Professional Documents
Culture Documents
Yang DSM For Underground Construction
Yang DSM For Underground Construction
12th ANNUAL
David S. Yang
davidyang@jafecusa.com
September 11, 2019
• Introduction
• Soil mixing equipment
• Installation procedure & QC/QA
• Engineering properties of soil-cement
• Applications
• Deep Soil Mixing (DSM) is an in situ soil treatment
technology whereby native soils are blended in situ
with cementitious materials, typically Portland
cement.
QC system
Soil type
Mix design
Mixing Energy
Mix design
Cement factor
Water cement ratio
Mix energy
Rotation speed
Penetration &
withdrawal rate
Courtesy of Dr. Masaki Kitazume
Tokyo Institute of Technology and
CDM Association, Japan
Ground improved with clay from the
Port of Yokohama
Sources: 1. CDIT 2002, “The Deep Mixing Method, Principal, Design and Construction”, edited
by Coastal Development Institute of Technology (CDIT), Japan, published by A.A. Balkema
Publisher. 2. Saitoh 1988, “Experimental study of engineering properties of cement improved
ground by the deep mixing method. Ph.D. Thesis, Nihon University .
Tensile strength, σt (MN/m2)
Void
ratio, e
Sources: 1. CDIT 2002, “The Deep Mixing
Method, Principal, Design and Construction”,
edited by Coastal Development Institute of
Technology (CDIT), Japan, published by A.A.
Balkema Publisher. 2. Kawasaki, Niina and
Babasaki 1978, “Study on engineering
Consolidation pressure, p characteristics of cement-base stabilized soil”,
(MN/m2 ) Takenaka Technical Research Report, 19.
Unconfined compressive strength
qu (MN/m2)
DSM ground
improvement outside
launching & receiving
shafts
Block
Cell
Shear wall
&
columns
CIDH
Pile Ring
Installation Procedure for Cutoff Wall and Shoring Wall
Alternating Procedure
Proceeding installation procedure Proceeding installation procedure
for cutoff & shoring walls for ground improvement cells
Cypress Freeway Replacement Project, Oakland; CA DOT
First Hawaiian Bank Building, Honolulu, Hawaii
Courtesy of JAFEC & OK Soil
Courtesy of Aomi Construction and CDM Association
Soil-cement cells
for
• Bearing capacity
• Settlement control
• Liquefaction mitigation
Courtesy of Dr. Masaki Kitazume
Tokyo Institute of Technology, Japan
Dam, Levee & Canal – USACE, BUREC, CA DWR
Flood Side
Protected
Side Flood Side
1-2 Fort Point Channel Crossing (C09A7) – DSM was used for
ground improvement for the construction of tunnel and depressed
roadway (boat section)
• I-93 – To expand existing six-lane highway to an eight-to-ten-lane underground expressway, constructed directly beneath existing roadways, buildings,
and subways in downtown Boston.
• I-90 - To extend I-90 from its existing terminus south of downtown Boston to Logan Airport through the Ted Williams Tunnel under Boston Harbor and
a tunnel beneath the Fort Point Channel.
Courtesy of Dr. T.D. O’Rourke and A.J. McGinn, Cornell University; Massachusetts Turnpike Authority; Federal Highway Administration and Bechtel/Parsons Brinckerhoff (illustration)
The BIF project involved the construction of approximately
915 m (3,000 ft) of Interstate I-90 adjacent to Logan Airport.
Source: Lessons Learned for Ground Movements and Soil Stabilization from the Boston Central Artery
T. D. O’Rourke, M.ASCE1; and A. J. McGinn, M.ASCE2, 2005 Ralph B. Peck Award Lecture
Source: 1) Taki and Yang 1991; 2) Lessons Learned for Ground Movements and Soil Stabilization from the
Boston Central Artery T. D. O’Rourke, M.ASCE1; and A. J. McGinn, M.ASCE2, 2005 Ralph B. Peck Award Lecture
Max. excavation depth = 19.4m (64 ft) Max. excavation depth = 15.9 m (52 ft)
After DMM and jet grouting, excavation was resumed, and the underground
highway structure was completed.
Source: Lessons Learned for Ground Movements and Soil Stabilization from the Boston Central Artery
T. D. O’Rourke, M.ASCE1; and A. J. McGinn, M.ASCE2, 2005 Ralph B. Peck Award Lecture
Source: Lessons Learned for Ground Movements and Soil Stabilization from the Boston Central Artery
T. D. O’Rourke, M.ASCE1; and A. J. McGinn, M.ASCE2, 2005 Ralph B. Peck Award Lecture
Existing SMW Wall
MW Hammer Head,
3 SMW elements
Source: Lessons Learned for Ground Movements and Soil Stabilization from the Boston Central Artery
T. D. O’Rourke, M.ASCE1; and A. J. McGinn, M.ASCE2, 2005 Ralph B. Peck Award Lecture
The interchange at FPC consists of a network of tunnels and depressed roadway (boat
section), requiring 18.3 m (60 ft) of braced excavations in very soft to soft soils.
Courtesy of Dr. T.D. O’Rourke and A.J. McGinn, Cornell University; Massachusetts Turnpike Authority; Federal Highway Administration
and Bechtel/Parsons Brinckerhoff (illustration)
Fort Point Channel
Fill
Organic Deposits
Sand/Inorganic silt
Marine clay
Glacial deposits
Sources: 1) Lambrechts, J.R., P.A. Roy, and E.J.Wishart (1998), “Deign Conditions and Analysis Methods for Soil-Cement Buttress in Fort Point
Channel”, GSP No. 83, ASCE, Reston, VA, pp. 153-174. 2) Performance of deep Mixing method at Fort Point Channel by A.J. McGinn &
T.D. O’Rourke, Cornell University, 2003
Courtesy of Dr. T.D. O’Rourke and A.J. McGinn, Cornell University;Massachusetts Turnpike Authority; Federal Highway Administration and Bechtel/Parsons Brinckerhoff
DMM rig on barge M250 DMM rig on land Triple shaft mixing tools
Source: Performance of deep Mixing method at Fort Point Channel by A.J. McGinn & T.D. O’Rourke, Cornell University, 2003
Tokyo Tunnel section – 9.6 km, 60m below sea bed
Tokyo Bay Bridge section – 4.4 km
Chiba
Kisarazu
Section City
Kawasaki Kisarazu
Bridge section
Ukishima access man-made island man-made island
Shield tunnel
advanced through
Plan soil-cement zones
installed by premixing
and deep soil mixing
Section
Source: Ground improvement by cement-treatment in Trans-Tokyo Bay Highway Project, K. Uchida , K. Imai, F. Tatsuoka and Y. Kohata;
Grouting and Deep Mixing, published by A.A. Balkema 1996
Premix fill
DSM
Shield tunnel
advanced through
soil-cement zones
installed by premixing and
deep soil mixing (DSM)
Premix fill
DSM
Source: Ground improvement by cement-treatment in Trans-Tokyo Bay Highway Project, K. Uchida , K. Imai, F. Tatsuoka and Y. Kohata;
Grouting and Deep Mixing, published by A.A. Balkema 1996
The picture can't be displayed.
Diaphragm wall
98 m diameter Ground improvement
119 m deep
2.8 m thick Diaphragm wall
DSM • Deep soil mixing
• Sand compaction pile