A-SHIFT REPORT Dt. 15.02.

2024
BLR-1 BLR-2 BLR-3 HRSG Total
Boiler Steam Load (current) 144 137 153 57 491
Mill in Service BCD ABD ABC HRSG NG flow
Mill Standby A C D 508
Mill/RCF under maint. --
RCFs on AUTO with Com. Stm. Press B|97.8 --
Igniter NG support 0 0 0
Burner NG support 0 0 0
BHEL BLRS NG CONS. (A+B+C shift) 1656 0 0 1656
Ash Truck Dispatched (A+B+C shift) 3 0 0 3
BLR-1 BLR-2 BLR-3 HRSG pH / Cl2
CBD SILICA 0.5 0.3 0.4 0.3 CPP
MAIN STEAM SILICA 0.01 0.01 0.01 0.01 7.3/1.5
EP Field Out (A - PASS) - - 2 -- CPSU
EP Field Out (B - PASS) 2 2 5 -- 7.3/0
TG-1 TG-2 GT Imp. Total
CURRENT POWER GENERATION 13.00 0.00 23.00 14.40 50.40
Pow. Imp.(A+B+C shift) 115.92 0.00 0.00 115.92
Bunkering: (Indian + Imp. + Rej.) 0 1314 10 1324
Boiler : 1 Steaming normal.

EP 1A path inlet damper actuator tial to be taken in delinked condition in presence of Mech.
LRSB 27 traverse motor replacement job u/p by Elect., Mech side oil top-up will done after completion of motor replacement job.
Furnace draft tapping defect observed, same will be attended later.
1) 1PI1594 PT tapping opened, but tapping found very chocked.Same needs to be dechocked by other means. Its tapping Cap is also
loose.
2) 1PI1595 Tapping cap is very hard to open.
3) PS1594B tapping location is not approachable. Same will be shown to piping agency person.
Boiler : 2 Steaming normal.

Mill-2C stopped at 8:55 hrs, due to X-roller stud broken, Mill-2B started but abnormal sound started coming from Scrapper of Mill-2B,
so mill-2C started again at 9:48 hrs, Mill-2C stopped again at 11:25 hrs. and mill-2B started after scrapper adjustment job.
Mill-2C u/m/m for X-roller stud repairing job.
VJP Discharge line suspected Leakage near BAH-3. Shown to Civil for precast removal.
Clinker grinder Fluid coupling & GB checking u/p by Mech.
BAH hopper round M/H bolt tightning require, same informed to Mech.
Boiler : 3 Steaming normal.
Air Ingress was observed as per below list, same job will continue.
1. Boiler 3 manhole 5 & 6 in A path.
2. Boiler 3 A&B path emitting elec. rapping motor 2,3,4 & 5.
3. Boiler 3 A path collecting elec. rapping motor 3.
Tappings & flanges list for blind provision job is u/p.
**FG side**
1) APH inlet duct east side 1 tapping - done.
2)APH inlet duct east side 1 flange - done.
3)APH outlet duct west side 1 tapping - done.
4)APH outlet duct east side 4 tapping (3 tapping + 1 flange) - u/p.(1 completed)
(air path)
(1)APH inlet east side 1 tapping - u/p.
(2)APH inlet east side 1 flange - u/p.
Ash : Normal.
Unit-1 Aa3 hopper ash leakage observed, insulation removal job u/p.
Unit-1 line 3 booster line dechocking done.
HP Pump-2 both NRV & gland replaced, p/s to be restore and trial to be taken.
Ca3 Hopper valve Connecting Piece Leakage job done.
Cb1 domeseal replacement job done.
OTHER REMARK.
GT : Running normal.

nlet air filter North side first header SOV 21Y23 detached. For that both sides filter removal required, job will be planned.
GT CO2 system alarm observed, Cylinder cap switch was disturbed, same adjusted by elec.
HRSG :Steaming normal.
GFD diverter damper MOV trial was taken in presence of Elect. but MOV not operated. Further checking will be done by elect after
availability of third party.
CW pH analyser calibration done. To be verified with lab results.
TG-1 :Running normal.
CEP-1 heavy gland leakage observed, gland will be changed after gland availabilty.
CEP-1 NRV abnormal sound observed, same job will be done after spare NRV availability.
TG-2 : U/S/D.
Boiler-4 : U/S/D.
NGCT : Normal.
CWP-1 suction line spool piece thickness reduced. Same welding work will done.
CHP : Normal.