Present Capacity - 60 M.Cum as against the need of 80 M.Cum. Balance capacity shall be met by
chartering / outsourcing for the intermittent period of next 2-3 years.

The major activities planned for next 10 year action plan are:

x Upgradation of DR- 15, 16 & 17.


x Refurbishment of DR- 8, 11, 12 & 14.
x Jumboization of DR 19, 20 & 21.
x Water Injection dredger (WID) and Barge.
x CSD Outsourcing / Condemnation / Refurbish.
x New Vessel procurement – 12000 Cubic Meter.

SN Activities Time lines

Requested Ministry for issuance of necessary directions to the ports for


1 financing on procurement of New Vessel. 18/12/2020
2 Maritime Vision 2030 Presentation. 01/01/2021
3 Letter sent to VPT for grant of Rs.100 Cr advance. 12/01/2021

Obtaining approval of Board of Trustee of JNPT, Deendayal, Paradeep &


Vizag Port for financing of New vessel alongwith long term contract to DCI.
4 Repayment to Ports could be by adjusting from yearly dredging bills. Jan 2021 - Mar 2021

JV to undertake Capital Dredging in Cost efficient & effective manner “DCI


5 Capital Dredging Ltd”.
6 Securing Cochin Port Capital & Maintenance dredging contract. Feb 2021 - Mar 2021
7 New Vessel Contract finalization with CSL with 20% equity contribution. Apr 2021 - Jun 2021
8 Upgradation of DR-16 (clubbed with scheduled dry dock). Apr 2021 - Jun 2021

9 Major repair of DR – 8 (clubbed with scheduled dry dock). May 2021 - Jul 2021
10 Refurbishment of DR-11 (clubbed with scheduled dry dock). May 2021 - Jul 2021
11 Securing Haldia dredging contract for 5 to 10 years. Jun 2021 - Sep 2021
12 Finalization of New Vessel specifications with CSL & IHC. Jul 2021 - Sep 2021
13 Procurement of Water Injection Dredger (WID). Feb 2021 - Sep 2021
14 Condemnation of Dredge Aquarius. Dec 2021
15 Inland waterways Dredging venture.
16 Development of New Vessel at CSL Yard. Oct 2021 - Sep 2023
17 Refurbishment of DR-14 (clubbed with scheduled dry dock). Jan 2023 - Mar 2023
18 Jumboization of DR-19 (clubbed with scheduled dry dock). Feb 2023 - Sep 2023

Upgradation of DR-15 & DR-17 (clubbed with scheduled dry dock repairs)
19 Post review and based on the performance of DR-16. Jun 2023 - Aug 2023
20 Refurbishment of DR-12 (clubbed with scheduled dry dock). Aug 2023 - Oct 2023
21 New Vessel delivery. Commencement of JNPT dredging. Oct 2023
22 Planning stage for procurement of New Vessel - 20000 Cu.M TSHD. Nov 2023 - Mar 2024
23 Refurbishment of DR-8 (clubbed with scheduled dry dock). Apr 2024 - Jun 2024

Jumboization of DR-21 (clubbed with scheduled dry dock repairs)


24 Post review and based on the performance of DR-19. Apr 2024 - Sep 2024

Jumboization of DR-20 (clubbed with scheduled dry dock repairs)


25 Post review and based on the performance of DR-19. Dec 2024 - May 2025
26 New Vessel - 20000 Cu.M TSHD development & delivery Apr 2024 - Sep 2028

27 Condemnation of vessels DR-8 & DR-11 2027 to 2030

You might also like