The major activities planned for next 10 year action plan are:
9 Major repair of DR – 8 (clubbed with scheduled dry dock). May 2021 - Jul 2021
10 Refurbishment of DR-11 (clubbed with scheduled dry dock). May 2021 - Jul 2021
11 Securing Haldia dredging contract for 5 to 10 years. Jun 2021 - Sep 2021
12 Finalization of New Vessel specifications with CSL & IHC. Jul 2021 - Sep 2021
13 Procurement of Water Injection Dredger (WID). Feb 2021 - Sep 2021
14 Condemnation of Dredge Aquarius. Dec 2021
15 Inland waterways Dredging venture.
16 Development of New Vessel at CSL Yard. Oct 2021 - Sep 2023
17 Refurbishment of DR-14 (clubbed with scheduled dry dock). Jan 2023 - Mar 2023
18 Jumboization of DR-19 (clubbed with scheduled dry dock). Feb 2023 - Sep 2023
Upgradation of DR-15 & DR-17 (clubbed with scheduled dry dock repairs)
19 Post review and based on the performance of DR-16. Jun 2023 - Aug 2023
20 Refurbishment of DR-12 (clubbed with scheduled dry dock). Aug 2023 - Oct 2023
21 New Vessel delivery. Commencement of JNPT dredging. Oct 2023
22 Planning stage for procurement of New Vessel - 20000 Cu.M TSHD. Nov 2023 - Mar 2024
23 Refurbishment of DR-8 (clubbed with scheduled dry dock). Apr 2024 - Jun 2024