Professional Documents
Culture Documents
Water Carry Over in Desalters Mockdrill Dated 07.10.23
Water Carry Over in Desalters Mockdrill Dated 07.10.23
Department : Production
Unit : AVU
Scenario : Water carry over In Desalters and subsequent furnace emergency
Introduction : Unit was running at a throughput of 1900 Mt/hr. Mock drill was conducted at 15:30 hrs. On 27h June 2023
In AVU as a part of exercise to improve preparedness for handling emergencies. An emergency scenario of
“Water carry over in desalters” was considered for the mock drill.
Methodology:
Prior information of the Mock drill was given to operating group of AVU (officers/Field Engineering Assistants) and RSM .
Emergency scenario was also explained.
Means of communication i.e. walkie-talkie and telephones were used during mock drill activities.
After the mock drill, a concluding session was conducted to discuss the handling of the emergency with all the participants.
The observers reviewed the steps followed during the mock drill with the standard operating procedure.
1. INCIDENT FACTS:
Date : 07-10-2023
Time : 15:30 hours
Shift in charge (SIC) : MD ARIF
Mock Drill Observer (External) : Chinnamal D
Panel Officer (PIC) : Subin Kumar , Rajakumar
Field operators : ARVIND, SRIHARI , GIRIRAJ . PRASHANT, Dharmendra , I P SINGH
1. Inform units, RSM, Unit In-Charge, CPNM, HOD and MD ARIF/ Subin 15:40 15:42
1 Kumar
CGM (T)
3. Fresh feed water inlet XZVs 1013 & 1012 closes and the Subin 15:47 15:47
interstage brine pumps 10 PM 103 A/B/C and 10 PM Kumar/Rajakumar
203A/B/C Trips
4. Maximize flow towards ETP manually from 1st stage Subin 15:47 15:49
desalters from both the trains. Kumar/Rajakumar
5. Inform ETP/RSM Arul Mani 15:49 15:49
6. Manually close Wash water Inlet I/Vs and make IZ Subin 15:51 15:53
130/132/ 530/532 healthy to start P 103 A/B/C and P Kumar/Rajakumar
203A/B/C to pump back excess water in second stage to
1st stage
7. Start P 103A/B/C and P 203A/B/C MD ARIF/I P SINGH 15:53 15:55
8. Check the brine and Tri-line quality I P SINGH 15:55 15:58
9. Effects are: Low level in V-03, Increase in CDU/VDU COT, Subin Kumara 15:55 16:10
3
Reduction in Desalter pressure
10. Monitor V-03 level closely. Maintain V-03 level by Rajakumar 16:10 16:15
adjusting crude flow to CDU heaters
Monitor COT and reduce Firing as per requirement.
11. During feed reduction, maintain CDU furnace COT and Subin 16:25 16:25
4 Kumar/ARVIND/Bhab
CDU operating parameters and reduce VDU furnace COT
ani
12. Maintain C001 Top pressure by maximizing AC 007 Load Arul Mani 16:15 16:20
and optimizing Off gas compressor load
13. Inform Downstream units for temporary reduction in Subin Kumar 16:15 16:20
rundown flows
14. Maintaining PA flows in column for temperature Subin 16:20 16:24
5 Kumar/Rajakumar
control
15. Reduce Product withdrawal and IR flow rates to Subin 16:25 16:27
6 maintain tray level. Continue CR flow to maintain Kumar/Rajakumar
column top temperature within limit.
16. Reduce and stop C001,C007 and side stripper stripping Rajakumar/ 16:30 16:35
steam and start additional V005 Boot water pump P 11 SRIHARI
17. Adjust P 003 Discharge Pressure to reduce the F101/201 Pankaj/Subin Kumar/I 16:35 16:40
7 Inlet Pressure
P SINGH
18. Reduce the firing further in F 101/201 Rajakumar/ ARVIND 17:10 17:15
8
19. Check the Tri-lines and provide feed back and start the Subin Kumar /I P 17:10 17:15
9
Desalter transformers SINGH
20. Establish wash water flow to desalter after stabilizing C001 Subin Kumar/I P 17:30 17:45
17 column.
SINGH
21. 17:55 17:10
Check the product quality and send check samples GIRIRAJ
17
22. Check brine and Tri-line quality and inform ETP Rajakumar/I P SINGH 18:30 18:45
19
23. Check Furnace pass flow area for abnormality ARVIND/Bhabani 18:25 18:35
14
24. Restore Furnace firing Subin 18:30 18:45
15
Kumar/ARVIND/Bhab
Refinery Head Quarters
Indian Oil Corporation Ltd.
ani
25. 18:45 18:55
Subin
Restore Crude throughput
Kumar/Rajakumar
26. Check exchanger area for abnormalities Pankaj/I P SINGH 18:55 19:00
Refinery Head Quarters
Indian Oil Corporation Ltd.
3. SHORTCOMINGS:- No shortcomings
4. OBSERVATIONS / COMMENTS: All staff members, panel officers and SIC followed SOP and performed
jobs correctly.