Professional Documents
Culture Documents
Material Requirements Planning (Chapter 14)
Material Requirements Planning (Chapter 14)
Material Requirements Planning (Chapter 14)
(Chapter 14)
Alok Raj
PODS Area
Office: Room No 14, 2nd Floor, Library Building, Tel. 3439
Email: alokraj@xlri.ac.in
Material Requirements Planning
Forecasting
Workforce
Supply Chain support
Aggregate
Planning
Master
production
Inventory on hand
External Capacity
Scheduling
Material Requirements Planning
Level
Product structure for “Awesome” (A)
0 A
1 B C
(2) (3)
2 E E F
(2) (2) (2)
3 D G D
(2) (1) (2)
BOM Example
1 2 3 4 5 6 8
Time in
7
weeks
Determining Gross
Requirements
❖ Starts with a production schedule for the end item – 50
units of Item A in week 8
❖ Using the lead time for the item, determine the week
in which the order should be released – a 1-week lead
time means the order for 50 units should be released in
week 7
❖ This step is often called "lead time offset" or
"time phasing"
Determining Gross
Requirements
WEEK
LEAD
1 2 3 4 5 6 7 8 TIME
A. Required date 50
Order release date 50 1 week
B. Required date 100
Order release date 100 2 weeks
C. Required date 150
Order release date 150 1 week
E. Required date 200 300
Order release date 200 300 2 weeks
F. Required date 300
Order release date 300 3 weeks
D. Required date 600 200
Order release date 600 200 1 week
G. Required date 300
Order release date 300 2 weeks
Inventory records
❖ Includes information on the status of each item by time
period, called time buckets
● Information about
◻ Gross requirements
◻ Scheduled receipts
◻ Expected amount on hand
A 10 E 10
B 15 F 5
C 20 G 0
D 10
2 × number of As =
80
3 × number of As =
120
Net Requirements Plan
2 × number of Bs = 130
2 × number of Cs = 200
2 × number of Cs = 200
2 × number of Bs = 130
2 × number of Fs = 390
1 × number of Fs = 195
Determining Net Requirements
❖ Starts with a production schedule for the end item – 50
units of Item A in week 8
❖ Because there are 10 Item As on hand, only 40
are actually required – (net requirement) = (gross
requirement – on-hand inventory)
❖ The planned order receipt for Item A in week 8 is
40 units – 40 = 50 – 10
Determining Net Requirements
❖ Following the lead time offset procedure, the
planned order release for Item A is now 40 units in
week 7
❖ The gross requirement for Item B is now 80 units in
week 7
❖ There are 15 units of Item B on hand, so the net
requirement is 65 units in week 7
❖ A planned order receipt of 65 units in week 7
generates a planned order release of 65 units in week
5
Determining Net Requirements
Gross
35 30 40 0 10 40 30 0 30 55
Requirements
Scheduled
Receipts
Projected
35 35 0 0 0 0 0 0 0 0 0
Inventory
Net Requirements 0 30 40 0 10 40 30 0 30 55
Planned Order
30 40 10 40 30 30 55
Release
LT = 1 0 1 2 3 4 5 6 7 8 9 10
Gross
35 30 40 0 10 40 30 0 30 55
Requirements
Scheduled
Receipts
Projected 35
Inventory
Net Requirements
Planned Order
Release
Gross
35 30 40 0 10 40 30 0 30 55
Requirements
Scheduled
Receipts
Projected 35
Inventory
Net Requirements
Planned Order
Release
1 2 3 4 5 6 7 8
105 80 130 50 0 200 125 100
● Use the lot sizing rules (lot for lot, EOQ, and Least unit
cost policy) and propose an MRP schedule under each
rule. Assume there is no beginning inventory