Checklist Safety Inspection
Checklist Safety Inspection
Checklist Safety Inspection
MOHD SHAIRAZI MAULA JAAFAR BANDAR CEMERLANG ZHEN YUAN CONSTRUCTION SDN BHD
3 Emergency telephone numbers (Police Dept., Fire Dept., Doctor, Hospital, and
Ambulance) posted in the proper places
6 It the site fence or hording board constructed at least 12 meter height at the
boundary of the site to prevent unauthorized person entering the site
9 Wall opening drop of more than 2 meter and bottom of the opening is less than
1meter above the working surface) are guarded accordingly
11 Are the floor are kept clean, no waste material stones or cement spilled
12 Arrangement for collecting and disposing of waste and scrap cement are done
regularly
13 Every flight of stairs are free from obstruction, stone, spilled cement or scrap
materials
Page 1 of 7
14 The site is kept tidy and there are proper arrangement for collecting and disposing
of waste and scrap regularly
15 Different sizes of plywood, timber are not bound together and stacked i.e. proper
storage of material and equipment’s close to the workstation.
16 Enough temporary storage areas provided in good condition (stable, not muddy)
18 Sanitary facilities provided and closed to workstation and regularly kept clean.
23 Protective clothing provided and maintained adequately clean and in good repair
24 Employees are provided with proper eye and face protection equipment when
machine or operations present potential eye or face injury from physical, chemical
or radiation agents
25 Life lines, safety belts and lanyards are used only for employees safe guarding,
and all are matched testing requirements
27 Safety nets are installed when work places are more than 25 ft. above the ground,
or other surface where the use of ladders, scaffolds, temporary floors etc. is
impractical
29 Safety belt in use when working at higher level and anchored to save and strong
place
30 Safety equipment issued are registered and regularly check for serviceability
Page 2 of 7
ACTIVITY INSPECTED: YES NO N/A REMARKS
HAND TOOL MANUAL AND POWERED
31 Workers who use hand tools are familiar with the tools and know how to repair
and maintained them
33 Impact tools (drift pins, wedges and chisels) are kept free of mushroomed head
34 The wooden handles of tools are kept free of splinters or cracks and are kept tight
in fixed to tools e.g. hammer / axes
41 Landing surface is not muddy or wet but clean and dry (muddy condition causes
42 Ladder are not being used for the job which required the scaffold
43 When ladder cannot be secured at the top for technical reasons, ensure that they
are secured near the bottom or footed
44 Ensure metal ladder are not being used near overhead power lines
Page 3 of 7
ACTIVITY INSPECTED: YES NO N/A REMARKS
SCAFFOLD
47 Working platform is enough wide to work safely with proper guard-rails and toe
boards
50 Ensure that no parts of the scaffold are removed or loose after it is erected
51 Make the upright of the scaffold vertical and securely braced to prevent swaying
or displacement
52 Board the working platform with scaffold boards or planks or proper grade timber
54 Provide sufficient number of fire extinguisher at all critical points and easily
accessible when need. Fire orders at each point
58 Keep the flammable liquid or LPG cylinders in a safe place when not in use
Page 4 of 7
ACTIVITY INSPECTED: YES NO N/A REMARKS
ELECTRICAL
60 Ensure that distribution cables are not causing a hazard at opening, passages,
ladders, stairs or lying on ground subject to damage and wetness
61 Not hanging directly from nails, etc. which may damage insulation and well
protected from sharp objects.
62 Suspended cable not carrying any weight and should be supported by rods or
poles
63 Ensure that all cables are visible. If necessary attach (yellow and black or red any
white) plastic bending strips
64 Ensure that there is no adequate supply of extension cable for site use
66 Plug covers etc., are not damaged and splash proof ones used
68 Check that the connection have been made color coding should be distinctive
69 Check that cable grips are used and that the earth cable s fitted with same slack
So that it is the last to be pulled out
71 Ensure that the correct type and rating of fuses are fitted and checked by
electrician
72 Ensure that improvised fuses (nails, silver paper etc) are removed and ideally
have fool proof earth leakage breaker fitted
73 Ensure that any special “make up” leads / extension are made by electrician
(competent person) only
75 Maintain every crane regular for wear and tear. Record of servicing maintained at
Site Office
Page 5 of 7
76 Ensure that every crane is inspected weekly by competent person and that a
record kept
77 Ensure that every crane operator and signalers are trained in the of use of hand
signal and ensure that their illustrations are displayed on the job site / cabin
78 Ensure that every crane of more than 1 ton capacity has efficient automatic safe
load indicator which is inspected weekly and record kept
79 Provide a safe mean of access to all parts of the crane to which it is necessary to
go for operation and maintenance
80 Train the operator and ensure that the age of the operator is over 18
82 Ensure that the crane operator is provided with safety equipment i.e. helmet and
safety belt
83 Ensure that the operator and maintenance personnel are fit before they are allow
to climb to the cabin or jib
85 Concrete workers protect themselves with boots, heavy gloves, long sleeved shirt,
safety helmet
86 Each iron worker (reinforced concrete) is not too close together and the periphery
of the slabs are properly guardrails
88 Protruding nails, wire ties and other unnecessary accessories are immediately
pulled, cut or taken
90 Check that the design and supports of form work and shoring are adequate to
support all intended load
91 Ensure that the form work is inspected by competent person before pouring of
concrete begin
Page 6 of 7
ACTIVITY INSPECTED: YES NO N/A REMARKS
POWER TOOLS
95 Check that the cable is protected from excessive flexing by the heavy rubber
sleeve where the cable enters the tool. Cable clamp is secure
96 Check that there are no crack or pieces missing from the machine. All screws are
in place and secure
97 Check that the chuck is in good condition and that the correct key is attached
98 Check that the name plate is secure .Detail available on the machine plate such
as make, voltage frequency, speed etc.
Inspected by:
…………………………………
Name:
Date: