the site
because you own your free Jira site that you will use in the labs, you are a site administrator. The next
level of administrator, is a Jira administrator. They can control things like the creation of projects and
configuration settings that can apply to multiple projects in the site. The next level of administrator is
a project administrator. These users can configure the specific project. Since you own your Jira site,
you will take on all of these administration responsibilities at various parts of the course. In addition
to these levels of settings and administration, we will see later that there are settings for project boards
and that each logged-in user has personal settings which apply no matter which site the user is logged
into. Atlassian is the company that owns Jira. One way that they offer their products is as a hosted
solution. This is known as they're cloud offering and it basically offers Jira as a service. An Atlassian
cloud site is a URL that is specific to you, your team, or your company that hosts your collection of
Atlassian products. For example, if your company was named Mycompany, your cloud site would be
hosted at mycompany.atlassian.net, the site that you will use in the lab, we'll end with atlassian.net,
but you will choose a unique name instead of mycompany. In the first reading or lab for this course,
you will sign up for a free cloud site and use Jira software cloud to perform the hands-on labs for the
course. A site administrator is responsible for the entire site. A site can contain other Atlassian
applications such as confluence and bitbucket. You can click on the switch to menu in the top
navigation bar to switch among applications in your site. If you are logged in as a site administrator,
you can click on administration to access site-level administration and settings. Another way to access
site settings is by clicking on the gear icon in the upper right of the top navigation bar and clicking on
one of the links shown here. When you click on a site setting's link, you'll be taken to
admin.atlassian.com. This is where you can administer your site. We will discuss this more later in the
course. Jira is very configurable and contains settings for different situations. If you click on the gear
icon in the top navigation, you can see a Jira's settings section. This is where you can configure
changes that apply to all of the Jira projects in your site. You will only see this functionality if you are
logged in as a Jira administrator. Since you own your Jira site, you are also a Jira administrator. In
addition to Jira settings, you will see access to site level settings, if you are a site administrator. All
users can view and modify their personal settings under the personal settings section. If you click on
the project's settings link for a project, those settings apply only to that project. You must be a project
administrator for the project to see the project settings link. We will discuss this more later in the
course. Here we have clicked on the project settings link while viewing a project. We can change
settings that relate only to this project. For example, this is where we can change the name of the
project or define the members of the project. In order to login to an Atlassian cloud site, you must
have an account. This account will be tied to your email address. The same cloud account can access
many cloud sites with different levels of permissions. This is because the account is tied to an email
address. If you currently don't have an Atlassian cloud account, one will be created for you when you
sign up for a free site in the first lab.
Play video starting at :13:48 and follow transcript13:48
Each Atlassian cloud account has personal settings that you can configure. For example, you can
update your profile information such as your full name and avatar. These profile settings apply to all
sites that your account is a member of. You can access your profile settings by clicking on your avatar
and selecting profile, or by clicking account settings. You can change personal settings related to this
Jira site by clicking on personal settings under the Jira heading. This allows you to configure things
like when you would like to get emails related to updates to issues that you are interested in. In this
course, we will discuss many aspects of Jira and provide a solid foundation for why and how to use
Jira. However, we will not cover everything. There are many resources available to you as you
continue to learn. Here are links to the Jira homepage, documentation, discussion forums or
community, general agile and Jira articles and tutorials, Atlassian team playbooks, Jira training, and
the Atlassian YouTube channel. In addition, a general web search on any specific Jira topic or
problem should return helpful information to you. Here's a review of what we've discussed in this
video. Jira is software used to help manage and deliver projects. A Jira application contains projects
which contain issues. A project is created from a template which provides common initial project
configurations. Keep in mind the scope of any changes to settings that you make. Now it's time for
you to work on some of the things that we've discussed in this video. Please consult the reading or lab
associated with this video, which will guide you as you sign up for your Jira account and perform the
lab.