Professional Documents
Culture Documents
Installation of Vaporizers JSA
Installation of Vaporizers JSA
1.1.1 Permits shall identify the specific work to be performed by the crew at the
specific location.
1.1.2 work description section of the work permit form shall be completed.
Request for work 1.1 scope of work
1.1.3 Hazard identification and control section of the work permit shall be completed.
permit not identified
1.1.4 review precautions taken and restrictions imposed to control the hazard
associated with the job site/ or work activity.
1.1.5 Attach the JSA with the work permit which will provide supplement information
for the particular activity.
1.1.1 Site supervisor shall conduct pre-job (toolbox) safety meetings with site address
job-specific safety issues prior to beginning work activity.
1.1.2 Supervisor shall inspect the site to detect and correct unsafe acts and condition
1.1.3 supervisory personnel or other qualified staff shall be present at the site while
Site preparation and
1.1 personal injury work in progress.
pre-task meeting
1.1.4 work permits shall be used to control the hazardous activities at all site location
1.1.5 adequate number and type of fire extinguishers shall be available at job site.
1.1.6 All personnel to wear complete PPE i.e. Safety helmet, safety shoes, gloves,
FRC ( fire retardant clothes )/ coverall, safety glasses.
Depressurizing of
1.1 unsafe approach 1.1.1 Perform gas testing prior to approach LPG tanks.
existing LPG vessels by
to vessels 1.1.2 No visual inspections shall be carried out until readings on gas detector are normal.
consumption
1.1.3 Operator / technician shall check the pressure of the tank from the gauge.
2.1.1 No work is allowed to be proceeded on pressurize tanks.
2.1.2 The client shall be informed to consume complete gas for depressurizing tank
2.1 Depressurization
2.1.3 supervisor shall confirm the tank has been depressurized by checking the gauge.
of vessels
2.1.4 Ensure gauge reading is ZERO.
2.1.5 Depressurization of LPG gas in open atmosphere is not allowed.
1.1.1 The flagman should give directions to the operator for positioning of heavy vehicle.
1.1 positioning of 1.1.2 Area barrication and signs shall be posted.
boom truck/crane 1.1.3 The ground condition of the area where the crane has to be established should be checked
thoroughly, must be leveled, compacted if its soft.
3.1.1 Taglines to be used to balance the load and arrest swinging of load.
3.1 falling of load
3.1.2 Follow SWL
3.1.3 install barricades and signages
1.1.1 No hotwork shall be carried at live plant area unless permission from the
authorized person.
1.1 Fire/ explosion
1.1.2 smoking is strictly prohibited
1.1.3 No Hotwork on existing pipes for connections, cold cutting shall be performed
1.1.4 No hotwork on pressurized lines or tanks.
2.1.1 Supervisor to ensure canopy is properly made so that sparks or splinters shall not
2.1 Improper canopy
be come out of canopy.
2.1.2 proper ventillation need to be established.
Take the Pipe
3.1 Defective 3.1.1 welding cables and tools shall be inspected for cuts, breaks, leaks or insulation
measurement and
welding damage & must be check before the use.
fabricate the pipes at
device/cables.
safe place away from
the exisiting LPG tanks. 4.1 personnel struck
4.1.1 Do not operate welding near tanks
by sparks, steel 4.1.2 remove all combustibles and fire hazards items from welding area, all welding within
buffer wire or approved barriers.
shattering grinding 4.1.3 barrier entrances to be closed securely at all times during welding.
disc 4.1.4 Use fire blanket to avoid any sparks to convert in shape of fire/explosion.
5.1.1 Ensure that grinder is disconnected from power source prior to changing /
adjusting discs.
5.1 Accidental 5.1.2 Use only inspected and tagged power cables and socket and ensure that cables
activation of grinder are properly secured and insulated to avoid electric shock
5.1.3 Grinder & disc shall be placed down on the ground when not in use.
5.1.4 Ensure safe guard shall be in placed
1.1.1 Appropriate PPE such as hand gloves, filter mask, chemical goggles etc, shall
be provided.
1.1 chemical contact
1.1.2 Refer and follow the instruction of material safety data sheet (MSDS)
with skin/eyes
1.1.3 In case chemical contacts with the eyes performer shall wash his eyes for atleast
Painting of pipes for
15minutes
vaporizers
2.1.1 Keep a spill clean-up kit nearby during painting.
2.1 Paint spillage
2.1.2 Deal with spills immediately
2.1.3 keep paint can on drip trays
1.1.1 only extension cords equipped with double insulated shall be used.
1.1.2 extension leads not lying on wet surface or metal grating, All cables must be
elevated from ground.
1.1.3 Use earth leakage protection unit for grinders, welding machines.
1.1.4 Competent electrician to inspect all electrical connections